The belt was snapped-off straight perpendicular to the running direction at about 200 meters from the
Head Pulley. Both snapped-off ends are separated 125 meters. Some frame rollers are found broken.
Challenges:
Plan:
1. Get additional manpower from Suprabakti and Upper Oreflow Splice Crew.
2. Prepare the slings and clips.
3. Release counter weight.
4. To clip the belt on the head end side.
5. Pull the other end belt with LHD loader on the head to tail end direction.
6. Join the belt with mechanical clips.
If the LHD loader is not strong enough to pull the belt, then we should reduce ore on the belt by manual
clean up first.