Professional Documents
Culture Documents
MN601 Lab Week 07
MN601 Lab Week 07
MN601 Lab Week 07
Instruction
All MN601 laboratory reports should be submitted weekly at the end of each laboratory
section as individual submissions via Moodle.
Organise and arrange your Moodle folder submission needly. You need to name your files
using the weekly laboratory number, your names, and student ID, such as LabWeek07
YourName MITID.
The laboratory activities have two sections, Section A is about Microsoft Project and Section
B has a few questions related to project management areas. Thus, it will provide you with a
better understanding of the topics.
Do not retype or reuse laboratory questions to avoid high similarities, always aim for 0%
similarities for all laboratory reports. For Microsoft Project Section A, when you submit
screenshots, please take the whole screenshots of your screen. Ensure your report is
different from that of other students and not plagiarised.
Late submissions will result in a loss of 10% marks for each day the report is late.
Learning Outcomes
1. Using MS Project 2021 to Build the Logical Network Diagram
a. Define dependencies using task table and mouse.
b. Define or delete a dependency series.
c. Understand network diagram presentation.
d. Verify the accuracy of the network diagram.
e. Identify the critical path
2. Save MyFirstProject file
2. Explain if you have to choose between fast tracking or crashing for project compression.
3. Draw a Gantt chart and project network diagram from the following information below.
a. Identify the possible paths and determine the critical path to complete the project.
b. Activity B and H can be shortened to a minimum of two weeks. Which activity would
you shorten to reduce the project duration by two weeks? Why?
a. Draw a Gantt chart and a network diagram and determine the critical path.
b. Assuming the direct total cost is $1000 and initial project duration is 12 weeks,
reduce the schedule unit (one time unit per move) until you reach the crash point of
the network.
c. For each move identify what activity(s) was crashed and the adjusted total cost.