Sub Grade With Cement
Sub Grade With Cement
Sub Grade With Cement
a) Labour
Mate day 0.36 520.00 187.20
Mazdoor (Skilled) day 1.00 550.00 550.00
Mazdoor (Unskilled) day 8.00 520.00 4,160.00
Add Municipal/ Agency Allowance 0% 0.00
b) Machinery
Tractor Mount Grader, (6 wheel - 4 wheel drive) is used in hour 12.00 520.00 6,240.00
place of motor grader, for grading @ 25 cum per hour
Three wheel 80-100 kN static roller @ 70 cum per hour hour 4.30 3,475.20 14,943.36
Tractor with rotaor and blade @ 25 cum per hour hour 12.00 520.00 6,240.00
Water tanker 6 kl capacity hour 5.00 769.00 3,845.00
c) Material
Cement at site @ 2.4 % t 12.60 4,300.00 54,180.00
Water kl 30.00 79.00 2,370.00
d) Overheads & Contractor’s profit @ 12.115% on (a+b+c) 11,232.49
Cost for 300 cum = a+b+c+d 1,03,948.05
Cess @ 1% 1.00% 0.00
1,03,948.05
Rate per cum =(a+b+c+d)/300 346.49