In one case of error SWG such as cannot start or stop we need to check connection of control cabinet of SWG,
so we need do test position of SWG without connect the power to load. In this OPL we want to share How to
test position MV SWG Roller Press machine. Detail working steps as following :
2. Install Lock Out and Tag out at the place of LOTTO M1 and M2
3. Prepare electrical drawing schematic diagram of SWG cubicle to check hardware interlocking
v v
Terminal for checking interlock from Water resistance (LSP) is 49 and 62 in SWG
Document No : FM-G-DC-018 (00)
One Point Lesson Effective Date : 13/03/2019
Page :1/1
PT SEMEN JAWA
4. Make sure all hardware interlocking have been completed (we check interlocking from water
resistance only because interlock from main cabinet roller press waiting pump for lubrication
is ON)
5. Ask to Operator team to check DCS interlocking of this machine (if possibly can block signal)
6. Prepare jumper terminal/cable jumper to bypass signal ready from limit switch of SWG
8. Connect bypass/jump cable from signal ready of SWG in terminal control, connect both of
SWG M1 and M2
11. Ask operator to prepare run the Machine, Operator run/start machine by command from DCS CCR
12. If complete SWG will energize without power from MV busbar and the lamp of indicator SWG is
close for SWG M2
13. After SWG M2 run one minute SWG M1 will be run also
14. When SWG M2 running we need contact flip flop Proximity Moving Roller 2 for interlock PLC
still complete until SWG M1 run
15. After all SWG is run, ask operator check signal run to DCS is completed
16. If all signal has been completed, ask operator again to turn Off SWG from CCR
17. When lamp indicator SWG has been opened, turn off the main control breaker
v SWG is open