Professional Documents
Culture Documents
K S Zamreen 00761734 Tciq Project
K S Zamreen 00761734 Tciq Project
Declaration: By submitting this assessment (Parts 1 – 4) for marking I declare that it is entirely my own work. I understand that falsely claiming that
the work is my own is malpractice and can lead to NEBOSH imposing severe penalties (see the NEBOSH Malpractice Policy for further information).
Important note: You must refer to the document ‘Unit IG2: risk assessment – Guidance and information for learners and Learning Partners’ while
completing all parts of this assessment. Your Learning Partner should provide you with a copy, but it can also be downloaded from the relevant
resources section for this qualification on the NEBOSH website.
Part 1: Background
I came to the conclusion that the current safeguards are insufficient; therefore, I proposed some
corrective measures and activities that may be taken to reduce the current risks using ILO
conventions and health and safety regulations.
2.VIBRATIONS JACK HAMMER • Due to constant • When using vibrating 1 week Site manager
OPERATORS AND vibration exposure, job equipment, the anti-vibration
Construction WORKERS. rotation is prevalent in mounting should be
equipment’s like the area but not employed.
grinding thorough.
7.FIRE ALL THE WORKERS • A designated area has • For welding, gas cutting, and 1 month Site manager
USING THE been made available grinding tasks, separate hot
Lack of fire EQUIPMENT, for the secure storage work booths should be
alarm systems NEIGHBOURING of gas cylinders constructed utilising fire-
and other WORKERS, resistant stands
firefighting SUPERVISORS, • Fire extinguishers are
equipment, hot ENGINEERS AND SITE • Mock drills should be 1 week Project
installed but not
works are VISITORS. conducted on safe manger
properly maintained.
carried out near evacuations.
flammable If there is no fire • Fire warden are • The best escape path should 1 week HSE manager
materials. detection and firefighting available for taking be clearly identified and kept
Spatters from hot systems then a small emergencies actions clear of obstructions.
work such as incident may cause
welding, grinding, catastrophic accidents. • Leather gloves, safety • Fire extinguishers should be 1 week Safety officer
gas cutting etc. The flammable materials boot, safety coverall, properly maintained and
are stored near hot welders’ goggles, high installed depending on the
working area. Fire can visibility safety vest and requirement.
lead to severe external welding helmets are • Generate an onsite 2 weeks Safety
and internal burns and provided. emergency action plan. manager
even death of a person
and may ignite other • Manual fire call points should 1 month Maintenance
combustible materials. be installed. manager
9.WORK WORKERS INVOLVED • Induction training and • Use fixed guards for 1 week Maintenance
EQUIPMENT IN THE OPERATION, inspection is done. protecting the workers from engineer
AND SUPERVISORS, rotating parts
MACHINERY CLEANING STAFFS • Gloves and safety • Conduct refresher trainings at 1 week Safety
ETC. helmets are provided. regular intervals. manager
10. SLIPS AND ALL PEDESTRIANS • Safety helmets and • Separate walkways should be 1 month Site manager
TRIPS (WORKERS, safety shoes are designed in the work place.
FOREMAN, FOREMAN, provided for workers.
Water, oil, or any VISITORS, ENGINEERS • Housekeeping shall be 2 weeks Site
other liquid on AND SITE MANAGERS • Proper illumination consistently throughout the supervisor
the ground; ETC.) during the night shift is site.
materials or provided. • Conduct toolbox talk before 1 week Safety officer
stones are Materials lying around • People can get the starting the shift.
strewn over the the workplace can create appropriate information
area; poor site a slip, trip, and fall about the site's layout
maintenance hazard, which could • Warning signs should be 2 weeks Safety officer
from a small map that installed
creates a danger result in fractures and is clearly displayed at
of injury. other serious injuries. the entrance area.
• All employees and other 2 weeks Site manager
members of the organisation
should wear non-slip shoes.
11. MOVEMENT COMPANY WORKERS, • The vehicles have a • Designated areas for 3 weeks Supervisor
OF PEOPLE CONTRACTORS, daily inspection system pedestrians should be made
AND VEHICLES VISITORS available.
12.SUBSTANCE WORKERS, FOREMAN • Company made a law • Purchase and use breathe 1 month Site manager
ABUSE AT AND SUPERVISORS. that strictly prohibit the analyser in cause of any
WORK use of alcohol and doubt.
Alcohol and drug abuse other drugs during • Proper guidance and 1 month Safety officer
Use of alcohols will cause workplace work time, but that is awareness should be
and other natural violence, which can not much effective in provided.
and synthetic result in minor and action.
drugs during severe injuries, shattered • Warning boards shall be 1 week Safety officer
work time. bones, and even installed
Legal arguments
The organisation has a legal duty or responsibility to protect their workers by providing a safe
working condition, a safe system of work, training, supervision, and competencies for staff. The
organisation has to follow rules and regulations implemented by the country to manage health and
safety in the workplace. As per article 16 of C-155, National Health and Safety Convention 1981,
and article 10 of R-164, Occupational Health and Safety Recommendation 1981, the employer has
to ensure the workplace equipment, machinery, and processes under control are free from hazards
and pose no risk to health. If there is any failure to implement these rules and regulations on the
work side, that can cause penalties and imprisonment for the concerned individual.
Specific legal arguments ILO C148, "Working Environment Convention 1971," specifies that the working environment shall
be kept free from any hazard related to air pollution, noise, and vibration.
As per article 16 of C155, the Occupational Health and Safety Convention of 1981, the employer
has to ensure the place of work equipment, machinery, and processes under its control are free
from hazards and without risk to health.
As per Article 10 of R 164, employees should provide necessary supervision, ensure hours of work
do not adversely affect their safety and health, and take measures to eliminate any physical or
mental fatigue.
By following these legal requirements, we can reduce the impact of hazards on workers and the
environment.
Consideration of likelihood AND severity On a construction site, the likelihood of injury or illness from continuous exposure to vibration is
very high. Once this disease occurs, of course, there is no cure. It would result in numbness.
• types of injury or ill health
chronic back pain, motion sickness, and visual disturbance
• number of workers at risk
• how often the activity is carried When considering severity, we can be categorised into four types.
out Minimal: no injury or damage occurred.
• how widespread the risk is
Minor: a minimal injury that required first aid
Major: injury required hospital treatment
Specific legal arguments Every worker who is exposed to electrical risks must have access to safety, as per ILO C167's
article 26. the laying and maintaining of electrical cables and apparatus on construction site shall be
governed by the technical rules and standards applied at the national level. And also, before the
construction is commenced and during the progress, adequate steps shall be taken to guard
against danger to workers from any live electrical cable or apparatus which is on the site. And also,
recommendation R175, article 9 states that, construction work should be planned, prepared and
undertaken in such a way that the risk liable to arise at the workplace are prevented as soon as
possible.
Consideration of likelihood AND severity Individuals may be hurt by electricity, and construction sites utilize a lot of electrical equipment for
things like cutting, welding, compaction, etc. The accident is quite likely to happen, and it will
• types of injury or ill health
probably be terrible. Burns, failure of the heart and other internal organs, and even death can result
• number of workers at risk from an electric shock. Daily labour is performed by about 35 employees. The workers will be at risk
• how often the activity is carried if sufficient upkeep is not provided. Supervisors and site engineers, as well as employees
out performing tasks requiring the use of electrical equipment, may be impacted.
• how widespread the risk is
How you will follow up on the risk I will set a reminder for each control measure and call the person in charge to inquire about the
assessment to check that the actions progress of implementation. I will physically inspect the location of that particular area and assess
have been carried out my new arrangement based on my risk assessments.
After that, I will conduct interviews with the site supervisor and project manager as well as collect
data after I receive input on any specific accident as a result of improved efforts, check accident