Professional Documents
Culture Documents
Assessment 4 PDF
Assessment 4 PDF
Assessment 4 PDF
ACC 223A /
Assessment 4 (Week 17) /
Assessment 4
Question 1 Activity-based management focuses management’s attention on activities resulting in improving customer value and
Correct profits.
False
Correct
False
Question 3 The activity-based management model has two dimensions: a cost dimension and a process dimension.
Correct
False
Question 4 Process value consists of three elements: .driver analysis, activity analysis, and performance measurement.
Incorrect
False
Correct
False
Question 6 Performance measurement is concerned with how well activities are performed.
Correct
False
Question 7 Financial measures of performance focus on the dollar effect of activity performance changes.
Correct
False
Correct
False
Question 9 Kaizen costing is concerned with reducing the costs by identifying small, continuous improvement for existing products
Correct and processes.
False
Correct
False
Question 11 Rowbee, Inc., sells one of its products for P40 each. Sales volume averages 2,000 units per year. Recently, its main
Correct competitor reduced the price of its product to P28. Metropolitan expects sales to drop dramatically unless it matches the
Mark 2.00 out of competitor's price. In addition, the current profit per unit must be maintained. Information about the product (for
2.00 production of 2,000) is as follows:
Calculate the target cost for maintaining current market share and profitability.
Answer: 12
Question 12
Rowbee, Inc., sells one of its products for P40 each. Sales volume averages 2,000 units per year. Recently, its main
Correct
competitor reduced the price of its product to P28. Metropolitan expects sales to drop dramatically unless it matches the
Mark 2.00 out of
competitor's price. In addition, the current profit per unit must be maintained. Information about the product (for
2.00
production of 2,000) is as follows:
Answer: 9.40
If non-value-added costs can be reduced to zero, can the target cost be achieved?
Answer: No
Question 14 Yori Company has developed cost formulas for the drivers of the following production activities:
Correct
Driver Activity Fixed Variable
2.00
Labor hours Labor 0 10
purchase orders
Answer: 34,000
Question 15
Yori Company has developed cost formulas for the drivers of the following production activities:
Correct
Driver Activity Fixed Variable
purchase orders
Setups 100
Answer: 295,150
The correct answer is: 295,150
Question 16
Yori Company has developed cost formulas for the drivers of the following production activities:
Correct
Driver Activity Fixed Variable
purchase orders
If the actual activity was 20 setups and the actual fixed cost for inspections was P28,000 and the variable cost for
inspections was P5,000, the total variance for inspections is
Question 17 Setup time for a product is 12 hours. A firm that uses JIT and produces the same product has reduced setup time to
Correct 1 hour. Setup labor is P6 per hour. The non-value-added costs are
Mark 2.00 out of
2.00
Answer: 66
Question 18 A company has 5 days of finished goods inventory on hand to avoid stockouts. The carrying costs of the inventory
Correct average P5,000 per day. The value-added costs are
Question 19 Each unit of product requires 16 kgs of material. Due to scrap and rework, each unit has been averaging 18 kgs of
Correct material. The material costs P4 per kg. The value-added costs are
Question 20 A firm's warranty costs are P375,000 per year. A competitor's warranty costs are P175,000 per year. The value-added costs
Correct are
Correct
False
Question 22 In a strategic-based responsibility accounting system, stretch targets are established for individual performance measures.
Correct
False
Question 23 The balanced scorecard is a strategic-based performance management system that identifies four perspectives.
Correct
False
Question 24 Strategy translation means specifying objectives and percentage of revenues from sale of products.
Correct
False
Question 25 Customer value is the sum of realization and sacrifice what the customer gives up and receives.
Correct
False
Correct
False
The correct answer is 'True'.
Question 27 The strategy map connects the balanced scorecard strategy with an organization's administration.
Correct
False
Question 28 In order for the balanced scorecard to succeed, the entire organization must be behind it.
Correct
False
Question 29 Performance expectations must be established once objectives and measures have been executed and advertised.
Correct
False
Question 30 Incentives must be structured and resources allocated to support the strategy chosen.
Correct
False
Question 31 White Industries has the theoretical capability to produce 120,000 units per month but currently produces 90,000 units.
Correct The conversion cost for the month is P2,550,000. There are 7,500 production hours available per month. In addition to
Mark 2.00 out of processing time, it takes 14 minutes of move time and 8 minutes of wait time to produce a unit.
2.00
Compute the theoretical velocity per hour.
Answer: 16
2.00
Compute the actual velocity per hour.
Answer: 12
Question 33
White Industries has the theoretical capability to produce 120,000 units per month but currently produces 90,000 units.
Correct
The conversion cost for the month is P2,550,000. There are 7,500 production hours available per month. In addition to
Mark 2.00 out of
processing time, it takes 14 minutes of move time and 8 minutes of wait time to produce a unit.
2.00
Compute the theoretical cycle times (minutes per unit produced). (Round answer to two decimal places.)
Answer: 3.75
Question 34
White Industries has the theoretical capability to produce 120,000 units per month but currently produces 90,000 units.
Incorrect
The conversion cost for the month is P2,550,000. There are 7,500 production hours available per month. In addition to
Mark 0.00 out of
processing time, it takes 14 minutes of move time and 8 minutes of wait time to produce a unit.
2.00
Compute the actual cycle times (minutes per unit produced). (Round answer to two decimal places.)
Answer: 5.00
Question 35
White Industries has the theoretical capability to produce 120,000 units per month but currently produces 90,000 units.
Correct
The conversion cost for the month is P2,550,000. There are 7,500 production hours available per month. In addition to
Mark 2.00 out of
processing time, it takes 14 minutes of move time and 8 minutes of wait time to produce a unit.
2.00
Compute the current manufacturing cycle efficiency (MCE). (Round answer to two decimal places.)
Answer: 0.19
Answer: 3
Question 37
Lionheart Manufacturing has a theoretical capability to produce 20,250 printers per quarter but currently produces 10,125
Incorrect
printers. The conversion cost per quarter is P4,860,000. There are 6,750 production hours available within the plant per
Mark 0.00 out of quarter. In addition to the processing minutes per unit used, the production of printers uses 12 minutes of move time, 8
2.00
minutes of wait time, and 10 minutes of rework time. (All work is done by cell workers.)
Answer: 1.50
Question 38
Lionheart Manufacturing has a theoretical capability to produce 20,250 printers per quarter but currently produces 10,125
Correct
printers. The conversion cost per quarter is P4,860,000. There are 6,750 production hours available within the plant per
Mark 2.00 out of
quarter. In addition to the processing minutes per unit used, the production of printers uses 12 minutes of move time, 8
2.00
minutes of wait time, and 10 minutes of rework time. (All work is done by cell workers.)
Answer: 20
Question 39
Lionheart Manufacturing has a theoretical capability to produce 20,250 printers per quarter but currently produces 10,125
Correct
printers. The conversion cost per quarter is P4,860,000. There are 6,750 production hours available within the plant per
Mark 2.00 out of
quarter. In addition to the processing minutes per unit used, the production of printers uses 12 minutes of move time, 8
2.00
minutes of wait time, and 10 minutes of rework time. (All work is done by cell workers.)
Answer: 40
Answer: 240
Question 41
Lionheart Manufacturing has a theoretical capability to produce 20,250 printers per quarter but currently produces 10,125
Correct
printers. The conversion cost per quarter is P4,860,000. There are 6,750 production hours available within the plant per
Mark 2.00 out of
quarter. In addition to the processing minutes per unit used, the production of printers uses 12 minutes of move time, 8
2.00
minutes of wait time, and 10 minutes of rework time. (All work is done by cell workers.)
Answer: 480
Question 42
Lionheart Manufacturing has a theoretical capability to produce 20,250 printers per quarter but currently produces 10,125
Incorrect
printers. The conversion cost per quarter is P4,860,000. There are 6,750 production hours available within the plant per
Mark 0.00 out of
quarter. In addition to the processing minutes per unit used, the production of printers uses 12 minutes of move time, 8
2.00
minutes of wait time, and 10 minutes of rework time. (All work is done by cell workers.)
Answer: 0.57