Client: Site Acceptance Test Report For Protection Relay

Contract No:
Project: EPC for Upgrade of Power, Control and monitoring
systems in SE Project
Contractor: Sub Station: CLUSTER 3 - 16-20-PSS-2103 Manufacture:
Ref.ID P16105-16-20-97-9639
Panel Type 3.3 kV SWGR PANEL
Bay Ref: 16-20-TP-4303-12
Date: 14-05-2023 Page 1 of 9

1. RELAY DATA :
MAKE : SCHNEIDER SERIAL NUMBER : 19460010
TYPE : SEPAM T82 PANEL REF : 7-1
CT Primary : 600 A CT SEC.CURRENT :1A
VT Primary : 3.3 KV VT Secondary : 110 V

2. GENERAL INSPECTION AND CHECKS:

Kind of check Remarks


OK
Check of transport damage

Visual check of external wiring OK

OK
Check of cubicle / relay earthing
OK
Check of supply voltage (DC)
OK
Check of settings
OK
Check of current transformer circuits

Check of voltage transformer circuits OK

OK
Secondary injection test
OK
Check of binary inputs

Check of binary output contacts OK

OK
Check of tripping circuits
OK
System time setting

Tested by Witnessed by Approved by


SIGNATURE
NAME: SOORAJ.K.S VIMAL PANDIYA
DATE: 14-05-2023 14-05-2023
COMPANY Schneider Sicon Oil & Gas ADNOC Project ADNOC Operation
Client: Site Acceptance Test Report For Protection Relay
Contract No:
Project: EPC for Upgrade of Power, Control and monitoring
systems in SE Project
Contractor: Sub Station: CLUSTER 3 - 16-20-PSS-2103 Manufacture:
Ref.ID P16105-16-20-97-9639
Panel Type 3.3 kV SWGR PANEL
Bay Ref: 16-20-TP-4303-12
Date: 14-05-2023 Page 2 of 9

3. MEASUREMENTS :

3.1 CURRENT MEASUREMENT


CT RATIO : 600/1A, REF CT RATIO:300/1A

Current Injected Primary PRIMARY CURRENT MEASURED IN RELAY (A)


Phase in Secondary Current
(A) (A) L1 L2 L3 Io
R 1.0 600 60.1 0 0 0
Y 1.0 600 0 601.6 0 0
B 1.0 600 0 0 600.6 0
R-Y-B 1.0 600 600.5 601.3 600.7 0
Io 1.0 300 0 0 0 301.2

3.2 VOLTAGEMEASUREMENT
VT RATIO : 3.3kV/√3/110/√3

Voltage Primary VOLTAGE MEASUREMENT (kV)


Phase Injected in Voltage
Secondary(V) (kV) U1 U2 U3 U12 U23 U31
RN 63.51 1.905 1.905 0 0 1.905 0 1.905
YN 63.51 1.905 0 1.905 0 1.905 1.905 0
BN 63.51 1.905 0 0 1.905 0 1.905 1.905
RY 110 3.3 1.905 1.905 0 3.301 1.905 1.905
YB 110 3.3 0 1.905 1.905 1.905 3.301 1.905
BR 110 3.3 1.905 0 1.905 1.905 1.905 3.301
R-Y-B 110 3.3 1.905 1.905 1.905 3.301 3.301 3.301

Tested by Witnessed by Approved by


SIGNATURE
NAME: SOORAJ.K.S VIMAL PANDIYA
DATE: 14-05-2023 14-05-2023
COMPANY Schneider Sicon Oil & Gas ADNOC Project ADNOC Operation
Client: Site Acceptance Test Report For Protection Relay
Contract No:
Project: EPC for Upgrade of Power, Control and monitoring
systems in SE Project
Contractor: Sub Station: CLUSTER 3 - 16-20-PSS-2103 Manufacture:
Ref.ID P16105-16-20-97-9639
Panel Type 3.3 kV SWGR PANEL
Bay Ref: 16-20-TP-4303-12
Date: 14-05-2023 Page 3 of 9

3.3 POWER MEASUREMENTS:

PowerMeasured
Voltage
Current Injected Angle [MW] [MVAr]
Injected PF
Expected Value Actual Value Expected Value Actual Value
63.5 V - 3 Ph 1 A - 3 Ph 0° 3.429 3.436 0 0 0.99
63.5 V - 3 Ph 1 A - 3 Ph 45° 2.424 2.433 -2.424 -2.426 0.70
63.5 V - 3 Ph 1 A - 3 Ph 90° 0 0 -3.429 -3.436 0.00
63.5 V - 3 Ph 1 A - 3 Ph 135° -2.424 -2.426 -2.424 -2.433 -0.70
63.5 V - 3 Ph 1 A - 3 Ph 180° -3.429 -3.436 0 0 -0.99
63.5 V - 3 Ph 1 A - 3 Ph 225° -2.424 -2.433 2.424 2.426 -0.70
63.5 V - 3 Ph 1 A - 3 Ph 270° 0 0 3.429 3.436 0.00
63.5 V - 3 Ph 1 A - 3 Ph 315° 2.424 2.426 2.424 2.43 0.70
63.5 V - 3 Ph 1 A - 3 Ph 360° 3.429 3.436 0 0 0.99

4. Over Current - 51 : (3I>)


a) Pickup & Drop off : (3I>) Set: 1.0 A

Pick Up (A) Drop Off (A) DO/PU


Phase Set value (A) Ratio
Expected Operated Expected Operated Error (%)
R - ph 1.0 1.00 1.005 0.950 0.925 -2.632
Y - ph 1.0 1.00 1.005 0.950 0.925 -2.632
B - ph 1.0 1.00 1.005 0.950 0.930 -2.105

b) Curve Characteristic : IEC Very Inverse curve (3I>)


Set: 1.0 A TMS: 2 sec

Operating Time in (Sec) Operating Time in (Sec) Operating Time in (Sec)


Set 2*In set 5*In set 10*In set
Phase TMS
value Error Error Error
Expected Operated Expected Operated Expected Operated
(%) (%) (%)
R - ph 1.0 2.0 27.00 27.03 0.110 6.750 6.742 -0.123 3.00 3.008 0.256

Y - ph 1.0 2.0 27.00 26.81 -0.685 6.750 6.722 -0.413 3.00 2.990 -0.320

B - ph 1.0 2.0 27.00 26.99 -0.035 6.750 6.737 -0.197 3.00 3.005 0.156

Tested by Witnessed by Approved by


SIGNATURE
NAME: SOORAJ.K.S VIMAL PANDIYA
DATE: 14-05-2023 14-05-2023
COMPANY Schneider Sicon Oil & Gas ADNOC Project ADNOC Operation
Client: Site Acceptance Test Report For Protection Relay
Contract No:
Project: EPC for Upgrade of Power, Control and monitoring
systems in SE Project
Contractor: Sub Station: CLUSTER 3 - 16-20-PSS-2103 Manufacture:
Ref.ID P16105-16-20-97-9639
Panel Type 3.3 kV SWGR PANEL
Bay Ref: 16-20-TP-4303-12
Date: 14-05-2023 Page 4 of 9

5. Over Current - 50: (3I>>)


a) Pickup & Drop off : (3I>>) Set: 3.35 A
Pick Up (A) Drop Off (A) DO/PU
Phase Set value (A) Ratio
Expected Operated Expected Operated Error (%)
R - ph 3.35 3.35 3.384 3.18 3.113 -3.158
-3.158
Y - ph 3.35 3.35 3.384 3.18 3.113
-3.158
B - ph 3.35 3.35 3.384 3.18 3.113

b)Curve Characteristic : IEC Definite Time (3I>>) : Set: 3.35 A Time: 0.15 Sec

Injected current (A) Operating Time in (Sec) Error


Phase Set value (A) (ms)
1.25* In Expected Operated
R - ph 3.350 4.188 0.150 0.158 5.60

Y - ph 3.350 4.188 0.150 0.155 3.733

B - ph 3.350 4.188 0.150 0.154 3.00

6. Earth Fault – 51N : (I0>)


a) Pickup & Drop off : (I0>) Set: 0.15 A

Pick Up (A) Drop Off (A) DO/PU


Phase Set value (A) Ratio
Expected Operated Expected Operated Error (%)
E/F 0.150 0.150 0.155 0.142 0.140 -4.920

b) Curve Characteristic : IEC Definite Time (3I0>) Set: 0.15 A


Time: 0.90 Sec

Injected current (A) Operating Time in (Sec) Error


Phase Set value (A) (ms)
2* In Expected Operated
E/F 0.150 0.300 0.900 0.920 2.300

Tested by Witnessed by Approved by


SIGNATURE
NAME: SOORAJ.K.S VIMAL PANDIYA
DATE: 14-05-2023 14-05-2023
COMPANY Schneider Sicon Oil & Gas ADNOC Project ADNOC Operation
Client: Site Acceptance Test Report For Protection Relay
Contract No:
Project: EPC for Upgrade of Power, Control and monitoring
systems in SE Project
Contractor: Sub Station: CLUSTER 3 - 16-20-PSS-2103 Manufacture:
Ref.ID P16105-16-20-97-9639
Panel Type 3.3 kV SWGR PANEL
Bay Ref: 16-20-TP-4303-12
Date: 14-05-2023 Page 5 of 9

7. Ground Fault – 51G : (I0>)


a) Pickup & Drop off : (I0>) Set: 0.05 A CT Ratio: 300/1A
Pick Up (A) Drop Off (A) DO/PU
Phase Set value (A) Ratio
Expected Operated Expected Operated Error (%)
E/F 0.050 0.050 0.055 0.047 0.040 -23.45

b) Curve Characteristic : IEC Definite Time (I0>>) : Set: 0.05 A Time: 0.90 Sec

Injected current (A) Operating Time in (Sec) Error


Phase Set value (A)
2* In (ms)
Expected Operated
E/F 0.050 0.100 0.900 0.910 1.167

8. OVER VOLTAGE PROTECTION

Pickup & Drop off : Set: 120% Vn = 132V


Pick Up (V) Drop Off (V)
Phase Set value (V)
Expected Operated Expected Operated
RYB 132.00 132.00 131.97 125.40 127.99

Trip Test: Set: 120% Vn=132V Time: 1.00 Sec

Operating Time in (Sec) Error


Phase Set value (V) Injected voltage (V) (ms)
Expected Operated
RY - ph 132.00 135.05 1.00 1.070 -0.07

YB - ph 132.00 135.05 1.00 1.010 -0.01

BR - ph 132.00 135.05 1.00 1.025 -0.025

Tested by Witnessed by Approved by


SIGNATURE
NAME: SOORAJ.K.S VIMAL PANDIYA
DATE: 14-05-2023 14-05-2023
COMPANY Schneider Sicon Oil & Gas ADNOC Project ADNOC Operation
Client: Site Acceptance Test Report For Protection Relay
Contract No:
Project: EPC for Upgrade of Power, Control and monitoring
systems in SE Project
Contractor: Sub Station: CLUSTER 3 - 16-20-PSS-2103 Manufacture:
Ref.ID P16105-16-20-97-9639
Panel Type 3.3 kV SWGR PANEL
Bay Ref: 16-20-TP-4303-12
Date: 14-05-2023 Page 6 of 9

9. UNDER VOLTAGE PROTECTION

Pickup & Drop off : Set: 70% Vn = 77V


Pick Up (V) Drop Off (V)
Phase Set value (V)
Expected Operated Expected Operated

RYB 77.00 77.00 76.90 80.80 79.325

Trip Test: Set: 70% Vn=77V Time: 3.00 Sec

Operating Time in (Sec) Error


Phase Set value (V) Injected voltage (V) (ms)
Expected Operated
RY - ph 77.00 76.20 3.00 3.028 27.80

YB - ph 77.00 76.20 3.00 3.026 26.10

BR - ph 77.00 76.20 3.00 3.025 25.10

10. UNDER VOLTAGE PROTECTION

Pickup & Drop off : Set: 60% Vn = 66V


Pick Up (V) Drop Off (V)
Phase Set value (V)
Expected Operated Expected Operated

RYB 66.00 66.00 65.98 69.28 68.06

Trip Test: Set: 60% Vn=66V Time: 2.00 Sec

Operating Time in (Sec) Error


Phase Set value (V) Injected voltage (V) (ms)
Expected Operated
RY - ph 66.00 62.35 2.00 2.005 5.00

YB - ph 66.00 62.35 2.00 2.017 17.00

BR - ph 66.00 62.35 2.00 2.004 4.00

Tested by Witnessed by Approved by


SIGNATURE
NAME: SOORAJ.K.S VIMAL PANDIYA
DATE: 14-05-2023 14-05-2023
COMPANY Schneider Sicon Oil & Gas ADNOC Project ADNOC Operation
Client: Site Acceptance Test Report For Protection Relay
Contract No:
Project: EPC for Upgrade of Power, Control and monitoring
systems in SE Project
Contractor: Sub Station: CLUSTER 3 - 16-20-PSS-2103 Manufacture:
Ref.ID P16105-16-20-97-9639
Panel Type 3.3 kV SWGR PANEL
Bay Ref: 16-20-TP-4303-12
Date: 14-05-2023 Page 7 of 9

11. BINARY INPUT

S.N BI.No DESCRIPTION CHECKED


01 I101 CB CLOSED OK
02 I102 CB OPEND OK
03 I103 CB RACK OUT OK
04 I104 CB RACK IN OK
05 I105 ES CLOSED OK
06 I106 ES OPENED OK
07 I107 SERVICE OK
08 I108 TEST OK
09 I109 LOCKOUT RELAY OPERSTED OK
10 I110 TRIP CIRCUIT UNHEALTHY OK
11 I111 MCBs AC SUPPLY FAIL OK
12 I112 MCBs DC SUPPLY FAIL OK
13 I113 SPARE OK
14 I114 CB READY TO CLOSE OK
S.N BI.No DESCRIPTION CHECKED
01 I201 VT CIRCUIT HEALTHY OK
02 I202 OIL TEMPERATURE ALARM OK
03 I203 WINDING TEMPERATUR ALARM OK
04 I204 OIL LOW LEVEL ALARM OK
05 I205 PRESSURE RELEASE DEVICE ALARM OK
06 I206 BUCHHOLZ ALARM OK
07 I207 OIL TEMPERATURE TRIP OK
08 I208 WINDING TEMPERATUR TRIP OK
09 I209 OIL LOW LEVEL TRIP OK
10 I210 PRESSURE RELEASE DEVICE TRIP OK
11 I211 BUCHHOLZ TRIP OK
12 I212 SPARE OK
13 I213 SPARE OK
14 I214 SPARE OK

Tested by Witnessed by Approved by


SIGNATURE
NAME: SOORAJ.K.S VIMAL PANDIYA
DATE: 14-05-2023 14-05-2023
COMPANY Schneider Sicon Oil & Gas ADNOC Project ADNOC Operation
Client: Site Acceptance Test Report For Protection Relay
Contract No:
Project: EPC for Upgrade of Power, Control and monitoring
systems in SE Project
Contractor: Sub Station: CLUSTER 3 - 16-20-PSS-2103 Manufacture:
Ref.ID P16105-16-20-97-9639
Panel Type 3.3 kV SWGR PANEL
Bay Ref: 16-20-TP-4303-12
Date: 14-05-2023 Page 8 of 9

12. BINARY OUTPUT


S.N BI.No DESCRIPTION CHECKED
01 O1 GENERAL TRIP OK
02 O2 CLOSE INHABIT OK
03 O3 SPARE CLOSE OK
04 O4 TRIP OR ALARM FOR LAMP OK
05 O5 WATCHDOG OK
06 O101 SEPAM TRIP OK
07 O102 ES CLOSED OK
08 O103 CB TEST OK
09 O104 SPARE OK
10 O105 SPARE OK
11 O106 SEPAM TRIP FOR LOCKOUT RELAY OK
12 O201 SPARE OK
13 O202 SPARE OK
14 O203 SPARE OK
15 O204 SPARE OK
16 O205 SPARE OK
17 O206 ANSI27&VT HEALTHY OK

Tested by Witnessed by Approved by


SIGNATURE
NAME: SOORAJ.K.S VIMAL PANDIYA
DATE: 14-05-2023 14-05-2023
COMPANY Schneider Sicon Oil & Gas ADNOC Project ADNOC Operation
Client: Site Acceptance Test Report For Protection Relay
Contract No:
Project: EPC for Upgrade of Power, Control and monitoring
systems in SE Project
Contractor: Sub Station: CLUSTER 3 - 16-20-PSS-2103 Manufacture:
Ref.ID P16105-16-20-97-9639
Panel Type 3.3 kV SWGR PANEL
Bay Ref: 16-20-TP-4303-12
Date: 14-05-2023 Page 9 of 9

13. Remarks : Nil

14. Test Equipment Details :

EQUIPMENT CALIBRATION CALIBRATION


S.NO TYPE
Sl. NO DATE DUE DATE
1 Omicron CMC 356 HE053P 08.11.2022 07.11.2023
2 Fluke-179 5490041 11-08-2022 10-08-2023

Tested by Witnessed by Approved by


SIGNATURE
NAME: SOORAJ.K.S VIMAL PANDIYA
DATE: 14-05-2023 14-05-2023