25 –INSPECTION REPORT)
INSPECTION REPORT
As per inspection conducted by the undersigned, the data gathering household survey
services with the Project Percentage of Completion (System Generated) of the above stated
project is found to be 60% completed and in accordance with the approved plans and
specifications.
Inspected by :
IT
Noted by :
This is to certify that we have inspected and evaluated the work accomplished on the
above-captioned project which was found to be in accordance with the approved plans and
specifications and was reported 60% completed on ___________________and verified
complete without deficiencies
.
Issued this ______________ day of____________ 2021
Inspected by :
IT
Approved by :
Conformed by :
This is to certify that the work on the above-captioned project was found to be in
accordance with the approved plans and specifications and was reported 60% completed on
_________________________and verified complete without deficiencies and hereby accepted.
Accepted by :
Conformed by :