Professional Documents
Culture Documents
Team Structured-Agile Scrum-Jira PDF
Team Structured-Agile Scrum-Jira PDF
Team Structured
Gagandeep Singh-200514995
Harman Kaur-200506613
Navdeep Kaur-200511569
Rajdeep Kaur-200524510
Varun Khajuria-200512064
Overview of project and project scope- Lithium ions migrate from the negative plate
through a medium to the positive terminal during depletion and back again during charging in
batteries commonly use graphite for the negatively charged electrode and interpenetrating
lithium material for the positively charged electrode. Li-ion cells have a low self-discharge
rate, no memory effect, and high energy density. It is possible to construct cells that
emphasize power density or energy. However, because they include volatile ions and can
Cathode, anode, electrolytes, and isolator are the four main components of a lithium-ion
battery. A Li-ion battery needs every element because it will not operate if one of them is
absent.
Product Backlog- Different issues related to the project are shown below:
3
Sprint-1
This sprint will focus mainly on the first two issues that were to be solved in the following
sprint i.e.
Sprint-1 Planning
Below we have identified the tasks which need to be completed in this sprint. Moreover, the
team has together decided to have a 1-week timeline for this sprint.
Sprint-1 Backlog
In this, the team has pulled together the tasks from the product (lithium-ion batteries) backlog
as shown below -
4
The meeting will be held every day to go through what has been accomplished, what must be
done next, and whether there are any obstacles. Following a status review by the entire team,
Sprint-1 Review
The team gives the product owner a demo of the subsequent iteration they developed during
the sprint. The work was examined by the product owner to determine if it was complete or
what was missing. All the features were effectively delivered as agreed upon, however, the
client still wanted a protective covering that is recyclable as well as suitable for all kinds of
temperatures.
6
Sprint-1 Retrospective
Sprint-2
As the customer demand was for a protective covering that is recyclable and also suitable for
all kinds of temperatures, we took back the recyclable card. This sprint will now focus on the
* Recycling issue
* Zero to no maintenance
7
Sprint-2 Planning
We have identified different tasks that need to be completed in this sprint. The duration of the
Sprint-2 Backlog
Two issues will be resolved in the meeting. One card is sent back to the issue section. The
reason for that is explained in the review section. Standup meet shows what must be done
next, and whether there are any obstacles. After following the status review, a new card from
Sprint-2 Review
All the deliverables were delivered effectively but the ‘Extraction of the lithium’ card was
sent back. The reason for doing so is the complaint from the manager staff that there is a lot
The work was examined by the product owner to determine if it was complete or what was
missing.
9
Sprint-2 Retrospective
10
Sprint-3
Sprint 3 will mainly focus on addressing and resolving the following issues that were
identified:
Sprint-3 Planning
As stated above, the sprint planning will include the actionable strategies to resolve the issues
and reach the sprint goal which is to make the extraction affordable.
In addition to this, both the respective issue will be resolved in sprint 3 within 1 week.
11
Sprint-3 Backlog
After the sprint planning is completed, the next step is the creation of the sprint backlog.
Respectively, the team has created the backlog for sprint 3 which contains the tasks that will
A daily scrum meeting will be held daily. The sole purpose of the daily scrum is to make that
each team member is on the same page concerning the current tasks at hand, project health,
project status, other project aspects, and any project-related problems that have occurred or
Sprint-3 Review
In this step, a working demo of the functionality developed during the sprint iteration is
presented to the product owner. The feedback from the product owner is recorded and the
team makes sure whether the stakeholder is satisfied or not. However, both tasks were
Sprint-3 Retrospective
The team collectively agreed upon the way the whole team worked and how each team
member tackled their respective obstacles with the help of the other team members.
14
Sprint-4
In this sprint, we have to overcome two issues of lithium batteries. The issues with lithium
batteries are it catches fire when exposed to a high amount of heat. Apart from this, the
Sprint-4 Planning
In the sprint planning our goal is to overcome two lithium battery issues. The duration of this
sprint is one week. So, our main goal for this sprint is to increase the lifespan of lithium
Sprint-4 Backlog
In the sprint backlog, we are trying to resolve the 6th and 7th issues of the lithium battery.
15
In the daily stand-up meetings, we resolve the 6th issue which is that lithium batteries catch
fire when exposed to a large amount of heat. But the issue number 7 Shorter life span of
Sprint-4 Review
The lifespan of lithium batteries is less compared to alkaline batteries because of the different
materials used. This is the main reason why this issue is in progress.
17
Sprint-4 Retrospective
The time of the retrospective meeting is one week. In this meeting, there are many things
which inspired us for the future such as Science fiction movies and also Engineers'
suggestions for substituting chemicals. We decided not to use previously used material which
can easily be caught fire. Apart from this, for future projects to extend the lifespan of
Sprint-5
Project development teams began with the aim of solving various problems with Li-ion
batteries. And this sprint highlights the need for non-corrosive material to make electrodes
and solutions to the issue of the short lifespan of batteries due to low capacity.
Sprint-5 Planning
Although many issues have been resolved, still we gave one week to mitigate the problem of
corrosion as we don’t have much time to solve all issues. Our team will be working hard to
gather knowledge so that we can use alternate electrode materials to get rid of corrosion.
19
Sprint-5 Backlog
The team has found solutions to issues of the short lifespan of the battery and protecting the
electrodes from corroding. After doing this, we will be left with one trouble, when due to
high voltage the separation barrier breaks down and affects the output of the battery.
20
A lithium-ion battery is an electrochemical cell. To solve some issues, it’s better to share and
discuss the concepts we learned. It was decided to hold a meeting every day to clear our
backlog. Progress of meeting can be seen in screenshots when one issue of short lifespan is in
progress while in the later screenshot attached, this issue finds a remedy and other in
progress.
21
Sprint-5 Review
Tests conducted by the expert illustrated that electrodes get rusted when came into contact
with air and water. It leads to a search for some non-resistant material with the same chemical
Sprint-5 Retrospective
23
Sprint-6
In this sprint, as we are reaching almost the end of project delivery, we focused on the final
issues that are being raised by the stakeholder and by the project development team. So as of
now, we have one new issue that we need to resolve and one is from the previous sprint that
we will focus on and get resolved within the given timeline of this week. We will be working
on how to get rid of the issues related to electrodes getting damaged when exposed to
moisture (already in progress from the last sprint). Second, we will focus on separation
barrier ruptures when exposed to high voltage and how to resolve it.
Sprint-6 Planning
As you can see in the below screenshot the two issues are in different stages i.e. one is in
progress from the last sprint and another one is a new issue from the current sprint. So we
have understood the issues and tried to resolve them within the 6th sprint. Also, the team
Sprint-6 Backlog
The team has already identified and we are working on a product backlog from the previous
sprint review we will try to resolve it in this sprint and the same has been depicted in the
below screenshot.
The standup meeting or a daily scrum call is done and we all connect here daily and try to
understand the issues that are or may delay the project delivery and try to resolve them within
The two issues were in two different stages in the above image and now as we have reached
the final timeline, the team has managed to resolve the issues and so the stages have been
moved to completed or done. Which you can see in the image below.
26
Sprint-6 Review
Now we will connect with the Product owner and will showcase our project updates and then
he will let us know if we are up to the mark as he expected or still there is a need to do some
For now, he liked what we have done and the project’s final delivery is complete.
Sprint-6 Retrospective
Team Structured final retrospective where we have mentioned our few learnings and how we
will implement them in a future project. All of it is mentioned in the retrospective leaves
Conclusion
In this project, we have worked as a team and conducted mock scrum meetings which helped
to understand how actually a scrum meeting takes place and also use different scenarios to
To achieve the same we have used the JIRA project management tool for covering the
complete scrum framework and we made sure that we cover all the different Agile processes
and understand the Agile methodologies used to complete the project delivery.
28
References
https://baldeepsingh93.atlassian.net/jira/software/projects/LIBTS/boards/2
Fleischer, J., Fraider, F., Kößler, F., Mayer, D., & Wirth, F. (2022). Agile Production
https://doi.org/10.1016/j.procir.2022.05.140
Galen, R., Fields, J., Galen-Personick, R., & Summers, M. (2022). Extraordinarily Badass
Agile Coaching: The Journey from Beginner to Mastery and Beyond. RGCG, LLC.
Peacocke, S. (2022). Agile Coach to Chief Agility Officer: Placing the agile coach on the