Professional Documents
Culture Documents
SKP TT DT Project
SKP TT DT Project
Implementation Contractor:
Reviewers:
Munir Ahmad – Project Manager (Shell Pakistan Limited)
Mir Hazar – Construction Manager (Shell Pakistan Limited)
1. Scope
1.1. Introduction
SPL wanted to resolve the problem related to the Thermal expansion in piping. Hence, this project
tends to resolve the problem regarding thermal relief of the Piping. When piping is exposed to the
temperature, vapours are produced, which tends to raise the pressure inside the pipe. Therefore,
thermal relief valves are used to overcome this pressure-rise due to thermal expansion. ESP has
provided with the detailed study report in this regard. Hence, the extent of this project is the
installation of TT AND DT’s at various locations as depicted in study report for Shikarpur
Installation.
1.2. Scope of Work
The scope of the project includes but is not limited to:
1. Installation of TT and DT at various locations in Shikarpur Installation. The following
describes the works required. This should be read in conjunction with the Bill of Quantities
(BOQs), Specifications and Drawings attached for complete understanding.
1.3. Definitions
In this document, the following definitions apply:
Term Meaning
Contractor Avanceon Limited
Consultant / ESP / Owner’s Engineer Petrochemical Engineering Consultant
TA Technical Authority
1.5. Responsibilities
The following responsibilities apply for all personnel undertaking activities covered by this
document.
Responsibilities Meaning
Project Manager (Shell) Project Manager is accountable for the delivery of the Pipeline Project, overseeing
Munir Ahmad the Execution phase of Construction until SOF / Mechanical Completion and
handover of the Pipelines projects.
Construction Manager (Shell) The Construction Manager is accountable for all site activities up to Mechanical
Completion, including managing the Contractors site activities to ensure a safe
Mir Hazar and quality Mechanical Completion. Construction Manager also support during
commissioning activities
Asset Manager (Shell) The AM supports construction and commissioning activities and is
accountable/responsible for commissioning and start-up of the asset while
Ali Murad Baloch ensuring the asset can be operated safely and successfully.
Contractor Project Manager (Avanceon) Accountable and Responsible for Supply, Construction, Mechanical and Electrical
Completion & Pre-commissioning of the Pipeline Project and handover of the
Muhammad Saad Pipelines projects. Contractor shall also support during commissioning of project
and liaison with Shell accordingly.
Phase 1
Fabrication , Installation , Testing of TT and DT
(Mechanical And Electrical Completion)
Phase 2
Pre-Commissioning and Hydrostatic Testing of Piping
Phase 3
Pre-Startup Safety Review (PSSR) and Statement of
Fitness (SoF)
Phase 4
Commissioning and Startup Acitivites
Document Attachments
Contractor HSSE Plan
Emergency Response Plan
2. System Description
2.1. Overview System Process Engineering Flow Scheme
3.1.1. Mechanical
System Visual inspection for complete and correct installation
Process verification at site as per PEFS
Bolt tensioning
3.1.2. Instrument
Calibration and testing of instruments prior to installation.
Visual inspection for complete and correct installation.
Insulation and continuity testing of cables.
Adjustment of control, alarm and shutdown settings.
3.1.3. Piping
The Mechanical works include, but are not limited to:
1. Procurement in accordance with BOQ after verification from site.
2. Construction documentation.
3. Dismantling of piping (as marked in piping Layout).
4. Re-installation of existing piping along with new gaskets for the fittings.
5. Pre-manufacturing and Installation of pipework spools.
6. Installation of piping fittings. (As mentioned in piping Layout)
7. Tie-ins in accordance with piping layout.
8. Installation Tests (e.g. NDT, Hydrostatic pressure test).
9. Finishing works (e.g. internal cleaning, touch-up paint, labeling and tagging).
10. Start-Up and Pre-commissioning Activities.
11. The Contractor shall issue all the necessary documentation required to undertake and to follow-up
proper procedures for dismantling and installation activities and to record all activities (as built
dossier).
On achievement of mechanical completion, responsibility for the facility will transfer from
those responsible for construction to those responsible for pre-commissioning and
commissioning. Pre-commissioning is also included in Contractor scope of work.
Note:
Note:
have been verified, assured and completed by competent persons to ensure that hydrocarbons
can be safely introduced, and associated risks effectively managed to ALARP.
The Statement of Fitness is the final sign off by Engineering (incl. Projects) and Asset
managers prior to the introduction of hydrocarbons and confirms that the criteria to safely
introduce hydrocarbons are met. After the handover of the asset, the Asset Manager will have
the sole accountability to facilitate and ensure safe operation of the asset.
Aim of Statement of Fitness document is to confirm that:
Process Safety Risks have been identified and documented and are managed to ALARP;
People executing HSSE Critical Activities are competent and fit to work;
HSSE Critical Equipment meets its Technical Integrity requirements, and Modifications
are complete and have been authorised as specified in the Management of Change
Manual Section;
The design and construction of New Assets and Modifications to existing Assets meet
design and engineering requirements;
Process Safety Basic Requirements are met;
Procedures are in place to operate HSSE Critical Equipment within its Operating Limits.
All 6 DGAME deliverables (6 pillars) shall be delivered prior to SoF sign off.
PCAP compliance shall be required for SoF Sign-off (as recommended by SPL).
Management
Management
Control Name
Construction
HSSE & SP
ORP Phases
Operations
(including
Accronym
Safety)
Project
No
Statement of Fitness
6 E SoF
(New asset) Munir Ahmed Malik Usman Ali Murad Baloch / Muhammad Asim
PCAP compliance shall be required for SoF Sign-off (as recommended by SPL). Below
RTA/ATA may change as per availability.
Management
Management
Control Name
Construction
HSSE & SP
ORP Phases
Operations
(including
Accronym
Safety)
Project
No
Statement of Fitness
6 E SoF Abdul Rehman / Khawar
(New asset) Supot Visuthranukul Harinthiren / Malik Usman
Khalid
The Contractor shall station personnel throughout piping system at high point vents to bleed
air. All flanges and equipment will be periodically inspected for leaks during filling
procedures.
Downstream valves shall be throttled to maintain a packed condition in vessels throughout
initial fill of piping system as described above.
First fill shall be sampled prior to usage. Shell PQ and Operations procedures shall be
followed for testing of products
5.3. Initial Low Point Flush
Perform an initial low point flush operation by flushing each low point drain through a
portable basket strainer for 10 seconds at a system pressure. Repeat flush until basket strainer
collects no additional debris.
5.4. Flushing
The intent of the flushing operation is to remove bulk solids and test leftovers from the
system. Flushing procedures shall precede cleaning procedures. All new pipelines, product
piping, including the transfer line, receipt system piping and supply lines to the storage tanks,
shall be flushed with product. Minimum 4-5 hours product hold time is required.
The flushing of system pipelines shall be accomplished by pumping in bowsers or contractor
can make any other decision after SPL approval. After the main piping system has been
flushed to the satisfaction of SPL, and periodically during the flushing operation, the
Contractor shall flush all high point vents and low point drains.
5.5. Cleaning, Testing & Sampling
Pump product through all new piping sections in the system. Product velocity during all
cleaning operations shall be full pumping capacity. Perform sampling at all system discharge
points, at tanks, and throughout pump house and piping system.
5.6. Commissioning Procedure
Commissioning to be carried out as per given procedure. This includes receipt, flushing,
testing and loading procedure
Attachments
6. Safety Measures
Take measures to ensure that all persons and property are adequately protected from the
consequences of a possible system failure or other causes during the clearing, line filling
and testing operations.
Avanceon will confirm to SPL that he has instructed all employees engaged on testing
work, or any work associated with testing, or any work in the immediate area (e.g., on
platform) of the possible consequences of a pipeline or test fitting failure under pressure
test conditions.
Avanceon will comply with any permit-to-work system applicable at any location
influenced by the hydrotest activities.
Warning notices reading 'KEEP AWAY - PIPELINE UNDER TEST' shall be placed at
appropriate locations such as blanked ends of the test sections, areas where pre-tests or
assembly testing are carried out and test equipment sites.
Avanceon will obtain the SPL approval in writing of the emergency plan before
commencing pressurization.
Avanceon team to be present with adequate fitters, mechanics and qualified personnel
during first receipt batch.
Before any work, including tightening of leaking flanges, is permitted on the test section
under pressure or associated connections, the pressure shall be reduced to a level not
greater than static head plus 1 bar (15 psi). Attached flange management procedure.