Professional Documents
Culture Documents
Contoh Costing
Contoh Costing
In this schedule of Prices the item description identify the work covered by the respective items but the nature and extent of the
work to be performed is to be ascertained by reference to the Drawings, Specifications, Conditions of Works Contract and all
The Tenderer shall quote in Ringgit Malaysia and the prices quoted shall not be subject to any alteration due to fluctuation in
the cost of material, labour, fuel, transportation and any other materials whatsoever unless expressively stated otherwise. The
************SITE VISIT IS COMPULSORY************
1.00 All payments for workmen compensation and for all the services 1 lot
as mentioned above.
1.02 Testing & commissioning, test report, briefing and training for 1 lot
satisfactory operation of the entire FPS, Elect, Medical Gas, Lift,
CDA system and equipments.
1.06 Liaison with all relevant Authorities and arrange for Authority 1 lot
inspection (e.g. Bomba, JKKP, Suruhanjaya Tenaga, TNB) and
to ensure securing Letter Of Clearance for CCC.
1.09 Labelling of all electrical boards and electrical circuits and 1 lot
laminated schematics in DBs/SSBs/CPs, labelling lighting
switches and S/S/O circuits and other services where relevant.
1.10 Single line diagram schematic A1 size wall mounted board 1 lot
for consumer room.
1.12 Temporary water & power supply from connection of main 1 lot
contractor provided water and power metering point for site
installation and testing & commissioning of M&E System.
1.13 All necessary scaffolding, scissors lift, etc and safety measures 1 lot
required for installation works at height.
1.14 All hoisting and lifting works c/w all its required associated 1 lot
safety measures required for loading and unloading goods or
materials, deliver to site and position for installation.
1.16 Provision of M&E coordinator for the entire project period. 1 lot
Total (RM)
Item Extend Of Works Qty U/Rate
SECTION 2A : LV SYSTEM
Supply, delivery, installation and testing & commissioning
of the following equipment c/w all necessary
components as shown on the drawings :-
1 Electrical Board
To supply and install the following metal-clad boards c/w
tinned copper bus-bars, all necessary components, accessories
c/w MCBs, MCCBs, ACBs, RCDs, contactors, busbar, relays,
fuse links, current transformers, kilowatt hour meters,
ammeters, voltmeters, LED indicator lights and etc. as
specified in the schematic diagram. :-
Brand: ___________________________________
Unless otherwise specified, copper cable is compulsory to
be used. SIRIM Certificate required.
2.37 Fire barrier sealant to seal up all opening at cable risers and 1 lot
other necessary
2.38 Cable supporting system c/w brackets, bolt, nuts and necessary 1 lot
accessories
3.24 15A 3-pin switch socket outlet for Air-Cond at high level c/w
nos
20A Dual Pole Neon Light Switch c/w wiring
3.25 15A 3-pin switch socket outlet for exhaust fan at high level
nos
c/w Switch c/w wiring
3.26 nos
16A SPN + E Isolator AC23A (IP66) for Signboard c/w wiring
4.1 lot
4.2 To supply & install entire 24V (D.C.) heavy duty nickel no
cadmium battery bank of sufficient capacity for 7 sucesssive
attemp start as per Bomba requirement, insulation, piping,
supporting brackets/rack and all other necessary accessories to
DOE/ST's requirements.
4.3 lot
To supply & install entire Engine exhaust system c/w silencer,
thermal insulation, piping, supporting brackets and all other
necessary accessories to DOE/ST's requirements.
4.5 no
To supply & Install Elevated fuel tank sufficient for 12 hrs at
100% load prime rating c/w hand-pump, piping to engine's
fuel supply system and full tank fuel upon handing over.
4.7 lot
To supply and install ATS controller with ACB, automatic
change over contactors, programmable time delay and other
etc accessories as per tender drawing.
4.8 lot
No-volt/under-voltage sensing cable from MSB to AMF Board
using 4C 2.5mm2 PVC/SWA/PVC(cu) in cable trench
4.90 Change-over ACBs' control cabling and control/sensing cable lot
to gen-set
4.10 m
4 x 185mm2 LSZH/XLPE/Mica (CU) fire-resistant cable + E
in cable trench from Gen-set to AMF Board and AMF Board
to auto change-over ACB of MSB
4.12 lot
To supply & install Complete genset earthing system and all
necessary earthing system for the genset and AMF boards
(including to related EMSBs) to Malaysia Electricity Supply
Regulations, IEE regulations (17th edition), BS 7671:2008,
MS IEC 60364 or latest. Earth electrode resistance to achieve
below 1 ohms.
Note: All Earthing chamber electrodes must be linked bonded
with 3mm x 25mm copper tape.
4.13 Earth electrode resistance measurement tests for genset, AMF lot
Board and related EMSB c/w test result certificate. Prior
approval by consultant required before appointment of
licensed service engineer required for these tests.
4.14 lot
Calibration setting and testing of all protection relays
(OC/EF/DIFF/REF/ELR), Insulation tests and etc testing and
commissioning. Provision of all testing results/ certificates
certified and endorsed by competent person. Prior approval by
consultant required before engineer for calibration setting,
testing and pre-appointment of licensed service commissioning
works.
4.15 lot
6mm thick rubber mat for AMF Boards, accessories, including
tool kit, CPR chart, necessary warning sign and safety kits for
the room.
4.17
Testing and commissioning, including factory witness test and
related expenses Representatives: Owner, Consultant &
Contractor
5.1 All necessary earthing system for the main switch board 1 lot
(MSBs), gen-set board and auxillary earthing system for the
entire installation.
5.2 Building Earthing with Copper Electrode & Heavy Duty 1 lot
Inspection Earth Chamber c/w copper tape and provide
insulation for test clamp and conductor below test clamp & etc
accessories (Achieve 1 ohm and below).
6.1 Ø15mm x 500mm (H) copper air terminal c/w air rod base nos
and etc accessories.
6.2 Roof & down conductor using 25mm x 3mm aluminium lot
tape from preventor down to lightning strike counter
mounted on high-base roof saddles, then to bimetallic
test clamp, and 25mm x 3mm copper tape to earthing points.
7.2 To supply and install all cables and metallic conduits including
terminations:
- between supply source (s) and isolating switch/medical
isolation transformer.
- between medical isolation transformer and IPS distribution
board.
- between IPS distribution board and remote operating and
alarm panel
a) EDB-IPS m
b) UDB-IPS m
7.3 To supply and install all cables and metallic conduits including
terminations:
-between socket-outlets and IPS distribution board
a) EDB-IPS m
b) UDB-IPS m
7.4 To supply and install equipotential junction c/w box and earth nos
clamps for wall mounting
7.7 To supply and install double pole switched socket outlets c/w nos
wiring and termination
(for free issue to Pendant supplier only)
8.1 To Supply & Install of Liebert APM 60+30 kW UPS (N+1 1 lot
Configuration with 10 years design life span Sealed Lead Acid
Maintenance Free battery sized at 30 minutes autonomy c/w
battery racks output @ 30kW inclusive of the following
features:
- Online dual conversion design
- Super wide input voltage and frequency range
- Input / Output Power Factor @ 1
- Hotswappable & Modular Power Module
- System efficiency up to 96%
- Low current harmonic distortion of less than 3%
- Intelligent battery management
- Battery System c/w Battery circuit breaker & accessories
- Transistorized PWM inverter (IGBT Inverter)
- Full digital signal processing using the latest DSP technology
- Fully rated automatic static bypass
- Testing & Commissioning
- One Year Equipment Warranty (2PM/Year)
Note:
- Inclusive of battery rack, battery circuit breaker and DC
Cable (10m)
9.2 Testing of all fixed type RCD (RCCB/RCBO) with RCD 1 lot
Tester by licensed competent service engineer.
9.3 Earth loop resistance measurement for all electrical L.V. 1 lot
switchboards e.g. main DB, main-switchboards, sub-
switchboards. Prior approval by consultant required before
appointment of tester/ service engineer.
9.4 Insulation resistance tests and all other necessary tests 1 lot
7 Door Access Controller points c/w Card Reader Unit, Access nos
Controller Unit, keyswitch, door release push button,
breakglass, fire alarm signal release function, electromagnetic
door lock, sensor for alarm c/w looping cabling & etc in
recessed termination box with nice aesthetic flush cover.
1
To supply and install Pre-Cast Telekom manhole c/w fittings,
cover, necessary accessories, excavation, backfilling and
making good to existing site condition as shown in the
drawing.
a) JC9C nos
3
To supply and install 100mm Dia PVC pipe encased in
concrete inclusive of reinstatement of the existing road c/w
sand bed, warning tape c/w draw wire from linked manhole to
the telephone pit, etc to connect all proposed and existing
manholes as shown in the drawing :
a) 2 ways nos
a) 4 ways nos
5 nos
Fibre Termination Box (FTB) c/w accessories & earthing.
(Brand : Netway)
______ports termination
6 Fibre Wall socket (FWS) c/w SOHO Box & etc accessories nos
10 2 core single mode fiber optic cable from FTB to FWS Socket m
in G.I cable tray or/and M.S Trunking or/and H.I PVC conduit
concealed c/w cable connector.
12 nos
Telephone points c/w RJ11 Wall Socket (Faceplate), telephone
cable in HDG covered trunking/H.I PVC concealed conduit
and accessories.
Faceplate brand: _____________________________
Cable brand/model: ___________________________
17 nos
Data points c/w RJ45 Wall Socket (Faceplate), CAT6A UTP
cable in HDG covered trunking/H.I PVC concealed conduit
and accessories.
Faceplate brand: _____________________________
Cable brand/model: ___________________________
Brand: _______________
Model: _______________
3 Single Bedhead panel c/w light fittings switches and power nos
outlet and cutting for 2-3 nos medical gas outlets.
5 Wiring point wiring Multicore cable for bedhead nurse call nos
panel.
14 lot
Testing and commissioning c/w configuration & programming 1
Brand: _______________
Model: _______________
8 1 lot
Testing and commissioning c/w configuration & programming
10 Optional Item:
a) Web counter terminal 1 nos
b) Network router 1 nos
c) Multimedia Information Controller (MIC) 1 nos
d) Voice Module c/w speakers 1 nos
1 To supply & lay earthing copper strip HD 25mm x 3mm c/w 1 lot
DC tape clip and all associated accessories from earthing point
copper busbar to earth chamber & looping between each
earthing point copper busbar and earth chamber.
2 To supply & install earthing system, earthing copper strip and 1 lot
earthing point copper busbar c/w copper earth electrode,
copper clamp brass bolt & heavy duty pre-cast concrete
inspection chamber with removeable RC cover for compact
substations. (at least 4 points)
5 3 nos. 2 layer 150mm diameter TNB approved PVC pipe Class 1 lot
B PN6 laid from compact substation plinth to be 1mtr
extended beyond boundary /external drain as per tender
drawing.
6 4 nos. 2 layer 150mm diameter TNB approved PVC pipe Class 1 lot
B PN6 laid from compact substation plinth to be 1mtr
extended beyond boundary /external drain as per tender
drawing.
7 1 x 50mm diameter TNB approved PVC pipe Class B PN6 laid 1 lot
underground to external beyond drainage
8 To Supply & Install the precast concrete system for compact 1 lot
substation as per TNB approval list until sucessfully accepted
by TNB.
9 To Supply & Install the concrete bollard c/w footing, reflector 1 lot
and etc for compact substation as per TNB approval list until
sucessfully accepted by TNB.
no cable
4 X 1C 150mmsq PVC Cu.+E metal trunking
4 X 1C 10mmsq PVC Cu.+E metal trunking
4 X 1C 10mmsq PVC Cu.+E metal trunking
4 X 1C 10mmsq PVC Cu.+E metal trunking
1 X 1C 185mmsq FR Cu.+E HDG cable tray
Calibration
500.00 500.00
500.00 500.00
500.00 500.00
-
-
250.00 250.00
250.00 250.00
250.00 250.00
250.00 250.00
250.00 250.00
250.00 250.00
250.00 250.00
250.00 250.00
250.00 250.00
250.00 250.00
250.00 250.00
Calibration
SURE REACH - SR
20W LED downlight (1884 lumen) c/w driver and necessary acessories and 40.00
ancillaries (4000K)
1 x 18W (l200mm) T8 bare channel LED fitting (4000K) c/w lamp and 29.00
control gear
1 x 18W (l200mm) T8 bare channel LED fitting (4000K) with fitting's 49.00
cover casing reflector c/w lamp and control gear
1 x 18W (l200mm) T8 bare channel LED fitting (4000K), Weatherproof 83.00
type c/w lamp and control gear
1 x 14W (l200mm) T8 bare channel LED fitting (4000K) c/w lamp and 27.00
control gear
200W Highbay LED Light (6500k), outdoor weatherproof type, IP54 c/w 360.00
Electronic Driver
200W Spotlight LED Light (6500k), outdoor weatherproof type, IP54 c/w 280.00
Electronic Driver
100W Bulkhead Surface Mounted
100W Highbay LED Light 300.00
PCO Davex Econlite NIKKON SJLITE
55.00 64.00 LE115
44.00 59.00
18.80 31.50
25.30 52.00
95.50 100.00
18.80
490.00 400.00
700.00 250.00
80.00 50.00
Light Fitting HBL
self contained 10 x Super Bright LED Emergency Light with 3 Hours
back up time
Self contained 15 x Super Bright LED Emergency Light With 3 hours
back up time battery
Self contained 15 x Super Bright LED Emergency Light With 3 hours
back up time battery (twin Lamp)
Self contained 10 x Super Bright LED Keluar Sign with 3 Hours back up
time battery
20W LED downlight (1884 lumen) c/w driver and necessary acessories and 40.00
ancillaries (4000K)
1 x 18W (l200mm) T8 bare channel LED fitting (4000K) c/w lamp and 29.00
control gear
1 x 18W (l200mm) T8 bare channel LED fitting (4000K) with fitting's 49.00
cover casing reflector c/w lamp and control gear
1 x 18W (l200mm) T8 bare channel LED fitting (4000K), Weatherproof 83.00
type c/w lamp and control gear
1 x 14W (l200mm) T8 bare channel LED fitting (4000K) c/w lamp and 27.00
control gear
200W Highbay LED Light (6500k), outdoor weatherproof type, IP54 c/w 360.00
Electronic Driver
200W Spotlight LED Light (6500k), outdoor weatherproof type, IP54 c/w 280.00
Electronic Driver
100W Bulkhead Surface Mounted
100W Highbay LED Light 300.00
PCO Davex Econlite NIKKON SJLITE
55.00 64.00 LE115
44.00 59.00
18.80 31.50
25.30 52.00
95.50 100.00
18.80
490.00 400.00
700.00 250.00
80.00 50.00
Item Extend Of Works Qty U/Rate
- To supply and replace the HEPA filter, bag filter, pre-filter of AHU
units ( duty & standby units) frequency: Annual.
3 Any other items not mentioned above but necessary to complete the scope
of work, please specify:-
(Write 'NIL', if there is none)
a.
b.
c.
a. AHU-OT-01 1 no.
b. AHU-OT-02 1 no.
c. AHU-OT-03 1 no.
1.02 Intelligent AHU's Remote Control Panel c/w Direct Digital Controller.
Touch screen graphical user interface for the control system (tempereture,
RH, AHU & EAF, start/stop) that located in Minor Operation Theatre
1,2&3
a. AHU-OT-01 1 no.
b. AHU-OT-02 1 no.
c. AHU-OT-03 1 no.
a. AHU-OT-01 1 no.
b. AHU-OT-02 1 no.
c. AHU-OT-03 1 no.
1.06 Outdoor condenser unit c/w all cabling work, G.I bracket, fitting, and
other necessary accessories as following :
a. CDU-OT-1 1 no.
b. CDU-OT-2 1 no.
c. CDU-OT-3 1 no.
1.07 AHU control panel c/w ACB, MCCB, EF/OC, c/w tag number, surge
protection device, starters, controls, indications, relays (including fire
trip), contactors, controls, timers, ammeter, voltmeter, power factor
regulator, capacitor banks, interlocking cabling between indoor and
outdoor unit, interlocking cabling with mechanical ventilation fan, all
cabling works & all neccessary accessories as shown in the drawing &
specification.
(Air cond panel shop drawing shall be submit to consultant for review
before manufacture.)
a. CP-AHU-OT1 1 no.
b. CP-AHU-OT2 1 no.
c. CP-AHU-OT3 1 no.
1.08 Supply and install G.I. pre-fabricated rectangular ducts for supply air,
return air and fresh air c/w plenum box, gasket, PE foam thermal
insulation (min 25mm THK), inner acoustic liner with rockwool, MS
flanges and bracing, MS supporting hanger, flexible duct, access door for
duct maintenance, fire seals, supply air collars, vanes, splitter damper
duly painted of the ducts, duct access panel, VCD at all branch duct and
all necessary accessories for air system.
(Slip joints are not acceptable in any case; all duct that serving OT room
area must be fully sealed air tight)
a. AHU-OT-01 1 lot
b. AHU-OT-02 1 lot
c. AHU-OT-03 1 lot
1.09 R-410A refrigerant and copper piping pre-insulated pipe c/w thermal
insulation with proper joining method using foam tape. Piping must run
on perforated G.I. tray and with G.I. sheet cover on top c/w steel support
and any other necessary accessories as per following:-
(All refrigerant pipe size and thickness shall select by vendor as per
manufacturer standard and to be approved by consultant.)
a. AHU-OT-01 1 lot
b. AHU-OT-02 1 lot
c. AHU-OT-03 1 lot
1.10 PVC and control system condensate water drain piping c/w thermal 1 lot
insulation on straight pipe, fittings and floor trap, supports, brackets and
other necessary accessories as following (concealed in wall or slab where
possible).
1.11 Power cabling (G.I Conduit) between indoor & outdoor unit, indoor 1 lot
remote controller, interlocking cabling for all the units.
Note: Installing M&E services at existing wall on surface conduit, new
wall consealed the conduit.
1.12 AHU fresh air inlet ducting from wall to the AHU unit. 3 nos.
1.13 AHU exhaust air outlet ducting from AHU units to external wall. 3 nos.
1.14 Diffusser, fresh air, supply air grilles, return air grilles, louvres, 1 lot
weatherproof external louvres, volume control dampers, opposed blade
dampers, fire dampers with Bomba Certificate, non-return dampers and
all necessary accessories for air system.
1.16 Insulate the floor trap for condensate water drain c/w insulation. 1 lot
1.19 RC plinth for AHU units and outdoor condenser units 1 lot
1.20 Any other items not mentioned above but necessary to complete the scope
of work, please specify:-
(Write 'NIL', if there is none)
(a)______________________________________
(b)______________________________________
(c)______________________________________
First Floor
a. ACSU-F-1 1 no.
b. ACSU-F-2 1 no.
c. ACSU-F-3 1 no.
d. ACSU-F-4 1 no.
e. ACSU-F-5 1 no.
f. ACSU-F-6 1 no.
g. ACSU-F-7 1 no.
h. ACSU-F-8 1 no.
i. ACSU-F-9 1 no.
j. ACSU-F-10 1 no.
k. ACSU-F-11 1 no.
l. ACSU-IT-1 1 no.
m. ACSU-IT-2 1 no.
n. ACSU-OT-1 1 no.
o. ACSU-OT-2 1 no.
First Floor
a. ACSU-UPS-1 1 no.
b. ACSU-UPS-2 1 no.
2.02 R-32 refrigerant and copper piping c/w thermal insulation with proper
joining method using foam tape. Piping must run on perforated G.I. tray
and with G.I. cover on top c/w steel support and any other necessary
accessories as per following:-
(All refrigerant pipe size and thickness shall select by vendor as per
manufacturer standard and to be approved by consultant.)
First Floor
a. ACSU-F-1 1 no.
b. ACSU-F-2 1 no.
c. ACSU-F-3 1 no.
d. ACSU-F-4 1 no.
e. ACSU-F-5 1 no.
f. ACSU-F-6 1 no.
g. ACSU-F-7 1 no.
h. ACSU-F-8 1 no.
i. ACSU-F-9 1 no.
j. ACSU-F-10 1 no.
k. ACSU-F-11 1 no.
l. ACSU-IT-1 1 no.
m. ACSU-IT-2 1 no.
n. ACSU-OT-1 1 no.
o. ACSU-OT-2 1 no.
First Floor
a. ACSU-UPS-1 1 no.
b. ACSU-UPS-2 1 no.
2.03 Conceal PVC condensate water drain piping c/w thermal insulation on
straight pipe, fittings and floor trap, supports, brackets and other
necessary accessories as following (concealed in wall or slab where
possible):
First Floor
a. ACSU-F-1 1 no.
b. ACSU-F-2 1 no.
c. ACSU-F-3 1 no.
d. ACSU-F-4 1 no.
e. ACSU-F-5 1 no.
f. ACSU-F-6 1 no.
g. ACSU-F-7 1 no.
h. ACSU-F-8 1 no.
i. ACSU-F-9 1 no.
j. ACSU-F-10 1 no.
k. ACSU-F-11 1 no.
l. ACSU-IT-1 1 no.
m. ACSU-IT-2 1 no.
n. ACSU-OT-1 1 no.
o. ACSU-OT-2 1 no.
First Floor
a. ACSU-UPS-1 1 no.
b. ACSU-UPS-2 1 no.
2.04 Power cabling (G.I Conduit) between indoor & outdoor unit, indoor 1 lot
remote controller, interlocking cabling for all the units.
First Floor
a. ACSU-F-1 1 no.
b. ACSU-F-2 1 no.
c. ACSU-F-3 1 no.
d. ACSU-F-4 1 no.
e. ACSU-F-5 1 no.
f. ACSU-F-6 1 no.
g. ACSU-F-7 1 no.
h. ACSU-F-8 1 no.
i. ACSU-F-9 1 no.
j. ACSU-F-10 1 no.
k. ACSU-F-11 1 no.
l. ACSU-IT-1 1 no.
m. ACSU-IT-2 1 no.
n. ACSU-OT-1 1 no.
o. ACSU-OT-2 1 no.
First Floor
a. ACSU-UPS-1 1 no.
b. ACSU-UPS-2 1 no.
2.05 Supply and installation of ACSU switch boards/ 24hrs changeover control
panel inclusive of all cabling and wiring complete with timer, starter,
starter pilot lamp, selection switch, MCB and other accessories.
a. CP-ACSU-OT2 1 no.
b. CP-ACSU-IT 1 no.
c. CP-ACSU-UPS 1 no.
2.06 G.I steel cage c/w G.I support and cover for the condenser units of ACSU 1 lot
2.07 Insulate the floor trap for condensate water drain c/w insulation. 1 lot
2.10 Any other items not mentioned above but necessary to complete the scope
of work, please specify:-
(Write 'NIL', if there is none)
a.
b.
c.
First Floor
a. FCU-F-1 high static ducted 1 no.
b. FCU-F-2 1 no.
c. FCU-F-3 1 no.
d. FCU-F-4 1 no.
e. FCU-F-5 1 no.
f. FCU-F-6 ceiling cassette 1 no.
g. FCU-F-7 1 no.
h. FCU-F-8 1 no.
i. FCU-F-9 1 no.
3.02 DAIKIN VRV Outdoor unit c/w all cabling work, bracket, fitting, and
other necessary accessories as following:
a. VRV-1 1 no.
b. VRV-2 1 no.
c. VRV-3 1 no.
3.03 Supply and install supply air grille c/w HEPA filter fan module and
power points and other necessary accessories as following:
a. CLEAN CORRIDOR AREA 2 nos.
*Please refer to drawing
3.04 Supply and install G.I. pre-fabricated rectangular ducts for supply air,
return air and fresh air c/w plenum box, gasket, PE foam thermal
insulation (min 25mm THK), inner acoustic liner with rockwool, MS
flanges and bracing, MS supporting hanger, flexible duct, access door for
duct maintenance, fire seals, supply air collars, vanes, splitter damper
duly painted of the ducts, duct access panel, VCD at all branch duct and
all necessary accessories for air system.
(Slip joints are not acceptable in any case; all duct that serving OT room
area must be fully sealed air tight)
a. FCU-F-1 1 lot
b. FCU-F-2 1 lot
3.06 Supply and installation of VRV for outdoor c/w MCCB, RCD, ELR,
EF/OC, starters, controls, indication relay, contractors, thermostat, all
cabling work and all necessary accessories.
a. CP-VRV-1 1 no.
b. CP-VRV-2 1 no.
c. CP-VRV-3 1 no.
3.07 Outdoor air processing unit c/w air filter G4,F8 and filter box, thermostat,
wired & wireless controller, secondary drain pan and other necessary
accessories as following:
a. OAPU-G1 1 no.
b. OAPU-F1 1 no.
3.08 Outdoor air processing unit G.I. pre-fabricated rectangular ducts for
supply air, return air and fresh air c/w plenum box, gasket, PE foam
thermal insulation (min 25mm THK), inner acoustic liner with rockwool,
MS flanges and bracing, MS supporting hanger, flexible duct, access door
for duct maintenance, fire seals, supply air collars, vanes, splitter damper
duly painted of the ducts, non-return damper, duct access panel, VCD at
all branch duct and all necessary accessories for air system.
Ground Floor
a. FCU-G-1 1 no.
b. FCU-G-2 1 no.
c. FCU-G-3 1 no.
d. FCU-G-4 1 no.
e. FCU-G-5 1 no.
f. FCU-G-6 1 no.
g. FCU-G-7 1 no.
h. FCU-G-8 1 no.
i. FCU-G-9 1 no.
j. FCU-G-10 1 no.
k. FCU-G-11 1 no.
l. FCU-G-12 1 no.
m. FCU-G-13 1 no.
n. FCU-G-14 1 no.
o. FCU-G-15 1 no.
p. FCU-G-16 1 no.
q. FCU-G-17 1 no.
r. FCU-G-18 1 no.
s. FCU-G-19 1 no.
t. FCU-G-20 1 no.
u. FCU-G-21 1 no.
First Floor
a. FCU-F-1 1 no.
b. FCU-F-2 1 no.
c. FCU-F-3 1 no.
d. FCU-F-4 1 no.
e. FCU-F-5 1 no.
f. FCU-F-6 1 no.
g. FCU-F-7 1 no.
h. FCU-F-8 1 no.
i. FCU-F-9 1 no.
j. ACSU-F-1 1 no.
k. ACSU-F-2 1 no.
l. ACSU-F-3 1 no.
m. ACSU-F-4 1 no.
n. ACSU-F-5 1 no.
o. ACSU-F-6 1 no.
p. ACSU-F-7 1 no.
q. ACSU-F-8 1 no.
r. ACSU-F-9 1 no.
s. ACSU-F-10 1 no.
t. ACSU-F-11 1 no.
3.09 PVC condensate water drain piping c/w thermal insulation
and other necessary accessories as following:
a. OAPU-G1 1 no.
b. OAPU-F1 1 no.
3.10 Power cabling (G.I Conduit) between indoor & outdoor unit, indoor
remote controller, interlocking cabling for all the units.
a. OAPU-G1 1 no.
b. OAPU-F1 1 no.
3.13 Any other items not mentioned above but necessary to complete the scope
of work, please specify:-
(Write 'NIL', if there is none)
a.
b.
c.
1.01 Axial fan c/w tag number, all wiring works, local fan switch,
starter/control panel and anti-vibration isolator, flexible connection, M.S
bracket, M.S hanger, external weather proof louver, moisture resistant
motor, galvanised steel cabinet as follows (silencer/ acoustic lining to be
include if the fan noise exceed allowable noise criteria):-
a. FAF-AHU-OT-1 1 no.
b. FAF-AHU-OT-2 1 no.
c. FAF-AHU-OT-3 1 no.
1.02 Fresh air G.I. ducting for the following fan c/w thermal insulation, non- 1 lot
return damper, M.S support, M.S hangers, M.S bracket, painting,
aluminium powder coated supply air grilles, exhaust air grilles, external
weather proof louver, volume control dampers, goose neck duct, puddle
flange/dog house for duct pass through water tight structure, fire seal,
insect/bird screen and associated accessories.
a. FAF-AHU-OT-1 1 no.
b. FAF-AHU-OT-2 1 no.
c. FAF-AHU-OT-3 1 no.
1.03 Fan control panel c/w tag number, MCCB/MCB, RCD, EF/OC, starters,
controls, indications, relay, contractors, interlocking system, interlocking
with AHU's, thermostat (if necessary), all cabling works and all necessary
accessories.
a. CP-AHU-OT-1 1 no.
b. CP-AHU-OT-2 1 no.
c. CP-AHU-OT-3 1 no.
2.01 Axial fan c/w tag number, all wiring works, local fan switch,
starter/control panel and anti-vibration isolator, flexible connection, M.S
bracket, M.S hanger, external weather proof louver, moisture resistant
motor, galvanised steel cabinet as follows (silencer/ acoustic lining to be
include if the fan noise exceed allowable noise criteria):-
a. EAF-G1 1 no.
b. EAF-G2 1 no.
c. EAF-G3 1 no.
d. EAF-G4 1 no.
e. EAF-F1 1 no.
f. EAF-F2 1 no.
g. EAF-R1 1 no.
h. EAF-R2 1 no.
i. EAF-R3 1 no.
2.02 Exhaust air G.I. ducting for the following fan c/w thermal insulation, 1 lot
non-return damper, M.S support, M.S hangers, M.S bracket, painting,
aluminium powder coated supply air grilles, exhaust air grilles, external
weather proof louver, volume control dampers, goose neck duct, puddle
flange/dog house for duct pass through water tight structure, fire seal,
insect/bird screen and associated accessories.
a. EAF-G1 1 no.
b. EAF-G2 1 no.
c. EAF-G3 1 no.
d. EAF-G4 1 no.
e. EAF-F1 1 no.
f. EAF-F2 1 no.
g. EAF-R1 1 no.
h. EAF-R2 1 no.
i. EAF-R3 1 no.
2.03 Fan control panel c/w tag number, MCCB/MCB, RCD, EF/OC, starters,
controls, indications, relay, contractors, interlocking system, interlocking
with AHU's, thermostat (if necessary), all cabling works and all necessary
accessories.
a. CP-EAF-G1 1 no.
b. CP-EAF-G2 1 no.
c. CP-EAF-G3 1 no.
d. CP-EAF-F1 1 no.
e. CP-EAF-F2 1 no.
2.04 Ceiling cassette ventilating fan c/w tag number, all wiring works, local
fan switch, starter/control panel and anti-vibration isolator, flexible
connection, M.S bracket, M.S hanger, moisture resistant motor,
galvanised steel cabinet as follows (silencer/ acoustic lining to be include
if the fan noise exceed allowable noise criteria):-
Ground Floor
a. EAF-G-1 1 no.
b. EAF-G-2 1 no.
c. EAF-G-3 1 no.
d. EAF-G-4 1 no.
e. EAF-G-5 1 no.
f. EAF-G-6 1 no.
g. EAF-G-7 1 no.
h. EAF-G-8 1 no.
i. EAF-G-9 1 no.
j. EAF-G-10 1 no.
k. EAF-G-11 1 no.
l. EAF-G-12 1 no.
m. EAF-G-13 1 no.
n. EAF-G-14 1 no.
o. EAF-G-15 1 no.
p. EAF-G-16 1 no.
q. EAF-G-17 1 no.
r. EAF-G-18 1 no.
First Floor
a. EAF-F-1 1 no.
b. EAF-F-2 1 no.
c. EAF-F-3 1 no.
d. EAF-F-4 1 no.
e. EAF-F-5 1 no.
f. EAF-F-6A 1 no.
g. EAF-F-6B 1 no.
h. EAF-F-7 1 no.
i. EAF-F-8 1 no.
j. EAF-F-9 1 no.
k. EAF-F-10 1 no.
l. EAF-F-11 1 no.
m. EAF-F-12 1 no.
n. EAF-F-13 1 no.
o. EAF-F-14 1 no.
p. EAF-F-15 1 no.
2.06 Any other items not mentioned above but necessary to complete the scope
of work, please specify:-
(Write 'NIL', if there is none)
a.
b.
c.
1.00 Addressable fire alarm panel c/w loop controller, LED lights, 1 set
mimic, zone control, battery charger, 6" dia. master alarm Bell,
all wiring works and etc. accessories at Lounge Area.
Brand: EST or equivalent
1.01 24V DC dome bell c/w cabling in G.I. conduit, supporting 1 lot
brackets and etc. accessories.
1.08 Isolator module c/w cabling in G.I. conduit, supporting brackets 1 lot
and etc. accessories.
1.09 Booster power supply unit c/w battery, cabling in G.I. conduit, 1 lot
supporting brackets and etc. accessories.
1.11 Water tank low electrode c/w signal cabling to the addressable 1 lot
fire alarm system.
1.12 Indication signal and wiring works from all the fire protection 1 lot
system including the status of hose reel pump, CO2 system and
etc.
1.13 Bomba Direct Fire Safety Link System (SPKA) link to 1 lot
Bomba complying Bomba's requirement c/w testing &
commisioning (including maintenance & subcription fees
for DLP period)
1.00 150mm dia. M.S.C.L. incoming pipe from fire water meter to 1 lot
each hydrant point for hydrant reticulation c/w stump valves,
brackets,hangers, supports, 'painting, connection, excavation,
back-filling, reinstatement and all necessary accessories.
1.01 Double pillar hydrant c/w connection, fitting and painting 1 nos
works.
1.02 Fire hose box c/w 2 1/2" dia., 30m long rubbing line canvas 1 nos
hose and coupling for each hydrant cabinet.
1.01 Standby diesel engine driven hosereel pump c/w lead acid 1 set
type batteries & charger unit as specified in the specification,
drawings and signages.
1.02 Pumpset control panel c/w control wiring in G.I. conduit 1 set
or trunking with pressure switch control . Charger unit &
Lead acid type battery c/w battery stand and complying to
1.03 65mm dia. G.I. Class "B" pipe from hosereel tank to 1 lot
hosereel pumps at pump house including gate valve,
Y-strainer, flexible joint, brackets, painting, concrete stump
and all necessary accessories.
1.04 50mm dia. G.I Class "C" hosereel pipe-work laids underground 1 lot
as specified in the drawing c/w valves, fittings, brackets,
concrete stump, connections painting and all necessary
accessories.
1.05 50mm dia. G.I Class "B" hosereel pipe-work as specified in the 1 lot
drawing c/w valves, fittings, brackets, concrete stump,
connections painting and all necessary accessories.
1.06 25mm dia. G.I. "B" dropper pipe c/w valves, fittings, 1 lot
brackets, painting and all necessary accessories.
1.07 Hydraulic hosereels c/w 25mm diameter, 30m long 1 lot
non-link rubber hose, shut-off nozzle and metal nozzle box
with key.
1.00 2 zones CO2 control panel c/w battery charger, lead acid
batteries, wiring for monitoring, alarm functions and
wirings to main fire alarm panel as specified in the drawing.
a) Genset Room 1 lot
b) Main Switch Board Room 1 lot
1.03 Fire curtain c/w auto release mechanism and wiring works
to be connected to CO2 control panel.
a) Genset Room 1 lot
b) Main Switch Board Room 1 lot
2.00 Any other items not mentioned above but necessary to complete the
scope of work, please specify:-
(Write 'NIL', if there is none)
a.
b.
c.
1.01 Secondary supply system c/w control panel manual, and manifold 1 lot
2.00 Any other items not mentioned above but necessary to complete the
scope of work, please specify:-
(Write 'NIL', if there is none)
a.
b.
c.
1.01 Secondary supply system c/w control panel manual and manifold 1 lot
2.00 Any other items not mentioned above but necessary to complete the
scope of work, please specify:-
(Write 'NIL', if there is none)
a.
b.
c.
2.00 Any other items not mentioned above but necessary to complete the
scope of work, please specify:-
(Write 'NIL', if there is none)
a.
b.
c.
2.00 Any other items not mentioned above but necessary to complete the
scope of work, please specify:-
(Write 'NIL', if there is none)
a.
b.
c.
1.01 AGSS remote start stop switches located inside the operating 1 lot
control panels.
2.00 Any other items not mentioned above but necessary to complete the
scope of work, please specify:-
(Write 'NIL', if there is none)
a.
b.
c.
2.00 Any other items not mentioned above but necessary to complete the
scope of work, please specify:-
(Write 'NIL', if there is none)
a.
b.
c.
1.00 Complete medical gases, vacuum and AGS pipeline reticulation 1 lot
system consisting of Ground Floor, First Floor and M&E Floor.
a All pipes and fittings to be phosphorous, de-oxidized, non arsenal
copper to BS 6017 grade C 106 : sizes and manufactured to BS 2871,
pt 1, Table X and BS 864 Pt. 2 respectively.
b Pipe runs to maintain minimum 25 mm clearance between each
service where pipe work crosses other services and the 25 mm
clearance cannot be maintained, be electrically bonded wrap insulated,
etc
c Secondary brass fitting supports
2.00 Any other items not mentioned above but necessary to complete the
scope of work, please specify:-
(Write 'NIL', if there is none)
a.
b.
c.
Sub-total for Section (5I) : RM
SECTION 5J: TERMINAL UNITS
1.00 To supply, deliver, install, test and commission the complete specified 1 lot
type terminal units and accessories as per specified type terminal units
and accessories as per specification drawings.
2.00 Any other items not mentioned above but necessary to complete the
scope of work, please specify:-
(Write 'NIL', if there is none)
a.
b.
c.
2.00 Any other items not mentioned above but necessary to complete the
scope of work, please specify:-
(Write 'NIL', if there is none)
a.
b.
c.
2.00 Any other items not mentioned above but necessary to complete the
scope of work, please specify:-
(Write 'NIL', if there is none)
a.
b.
c.
1.00 To supply, deliver, install, and test commission the complete repeater 4 nos
zone alarm panels and accessories.
2.00 Any other items not mentioned above but necessary to complete the
scope of work, please specify:-
(Write 'NIL', if there is none)
a.
b.
c.
1.00 To supply, deliver, install, and test commission the complete modular 3 nos
operating theatre panel complete with associated works as per
specification and drawings .
a. Modular Operating Theatre panel comprising of both 1st. Fix wall box
assembly, manufactured in 1.6mm zintec coated mild steel with
removable doors.
It shall be white powder epoxy coated, white RAL 9010. Front fascia,
door and tiles of 2mm brushed grain stainless steel.
b. Flushed mounted analog elapsed clock and analog
time of day showing hour and minutes c/w reset
button.
c. X-Ray viewer complete with film holder.
d. Line Isolation and overload monitor (LIOM) system
complete with approximately of 5kVA Isolating
Transformer complete with cabling connection and
termination. (Others)
e. Provide enclosed compartment in tiles system for
the following fittings :-
i. 8 nos. x Single socket outlet (Others)
2.00 Any other items not mentioned above but necessary to complete the
scope of work, please specify:-
(Write 'NIL', if there is none)
a.
b.
c.
1.00 To supply the necessary services, test instrument, etc, to execute the 1 lot
specified works fully in accordance with HTM 02-01:Part A & B
practices and as specified herein.
- Material, inspection.
- Jointing, inspection
- Labeling and marking, inspection
- Sleeving and supports, inspection
- Leakage test.
- Cross connection test
- Leakage test.
- Vacuum leakage test
- Area valve service units
- Closure and zoning tests.
- Cross-connection test
- Functional tests of terminal units and NIST connectors.
- Design flow performance tests.
- Sources of supply tests
- Pressure safety valves, certification.
- Verification of drawings
- Purging and filling.
- Quality, gas
- Gas identification.
2.00 Any other items not mentioned above but necessary to complete the
scope of work, please specify:-
(Write 'NIL', if there is none)
a.
b.
c.
2.00 Any other items not mentioned above but necessary to complete the
scope of work, please specify:-
(Write 'NIL', if there is none)
a.
b.
c.
-
Item Extent Of Works Qty Unit Rate (RM)
1.01 Passenger lift c/w lift car, car door, landing door, lift motor, internal lighting &
cabling, all requirements as detailed in the specifications and any other items and
features that required to form complete and functional systems of lifts.
1.02 Lift's starter / control panel to the lift motors c/w MCCBs, heavy duty contactors, 1 lot
overload protection, surge protection device, control systems, fire signal relay,
internal wiring, pilot /indicating lamps and etc. (Note: Genset supply is available
during TNB power outage)
1.03 All passenger lift to fit with Car Door Locking Device, Emergency Operated 1 lot
Power supply (EBOPS), Automatic Rescue Device (ARD), Ascending Car
Overspeed Protection (ACOP), Unintended Car Movement Protection (UCMP)
and any other relevant accessories.
1.04 Power cabling from lift's starter/ control panel/ switch board to the lift motors c/w 1 lot
termination, trunking, etc.
(Note: Eletrical schematic diagram has to be submitted for approval)
1.05 Control cabling and ELV integration for lift's starter/control panel to all lift- 1 lot
calling stations.
SUMMARY OF PRICE
__________________________
Chop & Signature of Tenderer
Name : _________________________
Designation : ____________________
Date : __________________________
& MAINTENANCE OF THE PROPOSED
HD
*****
____________
_____________)
THE SUPPLY, DELIVERY, INSTALLATION, TESTING, COMMISSIONING & MAINTENANCE OF THE
Lift's Specifications Passenger Lift
No.of Unit One (1)
Capacity (Persons) 21 Persons
Speed (metres/minute) 60 MPM
No.of stop/opening 2 stops / 2 openings
Service floor name To be specified
Travel distance (metres) Refer to Elevation Drawing
Control system Intelligent supervisory
Operation Duplex Car Control
Traction machine AC gearless
Machine position Machine Room-Less
Motor Control AC-VVVF
Motor power (KW) To be specified
Lift Shaft Size Provided 2500 mm (W) x 3000 mm (D)
Lift Pit Provided 1800 mm (D)
Overhead Provided 4900 mm (H)
Schedule
Delivery/Shipping Please state
Installation Please state
Testing & commissioning Please state
Payment mode Please state
Conditions
Defects Liability Period Refer to tender conditions.
Maintenance rates after Please state general and comprehensive maintenance rates for
first 5 years after D.L.P under section "Schedule of Unit Rate" of
this book.
Liquidated & Ascertained Damages Refer to tender conditions.
Items by others Please state (attach separate sheet)
THE SUPPLY, DELIVERY, INSTALLATION, TESTING, COMMISSIONING & MAINTENANCE OF THE PROPOSED
Tenderers shall quote for the Comprehensive maintenance service after expiry of the normal one year's free maintenance
period. (Comprehensive maintenance shall INCLUDE all labour and materials such as oil, grease, repairs and replacement of
A. Comprehensive Maintenance and Service
Item Description
1 One (1) passenger lift (21 persons) after DLP
1st year RM
2nd year RM
3rd year RM
4th year RM
5th year RM
TOTAL 5 YEARS :
B. Standard Maintenance Service EXCLUDING replacement of parts but including 24-Hour daily emergency service
Item Description
1 One (1) passenger lift (21 persons) after DLP
1st year RM
2nd year RM
3rd year RM
4th year RM
5th year RM
TOTAL 5 YEARS :
Item Description
2. Address of Depot
3. Person in-charge
4. Number of Technicians
5. Telephone No.
TOTAL
& MAINTENANCE OF THE PROPOSED LIFT
piry of the normal one year's free maintenance
s such as oil, grease, repairs and replacement of
Per annum
Per annum
Per annum
Per annum
Per annum
Per annum
Per annum
Per annum
Per annum
Per annum
Amount RM
…………………………….
…………………………….
…………………………….
…………………………….
…………………………….
…………………………….
ignature : ……………………………………………
Address : ………………...…………………………..
…………………..…………………………………….
…………………..…………………………………….
ate : ………………………………………………….