Professional Documents
Culture Documents
Work Out - OH With - Estimation
Work Out - OH With - Estimation
PROJECT NAME : Construction of water supply system at Samha, Al Bahya and Asheesh
Page 2 of 18
A/C
Description Quantity Period Unit Rate Amount Remarks
Code
a Compaction Test - - LS - -
b Trail Mix - - LS - -
c Concrete Cube Test - - LS - -
d Soil exploration - - LS - -
d Lab.testing charges - - LS - - -
2 Safety, Health and Welfare - - -
a First Aid kits - - LS 500.00 -
2 Medical - - LS 65.00 -
2 Coverall 4.00 - LS 45.00 -
b Emergency Escape Breathing Device - - LS 1,200.00 -
Other safety Consumables - Covid
b 1.00 1.00 LS 26,370.00 26,370.00
Expenses amd miscelleneous
House Keeping 1.00 - LS 500.00 -
Site provision 1.00 - LS 500.00 -
3 Floor Protection - - ls - -
a Documentation 1.00 - LS 500.00 - -
4 Electricity, Water, Drainage & Telephone - - - -
1 Lighting and Power - - -
a Cables, MDB,DB & Connection Charges - - LS - -
2 Provision of Water - - -
a Provision of Water Tank, Pumps - - LS - -
3 Provision of sanitation - - -
Drainage Charges
a - - LS - -
(Disposal by Tankers)
4 Telephone & Fax Monthly Charges - - -
a 889061 Internet Charges 1.00 - LS 750.00 -
b 89063 Fax Charges - - LS - -
c Mobile Phone Charges 2.00 - 1.00 50.00 -
5 Demobilization of all Temporary Facilities - - - -
Page 3 of 18
SITE OVER HEAD
SRC
Period 20k above - 15% Salary including
A/C Food &
Sl. No. Code Description Nos in Basic Salary Take Home 10 k - 20 k - 23% Accom. SRC and F&A per Total Amount Remarks
months 10k below - 26% month
1.7 Supply and installation of addc water supply piping from water meter to tank LSM 1 580.00 180.00 400.00 180.00 400.00 - - - 580.00 858.00
Installation and Final connection to sanitary fixtures as per dwg at service
1.8 LSM 1 600.00 550.00 50.00 - 550.00 50.00 - - - 600.00 888.00
area
1.9 other items not mentioned in BOQ but required to complete the work LSM 1 1,087.50 337.50 750.00 - 337.50 750.00 - - - 1,087.50 1,610.00
2 DRAINAGE SYSTEM
Supply, installation Testing and commissioning of Drainage system as
per below BOQ and in accordance with drawings.
Note:
All materials approval required prior to installation
Supply and installation of Underground Sewarage Fiber glass tank 1500 US
2.1 gallon, SIZE:2.89x1.82x1.80m as per the drawing and authority standards No 4 5,250.00 1,750.00 3,500.00 - 7,000.00 14,000.00 - - - 21,000.00 31,080.00
( Service area)
Supply and installation of Underground Sewarage Fiber glass tank 3000 US
2.2 gallon, SIZE:v4x2.21x2.36m as per the standards and authority standards No 4 7,500.00 2,500.00 5,000.00 - 10,000.00 20,000.00 - - - 30,000.00 44,400.00
( Main villa)
2.3 Under ground Upvc drainage pipes ( Service area only)
2.3.1 150MM dia UPVC class 16 between manholes mtr 120 108.75 33.75 75.00 - 4,050.00 9,000.00 - - - 13,050.00 19,314.00
2.3.2 100MM dia upvc under ground drainage pipe mtr 100 101.50 31.50 70.00 - 3,150.00 7,000.00 - - - 10,150.00 15,022.00
2.3.3 80MM dia upvc under ground drainage pipes mtr 100 94.25 29.25 65.00 - 2,925.00 6,500.00 - - - 9,425.00 13,949.00
2.3.4 50mm , 40mm dia as required as per drawing LS 1 870.00 270.00 600.00 - 270.00 600.00 - - - 870.00 1,288.00
2.3.5 vent pipe as per drawing and as per authority regulations LS 1 290.00 90.00 200.00 - 90.00 200.00 - - - 290.00 429.00
2.3.6 Final connection to sanitary fixtures and floor traps as per dwg LS 1 362.50 112.50 250.00 - 112.50 250.00 - - - 362.50 537.00
2.4 60x60 MH cover Heavy duty Ductile iron (Dranage label) nos 12 800.00 50.00 750.00 - 600.00 9,000.00 - - - 9,600.00 14,208.00
2.5 30x30 Gully trap MH cover Heavy duty Ductile iron nos 12 475.00 25.00 450.00 - 300.00 5,400.00 - - - 5,700.00 8,436.00
2.6 Channel drating stainless steel 3000x 300mm nos 4 3,570.00 70.00 3,500.00 - 280.00 14,000.00 - - - 14,280.00 21,134.00
2.7 Channel drating stainless steel 1500x300mm nos 4 2,550.00 50.00 2,500.00 - 200.00 10,000.00 - - - 10,200.00 15,096.00
2.8 Rain water outlet and necessary piping with free discharge nos 20 437.50 87.50 350.00 - 1,750.00 7,000.00 - - - 8,750.00 12,950.00
2.9 other items not mentioned in BOQ but required to complete the work LS 1 652.50 202.50 450.00 - 202.50 450.00 - - - 652.50 966.00
Al Asheesh
1 WATER SUPPLY SYSTEM
6 of 18
QF TEND-O3
Sl No. Description UNIT QTY Unit rates L M SC(L) SC(LM) Man Power Material SC(L) SC(LM) Others Total cost To quote Prices
Supply, installation Testing and commissioning of Water supply system
as per below BOQ and in accordance with drawings.
7 of 18
QF TEND-O3
PROJECT NAME : Construction of water supply system at Samha, Al Bahya and Asheesh
Sl No. Description UNIT QTY Unit rates To quote Prices
Materials and Services
Materials and Services - Al Samha Green House
1 WATER SUPPLY SYSTEM
Supply, installation Testing and commissioning of Water supply system
as per below BOQ and in accordance with drawings.
1.7 Supply and installation of addc water supply piping from water meter to tank LSM 1 702.00 702.00
Installation and Final connection to sanitary fixtures as per dwg at service
1.8 LSM 1 726.00 726.00
area
1.9 other items not mentioned in BOQ but required to complete the work LSM 1 1,316.00 1,316.00
2 DRAINAGE SYSTEM -
Supply, installation Testing and commissioning of Drainage system as
per below BOQ and in accordance with drawings.
-
Note:
All materials approval required prior to installation
Supply and installation of Underground Sewarage Fiber glass tank 1500 US
2.1 gallon, SIZE:2.89x1.82x1.80m as per the drawing and authority standards No 4 6,352.50 25,410.00
( Service area)
Supply and installation of Underground Sewarage Fiber glass tank 3000 US
2.2 gallon, SIZE:v4x2.21x2.36m as per the standards and authority standards No 4 9,075.00 36,300.00
( Main villa)
2.3 Under ground Upvc drainage pipes ( Service area only) -
2.3.1 150MM dia UPVC class 16 between manholes mtr 120 131.59 15,790.80
2.3.2 100MM dia upvc under ground drainage pipe mtr 100 122.82 12,282.00
2.3.3 80MM dia upvc under ground drainage pipes mtr 100 114.04 11,404.00
2.3.4 50mm , 40mm dia as required as per drawing LS 1 1,053.00 1,053.00
2.3.5 vent pipe as per drawing and as per authority regulations LS 1 351.00 351.00
2.3.6 Final connection to sanitary fixtures and floor traps as per dwg LS 1 439.00 439.00
2.4 60x60 MH cover Heavy duty Ductile iron (Dranage label) nos 12 968.00 11,616.00
2.5 30x30 Gully trap MH cover Heavy duty Ductile iron nos 12 574.75 6,897.00
2.6 Channel drating stainless steel 3000x 300mm nos 4 4,319.75 17,279.00
2.7 Channel drating stainless steel 1500x300mm nos 4 3,085.50 12,342.00
2.8 Rain water outlet and necessary piping with free discharge nos 20 529.40 10,588.00
2.9 other items not mentioned in BOQ but required to complete the work LS 1 790.00 790.00
Al Asheesh -
1 WATER SUPPLY SYSTEM -
8 of 18
QF TEND-O3
Sl No. Description UNIT QTY Unit rates To quote Prices
Supply, installation Testing and commissioning of Water supply system
as per below BOQ and in accordance with drawings.
-
Note: All materials approval required prior to installation
1.1 WATER PUMPS -
Make up water booster pump set with pressure vessel and VFD.
(1 duty
+ 1 Standby)
Capacity - 4 L/S at 35 mtr head,
1.1.1 Set 1 28,537.00 28,537.00
Pressure vessel capacity -100L ,
Automatic control panel with VFD.
Stainless steel header with Flexible coupling and Strianer to
be included in pump assembly.
Domestic water booster pump set with pressure vessel and VFD.
(1 duty + 1
Standby)
Capacity - 2 L/S at 35 mtr head,
1.1.2 Set 1 24,975.00 24,975.00
Pressure vessel capacity -100L ,
Automatic control panel with VFD.
Stainless steel header with Flexible coupling and Strianer to be
included in pump assembly.
1.2 SUPPLY INSTALLATION OF WATER TANK -
4 LAYER POLYCON WATER TANK 2000 GALLON WITH ALL
No 1 4,689.00 4,689.00
ACCESSORIES
SUPPLY INSTALLATION TESTING AND COMMISSIONIGN OF
1.3 -
UPVC CLASS 16 PIPES AND FITTINGS
1.3.1 UPVC PIPE 110MM, CLASS 16 MTR 16 43.88 702.08
1.3.2 UPVC PIPE 90MM, CLASS 16 MTR 20 42.10 842.00
1.3.3 UPVC PIPE 75MM, CLASS 16 MTR 65 38.60 2,509.00
1.3.4 UPVC PIPE 63MM, CLASS 16 ( include main villa supply) MTR 400 36.85 14,740.00
1.3.5 UPVC PIPE 50MM, CLASS 16 MTR 30 35.10 1,053.00
1.3.6 GATE VALVE 4" FLANGE TYPE NOS 1 1,210.00 1,210.00
1.3.7 GATE VALVE 3" FLANGE TYPE NOS 4 949.75 3,799.00
1.3.8 GATE VALVE 2" THREADED NOS 6 683.67 4,102.02
1.3.9 GATE VALVE 1-1/2" THREADED NOS 6 574.83 3,448.98
1.3.10 FLOAT VALVE 4" PILOT OPERATED TYPE NOS 1 1,573.00 1,573.00
1.3.11 FLOAT VALVE 1-1/2" THREADED NOS 4 707.75 2,831.00
1.3.12 FLOAT VALVE 2" THREADED NOS 1 768.00 768.00
1.3.13 OTHER FITTINGS AS PER DWG LS 1 908.00 908.00
1.4 MANHOLE COVER 45X45CM NOS 1 968.00 968.00
Final connection and installation sanitary fixtures and floor traps as per dwg
1.5 LS 1 756.00 756.00
at service area
Supply and installation of addc water supply piping from water meter cabinet
1.6 LS 1 817.00 817.00
to tank as per approved drawing and addc regulations
2 DRAINAGE SYSTEM -
Supply, installation Testing and commissioning of Drainage system as
per below BOQ and in accordance with drawings.
-
Note:
All materials approval required prior to installation
Supply and installation of Underground Sewarage Fiber glass tank 1500 US
2.1 gallon, SIZE:2.89x1.82x1.80m as per the drawing and authority standards No 1 6,564.00 6,564.00
( Service area)
Supply and installation of Underground Sewarage Fiber glass tank 3000 US
2.2 gallon, SIZE:v4x2.21x2.36m as per the standards and authority standards No 1 9,378.00 9,378.00
( Main villa)
2.3 Under ground Upvc drainage pipes ( Service area only) -
2.3.1 150MM dia UPVC class 16 between manholes mtr 35 131.60 4,606.00
2.3.2 100MM dia upvc under ground drainage pipe mtr 25 122.80 3,070.00
2.3.3 80MM dia upvc under ground drainage pipes mtr 20 114.05 2,281.00
2.3.4 50mm , 40mm dia as required as per drawing LS 1 105.00 105.00
2.3.5 vent pipe as per drawing and as per authority regulations LS 1 263.00 263.00
2.3.6 Final connection to sanitary fixtures and floor traps as per dwg LS 1 790.00 790.00
2.4 60x60 MH cover Heavy duty Ductile iron (Dranage label) nos 4 1,316.00 5,264.00
2.5 30x30 Gully trap MH cover Heavy duty Ductile iron nos 3 438.67 1,316.01
2.6 Channel drating stainless steel 3000x 300mm nos 1 4,320.00 4,320.00
2.7 Channel drating stainless steel 1500x300mm nos - -
2.8 Rain water outlet and necessary piping with free discharge nos 5 847.00 4,235.00
2.9 other items not mentioned in BOQ but required to complete the work LS 1 726.00 726.00
Total 982,316.94
9 of 18
QF TEND-O3
PROJECT NAME : Construction of water supply system at Samha, Al Bahya and Asheesh
Sl No. Description UNIT QTY Unit rates To quote Prices
Materials and Services
Materials and Services - Al Samha Green House
1 WATER SUPPLY SYSTEM
Supply, installation Testing and commissioning of Water supply system
as per below BOQ and in accordance with drawings.
1.7 Supply and installation of addc water supply piping from water meter to tank LSM 1 1,000.00 1,000.00
Installation and Final connection to sanitary fixtures as per dwg at service
1.8 LSM 1 1,000.00 1,000.00
area
1.9 other items not mentioned in BOQ but required to complete the work LSM 1 2,000.00 2,000.00
2 DRAINAGE SYSTEM -
Supply, installation Testing and commissioning of Drainage system as
per below BOQ and in accordance with drawings.
-
Note:
All materials approval required prior to installation
Supply and installation of Underground Sewarage Fiber glass tank 1500 US
2.1 gallon, SIZE:2.89x1.82x1.80m as per the drawing and authority standards No 4 6,355.00 25,420.00
( Service area)
Supply and installation of Underground Sewarage Fiber glass tank 3000 US
2.2 gallon, SIZE:v4x2.21x2.36m as per the standards and authority standards No 4 9,075.00 36,300.00
( Main villa)
2.3 Under ground Upvc drainage pipes ( Service area only) -
2.3.1 150MM dia UPVC class 16 between manholes mtr 120 132.00 15,840.00
2.3.2 100MM dia upvc under ground drainage pipe mtr 100 123.00 12,300.00
2.3.3 80MM dia upvc under ground drainage pipes mtr 100 115.00 11,500.00
2.3.4 50mm , 40mm dia as required as per drawing LS 1 1,053.00 1,053.00
2.3.5 vent pipe as per drawing and as per authority regulations LS 1 351.00 351.00
2.3.6 Final connection to sanitary fixtures and floor traps as per dwg LS 1 439.00 439.00
2.4 60x60 MH cover Heavy duty Ductile iron (Dranage label) nos 12 968.00 11,616.00
2.5 30x30 Gully trap MH cover Heavy duty Ductile iron nos 12 575.00 6,900.00
2.6 Channel drating stainless steel 3000x 300mm nos 4 4,320.00 17,280.00
2.7 Channel drating stainless steel 1500x300mm nos 4 3,090.00 12,360.00
2.8 Rain water outlet and necessary piping with free discharge nos 20 530.00 10,600.00
2.9 other items not mentioned in BOQ but required to complete the work LS 1 790.00 790.00
Al Asheesh -
1 WATER SUPPLY SYSTEM -
10 of 18
QF TEND-O3
Sl No. Description UNIT QTY Unit rates To quote Prices
Supply, installation Testing and commissioning of Water supply system
as per below BOQ and in accordance with drawings.
-
Note: All materials approval required prior to installation
1.1 WATER PUMPS -
Make up water booster pump set with pressure vessel and VFD.
(1 duty
+ 1 Standby)
Capacity - 4 L/S at 35 mtr head,
1.1.1 Set 1 29,500.00 29,500.00
Pressure vessel capacity -100L ,
Automatic control panel with VFD.
Stainless steel header with Flexible coupling and Strianer to
be included in pump assembly.
Domestic water booster pump set with pressure vessel and VFD.
(1 duty + 1
Standby)
Capacity - 2 L/S at 35 mtr head,
1.1.2 Set 1 26,500.00 26,500.00
Pressure vessel capacity -100L ,
Automatic control panel with VFD.
Stainless steel header with Flexible coupling and Strianer to be
included in pump assembly.
1.2 SUPPLY INSTALLATION OF WATER TANK -
4 LAYER POLYCON WATER TANK 2000 GALLON WITH ALL
No 1 5,500.00 5,500.00
ACCESSORIES
SUPPLY INSTALLATION TESTING AND COMMISSIONIGN OF
1.3 -
UPVC CLASS 16 PIPES AND FITTINGS
1.3.1 UPVC PIPE 110MM, CLASS 16 MTR 16 85.00 1,360.00
1.3.2 UPVC PIPE 90MM, CLASS 16 MTR 20 84.00 1,680.00
1.3.3 UPVC PIPE 75MM, CLASS 16 MTR 65 73.00 4,745.00
1.3.4 UPVC PIPE 63MM, CLASS 16 ( include main villa supply) MTR 400 70.00 28,000.00
1.3.5 UPVC PIPE 50MM, CLASS 16 MTR 30 45.00 1,350.00
1.3.6 GATE VALVE 4" FLANGE TYPE NOS 1 1,210.00 1,210.00
1.3.7 GATE VALVE 3" FLANGE TYPE NOS 4 950.00 3,800.00
1.3.8 GATE VALVE 2" THREADED NOS 6 690.00 4,140.00
1.3.9 GATE VALVE 1-1/2" THREADED NOS 6 580.00 3,480.00
1.3.10 FLOAT VALVE 4" PILOT OPERATED TYPE NOS 1 1,573.00 1,573.00
1.3.11 FLOAT VALVE 1-1/2" THREADED NOS 4 708.00 2,832.00
1.3.12 FLOAT VALVE 2" THREADED NOS 1 768.00 768.00
1.3.13 OTHER FITTINGS AS PER DWG LS 1 908.00 908.00
1.4 MANHOLE COVER 45X45CM NOS 1 968.00 968.00
Final connection and installation sanitary fixtures and floor traps as per dwg
1.5 LS 1 756.00 756.00
at service area
Supply and installation of addc water supply piping from water meter cabinet
1.6 LS 1 817.00 817.00
to tank as per approved drawing and addc regulations
2 DRAINAGE SYSTEM -
Supply, installation Testing and commissioning of Drainage system as
per below BOQ and in accordance with drawings.
-
Note:
All materials approval required prior to installation
Supply and installation of Underground Sewarage Fiber glass tank 1500 US
2.1 gallon, SIZE:2.89x1.82x1.80m as per the drawing and authority standards No 1 6,564.00 6,564.00
( Service area)
Supply and installation of Underground Sewarage Fiber glass tank 3000 US
2.2 gallon, SIZE:v4x2.21x2.36m as per the standards and authority standards No 1 9,378.00 9,378.00
( Main villa)
2.3 Under ground Upvc drainage pipes ( Service area only) -
2.3.1 150MM dia UPVC class 16 between manholes mtr 35 132.00 4,620.00
2.3.2 100MM dia upvc under ground drainage pipe mtr 25 123.00 3,075.00
2.3.3 80MM dia upvc under ground drainage pipes mtr 20 115.00 2,300.00
2.3.4 50mm , 40mm dia as required as per drawing LS 1 105.00 105.00
2.3.5 vent pipe as per drawing and as per authority regulations LS 1 263.00 263.00
2.3.6 Final connection to sanitary fixtures and floor traps as per dwg LS 1 790.00 790.00
2.4 60x60 MH cover Heavy duty Ductile iron (Dranage label) nos 4 1,316.00 5,264.00
2.5 30x30 Gully trap MH cover Heavy duty Ductile iron nos 3 440.00 1,320.00
2.6 Channel drating stainless steel 3000x 300mm nos 1 4,320.00 4,320.00
2.7 Channel drating stainless steel 1500x300mm nos - -
2.8 Rain water outlet and necessary piping with free discharge nos 5 847.00 4,235.00
2.9 other items not mentioned in BOQ but required to complete the work LS 1 726.00 726.00
Total 1,157,268.00
11 of 18
QF TEND-O3
PROJECT NAME : Construction of water supply system at Samha, Al Bahya and Asheesh
Sl No. Description UNIT QTY Unit rates To quote Prices
Materials and Services
Materials and Services - Al Samha Green House
1 WATER SUPPLY SYSTEM
Supply, installation Testing and commissioning of Water supply system
as per below BOQ and in accordance with drawings.
1.7 Supply and installation of addc water supply piping from water meter to tank LSM 1 1,500.00 1,500.00
Installation and Final connection to sanitary fixtures as per dwg at service
1.8 LSM 1 1,500.00 1,500.00
area
1.9 other items not mentioned in BOQ but required to complete the work LSM 1 2,000.00 2,000.00
2 DRAINAGE SYSTEM -
Supply, installation Testing and commissioning of Drainage system as
per below BOQ and in accordance with drawings.
-
Note:
All materials approval required prior to installation
Supply and installation of Underground Sewarage Fiber glass tank 1500 US
2.1 gallon, SIZE:2.89x1.82x1.80m as per the drawing and authority standards No 4 7,500.00 30,000.00
( Service area)
Supply and installation of Underground Sewarage Fiber glass tank 3000 US
2.2 gallon, SIZE:v4x2.21x2.36m as per the standards and authority standards No 4 10,000.00 40,000.00
( Main villa)
2.3 Under ground Upvc drainage pipes ( Service area only) -
2.3.1 150MM dia UPVC class 16 between manholes mtr 120 132.00 15,840.00
2.3.2 100MM dia upvc under ground drainage pipe mtr 100 123.00 12,300.00
2.3.3 80MM dia upvc under ground drainage pipes mtr 100 115.00 11,500.00
2.3.4 50mm , 40mm dia as required as per drawing LS 1 1,500.00 1,500.00
2.3.5 vent pipe as per drawing and as per authority regulations LS 1 351.00 351.00
2.3.6 Final connection to sanitary fixtures and floor traps as per dwg LS 1 439.00 439.00
2.4 60x60 MH cover Heavy duty Ductile iron (Dranage label) nos 12 968.00 11,616.00
2.5 30x30 Gully trap MH cover Heavy duty Ductile iron nos 12 575.00 6,900.00
2.6 Channel drating stainless steel 3000x 300mm nos 4 4,320.00 17,280.00
2.7 Channel drating stainless steel 1500x300mm nos 4 3,090.00 12,360.00
2.8 Rain water outlet and necessary piping with free discharge nos 20 530.00 10,600.00
2.9 other items not mentioned in BOQ but required to complete the work LS 1 790.00 790.00
Al Asheesh -
1 WATER SUPPLY SYSTEM -
12 of 18
QF TEND-O3
Sl No. Description UNIT QTY Unit rates To quote Prices
Supply, installation Testing and commissioning of Water supply system
as per below BOQ and in accordance with drawings.
-
Note: All materials approval required prior to installation
1.1 WATER PUMPS -
Make up water booster pump set with pressure vessel and VFD.
(1 duty
+ 1 Standby)
Capacity - 4 L/S at 35 mtr head,
1.1.1 Set 1 29,500.00 29,500.00
Pressure vessel capacity -100L ,
Automatic control panel with VFD.
Stainless steel header with Flexible coupling and Strianer to
be included in pump assembly.
Domestic water booster pump set with pressure vessel and VFD.
(1 duty + 1
Standby)
Capacity - 2 L/S at 35 mtr head,
1.1.2 Set 1 26,500.00 26,500.00
Pressure vessel capacity -100L ,
Automatic control panel with VFD.
Stainless steel header with Flexible coupling and Strianer to be
included in pump assembly.
1.2 SUPPLY INSTALLATION OF WATER TANK -
4 LAYER POLYCON WATER TANK 2000 GALLON WITH ALL
No 1 6,000.00 6,000.00
ACCESSORIES
SUPPLY INSTALLATION TESTING AND COMMISSIONIGN OF
1.3 -
UPVC CLASS 16 PIPES AND FITTINGS
1.3.1 UPVC PIPE 110MM, CLASS 16 MTR 16 85.00 1,360.00
1.3.2 UPVC PIPE 90MM, CLASS 16 MTR 20 84.00 1,680.00
1.3.3 UPVC PIPE 75MM, CLASS 16 MTR 65 73.00 4,745.00
1.3.4 UPVC PIPE 63MM, CLASS 16 ( include main villa supply) MTR 400 70.00 28,000.00
1.3.5 UPVC PIPE 50MM, CLASS 16 MTR 30 45.00 1,350.00
1.3.6 GATE VALVE 4" FLANGE TYPE NOS 1 1,210.00 1,210.00
1.3.7 GATE VALVE 3" FLANGE TYPE NOS 4 950.00 3,800.00
1.3.8 GATE VALVE 2" THREADED NOS 6 690.00 4,140.00
1.3.9 GATE VALVE 1-1/2" THREADED NOS 6 580.00 3,480.00
1.3.10 FLOAT VALVE 4" PILOT OPERATED TYPE NOS 1 1,573.00 1,573.00
1.3.11 FLOAT VALVE 1-1/2" THREADED NOS 4 708.00 2,832.00
1.3.12 FLOAT VALVE 2" THREADED NOS 1 768.00 768.00
1.3.13 OTHER FITTINGS AS PER DWG LS 1 908.00 908.00
1.4 MANHOLE COVER 45X45CM NOS 1 968.00 968.00
Final connection and installation sanitary fixtures and floor traps as per dwg
1.5 LS 1 756.00 756.00
at service area
Supply and installation of addc water supply piping from water meter cabinet
1.6 LS 1 817.00 817.00
to tank as per approved drawing and addc regulations
2 DRAINAGE SYSTEM -
Supply, installation Testing and commissioning of Drainage system as
per below BOQ and in accordance with drawings.
-
Note:
All materials approval required prior to installation
Supply and installation of Underground Sewarage Fiber glass tank 1500 US
2.1 gallon, SIZE:2.89x1.82x1.80m as per the drawing and authority standards No 1 7,500.00 7,500.00
( Service area)
Supply and installation of Underground Sewarage Fiber glass tank 3000 US
2.2 gallon, SIZE:v4x2.21x2.36m as per the standards and authority standards No 1 10,000.00 10,000.00
( Main villa)
2.3 Under ground Upvc drainage pipes ( Service area only) -
2.3.1 150MM dia UPVC class 16 between manholes mtr 35 132.00 4,620.00
2.3.2 100MM dia upvc under ground drainage pipe mtr 25 123.00 3,075.00
2.3.3 80MM dia upvc under ground drainage pipes mtr 20 115.00 2,300.00
2.3.4 50mm , 40mm dia as required as per drawing LS 1 105.00 105.00
2.3.5 vent pipe as per drawing and as per authority regulations LS 1 263.00 263.00
2.3.6 Final connection to sanitary fixtures and floor traps as per dwg LS 1 790.00 790.00
2.4 60x60 MH cover Heavy duty Ductile iron (Dranage label) nos 4 1,316.00 5,264.00
2.5 30x30 Gully trap MH cover Heavy duty Ductile iron nos 3 440.00 1,320.00
2.6 Channel drating stainless steel 3000x 300mm nos 1 4,320.00 4,320.00
2.7 Channel drating stainless steel 1500x300mm nos - -
2.8 Rain water outlet and necessary piping with free discharge nos 5 847.00 4,235.00
2.9 other items not mentioned in BOQ but required to complete the work LS 1 726.00 726.00
Total 1,209,413.00
13 of 18
QF TEND-O3
PROJECT NAME : Construction of water supply system at Samha, Al Bahya and Asheesh
Sl No. Description UNIT QTY Unit rates To quote Prices
Materials and Services
Materials and Services - Al Samha Green House
1 WATER SUPPLY SYSTEM
Supply, installation Testing and commissioning of Water supply system
as per below BOQ and in accordance with drawings.
1.7 Supply and installation of addc water supply piping from water meter to tank LSM 1 1,500.00 1,500.00
Installation and Final connection to sanitary fixtures as per dwg at service
1.8 LSM 1 1,500.00 1,500.00
area
1.9 other items not mentioned in BOQ but required to complete the work LSM 1 2,000.00 2,000.00
2 DRAINAGE SYSTEM -
Supply, installation Testing and commissioning of Drainage system as
per below BOQ and in accordance with drawings.
-
Note:
All materials approval required prior to installation
Supply and installation of Underground Sewarage Fiber glass tank 1500 US
2.1 gallon, SIZE:2.89x1.82x1.80m as per the drawing and authority standards No 4 7,500.00 30,000.00
( Service area)
Supply and installation of Underground Sewarage Fiber glass tank 3000 US
2.2 gallon, SIZE:v4x2.21x2.36m as per the standards and authority standards No 4 10,000.00 40,000.00
( Main villa)
2.3 Under ground Upvc drainage pipes ( Service area only) -
2.3.1 150MM dia UPVC class 16 between manholes mtr 120 132.00 15,840.00
2.3.2 100MM dia upvc under ground drainage pipe mtr 100 123.00 12,300.00
2.3.3 80MM dia upvc under ground drainage pipes mtr 100 115.00 11,500.00
2.3.4 50mm , 40mm dia as required as per drawing LS 1 1,500.00 1,500.00
2.3.5 vent pipe as per drawing and as per authority regulations LS 1 351.00 351.00
2.3.6 Final connection to sanitary fixtures and floor traps as per dwg LS 1 439.00 439.00
2.4 60x60 MH cover Heavy duty Ductile iron (Dranage label) nos 12 968.00 11,616.00
2.5 30x30 Gully trap MH cover Heavy duty Ductile iron nos 12 575.00 6,900.00
2.6 Channel drating stainless steel 3000x 300mm nos 4 4,320.00 17,280.00
2.7 Channel drating stainless steel 1500x300mm nos 4 3,090.00 12,360.00
2.8 Rain water outlet and necessary piping with free discharge nos 20 530.00 10,600.00
2.9 other items not mentioned in BOQ but required to complete the work LS 1 790.00 790.00
Total 866,178.00
Materials and Services - Al Asheesh -
14 of 18
QF TEND-O3
Sl No. Description UNIT QTY Unit rates To quote Prices
1 WATER SUPPLY SYSTEM -
Supply, installation Testing and commissioning of Water supply system
as per below BOQ and in accordance with drawings.
-
Note: All materials approval required prior to installation
1.1 WATER PUMPS -
Make up water booster pump set with pressure vessel and VFD.
(1 duty
+ 1 Standby)
Capacity - 4 L/S at 35 mtr head,
1.1.1 Set 1 29,500.00 29,500.00
Pressure vessel capacity -100L ,
Automatic control panel with VFD.
Stainless steel header with Flexible coupling and Strianer to
be included in pump assembly.
Domestic water booster pump set with pressure vessel and VFD.
(1 duty + 1
Standby)
Capacity - 2 L/S at 35 mtr head,
1.1.2 Set 1 26,500.00 26,500.00
Pressure vessel capacity -100L ,
Automatic control panel with VFD.
Stainless steel header with Flexible coupling and Strianer to be
included in pump assembly.
1.2 SUPPLY INSTALLATION OF WATER TANK -
4 LAYER POLYCON WATER TANK 2000 GALLON WITH ALL
No 1 6,000.00 6,000.00
ACCESSORIES
SUPPLY INSTALLATION TESTING AND COMMISSIONIGN OF
1.3 -
UPVC CLASS 16 PIPES AND FITTINGS
1.3.1 UPVC PIPE 110MM, CLASS 16 MTR 16 85.00 1,360.00
1.3.2 UPVC PIPE 90MM, CLASS 16 MTR 20 84.00 1,680.00
1.3.3 UPVC PIPE 75MM, CLASS 16 MTR 65 73.00 4,745.00
1.3.4 UPVC PIPE 63MM, CLASS 16 ( include main villa supply) MTR 400 70.00 28,000.00
1.3.5 UPVC PIPE 50MM, CLASS 16 MTR 30 45.00 1,350.00
1.3.6 GATE VALVE 4" FLANGE TYPE NOS 1 1,210.00 1,210.00
1.3.7 GATE VALVE 3" FLANGE TYPE NOS 4 950.00 3,800.00
1.3.8 GATE VALVE 2" THREADED NOS 6 690.00 4,140.00
1.3.9 GATE VALVE 1-1/2" THREADED NOS 6 580.00 3,480.00
1.3.10 FLOAT VALVE 4" PILOT OPERATED TYPE NOS 1 1,573.00 1,573.00
1.3.11 FLOAT VALVE 1-1/2" THREADED NOS 4 708.00 2,832.00
1.3.12 FLOAT VALVE 2" THREADED NOS 1 768.00 768.00
1.3.13 OTHER FITTINGS AS PER DWG LS 1 908.00 908.00
1.4 MANHOLE COVER 45X45CM NOS 1 968.00 968.00
Final connection and installation sanitary fixtures and floor traps as per dwg
1.5 LS 1 756.00 756.00
at service area
Supply and installation of addc water supply piping from water meter cabinet
1.6 LS 1 817.00 817.00
to tank as per approved drawing and addc regulations
2 DRAINAGE SYSTEM -
Supply, installation Testing and commissioning of Drainage system as
per below BOQ and in accordance with drawings.
-
Note:
All materials approval required prior to installation
Supply and installation of Underground Sewarage Fiber glass tank 1500 US
2.1 gallon, SIZE:2.89x1.82x1.80m as per the drawing and authority standards No 1 7,500.00 7,500.00
( Service area)
Supply and installation of Underground Sewarage Fiber glass tank 3000 US
2.2 gallon, SIZE:v4x2.21x2.36m as per the standards and authority standards No 1 10,000.00 10,000.00
( Main villa)
2.3 Under ground Upvc drainage pipes ( Service area only) -
2.3.1 150MM dia UPVC class 16 between manholes mtr 35 132.00 4,620.00
2.3.2 100MM dia upvc under ground drainage pipe mtr 25 123.00 3,075.00
2.3.3 80MM dia upvc under ground drainage pipes mtr 20 115.00 2,300.00
2.3.4 50mm , 40mm dia as required as per drawing LS 1 105.00 105.00
2.3.5 vent pipe as per drawing and as per authority regulations LS 1 263.00 263.00
2.3.6 Final connection to sanitary fixtures and floor traps as per dwg LS 1 790.00 790.00
2.4 60x60 MH cover Heavy duty Ductile iron (Dranage label) nos 4 1,316.00 5,264.00
2.5 30x30 Gully trap MH cover Heavy duty Ductile iron nos 3 440.00 1,320.00
2.6 Channel drating stainless steel 3000x 300mm nos 1 4,320.00 4,320.00
2.7 Channel drating stainless steel 1500x300mm nos - -
2.8 Rain water outlet and necessary piping with free discharge nos 5 847.00 4,235.00
2.9 other items not mentioned in BOQ but required to complete the work LS 1 726.00 726.00
Total 164,905.00
Total
15 of 18
QF TEND-O3
PROJECT NAME : Construction of water supply system at Samha, Al Bahya and Asheesh
Sl No. Description UNIT QTY Rate Budget
Materials
1 Epoxy paint 18 Lts ` No 0.5 459.00 230.00
2 Cement 50 kg Bag 5 15.30 77.00
3 Sand 20 kg Bag 2 10.20 20.00
16 of 18
Rate per Rate per
Sl NO Description/ Trade Unit Qty. Duration Amount
Hour Day
1 Mason No. 1 13.00 130.00 75 9,750.00
2 Carpenter No. 1 11.00 110.00 75 8,250.00
3 Helpers No. 4 9.00 90.00 75 27,000.00
4 Accomodation LS 1 60.00 75 4,500.00
5 Food LS 1 60.00 75 4,500.00
Total 54,000.00
Remarks