Kuwait Oil Company Integrity Management
Kuwait Oil Company Integrity Management
Jawad Akbar
OBJECTIVES
1. Introduction to KOC Operations
2. Causes of Equipment Breakdown
3. Stimulus
4. Integrity Management Development
5. IM KPI Basket & Implementation Plan
6. Summary
KOC Crude, Gas and Condensate Network
Arabian Gulf (MOE-E&W, North Kuwait )
Odorize Gas
RICH GAS RICH GAS BS-170 (GC-17, DZ) Old AGRP MAA LPG
Propane
GATHERING CENTRES FLARED BOOSTER STATIONS Shuaiba Butane
C3 , C4
RICH GAS North : BS 131
North : GCs 15, 23 & 25 ( & EPF) RICH GAS, BSs-131, 140 & 150
East : Injection
West : GCs West : East :
GCs 1, 2, 9, HP/LP BS 170 BS 140 GAS
17, 27 10, 11, FLARED ETHANE
16, 28 19, 20 RICH GAS LEAN FUEL GAS C2
South : GCs 3, 4, 6, 7, 8 & 21 & 22 Spillover C1
KGOC-Onshore South : BS 150 Manifold X
RICH
GCs 15, FUEL GAS BS-131
Effluent WATER
23 & 25 LEAN FUEL GAS,
Treatment Plant/s
LEAN FUEL GAS BSs-140, 150 & 170
South, East & West Kuwait GCs
WATER
Injection
North Kuwait Crude Supply to Doha Power Station
Plant/s
V-
Legend
Header South KEC
Crude Oil
STF
F/M Tank Farm via Gravity
Rich Gas Lines
Condensate 20” Eocene Line from Wafra
for Heavy Oil
32 Tanks, 6.7 MMSTB
Water
Seawater Oily Water
KNPC Refineries LOCAL
Lean Gas
Liquified Petroleum Gas (LPG) Ratawi Burgan / Eocene Crude Supply to Bitumen Plant
-Mina Al-Ahmadi (MAA),
-Mina Al-Abdullah (MAB), -Shuaiba.
PRODUCTS
Ethane Gas
Kuwait Natural Gas (KNG) EXPORT
Refined Petroleum Products Ratawi Burgan / Eocene Crude Export (Maximum 60 MBOPD)
SAT Export Terminal (SPM) Mina Al-Zour
Causes of Equipment Breakdown
Distribution of the Causes of Downtime of
a Gathering Center (Typical)
Root Cause Analysis of Incidents
Comprehensive List of Causes Parts
Management
Plant & Inherent Fire
Location Systems
Buildings Process Risk Protection
& Procedures
• How…
– Use the right PEOPLE
– doing the right things (PROCESSES)
– in the right way (BEHAVIOURS)
– Operate within the technical limits (pressure and
temperature) of the capability of the HARDWARE
Manpower Hazard
Leadership Evaluation In-plant
Accountability facilities
Awareness Management
& Authority of Change Pipelines &
Compliance associated
Skills & Emergency
Abilities works
Response
People Behaviours Processes Hardware
Issues….. Issues…. Facilities integrity
Wells and
Organisation & protective
Ethics Flow lines
systems
Direct hire Motivation
PC’s & Assurance Plant
Contractors Tolerance monitoring
Incident
& other
Trust Investigation
What Challenges Do we Face?
Facilities Design
And Construction
Asset Integrity Protective Systems
Management Strategy
Risk Assessment
and Management
Business Processes Information and
Documentation
Auditing, Assurance,
Measurements & CI
Procedures, Standards,& Practices
Accountability
KOC Integrity Management
People Process
Data Management
Ownership and & Documentation
Accountability
Hazards & Risk
Management
Competency Effective Integrity
Assurance Management of
Management Change
(11 Elements) Emergency
Management
Plant Incident
Investigation
Facility Design and Construction
Assessment &
Operations and Maintenance Continuous
Protective Systems Improvements
How Does Risk Management Work?
Separators
KPI Scorecard
Dehyradtion Separators PS/IM ELEMENT
Electrical Sub- Stations Export System 1. Hazard Evaluation
a. Number of outstanding HAZID / HAZOPs from schedule
Chemical Storage Condensate b. Percent assets/sites with hazard register in place
Systems c. Percent operating envelopes defined and used
Buildings Desalters 3. Mechanical Integrity
Water Handling
Glycol &
Proposed Workplan
a. Percent cathodic protection in compliance
Systems
Dehyradtion b. Leaks and spills per month
General Site c. Overdue Integrity Management related repairs
Electrical Sub- Stations
d. Percent corrosion inhibitor pumped versus plan
e. Number of inspection saved failures
Chemical Storage 4. Protective Systems
Buildings a. Overdue SCE inspections
b. Overrides, inhibits and interlocks
Water Handling c. Percent relief valves with overdue certification
Systems d. No. of SCE temporary equip. exceeding approved time limit
General Site 5. Competent People
a. Percent training completed versus plan
b. CMAS implementation
c%. ISSOW training completed
%
6. Incident Investigation
a. HIPO investigations completed & communicated in 24 hrs
7. Emergency Response
a. Spill drills completed versus planned
b. Contingency plans reviewed versus required
8. Performance Management & Assu rance
a. Number of Integrity Management audits completed
b. Number of OVP assessments completed
c. Number of excursions outside operating envelope
d. Number of routine maintenance issues outstanding
Improvement and Sustainability
Sustainable
Integrity
Assurance
Leadership
Behaviors
Integrity
Technical Integrity
Framework
Assessments
Fix-the-kit Total
Reliability
Time
Assess………………Fix………………. Sustain
Interrelationship between the Entities that influence the Asset
Integrity
DRAFT INTEGRITY MANAGEMENT IMPLEMENTATION PLAN
Five Year Rolling Plan Rev. 0
Protective Systems
All Protective Systems are identifed and in place as per risk
4.
assessments, fit-for-purpose, maintain over-ride/by-pass register and
SILA carried out as necessary
Competency Assurance
7. Adequate, qualified and competent workforce with appropriate
training programs alongwith assessment / evaluation system
Management of Change
MOC is applied to all temporary and permanent changes, ensure
8.
revision of all procedures / programs to reflect the changes and
confirm with pre-start up and post-implementation IM reviews
Emergency Management
All EM plans in place to address the full range of identified hazards
9.
and risks, adequate guidance and resources for mobilization with a
feed-back mechanism to ensure the plans are understood by all
Incident Investigation & Prevention
All Major and high potential incidents investigated, root causes
10. identified and published, all minor incidents investigated to capture
lessons learnt, all outcomes communicated to all and critical
equipments certified fit-for-purpose after any incident
Assessments & Continuous Improvements
KPI set to evaluate compliance and performance, audits and self-
11. assessments in place to confirm effectiveness and progress,
periodic IM reviews to absorb lessons learnt and to achieve a robust
integrity management
2007 2008 2009 2010 2011
IM Standard
Introduced
Introduction Implementation KOC’s Directorates
to IM in Assets Reorganization
Process
Asset IM KPI
Reports
2004 2006 2008 2010 2020
1.2 No. of review meetings held by the established IM Committee to discuss the IM
implementation issues and progress of action items
2. Assessments & Continuous Improvements
2.1 Number of IM related audits/self-assessments conducted per annum with follow-ups
to confirm the effectiveness and progress of the integrity management standard
3.3 Review of all projects for compliance with all the stipulated codes, standards and
procedures. (TS directorate)
KPIs
4. Hazards & Risk Management
4.1 Percentage of facilities covered under full Process Hazard Analysis (PHA), that is,
PHA carried out for the entire facility, including pipelines and ensuring defined safe
design envelope
4.2 Percentage of AIR/QRA amalgamated action plan recommendations closed
4.3 Percentage (%) of projects reviewed in the concept and FEED stage to ensure
incorporating Inherent Safe design. (TS directorate)
5. Protective Systems
5.1 Percentage of facilities with Register of Safety Critical Equipment (SCE) identified as
per KOC IM Guidelines (one per facility)
5.2 Percentage (%) of facilities where SIL assessment (safety integrity level) of the SCE
equipment are conducted to identify / verify the protective system requirements.
5.3 Percentage (%) of Overdue Safety Critical Work Orders (E&PD Directorate)
8. Management of Change
8.1 Percentage (%) of all changes that are carried out in compliance with KOC MOC
procedure.
9. Incident Investigation & Prevention
9.1 No. of lessons learnt/root causes related to IM issues from incident investigations
elsewhere absorbed and self-assessed for own operations to prevent occurrence of
similar incidents.
10. Emergency Management
10.1 Site specific emergency response procedure/plan (ERP) established to address the
full range of identified hazards and risks including the major accident risks.
10.2 Percentage (%) of recommendations from the mock ER drills implemented (some
drills need coordination with mutual aid)
10.3 Percentage(%) of emergency response equipments tested fit for purpose.
10.4 System in place to evaluate the head count at any given time at all facilities and
buildings.
11. Competency Assurance
T.B.A.