Checklist for Footing concrete

Project : Preeti Iksa Ville Drawing ref. No:


Client : Preeti Developers Date / Time :
PMC : Voptimise Location / Grid no :
Item of work : Reinforced Cement Concrete (RCC) villa no.

SL No : Description Yes N.A Remarks

PRE-EXECUTION CHECKS
Are the latest "Good for Construction" drawings
1
available ?
Markings to be done with paint using thin
brush over PCC bed. Generally markings are
2 done with cement mortar as thick as 1". (This is
not advisable and this creates structural
problem at the junction)

3 Marking of wall/ Column & footing orientation


to be checked by Site Engineer before placing
the mat and wall/column in position.
Cover blocks are to be provided properly below
4
matt and sides.
Check for diameter, spacing and Development
5
length of reinforcement
Has the shuttering material been properly
6
aligned using appropriate equipment?
All four sides of shuttering to be fixed properly.
7 Size of the shuttering, diagonal and height of
shuttering are to be checked.

8 Footing sides are of single sheet on each side


with nut &bolt system ( side supports are must )
Have markings been made on the column
9
dowels for concrete level ?
Check for mixing of cement ,sand & aggregate
10
adequate metearial.(Site Mix)
Have the vibrators been checked before start of
11
the concrete ?
12 Check for pouring height.

13 Is the test report of cement and steel available at


site office ?
CHECKS DURING EXECUTION
14 Check for grade of concrete
15 Check for slump
Checklist for Footing concrete

Project : Preeti Iksa


Is the Ville been properly compacted with a
concrete Drawing ref. No:
16 vibrator or manually ?
17 Have test cubes been cast (site lab) ?
Are all the labourers wearing gum boots while
18 concreting ?

POST-EXECUTION CHECKS
19 Is curing been ensured ?
20 Check for de-shuttering done as per specified time
21 Check for dimensions of footing
Check for line, level and plumb of wall/column rods
22
Check for arrangement of curing and marking of the
23 date.
Comments:

Prepared By : contractor - Engineer Checked by : PMC - Engineer :-


Signature : Signature :
Name : Name :