1 Specification Code: 2.6.

1
Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan)
2.6
including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.
2.6.1 All kinds of soil

Code Description Unit Quantity Rate Amount


Details of cost for 10 cum.
Average output of Hydraulic Excavator per
hour = 30cum
MACHINERY:
0020 Hydraulic Excavator (3D) with driver and fuel Day 0.041 6500.00 266.50
0018 Hire and running charges of loader
Day 0.041 6000.00 246.00
LABOUR:
0128 Mate
Day 0.32 407.00 130.24
Beldar/
0115 Coolie Day 1.2 368.00 441.60
TOTAL 1084.34
Add Water Charges @ 1% 10.84
TOTAL 1095.18
Add CPOH @ 15% 164.28
Cost of 10.0 cum 1259.46
Cost of 1 cum 125.95
Say 125.95

Cost index 39.89% 50.24


Total with Cost index 176.19
Say 176.19
DR PACKING Under foundation - Dry stone packing under foundation with good quality blasted rubble including conveyance of material and labour charges etc.
60.7.2
complete as per direction of departmental officers at site.

Code Description Unit Quantity Rate Amount


"Details of cost for 1 cum.
Material
1157 Stone for masonry work
cum 1.0 865.00 865.00
Carriage
2215 Carriage of Soling stone & masonry stone
cum 1.0 122.08 122.08
Labour
0125 Mason (for plain stone work) 2nd class Day 0.35 448.00 156.80
0114 Beldar Day 0.35 368.00 128.80
TOTAL 1272.68
Add Water Charges @ 1% 12.73
TOTAL 1285.41
Add CPOH @ 15% 192.81
Cost of 1.0 cum 1478.22
Cost per cum 1478.22
Say 1478.2
Cost index 39.89% 589.65
Total with Cost index 2067.85
Say 2067.85
5.9 Centering and shuttering including strutting, etc. and removal of form for:
5.9.5 Lintels, beams, plinth beams, girders bressumers and cantilevers

Code Description Unit Quantity Rate Amount


Details of cost for a beam of 6 m clear
span, 0.50 m deep 0.30 m wide and height
3.5 m from floor cubical contents
6.60x0.5x0.3 = 0.99 cum
1x1.30x6.00 = 7.80 sqm

MATERIAL:
Assuming shuttering will become
unserviceable after use of 40 times
Add maintenance charges @ 10% of cost
of material
Less salvage value of material after full use
@25% of cost of material
1. Steel plats for side and bottom (plate size 1.20 x 0.50 m)
Angle 40x40x5mm
2x1.20 = 2.40 m
3x0.50 = 1.50 m
Total 3.90 m @ 3.00 kg/m = 11.70 kg
sheet 1.6 mm thick 1.20 m x 0.50 m =0.60 sqm
0.60 sqm @ 12.55 kg/sqm. = 7.53 kg.Weight of one plate = 19.23 kg.
Add for wastage 5% 0.96 kg.
Total = 20.19 kg
Total weight of all plates
3x5x20.19 = 302.85 kg
Qty taken for cost of using once= 302.85 x 85/40 = 6.4356 kg

Rate as per item Number10.1 of SH:


kilogram 6.4356 58.45 376.16(A)
10.1 Steel Work
7343 Adjustable telescopic prop 3 m (2.02-3.75m)
each 0.1275 1000.00 127.50
Qty taken for using once = 6x0.85/40 = 0.1275m
7344 Beam clamp 300-380 mm (450-1070 mm)
each set 0.1063 370.00 39.33
Qty taken for cost of using once = 5x0.85/40 = 0.1063 m
9999 Sundries - Assembly nut & bolts etc.
Qty taken for cost of using once = L.S 22.1 1.73 38.23
1040x0.85/40 = 22.10
9999 Sundries - Carriage
L.S 78.0 1.73 134.94
LABOUR:
0116 Fitter(grade1) Day 1.25 487.00 608.75
0114 Beldar Day 2.5 368.00 920.00
9999 Sundries - Shuttering oil L.S 39.0 1.73 67.47
9999 Sundries - paper tape etc L.S 24.61 1.73 42.58
AddWater Charges @ 1% except on A ie
19.79
on ( 2354.96-376.16=1978.8 )
TOTAL 2374.75
AddCPOH @ 15% except on A ie
299.79
on ( 2374.75-376.16=1998.59 )

Cost of 7.8 sqm 2674.62


Cost of 1 sqm 342.90
Say 342.9
Cost index 39.89% 136.78
Total with Cost index 479.68