Dokumen - Tips Risk Assessment Erection of Bamboo Scaffold
Dokumen - Tips Risk Assessment Erection of Bamboo Scaffold
Prepared B y : Date :
Risk Assessment for Erection of Bamboo Scaffold Checked By : Date :
Approved by : Date :
1. Work Sequence:
Item Activities Affected p erson(s) Associated R isk I tems Remark
1. Erection of B amboo S caffold Laborers, W orkers 1
2. Working at Height Laborers, W orkers 2
3. Working w ithin the n ullah Laborers, W orker 3
Page 1 of 5
Leader-Sunnic Joint Venture
Reconstruction, Improvement and Rehabilitation of Kai Tak River
From Wong Tai Sin police Station to Tung Tau II Estate
DC/2011/04
Risk Assessment Ref. No. 1121/RA/
Working adjacent to the − Falling into − Erect rigid barriers along 1 2 L − Enhance site safety supervision 1 1 L − Engineer
sea water the edge of Landing Steps − Workers known swimming are − Foreman
− Provide working platform advised to engage for working over − Superintendent
with suitable access water
ladder
Workers should wear life
jacket
− Provide life buoys and
adequate length of rescue
ropes close to the works
area
Work in a team of at least
two.
Page 2 of 5
Leader-Sunnic Joint Venture
Reconstruction, Improvement and Rehabilitation of Kai Tak River
From Wong Tai Sin police Station to Tung Tau II Estate
DC/2011/04
Risk Assessment Ref. No. 1121/RA/
Page 3 of 5
Leader-Sunnic Joint Venture
Reconstruction, Improvement and Rehabilitation of Kai Tak River
From Wong Tai Sin police Station to Tung Tau II Estate
DC/2011/04
Risk Assessment Ref. No. 1121/RA/
Page 4 of 5
Leader-Sunnic Joint Venture
Reconstruction, Improvement and Rehabilitation of Kai Tak River
From Wong Tai Sin police Station to Tung Tau II Estate
DC/2011/04
Risk Assessment Ref. No. 1121/RA/
Page 5 of 5