No :
Engineering Refurbishment New Supply Installation Cold Hot Design Construction Design Refurbishment New Supply Installation Testing Commissioning Design Refurbishment New Supply Installation Programming Testing Commissioning
(if any) Commissioning Commissioning (if any) (if any)
1 Cane storage & feeding FT FT KSL FT FT FT/KSL KSL KSL KSL KSL
2 Cane Preparation FT FT KSL FT FT FT/KSL KSL KSL KSL KSL
3 Milling FT FT KSL FT FT FT/KSL KSL KSL KSL KSL
4 Mixed juice Handling, Liming & Heating FT FT KSL FT FT FT/KSL KSL KSL KSL KSL
5 Lime preparation station FT FT KSL FT FT FT/KSL KSL KSL KSL KSL
6 Flocculent preparation station FT FT KSL FT FT FT/KSL KSL KSL KSL KSL
7 Clarification FT FT KSL FT FT FT/KSL KSL KSL KSL KSL
8 Bagacillo collection and Handling FT FT KSL FT FT FT/KSL KSL KSL KSL KSL
9 Mud Filtration FT FT KSL FT FT FT/KSL KSL KSL KSL KSL
10 Clear juice Heating FT FT KSL FT FT FT/KSL KSL KSL KSL KSL
11 Evaporation FT FT KSL FT FT FT/KSL KSL KSL KSL KSL
12 Syrup Clarification FT FT KSL FT FT FT/KSL KSL KSL KSL KSL
13 Condensate & Hot water system FT FT KSL FT FT FT/KSL KSL KSL KSL KSL
14 Raw water system FT FT KSL FT FT FT/KSL KSL KSL KSL KSL
15 Condensers & ICW system FT FT KSL FT FT FT/KSL KSL KSL KSL KSL
16 Crytallisation: A/B/C FT FT KSL FT FT FT/KSL KSL KSL KSL KSL
17 Centrifugals FT FT KSL FT FT FT/KSL KSL KSL KSL KSL
18 Sugar Handling FT FT KSL FT FT FT/KSL KSL KSL KSL KSL
19 Drying FT FT KSL FT FT FT/KSL KSL KSL KSL KSL
20 Bagging FT FT KSL FT FT FT/KSL KSL KSL KSL KSL
21 Sugar Handling & Storage FT FT KSL FT FT FT/KSL KSL KSL KSL KSL
22 Molasses Handling & Storage FT FT KSL FT FT FT/KSL KSL KSL KSL KSL
23 TA 12.2 MW KSL* KSL* KSL FT/KSL* KSL* KSL* KSL KSL KSL KSL
24 TA 12.2 MW installation & integration FT N/A KSL FT FT/KSL FT/KSL KSL KSL KSL KSL
25 Boiler 50 T/h FT FT KSL FT FT FT/KSL KSL KSL KSL KSL
26 HP 31 barA & 45 barA steam system FT N/A KSL FT FT FT/KSL KSL KSL KSL KSL
27 Let down stations and Exhaust system FT N/A KSL FT FT FT/KSL KSL KSL KSL KSL
28 Bagasse Storage & Handling system FT N/A KSL FT FT FT/KSL KSL KSL KSL KSL
CIVIL
Survey of
New Supply
existing & Refurbishment (if any) Installation Testing Commissioning
new Design
1 Cane storage & feeding KSL KSL KSL FT KSL/FT KSL/FT
2 Cane Preparation KSL KSL KSL FT KSL/FT KSL/FT
3 Milling KSL KSL KSL FT KSL/FT KSL/FT
4 Mixed juice Handling, Liming & Heating KSL KSL KSL FT KSL/FT KSL/FT
5 Lime preparation station KSL KSL KSL FT KSL/FT KSL/FT
6 Flocculent preparation station KSL KSL KSL FT KSL/FT KSL/FT
7 Clarification KSL KSL KSL FT KSL/FT KSL/FT
8 Bagacillo collection and Handling KSL KSL KSL FT KSL/FT KSL/FT
9 Mud Filtration KSL KSL KSL FT KSL/FT KSL/FT
10 Clear juice Heating KSL KSL KSL FT KSL/FT KSL/FT
11 Evaporation KSL KSL KSL FT KSL/FT KSL/FT
12 Syrup Clarification KSL KSL KSL FT KSL/FT KSL/FT
13 Condensate & Hot water system KSL KSL KSL FT KSL/FT KSL/FT
14 Raw water system KSL KSL KSL FT KSL/FT KSL/FT
15 Condensers & ICW system KSL KSL KSL FT KSL/FT KSL/FT
16 Crystallisation: A/B/C KSL KSL KSL FT KSL/FT KSL/FT
17 Centrifugals KSL KSL KSL FT KSL/FT KSL/FT
18 Sugar Handling KSL KSL KSL FT KSL/FT KSL/FT
19 Drying KSL KSL KSL FT KSL/FT KSL/FT
20 Bagging KSL KSL KSL FT KSL/FT KSL/FT
21 Sugar Handling & Storage KSL KSL KSL FT KSL/FT KSL/FT
22 Molasses Handling & Storage KSL KSL KSL FT KSL/FT KSL/FT
23 TA 12.2 MW KSL KSL KSL FT KSL/FT KSL/FT
24 TA 12.2 MW installation & integration KSL KSL KSL FT KSL/FT KSL/FT
25 Boiler 70 T/h & Auxiliaries KSL KSL KSL FT KSL/FT KSL/FT
26 HP 31 barA & 45 barA steam system KSL KSL KSL FT KSL/FT KSL/FT
27 Let down stations and Exhaust system KSL KSL KSL FT KSL/FT KSL/FT
28 Bagasse Storage & Handling system KSL KSL KSL FT KSL/FT KSL/FT
Client : Job No : Doc. No :