Name of Contract: Installation of MERUS STATCOM

Location: PASAR Isabel Leyte

MANPOWER UTILIZATION SCHEDULE


EQUIPMENT CALENDAR DAYS
10 35 50 60 70 80 90 100 105 110 115 120
PROJECT 1 1 1 1 1 1 1 1 1 1 1 1
MANAGER
PROJECT QUALITY 1 1 1 1 1 1 1 1 1 1 1 1
MANAGER
PLANNING AND 1 1 1 1 1 1 1 1 1 1 1 1
PROJECT
CONTROL
PROJECT 1 1 1 1 1 1 1 1 1 1 1 1
ENGINEERING
MANAGER
PROCUREMENT 1 1 1 1 1 1 1 1 1 1 1 1
MANAGER
CONSTRUCTION 1 1 1 1 1 1 1 1 1 1 1 1
MANAGER
OPERATIONS 1 1 1 1 1 1 1 1 1 1 1 1
MANAGER
PROJECT 1 1 1 1 1 1 1 1 1 1 1 1
ENGINEER
SITE ENGINEER 2 2 2 2 2 2 2 2 2 2 2 2
CONSTRUCTION 1 1 1 1 1 1 1 1 1 1 1 1
FOREMAN
ELECTRICAL 1 1 1 1 1 1 1 1 1 1 1 1
FOREMAN
MECHANICAL 1 1 1 1 1 1 1 1 1 1 1 1
FOREMAN
PAYLOADER 1 1 1 1 1 0 0 0 0 0 0 0
OPERATOR
DUMPTRUCK 0 1 1 1 1 0 0 0 0 0 0 0
OPERATOR
BACKHOE 1 1 1 1 0 0 0 0 0 0 0 0
OPERATOR
HEAVY 1 1 1 1 1 1 1 1 0 0 0 0
EQUIPMENT
OPERATOR
TRANSIT MIXER 1 1 1 1 1 1 1 1 0 0 0 0
OPERATOR
CARPENTER 1 1 1 1 0 0 0 0 0 0 0 0
STEELMAN 1 1 1 1 0 0 0 0 0 0 0 0
EQUIPENT 1 1 1 1 1 1 1 1 0 0 0 0
OPERATOR
PIPEMAN 7 7 7 7 0 0 0 0 0 0 0 0
MECHANIC 3 3 3 3 3 0 0 0 0 0 0 0
ELECTRICIAN 4 4 4 4 4 4 4 4 4 4 4 4
MV TERMINATORS 0 0 0 0 2 2 2 2 2 0 0 0
LABORER 50 50 50 50 40 40 40 30 30 30 20 15
WAREHOUSEMAN 2 2 2 2 2 2 2 2 2 2 2 2
DRIVER 4 4 4 4 4 4 4 4 4 4 4 4

Submitted by:
WESTCO ELECTRICAL AND EQUIPMENT CORPORATION Date: APRIL 6, 2023

One of the requirements from the bidder to be included in its Technical Envelope is its equipment utilization schedule, referring to the weekly or
monthly scheduling of the minimum equipment required for the project .