Professional Documents
Culture Documents
RAPP - BQ - Earthwork
RAPP - BQ - Earthwork
GENERAL NOTES
The Contractor shall include and allow for all costs and expenses for
2 Note
the proper execution and completion of the Works.
The Contractor shall be required to insert the unit rates and all unit
rates inserted herein shall be used for the purpose of valuing
variations regardless whether variation works are carried out in small
5 Note
quantities and are valid for variation works carried out during the
contract period and within three months after contract and/or
extended completion.
General Notes :
Soil Improvement
Re-leveling - basecourse layer based on the level design and
1 slope direction, include re-test the CBR based on specification 1 Item 1,500,000,000
"Road & Stormwater Drainage"
GENERAL NOTES
2 The Contractor shall include and allow for all costs and expenses for the proper
Note
execution and completion of the Works.
3 This Schedule shall serve as a guidance for Tenderer's pricing purpose only. This is
a Fixed Lum Sum Price. Awarded contractor will be paid based on the Tender
Note
Drawing and Specification including all supporting documents during the Tender
Process.
4 The quantities shown in the Schedule of Works are strictly for guidance only and
shall be of no contractual effect. Note
5 The Contractor shall be required to insert the unit rates and all unit rates inserted
herein shall be used for the purpose of valuing variations regardless whether
variation works are carried out in small quantities and are valid for variation works Note
carried out during the contract period and within three months after contract
and/or extended completion.
6 The items described in the Sections may not be fully descriptive in themselves and
are not meant to limit the scope of the Works. The Contractor shall fully determine
for himself the scope of each item and price accordingly. No claim whatsoever will Note
be entertained from the Contractor concerning lack of knowledge on his part in
pricing of these items described in the Work Sections.
General Notes :
Parking area
1 50mm thk compacted sand m2 732 225,000.00 164,700,000
2 80mm thk aerated concrete pavers m2 732 320,000.00 234,240,000
Footpath/Walkways
1 Plastic sheet m2 3,560 10,500.00 37,380,000
2 150mm thk concrete pavement with chamfered edge m3 3,560 225,000.00 801,000,000
Concrete wheel stopper, overall size 250mm wide x 750mm long, fixed to concrete
slabs including 2No. of 12mm diameter mild steel anchors with epoxy grouting, as
described (1 parking lot 2No. Stopper)
Supply & install 200mm W x 150mm H precast concrete kerb in monolith finish as
described on drawings and spec;-
2 150mm precast concrete kerb m 1,790 175,000.00 313,250,000
Collection Page
A801 Addendum -
Jalan setapak/trotoar
Dwg Reff: K2 JKT1 - Tata Letak Layanan Bawah Tanah Secara Keseluruhan
Penggalian
Penimbunan Tanah Saja, termasuk perbaikan
(pengkondisian perlakuan tanah sesuai Gambar
Pengaktifan JKT1-DRG-CIV-5-Z0-L0-1004, JKT1-DRG-
CIV-4-Z0-L0-3002-3006)
Backfilling Cleanset 105Kg/m3, termasuk make good
(pengkondisian tanah sesuai Pengaktifan Gambar
JKT1-DRG-CIV-5-Z0-L0-1004, JKT1-DRG-CIV-4-Z0-L0-
3002-3006)
Backfilling Basecourse, termasuk make good
(pengkondisian tanah sesuai Enabling Drawing JKT1-
DRG-CIV-5-Z0-L0-1004, JKT1-DRG-CIV-4-Z0-L0-3002-
3006)
S14 - Addendum
Ref.: Description
Unit Qty Total
The Contractor is to specify any other items not listed in the foregoing and/or
specifically mentioned and described but which are either indispensably
necessary to be carried out and bring the works to completion. The
Contractor shall allow for and insert in details the below any other items not
specifically mentioned hereinbefore but are required to comply with the
drawings and specification and to the satisfaction of the Project Manager.
No. : 23/SPH-PSM/IV/2023
Perihal : Surat Penawaran Harga
Lampiran : Bill Of Quantity
Kepada Yth,
PT Wijaya Karya (Persero)
Up.
Dengan hormat,
Rp 285,256,595
Terbilang :
Demikian penawaran kami untuk menjadi periksa, sambil menunggu kabar baik dari
Bapak / Ibu. Atas perhatian dan kerjasama Bapak / Ibu kami ucapkan terima kasih.
Hormat kami,
PT Putra Sinartama Mandiri
cc. - Arsip
E. URAIAN HARGA SATUAN
c. Peletakan Pipa PVC diameter 4 ” tebal 5,5 mm selubung pasir (tanpa cor) Rp. 9,478
0.02000 ho Pekerja @Rp. 60,000.00 Rp. 1,200.00
0.01500 ho Tukang @Rp. 75,000.00 Rp. 1,125.00
0.00150 ho Mandor @Rp. 85,000.00 Rp. 127.50
——-
Rp. 2,452.50
Bahan :
0.00700 bh Climping brucket @Rp. 6,500.00 Rp. 45.50
0.00350 bh Stick @Rp. 3,500.00 Rp. 12.25
0.00130 bh Driving Caps @Rp. 2,800.00 Rp. 3.64
0.00250 kg Majun @Rp. 7,500.00 Rp. 18.75
0.01250 bh Liter spritus @Rp. 8,000.00 Rp. 100.00
0.02000 kg Lem PVC @Rp. 15,000.00 Rp. 300.00
110,000 m’ Pipa PVC 4″ 5,5 mm @Rp. 33,750.00 Rp. 37,125.00
Biaya ——
peletakan 37,605.14
Pipa per
meter
(c1+c2) Rp. 40,057.64
Rp. 9,903,934.85
Rp. 3,165,163.78
Rp. 30,636,178.81
Rp. 48,277,661.35
PEMBUATAN MANHOLE TYPE L HIS5
Rp. 42,708,975.50
Rp. 65,558,720.07
Rp. 47,889,221.42
a. Pembersihan/ pengecatan dinding MH, pengecatan vertical bearer, polling bolt, landasan tutup MH/tutup MH, pemasangan duct seal dan penggantian s
Upah
0.95000 ho Pekerja @ Rp. 60,000.00 Rp. 57,000.00
0.45000 ho Tukang Cat @ Rp. 75,000.00 Rp. 33,750.00
0.01500 ho Mandor @ Rp. 85,000.00 Rp. 1,275.00
———-
92,025.00
Bahan :
200,000 kg Cat Anti lumut @ Rp. 7,500.00 Rp. 15,000.00
0.20000 bh Kuas @ Rp. 2,500.00 Rp. 500.00
0.20000 bh Sendok dempul @ Rp. 2,500.00 Rp. 500.00
0.30000 klg Cat besi utk bearer @ Rp. 32,500.00 Rp. 9,750.00
0.20000 bh Sikat Baja @ Rp. 7,500.00 Rp. 1,500.00
0.20000 klg Duct seal @ Rp. 150,000.00 Rp. 30,000.00
150,000 klg Stopper @ Rp. 17,500.00 Rp. 26,250.00
200,000 hr Sewa pompa air @ Rp. 100,000.00 Rp. 200,000.00
———–
Biaya Rp. 283,500
pemeliharaa
n MH
(a1+a2) Rp. 375,525
HI (Kecil)
PEMELIHARAAN MANHOLE TYPE
a. Pembersihan/ pengecatan dinding MH, pengecatan vertical bearer, polling bolt, landasan tutup MH/tutup MH, pemasangan duct seal dan penggantian s
Upah
0.95000 ho Pekerja @ Rp. 60,000.00 Rp. 57,000.00
0.45000 ho Tukang Cat @ Rp. 75,000.00 Rp. 33,750.00
0.01500 ho Mandor @ Rp. 85,000.00 Rp. 1,275.00
Rp.
92,025.00
Bahan :
200,000 kg Cat Anti lumut @ Rp. 7,500.00 Rp. 15,000.00
0.20000 bh Kuas @ Rp. 2,500.00 Rp. 500.00
0.20000 bh Sendok dempul @ Rp. 2,500.00 Rp. 500.00
0.30000 klg Cat besi utk bearer @ Rp. 32,500.00 Rp. 9,750.00
0.20000 bh Sikat Baja @ Rp. 7,500.00 Rp. 1,500.00
0.20000 klg Duct seal @ Rp. 150,000.00 Rp. 30,000.00
150,000 klg Stopper @ Rp. 17,500.00 Rp. 26,250.00
200,000 hr Sewa pompa air @ Rp. 100,000.00 Rp. 200,000.00
——–
Biaya Rp. 283,500
pemeliharaa
n MH
(a1+a2) Rp. 375,525
a. Pembersihan/ pengecatan dinding MH, pengecatan vertical bearer, polling bolt, landasan tutup MH/tutup MH, pemasangan duct seal dan penggantian s
Upah
0.95000 ho Pekerja @ Rp. 60,000.00 Rp. 57,000.00
0.45000 ho Tukang Cat @ Rp. 75,000.00 Rp. 33,750.00
0.01500 ho Mandor @ Rp. 85,000.00 Rp. 1,275.00
————
92,025.00
Bahan :
200,000 kg Cat Anti lumut @ Rp. 7,500.00 Rp. 15,000.00
0.20000 bh Kuas @ Rp. 2,500.00 Rp. 500.00
0.20000 bh Sendok dempul @ Rp. 2,500.00 Rp. 500.00
0.30000 klg Cat besi utk bearer @ Rp. 32,500.00 Rp. 9,750.00
0.20000 bh Sikat Baja @ Rp. 7,500.00 Rp. 1,500.00
0.20000 klg Duct seal @ Rp. 150,000.00 Rp. 30,000.00
150,000 klg Stopper @ Rp. 17,500.00 Rp. 26,250.00
200,000 hr Sewa pompa air @ Rp. 100,000.00 Rp. 200,000.00
——–
Biaya Rp. 283,500
pemeliharaa
n MH
(a1+a2) Rp. 375,525
11,054
9,478
(c1)
(c2)
40,057.64
120,853.94
246,696.73
303,727.57
406,591.95
619,195.76
615,999.52
920,267.30
1,086,559.85
1,279,034.91
1,536,096.72
5,186,578.81
61,370,783.26
283,500
375,525
6,603,760.33
1,467,719.10
28,728,449.70
40,256,351.68
61,627,937.45
45,213,328.52
61,370,783.26
283,500
375,525
6,603,760.33
1,467,719.10
28,728,449.70
45,348,936.86
40,256,351.68
61,627,937.45
45,213,328.52
61,370,783.26
283,500
375,525
1 M' Pasang U-Ditch uk. 50x50x120 cm Tanpa Cover
HARGA
JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN SATUAN
Rp Rp
A TENAGA
Pekerja JAM 2.00 175,000 350,000
Tukang kayu JAM 0.50 185,000 92,500
Kepala Tukang JAM 0.05 200,000 10,000
Mandor JAM 0.01 215,000 2,150
JUMLAH TENAGA 454,650
B BAHAN
U.Dict UK 50 X 50 CM LBR 0.833 609,000 507,297
JUMLAH BAHAN 507,297
C PERALATAN
Alat bantu LS 1 45,000 45,000
HARGA
JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN SATUAN
Rp Rp
A TENAGA
Pekerja JAM 4.6669 21,875 102,088
Tukang kayu JAM 1.1169 25,000 27,923
Mandor JAM 1.1169 26,875 30,017
JUMLAH TENAGA 160,028
B BAHAN
U.Dict UK 150 X 150 CM LBR 1.00 1,200,000 1,200,000
JUMLAH BAHAN 1,200,000
C PERALATAN
Alat bantu LS 1.00 45,000 45,000
Crane on truck kap.10-15 ton JAM 0.3451 150,000 51,765
JUMLAH ALAT 96,765
HARGA
JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN SATUAN
Rp Rp
A TENAGA
Pekerja JAM 2.6250 21,875 57,422
Tukang kayu JAM 0.0875 25,000 2,188
Mandor JAM 0.0875 26,875 2,352
JUMLAH TENAGA 61,961
B BAHAN
TUTUP BETON PRACETAK UK.60 X LBR 1.00 - -
JUMLAH BAHAN -
C PERALATAN
Alat bantu LS 1.00 45,000 45,000
Crane on truck kap.10-15 ton JAM 0.04 - -
JUMLAH ALAT 45,000
HARGA
JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN SATUAN
Rp Rp
A TENAGA
Pekerja JAM 0.8835 21,875 19,327
Mandor JAM 0.1104 26,875 2,967
JUMLAH TENAGA 22,294
B BAHAN
Beton K.350 m3 1.05 - -
JUMLAH BAHAN -
C PERALATAN
Alat bantu LS 1.00 50,000 50,000
Concrete Vibrator JAM 0.4417 150,000 66,255
JUMLAH ALAT 116,255
HARGA
JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN SATUAN
Rp Rp
A TENAGA
Pekerja OH 0.6600 175,000 115,500
Tukang Kayu OH 0.3300 185,000 61,050
Kepala Tukang OH 0.0330 200,000 6,600
Mandor OH 0.0330 215,000 7,095
JUMLAH TENAGA 190,245
B BAHAN
Kayu Kelas II m3 0.03 4,000,000 120,000
Paku 5 - 12 cm kg 0.40 19,000 7,600
Minyak Begistisng ltr 0.20 25,000 5,000
Balok Kayu kelas II m3 0.02 5,000,000 100,000
Plywood tebal 12 mm lbr 0.35 250,000 87,500
Dolken Kayu uk.8-10 cm p.4 m btg 3.00 25,000 75,000
Penjaga Jarak/Begisting spacer bh 4.00 10,000 40,000
C PERALATAN
Alat bantu LS 1.00 50,000 50,000
JUMLAH ALAT 50,000
HARGA
JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN SATUAN
Rp Rp
A TENAGA
Pekerja OH 0.0095 175,000 1,663
Tukang Besi OH 0.0095 185,000 1,758
Kepala Tukang OH 0.0008 200,000 160
Mandor OH 0.0004 215,000 86
B BAHAN
Besi Beton kg 1.05 - -
Kawat Ikat kg 0.03 - -
JUMLAH BAHAN -
C PERALATAN
Alat bantu LS 1.00 2,000 2,000
JUMLAH ALAT 2,000
HARGA
JUMLAH HARGA
NO. URAIAN SATUAN VOLUME SATUAN
Rp Rp
GENERAL NOTES
2 The Contractor shall include and allow for all costs and
expenses for the proper execution and completion of
the Works.
Parking area
1 50mm thk compacted sand (Pasir urug) m2 732 118,333 50,000 168,333 123,220,000 225,000.00
2 80mm thk aerated concrete pavers m2 732 121,667 85,000 206,667 151,280,000 320,000.00
Footpath/Walkways
1 Plastic sheet m2 3,560 10,500 - 10,500 37,380,000 2,250.00
2 150mm thk concrete pavement with chamfered m3 3,560 118,333 50,000 168,333 599,266,667 225,000.00
edge
Concrete wheel stopper, overall size 250mm wide x
750mm long, fixed to concrete slabs including 2No. of
12mm diameter mild steel anchors with epoxy grouting,
as described (1 parking lot 2No. Stopper)
1 Car Park Lot (parkir mobil) nr 44 250,000 50,000 300,000 13,200,000 385,000.00
Collection Page
Note
Note
Note
Note
Note
Note
Total
2,600,000
62,475,000
26,980,000
53,650,000
5,550,000
5,370,000
7,500,000
87,000,000
212,100,000
121,000,000
60,500,000
78,600,000
29,200,000
4,050,000
82,550,000
25,520,000
Total
2,102,449,000
13,668,750
2,095,875,000
5,505,750
1,321,380,000
164,700,000
234,240,000
8,010,000
801,000,000
16,940,000
313,250,000
4,974,569,500
Total
173,625,000
-
11,000,000 209,000 (122x244cm)
6,600,000
24,000,000
27,600,000
10,500,000
11,800,000
6,250,000
13,500,000
7,450,000
7,900,000
16,400,000
9,000,000
58,200,000
32,100,000
149,500,000
25,000,000
12,900,000
68,000,000
28,300,000
31,300,000
65,600,000
15,300,000
16,250,000
17,100,000
35,900,000
18,600,000
58,500,000
21,000,000
21,200,000
47,500,000
78,000,000
81,000,000
112,000,000
58,000,000
30,000,000
62,000,000
64,000,000
Total
33,000,000
34,000,000
35,000,000
36,000,000
18,400,000
38,000,000
21,000,000
2,372,167,500
1,500,000,000.00
2,102,449,000.00
4,974,569,500.00
2,372,167,500.00
10,949,186,000
DAFTAR HARGA SATUAN UPAH KERJA
KABUPATEN BEKASI
TAHUN 2023
HARGA SAT
NO JENIS PEKERJA BANGUNAN SATUAN WAKTU
Rp.
110,000.00
120,000.00
165,000.00
175,000.00
175,000.00
175,000.00
250,000.00
250,000.00
225,000.00
550.00
500.00
69,000.00
1,380.00
85,000.00
5,500.00
4,000,000.00
5,000,000.00
5,000,000.00
5,000,000.00
5,000,000.00
5,000,000.00
6,500,000.00
4,500,000.00
4,500,000.00
4,500,000.00
10,500.00
9,000.00
25,000.00
RAP digunakan untuk menentukan jumlah material dan tenaga dalam pelaksanaan pembangunan.
1.139