Download as pdf or txt
Download as pdf or txt
You are on page 1of 191

2007 

Manoj Sharma 
W h a t   we   kn o w ,  
W h a t   we  d o n’ t   kn o w  a nd  

Engineering and Policy Analysis 
1285238 
W h a t   we   ne ed  t o  k n o w  
 
 Flow­based Market Coupling

  To develop a decision‐support model for evaluating the implications of and 
impediments  to  implementing  Flow‐based  Market  Coupling  for  alleviating 
  the issue of interconnector congestion in North West European region. 
 
   
 
   
 
   
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
   
 
 
Faculty of  
Technology Policy and Management 
+31 (0) 620 586 228 
manoj.mailbox@gmail.com     
   
 

   
Flow‐based Market Coupling  

W ha t   we   kn ow ,  
W ha t   we   do n ’ t k no w  an d  
W ha t   we   ne e d  t o k no w  
 
 
Name  Manoj Sharma 
Student number  1285238 
Email address  manoj.mailbox@gmail.com 
Date  August 2007 
University  Delft University of Technology 
Faculty    Technology, Policy and Management 
Programme  Engineering and Policy Analysis 
Division  Energy and Industry 
  Economics of Infrastructures 
Intern  Ministry of Economic Affairs, The Netherlands (EZ) 
   
Graduation Committee   
   
Prof. dr. ir. M. P. C. Weijnen  Professor  TU Delft 
dr. ir. R. A. Hakvoort  First Supervisors  TU Delft 
mw. ir. H.M. de Jong     
ir. M. Jonker  Second Supervisors  TU Delft 
Prof. ir. W.L. Kling     
drs. André Jurjus  External Supervisors  EZ 
drs. Lineke den Ouden     
mr. drs. Jon Eikelenstam     
drs. Kick Bruin     
 
 
   
   
 
 
 
Dedicated to my parents
 
 
   
 
   
ACKNOWLEDGEMENTS 
 

I am deeply indebted to my supervisor Dr. Rudi Hakvoort, from the Technical University Delft whose support, 
stimulating  suggestions,  encouragement  and  confidence  in  my  abilities  enabled  were  a  source  of  constant 
motivation.  I  cannot  possibly  imagine  completing  this  work  without  his  guidance  and  pragmatism.  I  also 
thank  him  for  providing  me  the  opportunity  of  working  on  a  real  policy  issue,  in  whatever  small  measure 
possible.  I also sincerely thank  Hanneke  de Jong  for  her daily presence and continuous mentorship through 
the  period  of  my  thesis.  Her  continuous  feedback  and  comments  have  played  the  most  important  role  in 
shaping up this work. 

I  would  like  to  thank  wholeheartedly  my  supervisors,  Professor  of  the  Energy  &  Industry  section,  Margot 
Weijnen for her scientific advice and astute feedback on the thesis and Prof. Wil Kling for the his support on 
understanding  the  working  of  complex  electricity  systems  and  components  and  sharing  his  knowledge  of 
electricity markets. I would like to thank Martijn Jonker for being on my graduation committee. 

I would especially like to thank people from the Ministry of Economic Affairs, Andre Jurjus, Lineke den Ouden, 
Jon Eikelenstam and Kick Bruin for their valuable feedback and insightful discussions. Their presence gave a 
direction to an otherwise very broad project. Their questions and deadlines were essential to keep the project 
on tractable both in terms of focus and duration. 

I would also thank my fellow students especially, Siamak Vaezpour and Paul Dailey, for sharing thoughts and 
offering  an  avenue  for  venting  difficulties  during  much  needed  and  unforgettable  coffee  brakes.  I  want  to 
thank them for all their help, support, interest and valuable hints. 

I  feel  profoundly  indebted  to  TU  Delft  and  Dutch  Ministry  of  Education  for  offering  me  financial  assistance 
during my graduate studies without which I could not have possible undertaken studies in the Netherlands. 

Finally and especially, I would like to give my special thanks to my family members back home whose patient 
love and encouragement enabled me to complete this work. 

 
August 2007 
Manoj   
   
 

1 ABSTRACT 
 

Since  late  90’s  the  European  electricity  market  has  been  opened  aiming  towards  development  of  a  single 
organized  competitive  internal  electricity  market.  However  given  the  limited  capacities  on  the  tie‐lines 
between countries achieving a single market is not a possibility yet. Congestion on these tie‐lines separates 
geographic markets into submarkets. Indeed cross‐border congestions run counter to the idea of the creation 
of  a  competitive  market.  Because  one  cannot  build  infrastructures  of  infinite  capacities,  congestion  is 
unavoidable but should not be excessive – and it is desired to economically allocate the limited transmission 
resource. In that context the optimal utilization of the available capacities is a major issue. To be economically 
efficient  the  price  of  transmission  capacity  should  be  based  on  its  marginal  utility.  However,  the  path  that 
electricity will take to reach from point A to point B connected by a meshed network is hard to predict on the 
day‐ahead  basis. Flow  based market  coupling (FMC) is a  suggested mechanism  for  cross‐border congestion 
management for the Northwest continental European region which takes into account both the market and 
technical aspects of system to calculate dispatch.  

The  Dutch  government  has  expressed  interest  in  possibility  of  further  regional  market  integration.  Though 
FMC holds a promise of being an upgrade over the current mechanisms, it still is a complex mechanism and is 
often  not  completely  understood.  It  is  thus  necessary  to  further  research  FMC  to  be  able  to  identify  and 
delineate  possible  technical  and  economical  implications  from  its  implementation  and  search  prognostic 
solutions prior to its introduction.  

 This master thesis aims first at giving an understanding of the flow based method. Second objective of the 
work  was  to  try  validating  the  claims  of  efficiency  and  welfare  gains  offered  by  flow‐based  method.  This 
entailed  designing  a  decision‐support  model  based  on  the  technical‐economic  realities  which  contribute  to 
making  some  of  the  major  issues  ‘transparent’  to  the  decision  makers  –  in  current  case  Dutch  Minister  of 
Economic  Affairs.  The  decision  support  model  was  based  on  realistic  data  from  the  four  countries  involved 
with FMC and delineates the effects on both regional and national level also offering an understanding into 
the  distribution  of  benefits  and  costs  amongst  the  involved  actors.  These  results  would  help  in  further 
progress  towards  acceptance  and  implementation  of  FMC.  In  the  last  part  of  the  work  institutional  aspects 
involved  with  adoption  of  flow‐based  method  were  studied  be  highlighted  along  with  listing  of  important 
actors, since though FMC might theoretically be efficient to reap these benefits in reality it will require a total 
coordination of all the actors concerned, and commitment from the involved governments. 

This report aims to be useful for people working on a project related to the cross‐border electricity exchanges‐ 
especially FMC. The report is written in a manner that it would be understandable to a person with no prior 
specialized knowledge of electricity networks or economics, though a basic understanding of concepts from 
electricity markets would be of assistance. Report will be useful for anybody who is interested in cross‐border 
electricity  exchanges  even  if  it  is  not  his  domain  of  study,  with  special  focus  on  the  North  West  European 
markets. 

Keywords: power system, electricity market, cross‐border exchanges, flow‐based market coupling. 

   
Chapter: Abstract 

  i 
 
ii  Flow‐based Market Coupling 
 

   
 

2 GLOSSARY 

2.1 COUNTRY CODES 
NL    Netherlands 

BE    Belgium 

FR    France 

DE    Germany 

2.2 OTHER ABBREVIATIONS 
Abbreviation   Signification  

   
HV   High Voltage  

ISO   Independent System Operator  

TSO   Transmission System Operator  

ETSO   Association of European Transmission System Operators  

UCTE   Union for the Coordination of Transmission of Electricity  

NTC   Net Transfer Capacity  

ATC   Available Transfer Capacity  

PTDF   Power Transfer Distribution Factor  

MCP  Marginal Clearing Price 

NWER  North‐West European Region 

OECD  Organisation for Economic Co‐operation and Development  

FC  Fixed cost 

VC  Variable Cost 

TC  Total Cost 

AD  Average demand 

Q*  Equilibrium demand/supply quantity 

P*  Equilibrium price 

LMP  Locational Marginal Pricing 

EC  European Commission 

CM  Congestion Management 
Chapter: Glossary 

FMC  Flow‐based Market Coupling 

  iii 
 
iv  Flow‐based Market Coupling 
 

TLC  Trilateral Market Coupling 

EDF   Electricité de France 

RTE   Réseau de Transport Electrique  

MC  Market Coupling 

2.3 DEFINITIONS 
 

∙  Power  system:  Set  of  means  of  electricity  production,  transport  and  distribution  and  loads  (national 
electricity network) 

∙ Marginal clearing price: Price of the last selected bid in the merit order. 

∙ Spot price: Price set by the intersection of the selling and the buying bids on the spot market. 

∙ Explicit auction: Auction where the product sold is a right to program an exchange on a given contractual 
path. 

∙  Implicit  auction:  Auction  for  which  the  allocations  capacities  are  combined  with  the  functioning  of  an 
organized electricity market. 

∙ Market coupling: Consists in a coupling of N markets, according to a decentralized approach, resulting in a 
unique virtual market as long as the interconnections capacities are not saturated. 

∙  Market  splitting:  One  market  which  is  split  in  N  independent  virtual  markets  when  the  capacities  are 
saturated. 

∙ Market value: The linear combination between the bid price and the allocated capacity 

∙  NTC:  The  net  transfer  capacity  represents  the  best  estimate  limit  for  physical  electricity  transfer  between 
two areas 

∙ ATC: The available capacity which can be defined for different periods of time (year, month, day…) 

∙  Critical  branch:  A  line  of  the  network  which  could  probably  limit  the  commercial  exchanges  between  the 
areas because it often reaches its physical limits. 

∙  Participating  nodes:  These  nodes  represent  the  junction  point  of  the  units  to  the  network  where  the 
production varies significantly when the total production of the zone varies. 

∙ PTDF: Based on a state of the initial network, this is the influence on the flow on a critical branch of every 
additional MW injected at a participating node. 

∙ Netting: Take into account that the exchanges in an opposite direction counterbalance each other. 

.  Fmax:  The  maximum  amount  of  electricity  that  can  be  exported  or  imported  by  a  country  depends  on  the 
capacity of the interconnector, this is called the Flow‐gate capacity (Fmax), calculated according to flow based 
method 
 

. Fref: A part of the maximum allowed flow on the critical branches is already used (i.e. prior to the allocation) 
by so‐called already‐occupied flows, this is termed as Fref, this is calculated considering flow based method 

∙ Approximation of the direct current load flow solution: approximation where the following hypotheses are 
taken into account: 

‐ Vi =VN, where VN is the corresponding nominal voltage 

‐ R=0 

‐ No losses 

‐ The angles θ between nodes are small and thus sin(θ) ~ θ 

   

Chapter: Glossary 

  v 
 
vi  Flow‐based Market Coupling 
 

   
 

3 STRUCTURE OF REPORT 
 

 
Section 1 Electricity Markets 
Appendix 
 
This section gives a brief introduction to the specifics of 
the electricity markets. Details the history of congestion  All  graphs  and  numbers  for 
  the results are attached with 
management in electricity followed by an introduction to 
the  the appendix. 
  idea  of  flow  based  market  coupling  for  managing 
congestion. 
Other important documents 
  Section 2 Simulation Model 
  can  also  be  found  in  the 
  A  step  by  step  description  of  how  the  model  was  Appendix.  Report  refers  to 
created  is  presented  in  this  section.    Details  and  appendix. 
  relevant data is presented in the appendices. 
 
   
 
 
 
 
Section 3 Results 
 
Here the results from the model are 
   
presented and conclusion are drawn 

Section 4 Market Design Issues   

The  final  section  of  the  report  sums  up  the  research  by   
identifying  and  delineating  the  risks  and  issues  associated 
with implementation of a new market design in a multi‐actor 
setting. The main focus would hinge around the institutional 
and informational aspects 

Conclusions and Reflection 

The  conclusion,  reflections  and  scope  for  future  work  is 


outlined in this section. 

 
Chapter: Structure of Report 

  vii 
 
viii  Flow‐based Market Coupling 
 

 
   
 

CONTENTS 
 
1  Abstract .................................................................................................................................................... i 
2  Glossary ................................................................................................................................................. iii 
2.1  Country Codes................................................................................................................................ iii 
2.2  Other Abbreviations ....................................................................................................................... iii 
2.3  Definitions ..................................................................................................................................... iv 
3  Structure of Report ................................................................................................................................ vii 
Figures .......................................................................................................................................................... xiv 
Tables ........................................................................................................................................................... xvi 
1  European Electricity markets ................................................................................................................... 3 
1.1  Background ..................................................................................................................................... 4 
1.2  Electricity – The special Case ........................................................................................................... 4 
1.3  Present European electricity system................................................................................................ 5 
1.4  March towards Internal Energy markets .......................................................................................... 7 
1.5  Conclusion ...................................................................................................................................... 8 
2  Congestion Management ...................................................................................................................... 10 
2.1  Congestion Management Methods ............................................................................................... 10 
2.2  Trilateral Market Coupling ............................................................................................................. 12 
2.3  Market splitting ............................................................................................................................. 15 
2.4  Locational marginal prices (LMP) .................................................................................................. 16 
2.5  Conclusion .................................................................................................................................... 16 
3  Flow‐based market coupling .................................................................................................................. 18 
3.1  Operation of market under FMC .................................................................................................... 19 
3.2  Flow Based Modeling .................................................................................................................... 20 
3.3  Market Coupling............................................................................................................................ 20 
3.4  Market Process of FMC ................................................................................................................. 20 
3.5  difference between FMC and Market Coupling .............................................................................. 21 
3.6  Conclusion .................................................................................................................................... 23 
4  Problem Formulation ............................................................................................................................. 25 
4.1  Problem Statement ....................................................................................................................... 25 
4.2  Scope Definition ............................................................................................................................ 25 
4.2.1  Geographical Scope .................................................................................................................. 25 
Chapter: Structure of Report 

4.2.2  Temporal Scope ........................................................................................................................ 26 
4.3  Perspective/Problem owner .......................................................................................................... 26 
4.4  Sub‐Questions .............................................................................................................................. 26 
4.4.1  System behavior ....................................................................................................................... 27 
4.4.2  Security of supply ...................................................................................................................... 27 

  ix 
 
x  Flow‐based Market Coupling 
 

4.4.3  Welfare effects .......................................................................................................................... 27 
4.4.4  Implementation issues .............................................................................................................. 27 
4.5  Research design ............................................................................................................................ 27 
5  Structure of Simulation Model ............................................................................................................... 31 
5.1  Transmission network module ...................................................................................................... 32 
5.1.1  Power Transfer Distribution Factor ........................................................................................... 33 
5.1.2  Use of PTDF .............................................................................................................................. 34 
5.1.3  Calculation of PTDF in PowerWorld .......................................................................................... 34 
5.1.4  How to get PTDF from PowerWorld .......................................................................................... 35 
5.2  Electricity demand and supply module .......................................................................................... 37 
5.2.1  Supply Curve ............................................................................................................................. 38 
5.2.2  Cost of electricity generation .................................................................................................... 38 
5.2.3  Installed generation capacity .................................................................................................... 41 
5.2.4  Calculation of Supply Curve Slope ............................................................................................. 42 
5.2.5  Demand Curve .......................................................................................................................... 43 
5.3  Tie line capacity ............................................................................................................................ 44 
5.4  Electricity day‐ahead market module ............................................................................................ 46 
5.4.1  Equilibrium without Market Coupling ........................................................................................ 47 
After Market Coupling ........................................................................................................................... 48 
5.5  Model Outputs .............................................................................................................................. 53 
5.5.1  Outputs for the Non‐Coupled markets ...................................................................................... 53 
5.5.2  Outputs for the coupled markets ............................................................................................... 53 
5.5.3  Overall Results .......................................................................................................................... 54 
5.5.4  Comparative Results ................................................................................................................. 54 
Capacity Utilization Results ................................................................................................................... 54 
5.6  Graphs .......................................................................................................................................... 54 
6  Validation and Verification of model ...................................................................................................... 56 
6.1  Validation of transmission model .................................................................................................. 56 
6.2  Quality of data used for supply curve ............................................................................................. 56 
6.3  Quality of data used for average demand ...................................................................................... 57 
6.4  Price of electricity without imports and exports ............................................................................ 59 
6.5  Validation of PTDF values from Power World ................................................................................ 60 
6.6  Conclusions ................................................................................................................................... 60 
7  Results ................................................................................................................................................... 65 
7.1  Base Case ...................................................................................................................................... 65 
7.1.1  Price of Electricity ..................................................................................................................... 65 
7.1.2  Electricity Demand .................................................................................................................... 66 
7.1.3  Welfare Data ............................................................................................................................. 67 
 

7.1.4  Interconnector Capacity Utilization ........................................................................................... 68 
7.1.5  Conclusions from base case ....................................................................................................... 69 
7.2  Current Situation vs FMC............................................................................................................... 69 
7.3  Comparison of FMC with Market Coupling .................................................................................... 71 
7.4  Scenarios ...................................................................................................................................... 76 
7.4.1  Increase generation capacity in Netherlands ............................................................................. 76 
7.4.2  Increased tie‐line capacity ......................................................................................................... 80 
7.4.3  Discussion on sensitivity of PTDFs ............................................................................................. 84 
7.4.4  Effect of Carbon Market ............................................................................................................ 86 
7.4.5  Decoupling of German system into North and South Block ....................................................... 92 
8  Actor Analysis ........................................................................................................................................ 96 
8.1  General Overview .......................................................................................................................... 96 
8.2  Structure of the electricity markets ............................................................................................... 97 
8.3  List of actors ................................................................................................................................. 98 
8.4  Interests ...................................................................................................................................... 100 
8.4.1  Generators .............................................................................................................................. 100 
8.4.2  Consumers .............................................................................................................................. 100 
8.4.3  Regulator ................................................................................................................................ 100 
8.4.4  Government ............................................................................................................................ 100 
8.4.5  Traders ................................................................................................................................... 100 
8.4.6  TSO ........................................................................................................................................ 100 
8.4.7  Power Exchanges .................................................................................................................... 101 
8.5  Position of Actors ........................................................................................................................ 101 
8.5.1  Power Exchanges .................................................................................................................... 102 
8.5.2  Generators .............................................................................................................................. 102 
8.5.3  TSOs ....................................................................................................................................... 103 
8.6  Strategic Generators ................................................................................................................... 104 
8.7  Questions raised by the actors .................................................................................................... 105 
8.7.1  Regulator ................................................................................................................................ 105 
8.7.2  TSO ........................................................................................................................................ 105 
8.7.3  Power Exchange ..................................................................................................................... 105 
8.8  Results from FMC ........................................................................................................................ 105 
8.9  Conclusions ................................................................................................................................. 106 
Chapter: Structure of Report 

9  Market design issues ........................................................................................................................... 109 
9.1  Legal and Organizational Issues .................................................................................................. 109 
9.2  Technical Issues........................................................................................................................... 109 
9.3  Market related issues .................................................................................................................. 110 
9.3.1  Transparency towards the market ........................................................................................... 110 

  xi 
 
xii  Flow‐based Market Coupling 
 

9.3.2  Economic signals to market participants and sharing of congestion income ............................ 110 
9.3.3  Liabilities of TSOs and position of individual regulatory authorities ......................................... 110 
9.4  Technical implementation issues ................................................................................................. 110 
9.4.1  Regional Base Case ................................................................................................................. 110 
9.4.2  Phase‐shifting transformers .................................................................................................... 111 
9.4.3  Network representation .......................................................................................................... 111 
9.4.4  Generation representation ...................................................................................................... 111 
9.4.5  Definition of flow‐gate capacity (Fmax) ..................................................................................... 111 
9.4.6  Type of bids ............................................................................................................................ 112 
9.5  Possible solutions ........................................................................................................................ 112 
10  Conclusions ......................................................................................................................................... 113 
10.1  System behavior ......................................................................................................................... 113 
10.2  Security of supply ........................................................................................................................ 114 
10.3  Welfare effects ............................................................................................................................ 115 
10.4  Implementation issues ................................................................................................................ 115 
11  limitations and Research recommendations ......................................................................................... 117 
11.1  Limitations of the study ............................................................................................................... 117 
11.2  Research recommendations ......................................................................................................... 117 
A  Appendix ............................................................................................................................................. 119 
A.1  Cost of electricity generation model ................................................................................................ 1 
A.2  Data sources and assumptions for Cost of electricity generation model .......................................... 5 
A.3  National Supply Curves ................................................................................................................... 8 
A.4  Average Historical Market Price of Electricity ................................................................................ 11 
A.5  Demand Worksheet from Market Module ..................................................................................... 14 
A.6  Tie line Capacities ......................................................................................................................... 15 
A.7  Power Transfer Distribution Factors for North‐West European Region .......................................... 17 
A.8  Electricity day‐ahead market module ............................................................................................ 18 
A.8.1  Constraints .................................................................................................................................... 18 
A.8.2  Objective Function ........................................................................................................................ 18 
A.9  Electricity day‐ahead market Results ............................................................................................ 19 
A.10  Capacity Utilization Results ........................................................................................................... 20 
A.11  Comparison of Market Coupling with Flow‐based Market Coupling............................................... 21 
A.11.1  Base Case Flow‐based market coupling ................................................................................ 21 
A.11.2  Base Case Flow‐based market coupling with NL reserving 1500MW on DE‐NL border .......... 22 
A.11.3  Market Coupling ................................................................................................................... 23 
A.12  Result of FMC after installation of 5000MW of coal based power plants in NL ............................... 27 
A.13  Result of FMC after installation of 10,000 MW of coal based power plants in NL ............................ 28 
A.14  Result of FMC after installation of 2000 MW transmission capacity between DE‐NL ..................... 29 
A.15  Increase tie line capacity between Fr‐BE +2000MW ....................................................................... 30 
 

A.16  Result of FMC after installation of 5000 MW transmission capacity between DE‐NL ..................... 31 
A.17  Result of FMC after installation of 10,000 MW transmission capacity between DE‐NL ................... 32 
A.18  Result of FMC after installation of 2000 MW transmission capacity between DE‐NL with PTDF from 
5000 MW case............................................................................................................................................ 33 
A.19  Effect of Carbon Market ................................................................................................................ 34 
A.18.1  FMC results with emission price of 15 €/ton of CO2 ................................................................ 34 
A.18.2  FMC results with emission price of 20 €/ton of CO2 ............................................................... 35 
A.18.3  FMC results with emission price of 30 €/ton of CO2 ................................................................ 36 
A.18.4  FMC results with emission price of 50 €/ton of CO2................................................................ 37 
A.20  List of Actors ................................................................................................................................. 38 
A.19.1  Netherlands .......................................................................................................................... 38 
A.19.2  Belgium ................................................................................................................................ 39 
A.19.3  France ................................................................................................................................... 40 
A.19.4  Germany ............................................................................................................................... 42 
Bibliography .................................................................................................................................................. 43 
Websites ........................................................................................................................................................ 46 
 

 
   

Chapter: Structure of Report 

  xiii 
 
xiv  Flow‐based Market Coupling 
 

FIGURES 
 

Figure 1 Present state of integration of electricity markets in Europe ............................................................... 3 
Figure  2  Percentage  of  flows  in  FR‐BE‐NL‐DE‐CH‐A‐I  zone  for  a  commercial  transaction  of  1  MWh  from 
France to Germany (IEA Workshop Presentation 2004) .................................................................................... 6 
Figure 3 Planned increase of interconnections in the EU (% of installed generation capacity). .......................... 8 
Figure 4 Current congestion management methods in NWE region ............................................................... 12 
Figure 5 Prices after implementation of TLC showing convergence (http://www.apxgroup.com) ................... 13 
Figure 6 Physical energy flows in 2006 (all values in GWh) from http://www.ucte.org .................................... 13 
Figure 7. Outline of FMC a combination of flow based modelling that takes care of the physical flow path and 
market coupling to maximize the competition and efficiency of electricity markets (ETSO and EuroPEX JWG 
2004) ............................................................................................................................................................. 19 
Figure 8. Market Coupling between two markets leading to increase in the net welfare (based on  H. de Jong 
and R. Hakvoort, 2005) .................................................................................................................................. 20 
Figure  9.  The  process  of  pricing  under  FMC,  this  will  be  modelled  for  a  simplified  market  case  to  create  a 
software model that helps understand the market operation better (ETSO and EuroPEX JWG 2004) ............ 21 
Figure 10 Transfer capacity definitions ........................................................................................................... 22 
Figure 11 Interdependencies of NTC between two araes (http://www.etso‐net.org) ....................................... 23 
Figure 12 The system under consideration ..................................................................................................... 26 
Figure 13 Research design .............................................................................................................................. 28 
Figure 14 Design of the simulation environment ............................................................................................ 31 
Figure 15 Interconnected Network of UCTE (http://www.ucte.org/) ............................................................... 32 
Figure  16  Physicl  flows  because  of  a  transaction  of  100  Units  of  trade  between  France  and  Germany 
(http://www.etso‐net.org) .............................................................................................................................. 33 
Figure 17 Generic Reference case for calculation of PTDF ............................................................................... 33 
Figure 18 Schematic of the Transmission Network Module ............................................................................ 34 
Figure 19 THe utilization of interconnector between the countries in the nort‐west european region from the 
modle run in PowerWorld .............................................................................................................................. 35 
Figure 20 UCTE network with enhanced NL‐BE border .................................................................................. 36 
Figure 21 Schematic of the Electricity Demand and Supply Module ............................................................... 38 
Figure 22 The equation of the demand function for the North‐West European Region ................................... 44 
Figure  23  Tie  Line  capacity  for  the  north  west  european  electricity  network  (based  on  data  from  website  of 
Tennet, RTE, RWE, Elia and TSO auction website) ......................................................................................... 45 
Figure 24 Schematic of the Market Moduel .................................................................................................... 46 
Figure 25 Principle of MCP (from http://www.apxgroup.com) ........................................................................ 47 
Figure 26 The definition of consumer surplus and producer surplus................................................................ 47 
Figure 27 Simple Stylized electricity market ................................................................................................... 48 
Figure 28 Effect of import and export on prices and quantity in the country ................................................... 49 
Figure 29 Welfare Calculations after inter country trade ................................................................................ 50 
Figure 30 Optimization using MS Excel Solver ................................................................................................ 51 
Figure 31 Optimization parameters ................................................................................................................ 51 
Figure 32 Effect of an inelastic demand for deciding the objective function .................................................... 52 
Figure 33 Merit order curves  for the North‐West European Region, model data and  comparision with actual 
data from the past ......................................................................................................................................... 57 
Figure 34 Load duration curve for Netherlands ............................................................................................... 58 
Figure 35 Load Duration Curve Belgium ......................................................................................................... 58 
Figure 36 Load duration curve for France ....................................................................................................... 58 
Figure 37 Load Duration curve for Germany ................................................................................................... 59 
 

Figure  38  Comparision  of  wholesale  price  of  electricity  based  on  the  model  and  actual  past  data  from  the 
power exchanges for year 2005‐07 ................................................................................................................. 59 
Figure 39  MCP, equilibrium demand and surplus calculation without market coupling .................................. 65 
Figure 40 Traded volumes for FMC and Trilateral Market Coupling comparision ............................................ 69 
Figure 41 results from simulation model for current state of trade in north west European region.................. 71 
Figure 42 Flow Direction for comparision of FMC with NTC based Market Coupling ....................................... 72 
Figure 43 New Supply curve with additional 5 GW of hard coal based power plant ......................................... 77 
Figure 44 Price change in NL, Imports and % tie line utilization for scenario with installation of 5000 MW coal 
based generation in NL .................................................................................................................................. 77 
Figure 45 New supply curve with additional 10,000 MW of hard coal based power plants ............................... 78 
Figure  46  Price  change  in  NL,  Imports  and  %  tie  line  utilization  for  scenario  with  installation  of  10,000  MW 
Hard coal based generation in NL .................................................................................................................. 79 
Figure 47 The dialog in PowerWorld to set up the values of parameters for the transmission line ................... 80 
Figure 48 New tie‐line capacity values............................................................................................................ 81 
Figure 49 Results from FMC after installation of 2000 MW transmission line between DE‐NL ........................ 82 
Figure 50 Price change after installation of +2000MW on NL‐DE Tie‐Line ...................................................... 83 
Figure 51 Price change with installation of +2000MW on BE‐FR Tie Line ........................................................ 83 
Figure 52 Utilization of flow line with +2000 MW on BE‐FR line, COmapre to Figure 45 .................................. 83 
Figure 53 Results from FMC after installation of 5000 MW transmission line between DE‐NL ......................... 84 
Figure 54 Price change and % Utilization from +2000MW on DE‐NL Border and PTDF's also from +2000MW 
case ............................................................................................................................................................... 85 
Figure  55  Price  change  and  %  utilization  of  interconnector  from  +2000MW  capacity  on  DE‐NL  border  and 
PTDFs from +5000MW ................................................................................................................................... 85 
Figure  56  Contribution  of  Electricity  and  heat  generation  towrds  total  carbon  emissions 
(http://www.defra.gov.uk/environment/climatechange/trading/eu/index.htm). ............................................. 86 
Figure 57 Development of Carbon prices in EU, Including the crash in april 2006 (SOurce: Point Carbon) ....... 86 
Figure 58 Effect of carbon pricing on the merit order within north‐west european region .............................. 89 
Figure 59 Results from FMC after considering carbon pricing ......................................................................... 91 
Figure 60 The divisionof Germany into north and south block ........................................................................ 93 
Figure 61 Flows after splitting germany into north and south blocks .............................................................. 93 
Figure 62 Annual share of daily wind power in respective daily peak demand on e‐on grid (Germany) ........... 94 
Figure  63  The  difference  between  transit  and  loop  flows  (Green  arrows  mark  the  transit  flows,  Grey  arrows 
mark the Loop Flows) .................................................................................................................................... 95 
Figure 64 The electricity value chain .............................................................................................................. 97 
Figure 65 Present position of the power exchanges ...................................................................................... 102 
Figure 66 Main strategic actors for the norty‐west European region (From vattenfall annual report 2006) ... 103 
Figure 67 The common data for cost of electricity ............................................................................................ 1 
Figure 68 Fixed cost data for electricity generation .......................................................................................... 1 
Figure 69 Variable cost data for electricity generation along with emission costs ............................................. 2 
Figure 70 Formulation for the capital cost calculations ..................................................................................... 3 
Figure 71 Formulaiton of the Variable and Total cost ........................................................................................ 4 
Figure 72 Data points for the merit curve (supply curve) ................................................................................... 8 
Figure 73 Supply curve for Netherlands ............................................................................................................ 8 
Figure 74 Electricity supply curve for Belgium .................................................................................................. 9 
Figure 75 Electricity supply curve for France ..................................................................................................... 9 
Figure 76 Electricity supply curve for Germany ............................................................................................... 10 
Chapter: Figures 

Figure 77 Equation of the supply curves (linear regression on the merit order curves) ..................................... 10 
Figure 78 Distribution of MCP for Netherlands APX, year 2006‐07.................................................................. 11 
Figure 79 Distribution of MCP for Belgium Belpex, year 2006‐07 .................................................................... 11 

  xv 
 
xvi  Flow‐based Market Coupling 
 

Figure 80 Distribution of MCP for France Powernext, year 2006‐07 ................................................................ 12 
Figure 81 Distribution of MCP for Germany EEX, September 06 – Jun. 07 ....................................................... 12 
Figure 82 Demand Work Sheet Values ........................................................................................................... 14 
Figure 83 Demand Worksheet Formulation .................................................................................................... 14 
 

TABLES 
Table 1 Senstivity matrix and PTDF based on the UCTE winter peak model from PowerWorld ....................... 37 
Table 2 Categories of generation technologies .............................................................................................. 38 
Table 3. Total cost of generation for different technologies ........................................................................... 40 
Table 4 Formulation of Cost sheet .................................................................................................................. 40 
Table 5 Installed generation capacities in the north west european region ..................................................... 42 
Table 6 Supply curves slope for the four countries. ......................................................................................... 42 
Table 7 Average demand of electricity based on the UCTE system adequacy forecast 2007‐20 ...................... 43 
Table 8 Reliable generation capacity based on the UCTE system adequacy forecast 2007‐20 ......................... 43 
Table 9 Output list for model from non‐coupled markets ............................................................................... 53 
Table 10 Outputs from the model after FMC .................................................................................................. 53 
Table 11 Comparative results from the model between FMC case and the base case ...................................... 54 
Table 12 Capacity utilization results from the simulation model ..................................................................... 54 
Table 13 Comparision of average demand of electricity used in the model and historical data ........................ 58 
Table 14 PTDF value comparison from power world model to actaul published values ................................... 60 
Table 15 Parameters for the new transmission line between DE‐NL ............................................................... 80 
Table 16 Comparision of the PTDF values before and after installation of 2000 MW transmission line between 
DE‐NL ............................................................................................................................................................ 81 
Table 17 Comparision of the PTDF values before and after installationof 5000 MW transmission line between 
DE‐NL ............................................................................................................................................................ 83 
Table  18  Impact  of  Carbon  pricing  on  the  merit  order  based  on  fuel  and  energy  technology  type  (the  items 
marked with olive are the once that moved) .................................................................................................. 87 
Table 19 Average demand in north‐west european region (UCTE system Adequacy report 2007‐20) ............. 90 
Table 20 PTDF values after splitting Germany into North and south block ..................................................... 94 
Table 21 General characteristics of the north west european electricity market ............................................. 96 
Table 22 List of all relevant actors for the north west european region ........................................................... 98 
Table 23 Interests of the actors and the quantifying/qualifying parameter ................................................... 101 
Table 24 Share of generaion companies in the total generation within north west european region............. 102 
Table 25 Details about the most strategic players in the North west european market ................................. 104 
Table 26 Actors perception of FMC .............................................................................................................. 105 
Table 27. Total cost of generation for different technologies based on Vattenfall 2006. ................................... 5 
Table 28 Consolidated MCP data for centre west European region for 2006‐07 .............................................. 13 
Table 29 TIe line capacity values .................................................................................................................... 16 
 

 
   

Section 1: Electricity Markets  

A general introduction to the electricity 
markets  followed  by  focus  on  the 
European system in general and north‐
west  European  region  in  particular. 
Congestion  management  methods  are 
introduced.  Flow‐based  market 
coupling  is  also  explained.  The  section 
concludes with problem definition. 

Chapter: Tables 

  1 
 
2  Flow‐based Market Coupling 
 

   
 

1 EUROPEAN ELECTRICITY MARKETS 
 

With  the  opening  of  the  electricity  markets  in  Europe  through  the  Directive  (EU96/92)  enforced  on  19 
February  1999,  the  European  market  integration  could  not  result  into  a  copper  plate.  The  variety  of 
generation mixes among the fifteen member countries, and the state of interconnection ties between them, 
has resulted into regional markets interfaced by bottlenecks, rather than into a single market with a unique 
price.  European  Authorities  have  quickly  understood  this  situation  and  defined  a  new  European  Regulation 
enforced  since  1  July  2004,  which  promotes  market  based  congestion  management  mechanisms,  able  to 
provide efficient use of the interconnection as well as appropriate market signals giving the right incentives 
for transmission or generation investments. 

EU Vision 

 
 

27 Individual electricity markets  One Integrated (internal) electricity market 
Current Progress 

Chapter: European Electricity markets 

Several regional markets 

FIGURE 1 PRESENT STATE OF INTEGRATION OF ELECTRICITY MARKETS IN EUROPE ‐ BASED ON (PETER SIMIG, CONGESTION 
MANAGEMENT  PRACTICE  AT  CROSS‐BORDER  TRADE  IN  ERRA  REGION,  ERRA  EU  INTEGRATION  WORKING  GROUP, 
BUDAPEST, HUNGARY, 13 SEPTEMBER 2004)

  3 
 
4  Flow‐based Market Coupling 
 

1.1 BACKGROUND 
1
Europe  faces  the  problem  of  congestion   on  the  inter‐country  electricity  transmission  networks 
2
(interconnectors ). Notice that the EU definition on congestion is focused only on interconnector congestion, 
however it must be realized that congestion can also occur in the internal network. The investment in building 
new  lines  is  a  feasible  long  term  solution;  however  the  capital  costs  are  high  and  return  on  investment 
depends strongly on both the regulatory environment and the future cross country demand‐supply trends. As 
a  short  term  operational  solution  regulators  and  system  operators  spend  considerable  time  in  trying  to 
optimally allocate capacity at interconnectors.  

In  its  preliminary  sector  enquiry  report  (ENERGY  SECTOR  INQUIRY  2006),  DG  Competition  (European 
Commission)  concluded  that  market  integration  in  the  European  electricity  sector  is,  among  others, 
hampered by insufficient interconnector capacity. Besides the interconnector congestion issue there are two 
other important reasons for concern namely; the deficiency of incentives harbored in the current congestion 
management  methods  for  maintaining  a  desirable  level  of  investment  in  additional  capacity  and  a  lack  of 
regulations/incentives to enforce/ensure efficient use of existing capacity. 

The  fact  that  electricity  does  not  follow  the  contract  path,  but  flows  in  the  network  governed  by  Kirchoffs 
Laws  makes  the  design  of  a  suitable  market  mechanism  for  pricing  the  transactions  difficult.  For  meshed 
transmission  network,  each  flow  has  an  effect  on  power  flow  conditions  over  the  whole  system;  the  new 
congestion  management  guidelines  (amending  the  existing  annex  to  the  European  Regulation  (EC) 
1228/2003)  entered  into  force  1  December  2006.  These  new  binding  guidelines  prescribe  that  TSOs  should 
implement a flow based allocation system as soon as possible. However, currently ministries, regulators and 
maybe even TSOs have no clear overview of the political and regulatory consequences; e.g. the effect on the 
security of supply of an individual nation, the effect of transparency, the effect on the national welfare, etc. To 
be  able  to  answer  these  questions  it  is  important  to  understand  the  behavior  of  FMC  and  explore  the 
sensitivities  of  the  system  that  can  be  exploited  by  market  participants.  The  thesis  work  aims  to  create  a 
simplified representative model of the north‐west European electricity market under FMC; this would be used 
to understand the issues that might arise from implementation of FMC. The results would help the Ministries 
and  regulators  in  understanding  FMC  and  its  behavior  and  also  figuring  out  what  to  ask  from  the  involved 
actors.   

1.2 ELECTRICITY – THE SPECIAL CASE 
Several significant features that distinguish the electricity industry from others contribute to the structure of 
market institutions: 
1. Nonstorability 
2. Intertemporal and random variability of demand 
3. Necessity of balance in an interconnected transmission network 
4. Direct connections to customers without any buffers 
5. Capital intensity and economies of scale 
The demand for electricity varies continuously and unpredictably from hour to hour, day to day, and season to 
season. Practically, however, electricity cannot be stored. 
                                                                         
1
 Regulation  on  cross‐border  trade of electricity (Regulation 1228/2003) Article  2 paragraph 2(c), provides 
definition  for  congestion  involving  international  transactions:  ‘‘congestion  means  a  situation  in  which  an 
interconnection  linking  national  transmission  networks  cannot  accommodate  all  physical  flows  resulting 
from  international  trade  requested  by  market  participants,  because  of  a  lack  of  capacity  of  the 
interconnections and/or the national transmission systems concerned’’ 

2
 High‐voltage links that couple national electricity systems and facilitate international competition 
 
 

In  an  interconnected  network,  the  demand  and  supply  of  electricity  must  be  balanced  instantaneously  over 
time at every point  of the network to maintain  frequency, voltage, and system stability and to avoid power 
outages. Unlike other types of networks, electricity in an AC electric transmission network flows in directions 
determined  by  physical  laws  rather  than  by  contracts  and  therefore  is  more  difficult  to  control.  A  local 
variation of demand or supply of electricity affects power flows throughout the interconnected network. An 
equipment  failure  in  one  part  of  the  network  can  cause  the  entire  system  to  collapse.  Efficiently  meeting  a 
new demand may involve coordinated adjustments of generators located far from the source of the demand. 
Therefore,  the  transmission  system  does  not  provide  a  simple  physical  connection  between  electricity 
generation  and  consumption  facilities;  it  also  involves  active  coordination  of  generating  units  dispersed 
throughout the network to meet variations in demand and supply.  

Due  to  these  technical  characteristics,  electricity  markets  are  inherently  incomplete.  The  centralized 
organization  afforded  under  the  traditional  structure  of  vertical  integration  facilitated  the  essential  task  of 
coordinating  efficient  system  operation  and  balancing  the  supply  and  demand  of  electricity  continuously  in 
response  to  changing  system  conditions.  The  challenge  now  is  to  design  a  market  organization  that  can 
accomplish  system  coordination  in  transmission  without  compromising  the  opportunities  for  market 
competition in energy. 

1.3 PRESENT EUROPEAN ELECTRICITY SYSTEM 
The  north‐west  European  region  is  a  subset  of  the  larger  synchronous  UCTE  region  composed  of  18 
continental  European  countries:  Portugal,  Spain,  France  (FR),  Belgium  (BE),  Luxemburg,  Switzerland,  Italy, 
Netherlands  (NL),  Germany  (DE),  Denmark  west,  Czech  Republic,  Slovakia,  Poland,  Austria,  Hungary, 
Slovenia,  Croatia  and  part  of  Bosnia  and  Herzegovina.  Synchronous  interconnection  means  that  individual 
systems are connected and being run together, at the same frequency, and assist each other if a disturbance 
occurs in a system. Vice‐versa this also means that major disturbances might propagate throughout this whole 
interconnected  system  and  endanger  its  stability.  UCTE  is  composed  of  the  highly  meshed  system  of  24 
European countries consisting of some 200,000 km of 400 and 220 kV lines, hundreds of generating capacities 
directly linked to the system, and hundreds of substations (www.ucte.org). Within a meshed system there will 
be  parallel  flows,  which  are  hard  to  predict  in  advance.  However,  they  would  use  up  the  available  transfer 
capacity on the interconnectors. From an economic efficiency viewpoint both transit and loop flows should be 
charged  for  the  marginal  and  opportunity  cost  of  using  the  available  capacity.  However  the  system  is 
governed  by  physical  laws  that  do  not  follow  economic  reasons.    Power  flows  over  the  multiple  paths 
between  supply  and  use  according  to  least  impedance,  and  not  according  to  the  shortest  path  or  the  path 
with the most unused capacity.  

In the present scenario tie‐line capacities are based on ATC/NTC values. ATC being the only limit for market 
operations greatly simplifies cross‐border trading. Considering that the  electric network is a highly  complex 
non‐linear system, such an abstraction has to be done in a careful manner. For example, one must recognize 
the difference between the commercial transfer between zones and actual flows in a system as illustrated in 
Figure 2. For a 1 MWh flow  occurring  between France and  Germany, 0.34 MWh  is flowing through  Belgium 
Chapter: European Electricity markets 

and Netherlands route, while only 0.35 MWh flows directly from France to Germany‐ flows through BE and NL 
are termed as transit flows. The remaining flows through networks of other neighbours. 

Up to now, most trade arrangements within Europe have been based on the “contract path” concept, where 
electricity  is  supposed  to  flow  according  to  the  chosen  trading  arrangements.  This  concept  has  been 
acceptable  as  long  as  it  has  been  applied  to  long  term  steady  transactions  between  integrated  companies. 
Although  it  has  severe  drawbacks  as  already  outlined  in  the  example  above,  at  least  it  prevents  taking 
maximum benefit from existing transmission facilities in meshed networks. At most it can severely jeopardize 
power system security (e.g. the chaining contracts without visibility, that have been made possible thanks to 
the  contract  path  paradigm,  have  been  the  origin  of  several  very  dangerous  operational  situations  due  to 

  5 
 
6  Flow‐based Market Coupling 
 

unexpected  flows  through  Belgium).  Moving  to  the  “physical  flow  path”  concept  while  managing  physical 
flows through the market itself poses a major challenge. ETSO and EuroPEX joint working group presented 
the  Flow‐based  Market  Coupling  (FMC)  as  a  solution  to  congestion  management  which  prices  according  to 
the  “physical  path”  concept  (ETSO  and  EuroPEX  JWG  2004).  However  it  is  still  different  from  the  Location 
Marginal  Pricing  (for  detail  discussion  on  LMP  refer  chapter  2)  –  or  nodal  pricing,  as  it  would  aggregate 
multiple nodes, the once belonging to one control area, into one super‐node. This super‐node is expected to 
cover  all  nodes  that  are  geographically  located  in  one  country.  As  the  EU  directive  only  dictates  FMC  for 
interconnector congestion management, hence the prices will only be calculated for each region separately 
considering the maximum amount of electricity that can flow given the capacity constraints. Next section will 
discuss FMC in detail. 

FIGURE  2  PERCENTAGE  OF  FLOWS  IN  FR‐BE‐NL‐DE‐CH‐A‐I  ZONE  FOR  A  COMMERCIAL  TRANSACTION  OF  1  MWH  FROM 
FRANCE TO GERMANY (IEA WORKSHOP PRESENTATION 2004) 

Other  important  consideration  to  be  taken  into  account  while  designing  a  market  based  congestion 
management mechanism for electricity trade are the following: 

• Electricity  transmission  is  a  natural  monopoly,  and  hence  needs  special  governing  structures  while 
dealing with efficiency issues.(Crew and Kleindorfer 1985) 
• Transport  pricing  issues  because  of  “one  country  one  price  paradigm”  do  not  agree  with  the 
economic optimization principles (Crampes and Laffont 2001) 
• Pricing  according  to  the  physical  flow  path  and  contract  path  are  different  (Borenstein  2001; 
Budhraja 2003) 
• Markets for electricity have undergone recent restructuring and liberalizing. Operations of electricity 
markets  after  restructuring  is  different  as  compared  to  vertically  integrated  companies  that 
proceeded them (Bhattacharya, Bollen et al. 2001) 
• Transmission lines are still regulated (as transmission is natural monopoly it needs to be regulated to 
prevent  abuse  of  market  power)  and  firm  behavior  is  different  under  regulation  not  always 
maximizing  the  profit.  (Averch  and  Johnson  1962)  In  case  of  Netherlands  the  system  operator  ‐ 
 

TenneT ‐ is under a revenue cap with some form of international benchmark. Which is not the most 
economically optimal solution but limits the gold‐plating. 
• The structure of the market is such that it will never be perfect competition because of huge capital 
costs  involved.  Oligopolies  will  exist  in  the  generation  side  which  will  hinder  operation  of  efficient 
markets. (Day, Hobbs et al. 2002) 
• TSOs try to reserve some transmission capacity due to security reasons. This further complicates the 
efficient operation of any market design.(Harvey, Hogan et al. 1996) 
• International  transmission  trade  would  call  in  for  standardization  of  the  legal  processes  to  enable 
neutral settling of the trade issues. (Knops, De Vries et al. 2001)  
• The externalities due to loop flows in a transmission network represent a critical issue that must be 
resolved before competition can be successfully introduced into the electric power industry for long‐
term economic benefits.(Chao, Peck et al. 2000) 
For the basic understanding of economics concepts book by Samuelson and Nordhaus was used (Samuelson 
and  Nordhaus  2005).  “Power  System  Economics”  was  used  for  more  specific  understanding  into  the 
operations of electricity markets (Kirschen and Strbac 2004). A book by Hunt was consulted for understanding 
the issues faced by efficient operation of electricity markets (Hunt 2002). To gain broader understanding into 
risks related to electricity infrastructures within European context book named Critical Infrastructures at Risk 
was also consulted (Gheorghe, Masera et al. 2006). 

1.4 MARCH TOWARDS INTERNAL ENERGY MARKETS 
In 1987 the Single European Act actively promoted integration of national markets into one single European 
market  and  invented  the  “1992  Internal  Market”  agenda.  The  Internal  Energy  Market  (IEM)  provides  new 
opportunities to energy consumers and to energy undertakings. It has the potential to increase economic and 
technical efficiency, as well as security of supply, thus improving European welfare and the competitiveness 
of  European  industry.  To  realize  Europeanization  of  energy  sector  three  concepts  were  focused  on  ‐
liberalization,  independent  regulation  and  supra‐national  integration  of  electricity  markets,  which  are  inter‐
related. The first IEM document (Directive 96/92/EC) defined some common rules to be applied by all Member 
States in order to open up their energy markets and established the legal basis for the IEM. For instance, the 
directives  defined  minimum  unbundling  requirements  applicable  to  vertically‐integrated  undertakings, 
minimum eligibility thresholds, a menu of network access regimes, etc. With opening up of market the cases 
where electricity is significantly cheaper in one member state than in its neighbor, a large demand for cross‐
border  transports  could  occur.  In  some  of  these  cases  the  demand  for  imports  exceeded  the  available 
transport  capacity  on  the  (cross‐border)  interconnector(s)  leading  to  congestion.  Transmission  system 
operators  (TSOs)  have  historically  not  designed  interconnections  between  their  networks  with  the  primary 
objective  of  facilitating  international  power  trade.  As  a  consequence,  the  integration  of  national  markets  is 
impeded  by  the  limited  amount  of  cross  border  transmission  capacity.  However  there  have  been  plans  to 
increase capacity of the interconnectors, as seen Figure 3, the by 2010 it is planned to raise the capacity of the 
interconnectors to almost 20% of the installed generation capacity. It becomes imperative to design efficient 
congestion  management  and  capacity  allocation  methods  for  this  additional  capacity  in  order  to  maximize 
Chapter: European Electricity markets 

the economic benefit from trade. 

  7 
 
8  Flow‐based Market Coupling 
 

 
 Interconnector  capacity  as  %  of 
total installed generation capacity 

 
FIGURE 3 PLANNED INCREASE OF INTERCONNECTIONS IN THE EU (% OF INSTALLED GENERATION CAPACITY).  

For  2003  a  level  of  approx  10%  were  foreseen,  while  the  level  graph  shows  that  the  actual  level  of 
interconnection capacity was only 7%. Currently the level was approximated at around 15% with the number 
growing up to 20% by year 2012. This underscored the importance that inter country trade of electricity has 
on the national markets. This would only become more important in the coming time(Source: EU Directorate 
General for Energy and Transport, 2000) 

Congestion may hamper the full integration of different national electricity markets into a single market. The 
existence of negotiated third party access regimes, the limited level of unbundling obligations and the lack of 
an obligation to establish a national energy regulator were also viewed as obstacles to creation of competitive 
markets.  To  address  these  concerns,  further  measures  were  proposed  by  the  Commission  leading  to  the 
adoption of (Directive 2003/54/EC)(“Second Electricity Directive”) and (Regulation (EC) No. 1228/2003 2003) 
(“Cross Border Electricity Trading Regulation”). The content of the Regulation largely reflects the outcome of 
the work of the Florence Regulatory Forum (see DG TREN web site http://europa.eu.int/comm./dgs/energy_ 
transport/).  The  Forum  began  its  work  in  1998,  with  an  aim  of  identifying  obstacles  in  the  way  of  IEM  and 
explores solutions, and has since issued several studies on the two subjects addressed by the Regulation. 

In 2004, ETSO and EuroPEX launched a joint proposal on Flow‐based Market Coupling (FMC) to achieve the 
goals envisioned by 1228/2003. On 1 December 2006 a new annex to the European Regulation (EC) 1228/2003 
entered into  force (congestion management guidelines) requiring that al  congestion  management methods 
applied  must  be  market  based  which  means  that  capacity  shall  be  allocated  only  by  means  of  explicit  or 
implicit auctions. These new binding guidelines prescribe that TSOs should implement a flow based allocation 
system as soon as possible. 

1.5 CONCLUSION 
Once all the above issues have been studied it would be possible to place FMC into the right perspective while 
considering  the  alternatives.  This  would  contribute  to  one  part  of  the  report  which  is  mostly  based  on 
literature and expert opinion and would study the long and short term implications of implementing FMC on 
Dutch interconnectors with Germany and Belgium, and the transactions from France. 

There is a need to  understand what makes a  market  design successful.  It has  been proven in literature that 


theoretically  all  current  congestion  management  methods  today  have  the  capability  of  being  economically 
efficient (De Vries and Hakvoort 2000b; De Vries 2004). However they differ with respect to distribution of the 
costs and welfare. This could lead to opportunistic behavior and hence any market design should be closely 
monitored  for  any  such  opportunity.  FMC  also  needs  to  be  studied  with  respect  to  the  distribution  of  the 
benefits and costs. The actors who bear the costs without any benefits will be against any such change and 
those who  enjoy benefits without any  cost would strongly support it. A neutral and  efficient method would 
 

need to distribute the benefits and costs justly. FMC has been said to build upon the present system without 
major  structural  changes  and  it  can  evolve  over  time.  However  it  has  been  shown  in  past  that  unsuitable 
market designs like the one in California could lead to huge damage. Hence FMC should be scrutinized more 
rigorously  especially  with  respect  to  the  impact  it  would  have  on  the  Dutch  electricity  system  and  national 
energy security. 

   

Chapter: European Electricity markets 

  9 
 
10  Flow‐based Market Coupling 
 

2 CONGESTION MANAGEMENT 
 

Congestion  occurs  when  the  demand  for  transmission  capacity  exceeds  the  available  transmission  network 
capabilities. Every power system will from time to time experience this situation. It is not economical to invest 
to a level where all constraints are eliminated. 

The  principles  for  congestion  management  in  a  country  or  a  wider  area  are  based  on  the  legislation  and 
regulation in place. An increased focus towards handling of congestions has developed over recent years. In 
Europe  the  EU  Directive  2003/54/EC  and  the  Regulation  1228/2003/EC  draw  up  the  basic  principles  for 
congestion management throughout Europe. 

Guidelines  are  being  developed  to  detail  the  principles.  Only  market  based  methods  for  congestion 
management will be accepted in the future. 

Congestion  separates  geographic  markets  into  submarkets.  Congestion  arises  from  the  saturation  of 
transport  infrastructure.  It  may  occur  in  any  spatially  distributed  sector  that  requires  transport  facilities. 
Because  one  cannot  build  infrastructures  of  infinite  capacities,  congestion  is  unavoidable  but  should  not  be 
excessive. The frequency of congestion and the size of the resulting submarkets depend on both the capacity 
and the management of the infrastructure. This also applies to electricity, with the additional complexity that 
this  product  creates.  In  the  next  section  various  congestion  management  methods  would  be  detailed.  This 
would  be  followed  by  description  of  the  current  state  of  congestion  management  methods  employed  in 
north‐western Europe. 

2.1 CONGESTION MANAGEMENT METHODS 
Congestion management in electricity is far from a new subject in the academic and professional literature. Its 
analysis  began  with  Hogan’s  seminal  paper  (Hogan  1992)  on  nodal  pricing  (also  referred  to  as  locational 
marginal  pricing  (LMP)).  The  subject  has  since  been  extensively  debated  and  there  is  now  considerable 
theoretical knowledge on it. Market splitting is a simplified form of nodal pricing that was implemented in the 
Nordic  system  in  1993  (http://  www.nordel.org/).  New  Zealand  introduced  a  first  version  of  nodal  pricing  as 
early as 1997. The real development began with the implementation of this method in PJM in 1998 and the 
progressive adoption of it by the voluntary pools of the East Coast of the United States. 

Congestion  management  methods  can  be  divided  into  different  sub‐categories.  It  can  be  methods  for 
handling  congestions  between  areas  (inter  area)  or  it  can  handle  congestions  within  an  area  (intra  area). 
Market based or not market based is another subdivision. Finally it should be divided between methods used 
to  allocate  capacity  up  to  the  capacity  limit  (allocation  methods)  and  methods  used  to  alleviate  the 
transmission network down to the capacity limit (alleviation methods). 

Based  on  the  literature  review,  the  three  forms  of  the  congestion  management  have  been  adopted  in 
deregulated electricity market (EM) around the world (Christie, Wollenberg et al. February 2000). One form is 
based  on  centralized  optimization  with  some  form  of  optimal  power  flow  program  or  depending  upon  the 
control measures executed by the TSO for congestion relief. A second form is based on the use of price signals 
derived from ex ante market resolution to deter congestion by constraining scheduled generator output prior 
to  real  time  operation.  A  third  form  seeks  to  control  congestion  by  allowing  or  disallowing  bilateral 
transmission agreements between a producer and a consumer, based on the effect of the transaction on the 
transmission system.   

Within  Europe  following  are  the  cross‐border  congestion  management  methods  that  are  currently 
implemented (ETSO May 2006)  
 

• Access  limitation:  Access  rationed  by  one  or  several  independent  companies  which  are  not  the 
owner of the network the link is connected to. 
• Priority  List:  One  gets  capacity  in  a  priority  order  until  the  whole  available  capacity  is  allocated. 
Examples  of  priority  criteria  are:  chronological  order  (first  come  first  served),  past  use  of  capacity, 
etc. 
• Pro rata rationing: All requests are partially accepted in the way that each  participant is granted a 
fixed share of his requested capacity amount. 
• Explicit auction (ATC Based): The applicants have to  declare the amount of capacity they want to 
obtain  and  how  much  they  are  willing  to  pay  for  this  capacity.  Bids  are  ordered  and  allocated  by 
price. In the SEE region they recently introduces coordinated (regionally optimized) explicit auctions. 
• Implicit  auctions  (Market  splitting;  Market  Coupling):  The  electricity  markets  provide  initially  a 
common clearing.  If the  interconnector  is congested, markets split  into pre‐determined price areas 
cleared individually. 
 
Countries  apply  the  methods  of  accession  according  to  regulation  EC  1228/2003.  Regarding  inter‐country 
transmission  capacity  within  EU,  regulation  1228/2003  of  prescribes  that  the  congestion  management 
methods  implemented  by  its  member  states  must  be  market  based  and  that  allocation  of  capacity  shall  be 
made  only  by  explicit  (only  capacity)  or  implicit  (both  capacity  and  energy)  auctions.(Regulation  (EC)  No. 
1228/2003  2003).  Priority  based  rules,  such  as  first  come  first  served,  and  pro‐rata  rationing  are  allocation 
based and non market  based methods. This entails that access‐limitation, priority and  pro rata will be soon 
phased out within EU.  

In  Europe  different  assignment  models  are  used.  For  example,  the  cross  border  capacity  between  the 
Netherlands and Germany is assigned through explicit auctions. Netherlands, Belgium and France day‐ahead 
market is assigned through trilateral market coupling; while the long term capacity (month/year) is allocated 
via explicit auctions. Nordic System uses the model of market splitting. The selection and implementation of 
a well‐suited congestion management model is a necessary precondition for developing a successful regional 
market(ETSO May 2006). 

Congestion management, in particular at the European level has become a relevant topic since liberalization 
of  electricity  markets  is  in  progress.  Boucher  and  Smeers  (2001)  analyzed  the  future  organization  of  cross 
border trade in the European electricity market concluding that the economic principles as proposed by the 
European  Commission  in  2001  are  not  sufficient.  Ehrenmann  and  Smeers  (2004)  analyze  the  regulation  of 
cross  border  trade  of  electricity  (Regulation  1228/2003)  in  terms  of  efficient  congestion  management.  They 
conclude  that  market  coupling  ‐  although  its  implementation  is  more  complex  ‐  can  path  the  way  to  a 
consistent  system  integrating  the  energy  and  transmission  markets.  Arriaga  and  Omos  (2004)  analyzed 
plausible congestion management schemes for the internal electricity market of the European Union. Taking 
a  joint  energy  and  capacity  auction  as  benchmark  they  test  two  alternative  approaches,  an  integrated 
transmission  and  energy  auction  and  a  coordinated  explicit  auction  of  transmission  capacity  followed  by 
separate energy auctions at the different power exchanges. The authors propose the latter since it is relatively 
close to the actual market structures.  
Chapter: Congestion Management 

Explicit  and  implicit  auctions  are  the  favored  methods  by  the  European  Union.  They  are  market  based 
allocation methods. Market splitting and market coupling are special cases of implicit auctions. In an implicit 
auction energy and capacity are traded at the same time. In an explicit auction only transmission capacity is 
traded. 

Locational Marginal Pricing (LMP) is similar to implicit auction since both methods consider both energy and 
capacity. But LMP is basically the backbone of a market organization with central bid based dispatch. 

  11 
 
12  Flow‐based Market Coupling 
 

Examples  of  alleviation  methods  are  counter  trading,  re‐dispatching,  coordinated  redispatching  and 
transmission loading relief (TLR). 

Next  section  would  outline  the  current  approach  of  congestion  management  that  has  been  implemented 
between France, Belgium and Netherlands. It is also important to discuss here the main features of two other 
successful  market  based  methods  for  congestion  management  that  have  been  implemented  elsewhere. 
Market  splitting  (MS)  as  employed  by  Nordic  countries  and  LMP  as  employed  by  PJM  would  be  discussed 
subsequently.  The  chapter  would  end  would  an  outline  of  FMC,  which  would  be  dealt  in  detail  in  the  next 
chapter.  

2.2 TRILATERAL MARKET COUPLING 
On 21 November 2006 the Trilateral Market Coupling (“TLC”) between the Netherlands, Belgium and France 
was successfully launched. The success of TLC proves the market coupling concept, and paves the way for the 
creation of a North‐West European energy market. 

Trilateral Market Coupling was the first coupling of separate, independent exchanges in Europe, so there were 
many  challenges  and  new  problems  to  solve.  The  success  of  the  project  was  due  to  increased  co‐operation 
between the six parties (RTE, Powernext, Elia, Belpex, TenneT and APX) together with the strong support of 
the  Governments,  the  European  Commission,  the  regulators  and  the  market  parties.  However  it  was  not  a 
smooth sailing. 

Market  coupling  is  a  way  to  integrate  power  markets  in  different  physical  areas  while  requiring  minimal 
changes to the local arrangements. Under TLC the three power exchanges continue to exist as separate legal 
entities  with  their  own  trading  platform,  contracts  and  clearing.   The  markets  are  nonetheless  brought 
together by using the available transmission capacity to create a single regional market most of the time. The 
transmission capacity is used in an optimal way, enabling the best bids and offers to be matched from across 
the region. 

 
FIGURE 4 CURRENT CONGESTION MANAGEMENT METHODS IN NWE REGION 
 

TLC replaced a two‐step process: a daily explicit auction of transmission capacity followed by the day‐ahead 
energy  markets.  This  sequence  has  some  inherent  inefficiency.  Market  coupling  integrates  transmission 
allocation and energy trading, removing many of the inefficiencies at the day‐ahead stage. Explicit auctions 
are still used for the monthly and yearly allocation of transmission capacity rights. 

Trilateral market coupling has already had a clear positive impact. There has been strong price convergence 
across the three coupled day‐ahead markets, with a single price the large majority of the time (and separation 
in to 3 price areas being very occasional).  The trend seems to be that convergence is increasing. 

 
FIGURE 5 PRICES AFTER IMPLEMENTATION OF TLC SHOWING CONVERGENCE (HTTP://WWW.APXGROUP.COM) 

As a result of the market coupling mechanism, the use of the available daily capacity (import and export flows 
between  the  Netherlands  and  Belgium)  has  changed  significantly.  There  has  been  a  marked  increase  in 
utilization of cross border capacity, occasionally reaching 100%, which theoretically must be 100% if there is 
any price difference between the countries. Historically, the Netherlands was a net importer but, while this is 
usually still the case during peak hours, it is becoming a strong exporter during off‐peak hours. These effects 
show that market coupling has contributed significantly to a better integrated and more efficient electricity 
market. Figure 6 shows the imports and exports between the countries in North West European region for the 
year 2006. Netherlands imports large percentage of electricity from Germany.  

Chapter: Congestion Management 

 
FIGURE 6 PHYSICAL ENERGY FLOWS IN 2006 (ALL VALUES IN GWH) FROM HTTP://WWW.UCTE.ORG 

  13 
 
14  Flow‐based Market Coupling 
 

Considering the benefits it is planned to extend the system to include Germany. The German power exchange 
EEX  is  also  considered  "a  pacemaker"  for  European  power  prices.  Inclusion  of  Germany  would  increase  the 
number  of  actors  involved  in  the  trading  and  hence  make  the  markets  more  competitive  and  hence  more 
efficient. It is also proposed to use Flow based market coupling calculation to calculate the available transfer 
capacity  on the tie‐lines.  This is claimed to  be  more efficient way of allocating the available  capacity – as it 
considers the physical realities of electricity flow  based  on the  Kirchoff’s laws rather than the contract path 
method. Not only would it make more realistic calculations on the flows, it would enable TSO’s to reduce the 
security margins as they would now be able to predict the flows more accurately now. Hence balancing would 
require reduced amount of reserved margins.  

The  11th  Florence  Regulatory  Forum  held  in  Rome  on  the  16th‐17th  September  2004  welcomed  the  ETSO‐
EuroPEX  joint  proposal  for  addressing  cross  border  congestion.  Their  jointly  developed  approach  ‐  called 
Flow‐based  Market  Coupling  or  FMC  ‐  provides  a  model  for  cross‐border  congestion  management  and 
integration of electricity markets across Europe. It consists of regional price areas with inter‐regional trading 
facilitated  by  market  coupling  subject  to  simplified  transmission  constraints.  The  model  included  detailed 
arrangements for day‐ahead trading as well as providing for alternative forward market structures. Since then 
the studies have been ongoing over the possibility of introducing flow based market coupling. It has been now 
proposed to introduce FMC in the north‐west European region. 

On  June  6,  2007  ministers  of  the  Pentalateral  Energy  Forum  and  the  High  Level  representatives  of  the 
Regulatory Authorities, TSOs, PXs and the Market Parties Platform of the Central Western European (CWE) 
region  (Belgium,  France,  Germany,  Luxembourg  and  the  Netherlands),  signed  a  Memorandum  of 
Understanding  (MoU)  on  Market  Coupling  and  Security  of  Supply  in  Central  Western  Europe.  The  MoU  is  a 
step forward towards a more efficiently functioning cross‐border electricity market in the five countries and 
towards  further  European  integration.  Key  elements  are  the  development  of  a  flow‐based  market  coupling 
system  for  the  region  and  several  measures  for  increased  security  of  electricity  supply.  However  it  is  still  a 
paper and developments in practice have not been visible yet. 

The target date for this endeavor is January 2009. The basic underlying assumption is that a pricing method 
that  couples  national  markets  and  maximizes  the  available  interconnector  capacity  (using  flow  based 
calculations)  would  be  most  economically  efficient.  The  flow‐based  market  coupling  will  support  the  global 
reliability  of  the  electrical  system  and  increase  economic  efficiency  in  the  region  by  introducing  a  single 
region‐wide  implicit  auctioning  system  of  the  cross‐border  interconnection  capacities,  based  on  a  regional 
load flow calculation. 

A working group of TSOs and PXs will analyze the requirements for design and implementation of the flow‐
based  market  coupling  mechanism.  The  working  group  is  also  in  charge  of  the  necessary  negotiations, 
steering and  decision‐making. TSOs and/or  PXs will also  examine the opportunity of setting up a  joint‐TSO 
company and/or PX company, which would be in charge of the relevant market issues within the CWE area. 

However,  FMC  is  still  not  completely  understood  and  should  be  analyzed  for  pitfalls,  if  any,  before  the 
implementation can take place. The initial phase would require the involved actors to agree on the terms and 
conditions of the FMC. The fact that FMC system is an integrated system governed both the technical realities 
and  market  economics  makes  it  tough  to  get  an  intuitive  understanding.  The  results  are  also  non‐linear 
making  predictions  impossible  without  help  of  a  appropriate  tool.  The  complexity  inherent  to  the 
transmission  system,  compounded  by  integration  of  four  independent  networks  and  additional  complexity 
introduced by FMC creates a non‐transparent system that is complicated for the policy makers to understand, 
and  hence  is  a  stumbling  block  towards  agreements  and  might  lead  to  rough  negotiations.  For  this  it  is 
important  to  bring  out  the  distributive  effects  that  FMC  would  entail  for  the  participants.  This  can  only  be 
understood  by  modeling  the  real  system  and  studying  the  impact  of  introducing  a  flow  based  system  with 
market coupling.  
 

The next chapter would introduce FMC is more detail. The salient features of Market Splitting and LMP would 
be discussed next. 

2.3 MARKET SPLITTING 
The  market  splitting  is  an  implicit  auction  where  the  capacity  is  traded  simultaneously  with  the  energy.  In 
cases with congestions, the markets are split into two or more price areas. Each price area is then balanced 
while  fully  utilizing  the  transfer  capacities  between  the  areas.  As  stated  earlier,  larger  areas  with  uniform 
prices are important for the competition and the market  splitting approach has therefore many advantages 
from this point of view. The economic outcome from market splitting would be same as market coupling only 
the process of getting there is different. 

Market  splitting  is  applied  in  the  Nordic  market  and  some  of  the  designs  used  there  will  be  described  and 
discussed for illustration purposes. The steps are: 

• The  whole  market  area  is  divided  into  smaller  bidding  areas,  mainly  defined  along  the  structural 
bottlenecks. 
• The  TSOs  calculate  transfer  capacities  and  all  capacity  for  each  hour  is  allocated  to  the  power 
exchange for trade in the day‐ahead market. Information on capacities are given to the market every 
morning. 
• Market actors can then submit bids in a bidding area. Bids must be in balance in each area. 
• Market clearing is performed for each hour by the latest 2 am the day ahead of operation. First an un‐
congested  market  clearing  is  performed  for  the  whole  market.  Flows  between  areas  are  checked 
against  available  capacity.  If  there  are  any  violations,  the  market  is  split  in  two  areas  and  separate 
clearing is done in each area. 
• This iteration process continues until all transfers are within capacity limits. All market actors will be 
compensated and charged according to the market prices in the area they are located. 
• The market actors’ obligations within each price area are then the basis for a detailed planning of the 
generation and loads. These detailed schedules are submitted to the 

TSO and will be the basis for calculating deviations from the schedules and need for secondary control. 

The  market  splitting  method  requires  a  centralized  market  operator  that  combines  the  bids  in  a  market 
clearing  procedure.  As  mentioned  the  market  splitting  enhances  the  competition  due  to  relatively  many 
market actors within the same price areas. The implicit auction principle also guarantees that the capacity is 
made available to the market participants in a nondiscriminatory way since no single market actor can reserve 
the  capacity  for  own  use.  In  a  case  of  congestion  all  the  market  actors  can  readily  see  the  effect,  since  the 
energy  price  will rise in the deficit area. This gives the right incentive to market actors on  both sides  of the 
congestion. The price in an area also reflects the value of the electricity for the market actors. 

Congestion  between  the  areas  will  generate  a  congestion  rent  to  the  TSOs.  According  to  EU  Directive  the 
congestion rent can only be used for transmission investments, reduced tariffs or counter‐trade. In the market 
splitting method the central load dispatch has been replaced by market forces. This gives as result a system 
Chapter: Congestion Management 

where generation and load are in balance in the planning phase. 

During the operating hour there is a decentralised dispatch where the generators follow their schedules. The 
System Operators will take care of the imbalances occurring after the planning by using the balancing market. 

   

  15 
 
16  Flow‐based Market Coupling 
 

2.4 LOCATIONAL MARGINAL PRICES (LMP) 
 

More  physical  network  models,  for  example  LMP,  make  it  possible  to  some  extent  to  operate  closer  to  the 
limit.  The  LMP  takes  into  account  that  inter  area  transactions  may  have  different  impact  on  the  flow  on 
congested transmission lines between those areas as well as on loop flows. This impact on the network flow is 
the reason for possible enhanced utilization of the transmission system. As long as the prices can be different 
on all nodes, it is in principle possible to find a power flow that gives the overall optimal solution and utilizes 
the transmission system as good as possible based on the bid curves. This requires however that all technical 
and  economical  details  to  run  an  optimal  power  flow  are  available  when  the  SO  is  performing  central 
dispatch. 

There are different types of transactions where some are firm and may have transfer rights while others are 
more  of  opportunistic  character.  It  is  important  to  account  for  these  differences  when  congestion 
management schemes are developed. In the follow description and discussion, the scheme developed by PJM 
and  MISO  will  used  as  an  example(PJM  Interconnection).  The  purpose  of  the  scheme  (CM  Process)  was  to 
balance system security with a market‐sensitive usage of PJM’s available transfer capability. 

The  cornerstone of CM Process is the delineation between energy flows associated with serving ‘firm’ load; 
and other energy flows associated with commercial activity. Firm flows are defined as those flows that would 
occur to serve only customer loads and those transactions that have Firm Transmission Rights (FTR). What is 
left over would be opportunistic transactions that do not have Firm Transmission Rights. This approach allows 
those with firm FTRs to be secure that their respective transactions will flow; and those without FTRs can still 
make use of the system as subject to the requirement that there are no actual transfer problems. As long as 
the  actual  tie  line  flows  are  within  the  agreed  transfer  limit,  then  there  is  no  reason  to  preclude  additional 
transactions. 

In an LMP‐based system the bus prices will reflect which resources are more financially attractive and which 
resources  are  not.  As  long  as  the  Market  price  shifts  keep  the  flows  within  the  transfer  limits,  the 
opportunistic  transactions  continue.  When  the  normal  market  prices  are  not  sufficient  to  control  the  flows, 
then the opportunistic transactions would be curtailed. This approach allows SO to let transactions continue 
as  long  as  the  market  players  are  willing  to  pay  the  energy  costs  caused  by  redispatching  the  system.  The 
LMP will diverge until the flows are appropriately reduced. 

Another benefit is that the transfers are based on real time flows and not on predicted flows. 

This approach increases both reliability (in the case where conditions adversely impact the transfer limits) and 
commerce (in the case where conditions support additional interchange.) 

The  use  of  the  simplified  Interconnection  Model  provides  recognition  that  in  a  meshed  interconnection 
transactions  themselves  are  neither  good  nor  bad,  it  is  the  effects  of  the  transactions  that  help  or  hurt  and 
those effects are a result of more than just the owner‐area of the point of delivery and point of receipt of the 
respective transaction. 

2.5 CONCLUSION 
Congestion  management  methods  can  be  divided  into  different  sub‐categories.  It  can  be  methods  for 
handling  congestions  between  areas  (inter  area)  or  it  can  handle  congestions  within  an  area  (intra  area). 
Market based or not market based is another subdivision. Finally it should be divided between methods used 
to  allocate  capacity  up  to  the  capacity  limit  (allocation  methods)  and  methods  used  to  alleviate  the 
transmission network down to the capacity limit (alleviation methods). 
 

It is not possible to state that one method is superior to the others. It is more a question of how it is necessary 
to prioritize between the general requirements of congestion management methods given specific systems. 
Giving priority to some specific features will often make it necessary to come up with countermeasures for the 
requirements not that well covered. 

Priority  based  rules,  such  as  first  come  first  served,  and  pro‐rata  rationing  are  allocation  based  and  non 
market based methods. 

Explicit and implicit auctions are the favored methods by the European Union. They are market and allocation 
based  methods.  Market  splitting  and  market  coupling  are  special  cases  of  implicit  auctions.  In  an  implicit 
auction energy and capacity are traded at the same time. In an explicit auction only transmission capacity is 
traded.  Flow  based  market  coupling  tries  to  use  both  the  technical  specification  of  the  system  and  market 
coupling together. FMC would be discussed in detail in the next chapter. 

   

Chapter: Congestion Management 

  17 
 
18  Flow‐based Market Coupling 
 

3 FLOW‐BASED MARKET COUPLING 
 

The new congestion management guidelines (amending the existing annex to the European Regulation (EC) 
3
1228/2003) entered into force on 1 December 2006. These new binding guidelines  prescribe that TSOs should 
implement a flow based allocation system/or a similar mechanism that couples the markets and takes care of 
the physical flows as soon as possible.(Congestion Management Guidelines 2006) 

At  the  moment,  TSOs  calculate  the  ‘for  the  market  available  capacity’  for  each  border  separately  based  on 
quite conservative base cases. After this, the calculated available capacity is attributed to the market through 
a certain allocation method such as explicit auctions (capacity only) or implicit auctions (capacity and energy 
actions). 

New  regulatory  guidelines  of  the  EU  prescribe  the  implementation  of  flow‐based.  In  short,  (FMC)  is  a  new 
method for Cross‐Border Congestion Management. It combines commercial energy bids with physical reality 
to  optimize  network  use  with  respect  to  market  value.  Commercial  energy  bids  and  available  capacity  are 
evaluated  simultaneously  in  an  iterative  process  which  should  lead  to  a  more  efficient  use  of  transmission 
capacity with respect to commercial  value. Optimization is performed  based upon  commercial bids and the 
linear relation between accepted bids and physical flows on flowgates (defined in the PTDF‐matrix).  

Theoretical FMC has been proven to be an efficient market design: (Chao, Peck et al. 2000) 

“System of flow‐based transmission rights enables market‐based congestion management or efficient energy 
and transmission markets. Further, once a system of tradable flowgate rights is established, the control of the 
transmission  system  is  shifted  from  line  owners  to  the  market,  in  which  the  transmission  charges  are 
determined competitively without excessive complexity or monopoly power abuses.” 

Flow‐based market coupling is an implicit auction similar to market splitting but performed in opposite order. 
First  each  sub‐market  is  cleared,  and  then  these  markets  are  coupled.  It  is  a  mixture  of  a  “flow  based 
modelling”  and  a  “Decentralised  Market  Coupling”.  A  “flow  based  modelling”  considers  the  physical  flows 
that  can  be  exchanged  between  different  electric  systems  taking  into  account  the  mutual  influence  of  the 
exchanges. A “Decentralised Market Coupling” is a method to execute a coordinated market among different 
markets,  using  their  own  market  rules  in  each  area.  This  method  is  still  under  development  but  is  likely  to 
become an important solution in Europe. 

A simplification must be made, considering that a joint system can be operated as a number of single‐price 
regions, connected with the other regions by notional transmission circuits. The real flow between different 
nodes  is  modelled  by  flow  factors  and  the  limits  between  nodes  are  calculated  taking  into  account  the 
influence of the bottleneck capacities on the crossborder inter‐connectors.  

Bottleneck capacities (Fmax and Fref) and flow factors (PTDFs) need to be estimated and published in advance 
to  inform  users  and  updated  before  operation  of  the  day‐ahead  market  by  the  TSOs.  This  information  is 
required  by  the  day‐ahead  markets  to  describe  the  state  of  the  simplified  transmission  model  used  for 
flowbased market coupling. 

Users have the possibility to submit bids and offers to the regional day‐ahead markets in order to purchase or 
sell energy in their region. In the same way they also have the option to submit price‐difference bids in which 

                                                                         
3
See guidelines Article 3.2 prescribes that regional coordination shall include, in particular:
(a) Use of a common transmission model dealing efficiently with interdependent physical loop-flows and having regard to
discrepancies between physical and commercial flows,
(b) Allocation and nomination of capacity to deal efficiently with interdependent physical loop-flows
 

they offer to transfer energy between two markets and pay or receive the inter‐regional congestion rent. This 
method allows users to participate for crossborder trade through bilateral‐contract or day‐ahead access in a 
non discriminatory manner. 

Every market will execute the matching process, firstly without exchanges, and will calculate an import/export 
curve  for  every  hour,  that  represents  the  market  price  with  different  quantities  of  imported  or  exported 
energy.  Every  market  executes  the  process  with  their  own  rules.  A  central  module  with  all  import/export 
curves, considering local prices, and price‐difference bids, optimizes the flows between the regions, subject to 
the  inter‐regional  transmission  constraints  represented  by  the  simplified  transmission  model.  Every  market 
with the result (imported/exported energy) will execute its matching process considering imported/exported 
energy and calculates a new import/export curve, sending the new curves to the central module. Iteration is 
required  between  the  different  areas  because  of  ’block’  bids  and  offers.  This  sequence  is  repeated  until  it 
converges.  

The  described method  can coexist with several forms of  forward market arrangements. This will be needed 


for those users that want to hedge cross‐border price risk (instead of facing the risk in the day‐ahead market). 
It  should  be  done  independently  from  the  FMC  through  forward  transmission  rights,  explicit  auctions  or 
electricity financial markets. 

Therefore  it  is  not  needed  to  have  a  single  market  in  a  whole  area,  as  it  is  needed  in  the  market  splitting 
method. The corridors will always be full of energy from the cheapest market to the most expensive one. The 
only problem that must be resolved is that a production shift in an area is a meshed network to some extent 
influence the flow on all connections. Therefore, it will be necessary to establish a base case fairly close to the 
final schedules for the calculated maximum transfer capacities between market areas to be valid. 

3.1 OPERATION OF MARKET UNDER FMC  
FMC couples the physical flow path modeling with the market coupling as can be seen in Figure 7. Both these 
mechanisms will be discussed in next. (ETSO and EuroPEX JWG 2004) 

Chapter: Flow‐based market coupling 

 
FIGURE 7. OUTLINE OF FMC A COMBINATION OF FLOW BASED MODELLING THAT TAKES CARE OF THE PHYSICAL FLOW PATH 
AND MARKET COUPLING TO MAXIMIZE THE COMPETITION AND EFFICIENCY OF ELECTRICITY MARKETS (ETSO AND EUROPEX 
JWG 2004) 

  19 
 
20  Flow‐based Market Coupling 
 

3.2 FLOW BASED MODELING 
Flow based refers to fact that one takes into account the physical effect of a certain contract on various flow 
gates as electricity follows Kirchhoff’s laws. For example, a commercial transaction from A to B could lead to a 
physical flow from A to B, B to C and C to A. Bottleneck capacities are the operational limits on variations in 
physical  bottleneck  flows.  The  relation  between  a  commercial  exchange  and  the  physical  flows  through 
flowgates  is  expressed  in  so‐called  power  transfer  distribution  factors  (PTDFs).  FMC  relies  on  PTDFs  to 
evaluate  the  impact  of  each  transaction  on  the  transmission  overload.  However,  PTDFs  provide  only 
approximate  and  sometimes  even  inaccurate  results,  and  are  not  suitable  for  the  next  day  line  loading 
forecast. There is need to be concerned with the accuracy of the PTDF approach. There are deficiencies with 
current  PTDF  which  need  to  be  addressed  before  it  can  be  implemented  for  cross  country  electricity  trade 
(Yan 1999). Also because of asymmetric information with the TSO (they calculate the PTDFs and also earn the 
congestion rent) there is a possibility of perverse incentives to keep the congestion on the borders.  

3.3 MARKET COUPLING 
Market Coupling refers to a capacity allocation method using implicit auctions in which capacity is allocated 
implicitly (see  Figure 8). Market Coupling may also be used without using a Flow Based capacity calculation 
method  as  is  in  fact  the  case  today  in  the  North‐West  European  region.  On  the  other  hand,  a  Flow  Based 
method could also be used in combination with explicit auctions. However, the introduction of a flow based 
mechanism is often explored in combination with implicit auctioning (e.g. market coupling). Market coupling 
has obvious benefit of improving net welfare of the whole system. However it is not clear how the customers 
of the exporting country would react to increased prices.  

PX area A PX area B

Price Import Price


Export

Independent
area price A
Independent
area price B

Volume Volume

Market Coupling
no congestion
congestion Im/export price dependency curve A
Area A
Prices
Independent area Price A
Integral system price
Independent area Price B
B Im/export price dependency curve B

B to A 0 A to B
Interconnector capacity (used)  
FIGURE 8. MARKET COUPLING BETWEEN TWO MARKETS LEADING TO INCREASE IN THE NET WELFARE (DE JONG, H. M. AND 
R. A. HAKVOORT (2007)) 

3.4 MARKET PROCESS OF FMC 
As it already follows from the discussion thus far FMC is a complex mechanism and is fairly technical and not 
transparent to the policy makers. It is hence desired to create a simplified simulation model of the market to 
aid  in  understanding  the  behavior  of  the  market  under  various  conditions.  Figure  9  shows  the  simplified 
model  of  the  market  operation  under  FMC.  This  process  would  be  modeled  for  a  simplified  network  and 
limited number of actors to understand the distributive effects and sensitivity of the prices to the PTDFs.  
 

 
FIGURE 9. THE PROCESS OF PRICING UNDER FMC, THIS WILL BE MODELLED FOR A SIMPLIFIED MARKET CASE TO CREATE A 
SOFTWARE MODEL THAT HELPS UNDERSTAND THE MARKET OPERATION BETTER (ETSO AND EUROPEX JWG 2004) 

3.5 DIFFERENCE BETWEEN FMC AND MARKET COUPLING 
It  is  important  to  understand  the  fundamental  differences  between  MC  and  FMC,  as  both  of  them  on  the 
surface  seems  to  be  very  similar  –  both  are  implicit  market  coupling  based,  and  both  use  a  measure  of 
capacity  on  the  interconnector.  To  be  able  to  appreciate  the  difference  a  few  variables  would  need  to  be 
defined: 

• Total Transfer Capacity (TTC): is the maximum exchange programme between two areas compatible 
with  operational  security  standards  (stated  in  the  grid  codes)  applicable  at  each  system  if  future 
network conditions, generation and load patterns were perfectly known in advance. 
• Net  Transfer  Capacity  (NTC):  NTC  is  the  maximum  exchange  programme  between  two  areas 
compatible  with  security  standards  applicable  in  both  areas  and  taking  into  account  the  technical 
uncertainties on future network conditions. 
o NTC = TTC‐TRM 
• Available  Transfer  Capacity  (ATC):  is  the  transfer  capacity  remaining  available  between  two 
interconnected areas for further commercial activity over and above already committed utilization of 
the transmission networks. ATC is given by the following equation: 
o ATC = NTC‐ NTF 
• Transmission  Reliability  Margin  (TRM):  is  a  security  margin  that  copes  with  uncertainties  on  the 
computed TTC values arising from: 
o Unintended deviations of physical flows during operation due to the physical functioning of 
load‐frequency regulation 
o Emergency exchanges between TSOs to cope with unexpected unbalanced situations in real 
time 
Chapter: Flow‐based market coupling 

o Inaccuracies, e. g. in data collection and measurements 
• Notified  Transmission  Flow  (NTF):  can  be  interpreted  as  the  already  occupied  part  of  NTC  by  the 
already accepted transfer contracts at the studied time frame. 

  21 
 
22  Flow‐based Market Coupling 
 

 
FIGURE 10 TRANSFER CAPACITY DEFINITIONS 

The  above  set  of  capacity  parameters  are  in  terms  of  bilateral  exchange  programmes  between  two 
neighboring areas. In case of MC, the values of NTC and ATCs are calculated for each pair of countries that are 
being coupled, without any consideration of parallel flows. The ATC values are used in the implicit auctioning 
algorithm as a constraint to the maximum energy exchange that can take place between these two countries. 

In the highly meshed interconnected transmission networks in Europe programmed exchanges and physical 
flows  differ  often  considerably.  They  would  be  closely  connected  to  the  power  flows  through  the  cross 
borders only in the ideal case of a peninsular system and its neighbor if both were interconnected through a 
single tie line, in case of market coupling in between Netherlands, Belgium and France there are no parallel 
paths  hence  it  is  a  good  approximation  to  peninsular  system  with  the  neighbors  lying  in  a  straight  line. 
However, in a widely interconnected network like for example the UCTE network the power flow through the 
cross border tie lines between two neighbor areas A and B may be interpreted as a superposition of a direct 
flow,  which  is  related  to  exchanges  between  A  and  B  and  a  parallel  flow,  which  is  related  to  all  the  other 
exchanges in the meshed network and to the location of generations and loads in the several grids. Therefore 
there would be a parallel flow even if all the exchanges in the interconnected system were set at zero. With 
introduction of Germany into the market coupling there would be large implications due to transit and loop 
flows on the values of ATC and NTCs. Hence it would not be advisable to use NTC based MC for integration of 
NL, DE, BE and FR markets. 

The figures provided about capacities for highly meshed systems are limited in scope, in several senses: 

• TTC and NTC values are computed between neighbour areas; these values are the result of assuming 
that  only  the  transactions  between  these  two  areas  are  modified  and  the  rest  (‘third  parties’ 
transactions) remain unaltered. This fact has two consequences: 
‐ The  published  values  cannot  be  used  for  an  exact  planning  of  transactions  if  these  do  not 
correspond  to  generation  and  to  consumption  in  the  pair  of  control  areas  for  which 
capacities  are  defined,  i.e.  NTCs  cannot  be  combined  to  derive  possibilities  of  executing 
transactions according to a given transaction path (contract path). 
‐ If the pattern of ‘third party transactions’ differs noticeably from that taken into account in 
the forecast, TTC values may significantly differ. That may have an important impact upon 
the NTC value. 
• NTC  values  between  pairs  of  control  areas  in  meshed  network  systems  are  interdependent.  For 
planning and for the sake of simplicity normally only one set of NTC values, that do not reflect NTC 
 

interdependencies between several borders, is published. In case of strong NTC interdependencies, 
better information can be provided by additionally computing values of transfer capacities for groups 
of  areas.  i.e.,  if  there  is  a  strong  physical  coupling  between  areas  A  and  B  regarding  exchanges  to 
area C, NTC would be provided from area A to area C, from area B to area C and from areas A + B, 
considered as a whole, to C. However, during the allocation phases the coupling between the areas 
has to be respected. Allocation thus may lead to new restrictions as shown in the following Figure 11. 
 

 
FIGURE 11 INTERDEPENDENCIES OF NTC BETWEEN TWO ARAES (HTTP://WWW.ETSO‐NET.ORG) 

In the figure it is assumed that in the planning phase the NTC value between areas A and C was assessed to 
2000 MW and that independently from this the calculation of NTC between areas B and C lead to a value of 
4000  MW.  For  planning  purposes  the  TSOs  thus  have  given  to  market  participants  maximum  values,  not 
reflecting  the  interdependencies  between  the  areas.  Indeed  the  sum  of  import  to  area  C  may  be  limited  to 
only 5000 MW. Then, at least during the allocations this fact has to be taken into consideration. It is out of the 
scope  of  this  document  to  define  the  criteria  for  the  split  of  this  total  value  into  the  capacity  for  allocation 
from A to C and from B to C. 

• Finally the NTC values itself do not provide the basis for a co‐ordinated method of allocating cross border 
trade  over  several  borders  in  a  meshed  network.  A  vision  for  a  coordinated  approach  was  already 
4
presented in ETSO document . It relies on the same computation principles as NTC, but the allocation of 
transfer  capacities  would  be  effected  on  the  basis  of  the  consequences  in  terms  of  load  flows  and  not 
directly using the bilateral values of NTC. Therefore, the importance that NTC values actually have in the 
transaction based concepts of the international trade in Continental Europe will diminish. 

From the discussion above it can be concluded that NTC values have significant shortcomings while dealing 
with  parallel  flows,  hence  it  would  not  be  easy  to  implement  this  system  for  coupling  Germany  into  the 
current system of MC existing between NL, BE and FR. Even if it can be implemented major changes would 
need  to  be  introduced  into  the  algorithm  to  be  able  to  care  of  the  new  additional  complexity.  TSO’s  would 
also request higher TRMs to be able to balance the unexpected flows. Hence MC is not a suitable system for 
coupling North West European region. FMC is able to address these issues by considering the whole network 
at once and calculating the effects of each transaction on each tie line. The details of FMC and power transfer 
distribution functions (PTDF’s) are presented in section 5.1.1 

By  introducing  PTDF‐based  allocation,  the  transmission  capacity  available  for  each  border  and  exchange 
direction is only specified within the allocation process (and thus not ex‐ante before the auction as is the case 
with  NTC).  This  is  implemented  taking  the  capacity  bids  and  the  physical  interrelationships  between  the 
Chapter: Flow‐based market coupling 

exchange  directions  and  the  load  flows  on  crucial  transmission  lines  into  account.  In  practical  terms,  this 
facilitates short‐term capacity transfers between borders compared to the NTC model. 

3.6 CONCLUSION 
In  short,  FMC  is  a  new  method  for  Cross‐Border  Congestion  Management.  It  combines  commercial  energy 
bids  with  physical  reality  to  optimize  network  use  with  respect  to  market  value.  FMC  is  similar  to  by  yet 

                                                                         
4
Co-ordinated Auctioning of Transmission Capacity in Meshed Networks, Discussion paper, ETSO, November
2000

  23 
 
24  Flow‐based Market Coupling 
 

different  from the market splitting approach  implemented in the Nordic  electricity system, which  it tries to 


imitate  (Glachant  and  Pignon  2002).  Market  splitting  approach  has  one  common  pool  where  generation 
entities  submit  offers  and  load  entities  submit  load  bids.  Then  the  market  is  cleared  based  on  merit‐order 
while  respecting  the  system  constraints  and  reliability  margins,  and  the  subsequent  unit‐dispatch  and 
scheduling  is  managed  by  the  independent  national  system  operators.  The  market  is  split,  or  has  different 
prices  if  there  exists  any  congestion  preventing  complete  convergence  of  prices  across  all  area.  However  in 
case of FMC the bids are submitted to the individual Power Exchanges who calculate the import‐export curves 
for each country and submit it to a supra‐national entity (or an algorithm) that calculates the prices for each 
market while respecting the capacity available at the tie‐lines between the countries. Thus it tries to couple 
the  markets;  though  the  results  of  the  algorithm  may  be  same  to  that  of  market  splitting  the  approach  is 
different. The other major difference lies in the fact that Market Splitting and Market Coupling is still based on 
NTC method for capacity calculation and not on flow based method. 

FMC is also different from nodal pricing which is implemented in PJM, the largest single energy market in the 
world.  Nodal  pricing  calculates  price  on  each  node  based  on  the  price  and  congestion,  it  is  also  called 
Locational  Marginal  Pricing,  and each node has  different  price. FMC does not give one price for each node, 
but gives zonal prices, i.e. it considers set of nodes as a zone and assumes them as being “copper plates” while 
the zones are connected by means of tie‐lines. The tie‐line limits the amount of electricity that can be traded 
across the regions and so the prices in the two regions may or may not converge depending on congestion of 
the  tie‐lines.  FMC  is  complex  market  mechanism  to  understand  and  hence  its  implications  on  the  national 
welfare  are  not  fully  understood.  The  thesis  would  aim  to  answer  some  of  these  questions  by  developing  a 
simulation tool to help understand the system and its sensitivities towards aspirations and actions of involved 
actors. 

   
 

4 PROBLEM FORMULATION 
 

For  public  authorities  (who  must  approve  of  the  congestion  management  method  to  be  used)  the 
introduction of a more efficient method such as FMC seems to be an attractive option. As the implementation 
of the system is now also prescribed in European legislation, the introduction of FMC is currently high on the 
political  agenda  (especially  in  the  Central  West  Region  –  Netherlands,  France,  Germany,  Luxemburg  and 
Belgium).  

The chosen approach for congestion management (FMC) will impact the possibility and incentive to utilize the 
transmission network. There are a few but important requirements to congestions management methods as: 
fair and non‐discriminatory, economically efficient, transparent, feasible and compatible with different types 
of trades. 

The  currently  used  method  will  to  an  extent  fulfill  these  requirements,  but  it  is  important  to  realize  that 
systems have different structure and by this technical challenges. 

From  the  feasibility  point  of  view,  the  methods  will  have  to  be  analyzed.  The  market  design  will  also  be 
important for which kind of method that best suits a particular system. 

The functioning of FMC method is quite complex, the sensitivity of the system are unknown and the effects 
(on  national  level)  are  difficult  to  predict.  Various  questions  remain  unanswered  at  this  moment.  The  main 
research question can be formulated as follows 

4.1 PROBLEM STATEMENT 
What  are  the  impediments  to  and  implications  of  implementing  Flow‐based  Market  Coupling  as  a 
Congestion Management Mechanism in the North West European Countries? 

To  answer  the  above  question  one  needs  to  understand  FMC,  and  its  operation.  Once  the  operation  is 
understood next step is to understand the distributive effects of the welfare gain. To this cause a model needs 
to be developed for FMC which can enable better understanding of “what if “ scenarios. Thus the research is 
hinged on development of an decision support model which would enable the policy maker, in case of present 
research the Ministry of Economic Affairs of The Netherlands, to understand the implications of FMC to Dutch 
electricity supply. The main research objective can thus be formulated as follows: 

To  develop  a  decision‐support  model  for  evaluating  the  implications  of  and  impediments  to  implementing 
Flow‐based  Market  Coupling  for  alleviating  the  issue  of  interconnector  congestion  among  European 
countries. 

4.2 SCOPE DEFINITION 
However  the  scope  of  the  question  is  broad  and  needs  to  be  structured  to  make  it  easily  tractable.  The 
boundaries of the problem are defined both in geographical sense and temporal sense. The scope covered in 
Chapter: Problem Formulation 

the research would be: 

4.2.1 GEOGRAPHICAL SCOPE  
The  Netherland  and  immediate  continental  neighbors  (Northwest  European  region  namely  Belgium, 
Germany and France). It should also be stated that Luxembourg is also officially a part of the region and is also 
participating  the  regional  initiative  and  pentalateral  forum.  Luxembourg  has  two  electricity  transmission 
networks  that  are  not  interconnected,  but  are  integrated  with  the  networks  of  the  neighboring  countries, 
Germany and Belgium. Hence Luxembourg is not considered as a special prices area and because the network 

  25 
 
26  Flow‐based Market Coupling 
 

is not connected within Luxembourg it does not lead to any parallel flows and can hence be counted out of the 
market model. 

 
FIGURE 12 THE SYSTEM UNDER CONSIDERATION 

4.2.2 TEMPORAL SCOPE 
The  study  is  going  to  study  the  distributive  effects  of  the  benefits  earned  through  the  FMC,  so  it  needs  to 
consider both the short term and long term effects. Hence the study would be conducted at two levels. Firstly, 
from the operational efficiency point of view focusing on day ahead or intraday market, on which much of the 
literature  is  focused  and  secondly,  from  a  long  term  capital  investment  perspective.  Given  the  investment 
cycle is usually 15‐20 years; the second analysis should take into consideration this time scale. The former part 
of the study  would  be answered  primarily by the outcomes of the model simulations.  Once the  operational 
results have been determined it is possible to predict the longer term implications by a mix of expert opinion 
and the literature survey. 

4.3 PERSPECTIVE/PROBLEM OWNER 
The  main  problem  owner  for  the  given  research  question  is  the  Dutch  Ministry  of  Economic  Affairs.  The 
problem will be analyzed through their lenses. It is also important to state here hat partly the regulator DTe 
and TSO Tennet also could have considerable interest in outcomes study.  

By  taking  the  Ministry  of  Economic  Affairs  as  the  problem  owner,  additional  constraints  exist  for  the  end 
result of this thesis: The results should be such that people at the Ministry who deal with market integration 
but who do not want to bother with detailed technical or economic calculations may gain from the results of 
the present study. 

4.4 SUB‐QUESTIONS 
Further the  problem statement can be sub‐divided and grouped under the following  classifications to make 
the research better structured. 

   
 

4.4.1 SYSTEM BEHAVIOR  
a) How sensitive is the system for the choice of a specific set of PTDFs ? 

b) What is the effect of constraints on the system? Could it lead to a less optimal outcome with respect 
to optimizing market value? 

E.g. policy makers may want to reserve a minimum amount of capacity on certain flow gates with respect to the 
investments they made regarding those flowgates in the past or with respect to security of supply 

c) What will be the net benefit of future network investments on available interconnector capacity and 
the Dutch electricity price level? 

o What would be the effect on the price level within Netherlands? 

o Would it lead to more transits and loop flows? 

o How would the actors perceive this change? 

4.4.2 SECURITY OF SUPPLY  
• What is the risk that FMC would lead to a net reduction of the import capacity? 

• How  may  FMC  interfere  with  security  of  supply  in  the  Dutch  electricity  system?  (As  less  or  no 
capacity at all could be distributed to a certain border if market value is low)? 

4.4.3 WELFARE EFFECTS 
• What could be the effect of such system on national welfare as the system optimizes regional welfare 
in terms of market value? 

• What is the effect of the presence of four national systems on the distribution of the welfare for each 
of the four systems? 

• How  many  incentives  will  FMC  give  to  increase  electricity  production  from  renewable  energy 
sources? 

4.4.4 IMPLEMENTATION ISSUES 
• What is the effect on transparency? 

• Would  some  kind  of  European  central  decision  making  unit  be  required?  (e.g.  to  decide  about  the 
distribution of capacity on the national borders). 

• What about gaming opportunities because of strategic actors? 

The  questions  on  system  and  welfare  would  be  answered  primarily  by  the  simulation  model.  The  questions 
with respect to security and implementation would be answered using the expert opinion/interviews with the 
problem owner/literature survey. 
Chapter: Problem Formulation 

4.5 RESEARCH DESIGN 
To be able to answer the above mentioned questions it was necessary to first understand FMC from the 
theoretical perspective. It would be possible to gauge the effects of FMC on the national and regional level if a 
simulation model with FMC can be set up with the present level of generation, loads and the transmission line 
typography. The first step in the research would hence be to study FMC and its working within the North West 
European region context. The study would aim to study the impact that FMC would have on the various actors 

  27 
 
28  Flow‐based Market Coupling 
 

within the four countries defined in the geographical scope of research. The part of research would be based 
on the Neo‐classical economics treatment of the market design.  The details of the simulation model would 
be discussed in the subsequent chapter. 

 
FIGURE 13 RESEARCH DESIGN 

The second part that needs to be explored is the institutional aspects of the multi‐actor environment into 
which this system would be introduced. The process of implementation of such a market design is further 
complicated because of presence of large number of actors and stakeholders. This impact of this market 
design on various actors and interests of the various actors would be studies in this section. The last part of 
the report would detail in brief the issues associated with implementation of a market design – like 
transparency, legal aspects, etc. 
   
 

 
   
Section 2: Simulation Model 

A  step  by  step  description  of  how  the 


model  was  created  is  presented  in  this 
section.    Details  and  relevant  data  is 
presented in the appendices.  

Chapter: Problem Formulation 

  29 
 
30  Flow‐based Market Coupling 
 

   
 

5 STRUCTURE OF SIMULATION MODEL 
 

Flow‐based  allocation  is  a  supra‐national  approach:  all  bids  for  energy  and/or  cross‐border  capacity  are 
optimized by collected by the national PXs, and are then combined together by using an algorithm that takes 
care of final allocation and dispatch. In the flow‐based allocation mechanism, the commercial transactions are 
no longer limited to the interconnections where they are reported, but they are converted into physical power 
flows by using a simplified representation of the network so that their impacts on third interconnections can 
be considered thus ensuring overall security.  

NL Supply Curve
€ 80.00
€ 70.00 y = 3 .183x

Pri ce (euro s/MWh)


€ 60.00 R ² = 0.831
€ 50.00
€ 40.00
€ 30.00 N L Supply
€ 20.00 Curve
€ 10.00
€-
0 .00 5.00 1 0.00 15 .00 20.00 2 5.00
Gen eratio n Cap aci ty ( GW)

Prices (euros)
€ 6 0.0 0

€ 5 0.0 0

€ 4 0.0 0

€ 3 0.0 0

€ 2 0.0 0

€ 1 0.0 0

€-
NL BE FR DE
P*

 
FIGURE 14 DESIGN OF THE SIMULATION ENVIRONMENT 

The  simulation  model  for  the  integrated  markets  in  the  four  countries  of  interest  was  created.  None  of  the 
commercially available software was able to address all the aspects of modelling. Hence the work was divided 
into three main parts for both data gathering and modelling: 

1. Transmission  network  module  for  the  four  countries  (BE,  NL,  FR  and  DE).  This  included  simulating 
the  transmission  network  in  the  north‐west  European  region  using  specialized  software  used  for 
solving large transmission network problems (PowerWorld).  
Chapter: Structure of Simulation Model 

2. Electricity  demand  and  supply  module:    Includes  a  sub‐model  for  calculating  the  marginal  cost  of 
generation.  Marginal  cost  of  generation  data  along  with  installed  capacity  data  is  used  to  create  a 
representative  merit  order  for  each  country.  From  the  merit  order  a  linear  supply  function  is 
extracted. Demand function is also defined.  
3. Electricity  day‐ahead market module: This is essentially an optimization module that simulates the 
implicit flow‐based market coupling for calculating the electricity dispatch on day‐ahead basis. 

The process is outlined in Figure 14.  

The next sections would elaborate the process of creating each one of the three modules outlined above. 

  31 
 
32  Flow‐based Market Coupling 
 

5.1 TRANSMISSION NETWORK MODULE 
The  research  required  an  appropriate  benchmark  system  to  base  the  simulation  on.  Creation  of  a  realistic 
benchmark system is difficult as utilities are often not willing to disclose details of their own systems because 
of commercial sensitivity and security reasons. Most TSOs, generators and industrial loads normally refused 
to share any information  whatsoever  citing  commercial sensitivity or security reasons. The former excuse is 
debatable  as  transparency  is  one  of  the  main  pre‐requisites  for  an  efficient  market.  The  subject  becomes 
more  complex  because  of  dealing  with  four  countries  and  hence  most  of  the  required  information  was 
inaccessible. Also there was no specialized software available at TU Delft that could be used to simulate such 
a  complex  network.    After  spending  considerable  time  on  trying  to  resolve  these  operational  and 
informational  issues  –  it  was  considered  to  look  at  past  research  on  UCTE  region  conducted  elsewhere. 
University  of  Edinburgh  has  developed  a  benchmark  transmission  network  for  the  UCTE  region.  It  was 
possible to get this model and use it for the current research(Qiong and Bialek 2005). With access to the UCTE 
transmission  network  model  and  purchase  of  PowerWorld  the  work  could  proceed.  The  entire  UCTE 
transmission network model was used – as decoupling the four countries of interest from the rest would lead 
to imbalance in the system and hence the solution could not converge.  

 
FIGURE 15 INTERCONNECTED NETWORK OF UCTE (HTTP://WWW.UCTE.ORG/) 

The approximate model of a European interconnected system was used to study the effects of cross‐border 
trades. The system was considered as a realistic representation of the reality for the purpose of the simulation 
because the results from the model were tested with the real PTDFs values by the researchers and significant 
correlation  was  found  between  the  two.  More  details  are  attached  in  the  chapter  on  verification  and 
validation chapter 66 Validation and Verification of model, pg 56 

… “Comparison of simulation results conducted on the test system with the published cross‐border flows and 
power transfer distribution factors showed a very good correlation, exceeding 90%.”.(Qiong and Bialek 2005) 

Using  the  model  as  a  research  tool  which  would  replicate  main  physical  characteristics  of  the  real  network 
without pretending to be an accurate model, the PTDF’s were derived for the four countries. 

   
 

5.1.1 POWER TRANSFER DISTRIBUTION FACTOR 
Transmission capacities are nowadays allocated at all European borders on the basis of NTCs. The NTC values 
indicate  the  maximum  commercial  power  exchange  allowed  between  two  countries  (more  specifically: 
control zones and blocks). They are fixed prior to allocation (e.g. before bids for an explicit capacity auction 
are submitted) by the TSOs involved and remain static during the allocation. 

 Electricity transmission flows fan out across all available parallel paths in accordance with the laws of physics. 
This  is  illustrated  in  the  next  figure,  in  which  all  countries  are  balanced  and  only  a  100  MW  commercial 
exchange  from  Germany  (DE,  source)  to  France  (FR,  sink)  is  taking  place  and  the  resulting  physical  cross‐
border flows are shown. 

 
FIGURE  16  PHYSICL  FLOWS  BECAUSE  OF  A  TRANSACTION  OF  100  UNITS  OF  TRADE  BETWEEN  FRANCE  AND  GERMANY 
(HTTP://WWW.ETSO‐NET.ORG) 

PTDF  factors  describe  what  physical  flow  on  a  given  interconnection  would  be  provoked  by  a  requested 
commercial  exchange  between  two  countries  or  two  control  areas  (or  ‘hubs’).  These  two  hubs  do  not 
necessarily need to be directly connected. Simply said, the PTDF factors translate a commercial transaction 
between  two  hubs  into  the  expected  physical  flows  over  the  entire  network.  The  PTDF  factors  that 
correspond to the situation that is illustrated in the Figure 16, can be seen from the column on the right: the 
PTDF  factor  D‐NL  with  regard  to  an  exchange  D‐F  is  27%,  the  PTDF  D‐F  is  36%  etc.  Thus  it  can  be  easily 
derived for example, that a 100 MW commercial exchange from Germany to France results in a 27 MW flow 
from Germany to the Netherlands. 

In theory the PTDFs are calculated as described below. 
Chapter: Structure of Simulation Model 

 
FIGURE 17 GENERIC REFERENCE CASE FOR CALCULATION OF PTDF 

The PTDF in theory can be calculated as follows: 
• Let   be the flow of the branch j ‐> k in the reference state. 

  33 
 
34  Flow‐based Market Coupling 
 

• Let   be the flow of the branch j ‐> k after the injection of 1 MW at node I (and compensation at the 
hub also referred to as the slack node). 
 
The expression of the nodal PTDF   which means the influence of the injection of 1MW at node i on the 
branch j ‐> k is: 
 
   
 
This  process  is  automated  while  using  PowerWorld.  Next  section  would  describe  the  process  followed  by 
PowerWorld for calculating PTDF, followed by the section on how to actual perform the process. 

5.1.2 USE OF PTDF 
Allocation on the basis of Power Transmission Distribution Factors (PTDF) represents a further development 
of this concept which dynamises the specification of commercially available capacities for each border. This 
does not occur prior to the allocation, but is part of it, based on an economical optimization, taking parallel 
flows into account, coordinated for several borders and taking account of the differences in price and costs of 
power generation between the regions. 

To  this  end,  so‐called  PTDF  coefficients  are  used  that  describe  how  commercial  power  exchange  between 
regions is distributed on physical power flows at the interfaces (interconnectors) between these and between 
other  regions.  Compared  to  traditional  NTC‐based  allocation,  this  basically  facilitates  a  transfer  of 
commercial  transmission  capacities  between  the  borders  that  is  not  at  a  ratio  of  1:1,  but  at  a  ratio  of  the 
respective PTDF values 

Based on the values of PTDFs, transactions are curtailed and increased in order to relieve lines overloads. Due 
to  the  phenomenon  of  loop  flows  in  a  meshed  network,  PTDF  calculation  requires  the  full  network 
information. 

5.1.3 CALCULATION OF PTDF IN POWERWORLD 
The Power Transfer Distribution Factor (PTDF) display is used to calculate the incremental distribution factors 
associated  with  power  transfers  between  two  different  areas  or  zones.  These  values  provide  a  linearized 
approximation  of  how  the  flow  on  the  transmission  lines  and  interfaces  change  in  response  to  transaction 
between the Seller and the Buyer. These values can then be visualized on the onelines using animated flows 
(see below for details). The transaction for which the PTDFs are calculated is modeled by scaling the output of 
all  generators  on  Automatic  Generation  Control  in  the  source  and  sink  areas  in  proportion  to  their  relative 
participation factors,i.e, generators in the source area increase their output, while generators in the sink area 
decrease their output. 

FIGURE 18 SCHEMATIC OF THE TRANSMISSION NETWORK MODULE 
 

An  important  aspect  to  consider  in  calculating  the  PTDF  is  how  the  losses  associated  with  the  transfer  are 
allocated.  Simulator  assumes  that  the  Seller  increases  the  output  of  its  generators  by  100%  of  the  transfer 
amount, while the Buyer decreases the output of its generators by 100% minus any change in system losses. 
In other words, the Buyer accounts for the entire change in the system losses. Of course it is possible that a 
transfer may result in decreased system losses; for that case, the Buyer’s generation will be greater than 100% 
of the transfer.  

5.1.4 HOW TO GET PTDF FROM POWERWORLD 
Open the *.pwb file using  PowerWorld  open new  file menu. Once the model  has been opened  perform the 
following  steps  to  get  the  PTDF  for  each  set  of  the  country.  Repeat  the  steps  with  other  combinations  of 
countries till all the required data has been collected. 

• Perform an initial Power Flow Solution. 

• In Run Mode, select  Tools > Power Transfer Distribution Factors (PTDFs)  from the main menu to 


open the Power Transfer Distribution Factors Dialog. 

• Supply  the  requested  information  on  the  Power  Transfer  Distribution  Factors  Dialog  and  click  the 
Calculate PTDFs button. The distribution factors are calculated and displayed for the element set of 
your choice in the table at the bottom of the dialog. 

 Figure  20  displays  the  UCTE  model  from  PowerWorld,  while  zooming  in  on  the  Dutch‐Belgian  border.  The 
circles show the amount of interconnector capacity that is being utilized. 

 
FIGURE  19  THE  UTILIZATION  OF  INTERCONNECTOR  BETWEEN  THE  COUNTRIES  IN  THE  NORT‐WEST  EUROPEAN  REGION 
FROM THE MODLE RUN IN POWERWORLD 

   
Chapter: Structure of Simulation Model 

  35 
 
36  Flow‐based Market Coupling 
 

Zoom‐in  on  Dutch  Belgian  Interface 


showing  the  usage  of  interconnector 
capacity  and  the  direction  of  flow  of 
electricity for winter offpeak base case 

 
FIGURE 20 UCTE NETWORK WITH ENHANCED NL‐BE BORDER 

   
 

TABLE 1 SENSTIVITY MATRIX AND PTDF BASED ON THE UCTE WINTER PEAK MODEL FROM POWERWORLD 

Sensitivity Matrix     
                   
           NL→NL  BE→NL  FR→NL  DE→NL     
  BE  →  FR  0  0.196  ‐0.484  ‐0.244     
  BE  →  NL  0  0.804  0.484  0.244     
  DE  →  FR  0  ‐0.138  ‐0.272  0.107     
  DE  →  NL  0  0.196  0.516  0.756     
                   

PTDF Matrix      
                   
        Commercial Exchange          
           BE→NL  FR→NL  DE→NL  FR→BE  DE→BE  DE→FR 
  BE  →  FR  0.196  ‐0.484  ‐0.244  0.31  ‐0.44  0.24 

  BE  →  NL  0.804  0.484  0.244  0.31  ‐0.56  ‐0.24 

  DE  →  FR  ‐0.138  ‐0.272  0.107  ‐0.69  0.245  0.379 

  DE  →  NL  0.196  0.516  0.756  0.31  0.56  0.24 

  Physical Flow                
 

It can be observed that sum of the numbers do not add up to 1,in the PTDF and Sensitivity matrix – the reason 
is because the north‐west European region is not completely decoupled from rest of UCTE region and some of 
the flows take place through neighboring countries. In case of a commercial transaction between France and 
Netherlands almost 14% of flow takes place from France through Switzerland and then into Germany. This is 
interesting  feature  of  the  FMC  as  not  there  could  be  exchanges  between  Switzerland  and  Germany  or 
Switzerland and France that would make use of the interconnector between France and Germany – however 
Switzerland is out of the FMC and hence calculation of the rent or marginal cost for usage of interconnector 
capacity would create additional problems. 

These  PTDF  values  were  used  in  the  market  module  to  calculate  the  actual  flows  occurring  on  the 
interconnectors  given  the  commercial  exchanges  which  would  maximize  the  market  value,  or  minimize  the 
net cost of electricity generation.  

5.2 ELECTRICITY DEMAND AND SUPPLY MODULE 
Chapter: Structure of Simulation Model 

Economic  model  of  the  system  comprised  of  getting  the  supply  and  demand  curves  for  the  four  countries. 
Supply curve was based on the real data for cost of generation and the installed generation in every country. 
The demand curve was derived from the supply curve by substituting the average demand in the country and 
then obtaining the slope and the intercept. The next sections will describe in  detail the procedure to obtain 
the demand and supply curves. 

  37 
 
38  Flow‐based Market Coupling 
 

NL Supply Curve
€ 80.00
€ 70.00 y = 3.183x

Pric e (euros/MWh)
€ 60.00 R² = 0.831
€ 50.00
€ 40.00
€ 30.00 NL Supply
€ 20.00 Curve
€ 10.00
€-
0.00 5.00 10.00 15.00 20.00 25.00
Generation Capacity (GW)

FIGURE 21 SCHEMATIC OF THE ELECTRICITY DEMAND AND SUPPLY MODULE 

5.2.1 SUPPLY C URVE 


Supply curve for a country needs two basic inputs 

1. Cost of electricity generation 
2. Installed generation capacity 

However the supply curve obtained this way, as also in real life, is not linear – it is a discrete stepwise function. 
To  simplify  the  calculations  linearity  assumption  is  made.  The  data  for  cost  of  electricity  generation  and 
capacity is plotted and then a best fit for the supply curve is calculated. The data for the cost and capacity is 
collected from different sources – as variable cost data is not easily available because it is classified.  For the 
actual values turn over to Appendix A1.  

5.2.2 COST OF ELECTRICITY GENERATION  
The sources of electricity generation can be grouped predominantly into two categories – fossil (coal, oil and 
gas) and others (wind, hydro, nuclear and biomass). To convert energy from its original form into electricity 
many different technologies can be employed – Turbines, Internal Combustion engines, nuclear fission based 
power  plants,  combined  cycle  plants  and  combined  heat  and  power  plants.  Cost  structures  of  electricity 
generated  from  all  these  resources  and  technologies  vary  widely.  Hence  a  comprehensive  data  base  was 
collected to get as realistic values of the costs involved as possible. Also there is a debate on use of short term 
variable cost or the long term total cost for the market simulation. However fixed costs are also earned back 
based  on  marginal  pricing,  i.e.  equal  to  only  the  variable  costs(Stoft  2002)  because  of  price  volatility  and 
peaks in prices. Based on the cost of generation the technologies were classified into following categories:  

TABLE 2 CATEGORIES OF GENERATION TECHNOLOGIES 

Energy Technology  Symbol 
Hydro  H 
Wind  W 
Nuclear  N 
Hard Coal Condensation  HC 
Lignite Condensation  LC 
CHP Natural Gas  CHP‐G 
Natural Gas Combined Cycle  G 
Oil  O 
CHP Biomass  CHP‐B 
CHP Oil  CHP‐O 
 

CHP oil is not present in all  countries, and the installed capacity is very low. Also the cost of generation are 
usually higher, hence it was removed from the list for further analysis. 

The generation companies do not reveal any data about the marginal cost of generation or the variable costs. 
It is considered to be sensitive information and is kept secret. Hence data was collected from varied sources: it 
was ensured that data be  from real plants. The secrecy of the plants was not revealed  in the reports by not 
declaring  the  plant  name,  location  or  ownership  information  –  thus  also  respecting  the  fears  of  generation 
companies.  Data from various sources was collected for all three cost categories (more can be looked up in 
the Appendix A1), i.e.  

1. Fixed cost (FC): Fixed cost comprised mainly of the cost of capital. It includes debt and equity costs 
associated  with  the  capital  invested  in  the  plant  that  do  not  depend  on  its  level  of  operation.  The 
upfront  investment  is  distributed  over  the  lifetime  operation  of  the  plant  for  being  earned  back. 
Nominal discount rate is applied to get the NPV of the investment. 
2. Variable Cost (VC): A cost that varies with the level of output. In special case of electricity this is also 
the generators marginal cost until the full output is reached. This cost is comprised mainly the fuel 
cost, though it also includes operation and maintenance costs.  
3. Total Cost (TC): This is the total cost of generation of one MW of electricity.  It includes fixed costs, 
variable costs, start‐up costs and no‐load costs. It is also called total cost of production. 
4. Start‐up Costs: The costs associated with additional fuel usage and extra labor and process required 
to start generation in a plant. These are usually high for base load coal based power plants and are 
much smaller for gas based CCGT power plants. 
5. No‐load  Costs:  The  costs  associated  with  just  keeping  the  plant  in  stand‐by  mode,  including  the 
cooling and fuel costs are termed as no‐load costs. 

The costs are related as follows: 

Total Cost = Variable Cost + Fixed Cost + Start‐up Costs + No‐load Costs 

Also  in  present  scenario,  with  Carbon  trading  coming  in  force,  emission  costs  were  also  included.  Hence 
information was also collected on the emissions related to each generation technology and the cost of carbon 
credits. Thus giving rise to an additional category of  costs that would be referred to as environmental  costs 
(EC) henceforth in the report. 

Therefore the total costs can be defined as  

Total Cost = Variable Cost + Fixed Cost + Start‐up Costs + No‐load Costs + Environmental Costs 

Additionally, given the importance that has been attached to the environmental impact from the generation 
technologies  and  the  emission  trading  a  cost  for  the  emissions  has  also  been  included.  Variable  costs  as 
displayed  in  the  model  are  the  sum  of  fuel  costs,  operation  and  maintenance  costs  and  the  CO2  emission 
costs. 
Chapter: Structure of Simulation Model 

The  No‐Load  Cost  is  defined  as  the  total  theoretical  heat  or  fuel  input  at  zero  net  output  multiplied  by  the 
performance factor, multiplied by the (Total Fuel‐Related Cost (TFRC)), plus the No‐Load Additional Labour 
Cost(PJM  2006).  The  dollars  per  start  as  determined  from  start  fuel,  total  fuel‐related  cost,  performance 
factor, electrical costs, start maintenance adder, and additional labour cost, if required above normal station 
manning  levels  (PJM  2006).  For  the  model  assumption  is  made  that  start‐up  costs  and  no‐load  costs  are 
negligible compared to the rest and are hence assumed to be absent. i.e.  

TC = VC + FC 

The generation cost for each of the technologies was broadly based on six different sources: 

  39 
 
40  Flow‐based Market Coupling 
 

1. Risto  TARJANNE  ,  “EU  POLICY  AND  CARBON  EMISSION  TRADING:  IMPLICATIONS  FOR  THE 
ENERGY MARKET”, Lappeenranta University of Technology 
2. Vattenfall Annual Report 2006 (Vattenfall 2006) 
3. Projected Costs of Generating Electricity 2005 Update (OECD) 
4. Paper about game theoretic model of the Northwestern European electricity market (Lise, Linderhof 
et al. 2006) 
5. Federal  Energy  Regulatory  Commission,  FERC  Form  1,  "Annual  Report  of  Major  Electric  Utilities, 
Licensees and Others." 
6. Hoogwijk, M., D. van Vuuren, et al. (2007). "Exploring the impact on cost and electricity production of 
high  penetration  levels  of  intermittent  electricity  in  OECD  Europe  and  the  USA,  results  for  wind 
energy." Energy 32(8): 1381‐1402. 
 

The Vattenfall annual report for 2006 gave detailed break‐up of cost for 7 different generation technologies. 
More details about the advantages, disadvantages and brake‐up of the costs can be found in the appendix A.2 

TABLE 3. TOTAL COST OF GENERATION FOR DIFFERENT TECHNOLOGIES 

Specific Investment Full Load Real Interest


Energy Technology Symbol Installed Capacity Investment Cost Cost Utilization Time Capacity Factor Economic Lifetime Rate Anuity Payment Capital Cost

MW million € €/kW h/a % a % € €/MWh


Hydro H 1 1.5 € 1,500.00 4500 51% 50 5% (€82,165.10) € 18.26
Wind W 1 1.1 € 1,100.00 2200 25% 25 5% (€78,047.70) € 35.48

Nuclear N 1500 3075 € 2,050.00 8000 91% 40 5% (€179,205,345.59) € 14.93

Hard Coal Condensation HC 500 525 € 1,050.00 8000 91% 25 5% (€37,250,040.08) € 9.31
Lignite Condensation LC 150 172.5 € 1,150.00 8000 91% 25 5% (€12,239,298.88) € 10.20

CHP Natural Gas CHP-G 81 104 € 1,283.95 8000 91% 40 5% (€6,060,928.76) € 9.35

Natural Gas Combined Cycle G 400 232 € 580.00 8000 91% 25 5% (€16,460,970.09) € 5.14

Oil O 100 117 € 1,170.00 7450 85% 25 5% (€8,301,437.50) € 11.14


CHP Biomass CHP-B 1 3.415 € 3,415.00 8000 91% 30 5% (€222,150.65) € 27.77
 
Total
Total Variable Total Cost
O&M Costs, Variable Cost (with (with
Fuel Cost of for given Heat Credit Cost (w/o Total Cost (w/o Emission emission emission
Symbol Fuel Price Net Efficiency Rate Electricity utilization (Only CHP) emission) emission) Emission Price Emissions Cost pricing) pricing)

€/MWh % €/MWh €/MWh €/MWh €/MWh €/tonne kg CO2/MWh €/MWh €/MWhe €/MWhe
H € - 100% € - € 6.60 € 6.60 € 24.86 20 0 € - € 6.60 € 24.86

W € - 100% € - € 10.00 € 10.00 € 45.48 20 0 € - € 10.00 € 45.48

N € 1.10 37% € 2.97 € 8.00 € 10.97 € 25.91 20 0 € - € 10.97 € 25.91

HC € 7.50 42% € 17.86 € 7.50 € 25.36 € 34.67 20 811 € 16.22 € 41.58 € 50.89

LC € 7.40 40% € 18.50 € 7.00 € 25.50 € 35.70 20 954 € 19.08 € 44.58 € 54.78

CHP-G € 27.00 € 59.62 € 8.15 € 29.85 € 37.92 € 47.28 20 348 € 6.96 € 44.88 € 54.24

G € 27.00 58% € 46.55 € 4.00 € 50.55 € 55.70 20 348 € 6.96 € 57.51 € 62.66

O € 25.15 41% € 61.34 € 10.70 € 72.04 € 83.18 20 1 € 0.02 € 72.06 € 83.20

CHP-B € - € 14.59 € 122.50 € 29.85 € 107.24 € 135.01 20 0 € - € 107.24 € 135.01


 
TABLE 4 FORMULATION OF COST SHEET 

Variable  Units  Significance 


Installed Capacity  MW  The electricity generation capacity of the plant whose data was used 
as being representative of plants operating with same fuel type. 
Investment Cost  million €  Overnight cost of installing the plant under consideration. 
Specific Investment Cost  €/kW  Ratio of Investment cost to installed capacity 
Full Load Utilization Time  h/a  Number of hours the plant is expected to operate in a particular year 
Capacity Factor  %  Number of hours of operation divided by total number of hours in a 
year 
Economic Lifetime  a  The number of years the plant is expected to be in operation. 
Real Interest Rate  %  The interest rate for the loan that was used to pay for installation of 
 

the power plant 
Annuity Payment  €  It was assumed that the loan was paid back by means of installments 
paid annually for the period of lifetime of the plant. Depreciation was 
not considered in the model. Annuity was calculated using PMT 
function from excel. PMT(rate,nper,pv,fv,type) = PMT(Real Interest 
Rate, Economic Lifetime, Investment Cost) 
Capital Cost  €/MWh  The fixed cost associated with generation of 1MWh. It was calculated 
by dividing the Annuity Payment by the net electricity generation per 
year. Net electricity generation per year was calculated by multiplying 
the installed capacity with full load utilization time. 
Fuel Price  €/MWh  The cost of fuel used in the plant in Euros per MWh. This is the major 
part in the variable cost for plants based on fossil and nuclear fuels. 
Net Efficiency Rate  %  Net electrical efficiency of the plant 
Fuel Cost of Electricity   €/MWh  Cost of generating one MWh of electricity because of the fuel. It was 
calculated by dividing the fuel price by net efficiency rate. 
O&M Costs, for given  €/MWh  The operating and maintenance costs for the plant. It is the second 
utilization  important contributor to the variable cost of electricity generation. 
Heat Credit (Only CHP)     In case of CHP, heat as well as electricity is generated. Hence it is 
important to consider the profits that are made by selling the heat 
which is generated as by product of electricity generation. This was 
collected from the reference data as well. (mainly the OECD report) 
Total Variable Cost (w/o  €/MWh  Sum of fuel cost of electricity and O&M costs. In case of CHP the heat 
emission)  credit was subtracted from the sum to get total variable cost. 
Total Cost (w/o emission)  €/MWh  Sum of the total variable cost and capital cost 
Emission Price  €/tonne  The price of carbon credits in euros per ton of carbon di oxide emission 
Emissions  kg CO2/MWh  Emission of carbon di oxide because of generation of 1 MWh of 
electricity using a particular fuel type 
Emission Cost  €/MWh  Product of emission and emission price 
Total Variable Cost (with  €/MWhe  Sum of total variable cost and emission cost 
emission pricing) 
Total Cost (with emission  €/MWhe  Sum of capital cost and total variable cost(with emission pricing) 
pricing) 
 

The data for the 3 technologies namely ‐ CHP Natural Gas, CHP Oil, Oil was based on assumptions and other 
sources.  Oil  plant  data  was  based  on  report  on  projected  cost  of  generation  2005  (OECD).  Rest  of  the  data 
was  based  on  Vattenfall’s  annual  report  and  Risto  T.  ,  “EU  POLICY  AND  CARBON  EMISSION  TRADING: 
IMPLICATIONS  FOR  THE  ENERGY  MARKET”,  Lappeenranta  University  of  Technology.  For  CHP  plants 
assumption was made that they share the similar cost structure as the natural gas combined cycle. Detailed 
assumptions are outlined in the model itself. 

If  the  markets  are  working  efficiently  is  reasonable  to  make  assumption  that  the  market  players  would  bid 
according  to  their  marginal  costs.  Though  it  may  sound  contradictory  as  marginal  costs  would  equal  to  the 
variable costs and thus it would not be possible to recover the investment  cost. However it must be kept in 
mind that the markets are volatile and the prices are set at the market clearing price(MCP) – or equal to the 
Chapter: Structure of Simulation Model 

marginal  cost  of  the  most  expensive  generator  that  was  dispatched,  and  the  generators  would  make  profit 
because their marginal costs were lower than MCP. Also in times of price peaks the generators make profits 
that substantially offset the investment cost. Hence in the model variable cost of electricity generation was 
used for obtaining the merit order. In case of scenario with carbon pricing the total variable cost with emission 
pricing was used. The fixed cost data is important for use in investment decisions. It might be used in further 
studies on congestion management or investment decisions under FMC system.  

5.2.3 INSTALLED GENERATION CAPACITY  
The  installed  generation  capacity  in  based  on  UCTE  system  adequacy  report:    2007  ‐  2020  Forecast  (UCTE 
2007). The data is given for the fossil and renewable sources. However the fossil fuels are not further divided 

  41 
 
42  Flow‐based Market Coupling 
 

into  CHP  and  non‐CHP  based  generation.  For  obtaining  this  classification  data  from  this  aggregated  data 
results from a previous study (Lise, Linderhof et al. 2006) were used. The data is based on statistics of 2001, 
hence  assumption  was  made  that  most  of  plants  installed  post  2001  are  based  on  CHP  and  hence  it  was 
assumed that the conventional plants capacity stayed at 2001 level. To get CHP capacity difference between 
current total capacity and 2001 capacity of conventional plants was taken. Other assumptions that were made 
have been elaborated in the model itself. 

TABLE 5 INSTALLED GENERATION CAPACITIES IN THE NORTH WEST EUROPEAN REGION 

Installed Generation 
      Variable Cost  Capacity    

   Symbol  VC            

      Avg  NL  BE  FR  DE 

    €/MWh  GW  GW  GW  GW 

Hydro  H   €         6.60   0.04  1.42  25.40  9.11 

Wind  W   €        10.00   1.65  0.19  1.40  21.17 

Nuclear  N   €        10.97   0.45  5.80  63.26  20.54 

Hard Coal Condensation  HC   €        25.36   4.49  0.95  12.00  27.19 

Lignite Condensation  LC   €        25.50   0.00  0.00  0.00  19.33 

CHP Natural Gas  CHP‐G   €        37.92   7.65  0.77  2.71  0.70 

Natural Gas Combined Cycle  G   €        50.55   7.17  3.50  1.89  13.82 

Oil  O   €        72.04   0.20  3.07  8.80  7.14 

CHP Biomass  CHP‐B   €      107.24   0.47  0.63  0.90  3.59 

5.2.4 CALCULATION OF SUPPLY  CURVE SLOPE 


The data of capacity and cost was used to generate the merit order curves for each country. The variable cost 
of electricity generation was used to sort the electricity sources in increasing order of their variable costs and 
get the merit order. It was assumed to use a straight line for the supply curve approximation – hence a linear 
2
regression  fit  was  made  to  the  plotted  data  points.  The  equation  of  the  curve  and  the  R   values  were 
2
calculated. Based on the R  (statistical significance parameter) values it was decide to exclude CHP biomass 
from  the  merit  order.  It  had  a  very  high  variable  cost  and  effected  the  equation  of  straight  line  fit 
substantially.  

TABLE 6 SUPPLY CURVES SLOPE FOR THE FOUR COUNTRIES. 

Inverse Supply Function y=mx+c

y Price €/MWh
x Quantity Supplied MWh

m c
NL 3.18 0
BE 4.217 0
FR 0.39 0
DE 0.452 0
 
 

The  intercept  value  for  each  curve  was  set  to  zero  to  have  consistent  equations,  without  this  assumption 
some of the demand curves had negative values for supply at zero price. This value was then entered into the 
output  matrix  for  the  supply  curves.  The  supply  curves  for  each  country  and  their  equation  are  displayed  in 
Appendix A.3 

5.2.5 DEMAND CURVE  
To complete the economic model demand curve was required. It is debatable whether the demand curve for 
electricity is inelastic and hence vertical or it is elastic. For the sake of model the demand curve was assumed 
to be elastic – which is more realistic especially while considering the wholesale customers. Two set of data 
were required to calculate the demand curve: 

1. Average  electricity  demand  per  country:  This  data  was  collected  from  UCTE  System  Adequacy 
Forecast  2007‐2020 (UCTE 2007). The  value for  demand  was assumed to  be  equal to  the reference 
load on the 3rd Wednesday of January, 2007 at 11:00. 

TABLE 7 AVERAGE DEMAND OF ELECTRICITY BASED ON THE UCTE SYSTEM ADEQUACY FORECAST 2007‐20 

   Average Demand 
  GW 
NL  16.30 
BE  12.60 
FR  79.40 
DE  74.00 
 
2. Reliable  Available  Capacity:  The  net  generation  capacity  for  each  country  has  already  been 
calculated  in  the  supply  curve  calculations.  However  for  the  demand  curve  calculation  reliable 
available capacity was needed. This data was collected from UCTE System Adequacy Forecast 2007‐
2020 (UCTE 2007). The value for demand was assumed to be equal to the reference reliable capacity 
available on the 3rd Wednesday of January, 2007 at 11:00. The capacity is given below in the Table 8. 
The methodology for calculating the reliable available capacity is as follows 

Reliably available capacity  =    National generating capacity 
‐ non‐usable capacity  
‐ maintenance and overhauls  (nuclear and fossil fuel power stations)  
‐ outages (nuclear and fossil fuel stations) ‐ system services reserve 
 

TABLE 8 RELIABLE GENERATION CAPACITY BASED ON THE UCTE SYSTEM ADEQUACY FORECAST 2007‐20 

   Reliably Available Capacity 
  GW 
NL  17.1 
Chapter: Structure of Simulation Model 

BE  13.5 
FR  91.6 
DE  83.9 
 

To calculate the slope of demand curve the following procedure was followed. 
*
1. Calculation  of  P :  The  demand  curve  and  supply  curve  at  equilibrium  would  intersect  to  give  the 
equilibrium  price  and  quantity.  Assuming  that  the  average  demand  (AD)  would  be  the  equilibrium 
*
demand  (Q )  and  hence  the  result  of  intersection  of  demand  and  supply.  The  AD  value  was 

  43 
 
44  Flow‐based Market Coupling 
 

*
substituted into the supply function calculated in 5.2.4.  This gives the equilibrium price (P ). This is 
one point on the demand curve. If another point on the demand curve can be calculated it would be 
*
possible to get the slope and intercept of the demand function. As a validation the value of P  were 
also compared to the actual energy spot prices in the four countries.  
2. The net installed capacity was assumed to be equal to the demand when price of electricity is equal 
to zero. This is perhaps not completely true – however the demand curve becomes vertical at a point, 
this  was  assumed  to  be  the  point  [refer  Figure  25  Principle  of  MCP  (from 
http://www.apxgroup.com)]. This gives the second point on the demand curve, which is assumed to 
be linear in the simulation model 
3. With two points known on a linear curve the slope and intercept was calculated . The equation of the 
line was given in the form : y = mx + c 

Demand  data  from  UCTE  System  Adequacy  Forecast  2007‐2020  Reference  load  on  the  3rd  Wednesday  of 
January, 2007 at 11:00     

 
FIGURE 22 THE EQUATION OF THE DEMAND FUNCTION FOR THE NORTH‐WEST EUROPEAN REGION 

5.3 TIE LINE CAPACITY 
The constraints for the market model are based on the capacity of the interconnector. The maximum amount 
of electricity that can be  exported  or imported  by a country depends on the  capacity of the interconnector, 
this  is  called  the  Flow‐gate  capacity  (Fmax).  A  part  of  the  maximum  allowed  flow  on  the  critical  branches  is 
already used (i.e. prior to the allocation) by so‐called already‐occupied flows that can consist of the following 
components: 

•  ‘natural  flows’  (cross‐border  physical  flows  that  will  always  occur,  even  when  there  is  no  scheduled 
commercial exchanges between areas); flows that result from sources/sinks that are located in a single control 
area 

• commercial exchanges resulting from firm nominations in previous auction rounds 

• flows caused by exchanges between sources and sinks that are not located in the region that is participating 
in the flow‐based allocation 

• flows caused by exchanges between areas where the source is located in the region that is participating in 
the flow‐based allocation whereas the sink is outside, and vice versa. 

These values would be summed up to calculate the base case Fref or the capacity that is already used up. It can 
be  assumed  to  be  similar  to  NTF  (notified  transmission  flow)  from  the  NTC  based  methods,  the  main 
difference being that it considers flow based calculation. 

The capacity that is allowed to for the implicit market coupling is then equal to the difference of Fmax and Fref. 
 

These values are not available for the countries right now. Hence couple of assumptions were made. First the 
Fmax was assumed to be equal to the current NTC value at the borders. Secondly it was assumed that all the 
flows are allocated on day ahead. Hence Fref was assumed to be zero.  

It should also be remarked here that NTC values are not the correct measure of how much physical capacity is 
available. It is also likely to go up with implementation of FMC, as reserve margin could be reduced because of 
better prediction of flows. However it is tough to define actual values that capacities – to get a picture of what 
the maximum thermal capacities that exist on the borders more data was collected on the actual transmission 
lines  that  currently  connect  the  national  markets.  The  data  on  actual  thermal  capacities  is  attached  in  the 
appendix for reference A.6. A transmission network consists of a number of transmission elements (e.g. lines 
and  transformers),  each  one  having  a  definite  maximum  transport  capacity  that  is  mainly  determined  by 
thermal  limits.  NTC  values  reflect  real  electricity  transport  possibilities  in  the  meshed  and  internationally 
interconnected transmission systems. Two factors limit transfer capacities at values normally much below the 
thermal capacities: 

‐ The network element within a transmission system that is the most sensitive to the load flow,  

‐    When  temporary  admissible  overloads  are  taken  into  account,  the  security  criteria  related  to  voltage  or 
frequency stability lead to constraints that may limit physical load flows at significantly lower values than the 
thermal capacities of lines.  

 
FIGURE 23 TIE LINE CAPACITY FOR THE NORTH WEST EUROPEAN ELECTRICITY NETWORK (BASED ON DATA FROM WEBSITE 
OF TENNET, RTE, RWE, ELIA AND TSO AUCTION WEBSITE) 

For the model it was assume that the Fmax values are equal to the current NTC values on the borders and were 
entered  into  the  interconnector  capacity  tab.  The  Figure  23  shows  the  values  that  were  used  in  the  model. 
Also  not  that  the  capacity  values  in  two  directions  are  different,  this  is  also  because  NTC  values  in  both 
Chapter: Structure of Simulation Model 

directions depend on the initial load flow conditions set by the base generation and load patterns due to the 
already  existing  transactions.  If  a  sensitive  network  element  regarding  NTC  limits  has  an  initial  load  in  one 
direction,  additional  cross‐border  transactions  that  increase  the  load  flow  over  this  element  in  the  same 
direction result in tighter NTC‐limits than cross‐border transactions in the opposite direction. 

  45 
 
46  Flow‐based Market Coupling 
 

5.4 ELECTRICITY DAY‐AHEAD MARKET MODULE 

€ 60.00
Prices (euros)
€ 50.00

€ 40.00

€ 30.00

€ 20.00

€ 10.00

€-
NL BE FR DE
P*

FIGURE 24 SCHEMATIC OF THE MARKET MODUEL 

In  the  market  module  implicit  flow‐based  day  ahead  wholesale  market  four  electricity  is  simulated.  The 
previous sections have already described the data that would be used as input to this module. Essentially this 
module  is  a  optimization  module.  Here  the  electricity  dispatch  is  calculated  which  respects  the  constraints 
while maximizing the market value,  or while minimizing the net  cost of  electricity generation for the whole 
region.  The  description  of  the  market  model  is  divided  into  two  parts,  first  the  description  of  model  which 
calculated prices without any imports and exports and then with flow‐based market coupling.   
 

5.4.1 EQUILIBRIUM WITHOUT MARKET COUPLING  

FIGURE 25 PRINCIPLE OF MCP (FROM HTTP://WWW.APXGROUP.COM) 

Bid blocks are arranged in bid‐price (€/MWh) order to form the merit order for the system. The energy market 
is then dispatched by traversing the energy stack, climbing up/down the stacked bid blocks until load demand 
is met. The market is not coupled hence both the supply and demand curves are local. It must be mentioned 
here that in real life the demand curves move up and down with time, but the dynamics of the system are not 
being studied by the current research. Here an average demand function was set up and assumed to be same 
over the period of time. 

The  supply  function  that  was  calculated  in  the  sections  above  and  the  demand  function,  also  calculated 

above, would intersect at equilibrium and the values would give equilibrium price or MCP, P and the market 
*
clearing quantity, Q . Next step would be to calculate the coupling and optimization. 

5.4.1.1 W ELFARE AND NET COST OF GENERATION CALCULATIONS  

 
Chapter: Structure of Simulation Model 

FIGURE 26 THE DEFINITION OF CONSUMER SURPLUS AND PRODUCER SURPLUS 

Consumer surplus is the difference between the price consumers are willing to pay (or reservation price) and 
the actual price. If someone is willing to pay more than the actual price, their benefit in a transaction is how 
much they saved when they didn't pay that price. It is calculated as the area of triangle ABC from Figure 26 
The definition of consumer surplus and producer surplus 

The producer surplus is the amount that producers benefit by selling at a market price that is higher than they 
would  be  willing  to  sell  for.  Note  that  producer  surplus  flows  through  to  the  owners  of  the  factors  of 

  47 
 
48  Flow‐based Market Coupling 
 

production,  unlike  economic  profit  which  is  zero  under  perfect  competition.  It  is  calculated  as  the  area  of 
triangle EBC from the Figure 26. 

Combined, the consumer surplus, the producer surplus, and the government surplus (if present) make up the 
social surplus or the total surplus or net surplus. The net welfare is calculated as the sum of areas of triangle 
ABC and EBC. 

Total  cost  of  generation  is  calculated  from  the  Figure  26  as  the  area  of  triangle  CBE.  This  is  done  for  each 
country.  

Each  of  the  above  four  values  are  calculated  independently  for  the  four  countries  in  north  west  European 
region. Finally to get the regional values these are summed up together. The formulations are attached in the 
appendix.  

AFTER MARKET COUPLING  
The  optimization  module  simulates  merit‐order‐based  economic  dispatch.  Bid  blocks  are  arranged  in  bid‐
price  (€/MWh)  order  to  form  the  merit  order  for  the  system.  The  energy  market  is  then  dispatched  by 
traversing the  energy stack, climbing up/down the stacked bid  blocks until load demand is met as shown in 
Figure 27. In this case the markets are coupled hence the value of demand and supply functions would have to 
optimize over the whole region under the given constraints.  

 
FIGURE 27 SIMPLE STYLIZED ELECTRICITY MARKET 

The central dispatch process should aim to maximize the value of spot market trading i.e. to maximize the value 
of dispatched load based on dispatch bids less the cost of dispatched generation based on dispatch offers, subject 
to: 

• dispatch offer and dispatch bid quantity constraints; 
• constraints due to availability and commitment; 
• non‐scheduled load requirements in each zone; 
• constraints due to power system reserve requirements determined; 
• intra‐zonal network constraints and intra‐zonal losses; 
• inter‐zonal network constraints and inter‐zonal losses; 
• constraints consistent with registered bid & offer data; 
• current levels of dispatched generation and load; and 
• procedures to take account of constraints imposed by ancillary services requirements. 

The  above  statements  establish  the  framework  within  which  more  detailed  rules  on  specific  topics  may  be 
defined. In the current module, given the non‐availability of data for detailed constraints, only the following 
constraints were modeled: 
 

• dispatch offer and dispatch bid quantity constraints; 
• intra‐zonal network constraint; 

5.4.1.2 E FFECT OF IMPORT AND EXPORT ON PRICES AND QUANTITY DEMANDED  

 
FIGURE 28 EFFECT OF IMPORT AND EXPORT ON PRICES AND QUANTITY IN THE COUNTRY 

It  is  important  to  calculate  the  effect  of  import  and  export  on  the  prices  and  quantities  demanded  and 
supplied in the country. The calculations were made as follows, the diagram of the effect is shown above in 
Figure 28 Effect of import and export on prices and quantity in the country 

Assume that the demand function is defined as follows 

       

The supply function is defined as follows 

       

However the prices would equalize, i.e.  

               

Also since 

∆       

∆    
Chapter: Structure of Simulation Model 

Replacing value of Qs from above in the equations 

    ∆      

      ∆  
 
 

And 

      ∆  
 
 

  49 
 
50  Flow‐based Market Coupling 
 

This was programmed into the MS Excel model. The input variable for the optimization was set be ∆Q. Since 
there are four countries there were also all four ∆Q’s.  

5.4.1.3 W ELFARE CALCULATIONS  

 
FIGURE 29 WELFARE CALCULATIONS AFTER INTER COUNTRY TRADE 

• Consumer Surplus = Area (∆AIK) 
• Producer Surplus = Area (∆KJD) 
• Net Welfare = Area (∆AIK) + Area (∆KJD) 
• Cost of Generation = Area (∆DJG) 

These  values  for  each  country  were  added  up  to  give  the  net  regional  values  for  the  North  West  European 
region. 

5.4.1.4 S ETTING UP THE OPTIMIZATION USING SOLVER  
Since the main aim of the simulation program is to study the average static behavior of the markets bring out 
sensitivities – it was considered sufficient to consider only the above two constraints. 

For setting up the optimization problem Solver feature of MS Excel was employed. The optimization variable 
was the net import/export into a country. If there are imports, or exports from a country it leads to change in 
both  supply  and  demand.  This  was  modeled  using  the  equations  that  calculate  the  change  in  demand  and 
supply in a country that import/exports some known amount of electricity from outside. This has already been 
discussed above in the section, the equations were entered into the excel sheet and the solver was set up as 
follows. It needed the reference to the (Figure 30 and Figure 31) 

• objective function – net cost of generation,  
• what the objective was – minimization of the objective function, and  
• constraints 
 

 
FIGURE 30 OPTIMIZATION USING MS EXCEL SOLVER 

   
FIGURE 31 OPTIMIZATION PARAMETERS 

5.4.1.5 C HOICE OF  O BJECTIVE  F UNCTION  


Congestion  management  methods  can  have  different  goals.  Before  the  operating  hour,  it  be  hours,  days, 
weeks or months, the goal may be to optimally allocate available capacity among market parties. In real time 
the goal may be to deal with congestions occurring during operation. In the current simulation the focus was 
solely on the day ahead markets – hence it was required to decide on an objective function that was suitable 
for this situation and was practical with the assumptions made and the data available. 

There  is  a  debate  on  what  should  be  used  as  an  objective  function  –  maximization  of  market  value, 
minimization of cost of generation, maximization of traded volume, etc. For the current study it was decided 
to  use  minimization  of  cost  of  generation  as  the  objective  function  mainly  because  that  is  the  ultimate 
objective of coupling markets.  
Chapter: Structure of Simulation Model 

Also  there  are  operational  and  mathematical  issues  with  using  maximization  of  market  value  with 
approximate linear demand and supply curves – this method works well for explicit auction and also implicit 
auctions but when actual merit order is given, but not an approximate supply curve. In case of approximate 
linear supply curves with optimization variable are the net imports into the four countries – the optimization 
problem  that  is  set  up  can  have  multiple  solutions.  The  solution  also  depends  on  the  initial  values  of  trade 
what are entered into the model. Basically it’s a 8 variable problem with only five governing equations, and 
can hence have any number of solutions. This issue can be possibly resolved by introducing more constraints 
and intelligent actors into the simulation. However as the aim of research was to understand the working of 
the market and distinguish it from the effects that might happen due to idiosyncrasy of the actors (bids and 
offers)  it  was  decided  to  use  another  objective  function.  The  In  case  of  approximate  linear  supply  curve 

  51 
 
52  Flow‐based Market Coupling 
 

minimization  of  total  cost  of  generation  leads  to  unique  solutions  and  also  to  higher  net  welfare  for  each 
country.  However  in  real  implementation  of  the  system  it  is  possible  to  use  net  welfare  or  market  value 
maximization – when actual bids and offers are available. It is possible to use quadratic programming to solve 
such problems.  

 
FIGURE 32 EFFECT OF AN INELASTIC DEMAND FOR DECIDING THE OBJECTIVE FUNCTION 

Other reason for using the minimization of the total cost is because of the nature of the demand curve. The 
demand  curve  that  was  calculated  from  the  model  was  inelastic.  (slope  was  almost  a  ‐65  for  Netherlands, 
meaning  that  demand  would  change  by  1GWh  for  a  change  of  €65  in  the  electricity  price).  Under  such 
situation the  demand supply  graph would look as shown in figure. If the demand  function is assumed to  be 
perfectly inelastic then the consumer surplus would tend towards infinity. More inelastic demand makes the 
Net Welfare completely dependent only on consumer surplus. Producer surplus becomes less significant if the 
slope  of  demand  function  is  high.  In  PJM,  with  LMP,  the  optimization  function  also  employs  an  perfectly 
inelastic  demand  function  and  minimization  of  cost  of  generation  as  objective  function.  If  net  welfare  is 
completely  dependent  on  consumer  surplus,  another  way  of  saying  maximization  of  net  welfare,  hence 
consumer surplus is to minimize the cost of generation of electricity. Also if the aim of integration of markets 
is to achieve a copper plate – then the final aim of markets would be to minimize the net cost of generation. 
The objective function can be formulated as follows: 

  :  

Where, dQsi is the electricity demand in a country fulfilled by local generators. 

P’i is the price of electricity after coupling in the national market.  

5.4.1.6 C ONSTRAINTS  
The constraints were three: 

• Net trade should equal to zero 
 

• All electricity that is generated is also consumed 
• Tie‐line capacities are respected 

Using  these  inputs  to  the  Microsoft  Excel  Solver  it  was  possible  to  obtain  a  solution  to  the  market 
optimization. The results of this would be discussed in the section 7.1Base Case. 

5.5 MODEL OUTPUTS 
The model gives the following outputs 

5.5.1 OUTPUTS FOR THE NON‐COUPLED MARKETS 
The following results were calculated for the national markets, assuming there was no coupling. 

TABLE 9 OUTPUT LIST FOR MODEL FROM NON‐COUPLED MARKETS 

Price and Quantitiy  Surplus  
GW  €/MWh  €/hr  €/hr  €/hr  €/hr 
Consumer  Producer  Cost of 
Q*  P*  Surplus  Surplus  Net Welfare  generation 
NL 
BE 
FR 
DE 
Total Cost of 
Net Welfare  Generation 
 

5.5.2 OUTPUTS FOR THE COUPLED MARKETS 
Following parameter were calculated from the model after FMC. 

TABLE 10 OUTPUTS FROM THE MODEL AFTER FMC 

Price and Quantity  Surplus 
GW  GW  €/MWh  GWh  €/hr  €/hr  €/hr  €/hr  
Net  Consumer  Producer  Net Welfare  Cost of 
Qd  Qs  P'  Exchange  Welfare(FMC)  Welfare(FMC)  (FMC)  generation 
NL 
BE 
FR 
Chapter: Structure of Simulation Model 

DE 

   

  53 
 
54  Flow‐based Market Coupling 
 

5.5.3 OVERALL RESULTS  
The  comparison  was  made  between  the  results  of  market  after  FMC  and  the  independent  market  case.  In 
scenarios comparison was also made between the results from the scenario and the results of FMC if applied 
in present case. Two main values of interest were the following, which were calculated from the model. 

1. ∆   C OST OF  G ENERATION :   R EGIONAL CHANGE  

2. ∆   N ET  W ELFARE :   R EGIONAL  C HANGE  


5.5.4 COMPARATIVE RESULTS 
The following result were calculated to be able to make decisions on the effectiveness of FMC under different 
scenarios. 

TABLE 11 COMPARATIVE RESULTS FROM THE MODEL BETWEEN FMC CASE AND THE BASE CASE 

€/MWh 
% ∆  % ∆  % Installed 
Consumer  Producer  % ∆ Net  % Demand  Capacity 
∆ Price  % ∆ Price  Surplus  Surplus  Welfare  Imported  Used 
NL 
BE 
FR 
DE 
 

CAPACITY  UTILIZATION  RESULTS 


It  was  important  to  also  see  what  the  results  were  from  the  utilization  perspective  of  the  tie‐lines.  It  would 
help in deciding which tie‐lines need further investments to relieve congestion. 

TABLE 12 CAPACITY UTILIZATION RESULTS FROM THE SIMULATION MODEL 

Reverse  Forward 
Reverse  Forward  Capacity  Capacity 
Reverse  Forward  Reverse  Forward  Unused  Unused  Utilizatio Utilizatio
Capacity  Capacity  Flow  Flow  Capacity   Capacity   n  n 
GW  GW  GW  GW  GW  GW       
BE‐FR 
BE‐NL 
DE‐FR 
DE‐NL 
 

5.6 GRAPHS 
The following graphs were also plotted to give easier insights and comparisons into the market operation and 
comparison. 

• Price of Electricity   
o Electricity Prices 
o Change in Prices 
• Electricity Demand   
o Consumption per Country 
o Imports and Exports 
 

• Welfare Data   
o Consumer Surplus 
o Producer Surplus 
o Net Welfare 
o Distribution of Welfare 
• Interconnector Capacity Utilization   
o Actual Flows 
o % Utilization of capacity 

   

Chapter: Structure of Simulation Model 

  55 
 
56  Flow‐based Market Coupling 
 

6 VALIDATION AND VERIFICATION OF MODEL 
 

As it is a simulation model and all simulation models have the property of “garbage in – garbage out”. Hence 
there was a need to carefully and considerately ensure quality of the input data. It was tough to ensure this as 
most  of  data  was  not  available  directly  from  the  owners,  but  was  picked  up  from  other  studies,  and  was 
sometimes  dated.  It  was  tried  to  the  utmost  degree  to  have  data  which  reflects  reality,  so  that  conclusions 
can be made on basis of this data. 

In this chapter you would find detailed verification of model and validation of the intermediate results. It is not 
possible to validate the final results as the market in this form does not exist yet. 

6.1 VALIDATION OF TRANSMISSION MODEL 
The  model  has  already  been  verified  in  detail  by  the  authors  (Qiong  and  Bialek  2005).  After  studying  the 
report it was considered sufficient to take the model as being correct.  

6.2 QUALITY OF DATA USED FOR SUPPLY CURVE 
This was one of the most important data for the economic calculations‐ as all the rest of calculations would 
hinge on it. Any issue with data would reflect in the results of from the model. Hence below the supply curve 
calculated from the simulation model and actual merit order curves for the four countries are given below. 

Merit  order  curve  based  on  the  cost  data  from  Merit  order  based  on  the  actual  data  from  the 
current model  past  (DG  Competition  report  on  energy  sector 
inquiry (SEC(2006)1724, 10 January 2007) 

NL Supply Curve

€ 80.00 
€ 70.00  y = 3.183x
R² = 0.831
Price (euros/MWh)

€ 60.00 
€ 50.00 
€ 40.00 
€ 30.00 
€ 20.00 
€ 10.00 
€‐
0.00 5.00 10.00 15.00 20.00 25.00

Generation Capacity (GW) NL Supply Curve
Linear (NL Supply Curve)
   
BE Supply Curve
€ 80.00  y = 4.217x
R² = 0.829
€ 70.00 
Price (euros/MWh)

€ 60.00 
€ 50.00 
€ 40.00 
€ 30.00 
€ 20.00 
€ 10.00 
€‐
0.00 5.00 10.00 15.00 20.00
BE Supply Curve
Generation Capacity (GW) Linear (BE Supply Curve)
   
 

FR Supply Curve
€ 80.00 
y = 0.392x
€ 70.00  R² = 0.603
Price (euros/MWh)

€ 60.00 
€ 50.00 
€ 40.00 
€ 30.00 
€ 20.00 
€ 10.00 
€‐
0.00 50.00 100.00 150.00
FR Supply Curve
Generation Capacity (GW)
Linear (FR Supply Curve)    
DE Supply Curve
y = 0.452x
€ 80.00  R² = 0.788
€ 70.00 
Price (euros/MWh)

€ 60.00 
€ 50.00 
€ 40.00 
€ 30.00 
€ 20.00 
€ 10.00 
€‐

0.00 50.00 100.00 150.00

DE Supply Curve
Generation Capacity (GW)
Linear (DE Supply Curve)
   
FIGURE  33  MERIT  ORDER  CURVES  FOR  THE  NORTH‐WEST  EUROPEAN  REGION,  MODEL  DATA  AND  COMPARISION  WITH 
ACTUAL DATA FROM THE PAST 

As  can  be  clearly  seen  both  the  graphs  are  very  similar  –  considering  both  the  prices  and  the  installed 
generations. Hence it would be acceptable to use the data that has been collected from the sources and still 
be able to get realistic results.  

6.3 QUALITY OF DATA USED FOR AVERAGE DEMAND 
Second  most  important  data  was  the  data  for  average  demand  in  a  country.  There  were  many  sources  to 
gather this data from – Eurostat website, past studies and UCTE system adequacy report. For the model the 
values  were  picked  up  from  the  UCTE  system  adequacy  report  2007‐20.  This  was  the  most  recent  data. 
However the values were not averages but were snapshots in time. To see how well these values reflect reality 
they  were  compared  to  the  Load  Duration  Curves  Calculated  for  the  last  three  years  for  the  north‐west 
European  region  by  London  Economics  report  for  the  DG  Trent.  (DG  Competition  report  on  energy  sector 
inquiry (SEC(2006)1724, 10 January 2007) 

   
Chapter: Validation and Verification of model 

  57 
 
58  Flow‐based Market Coupling 
 

TABLE 13 COMPARISION OF AVERAGE DEMAND OF ELECTRICITY USED IN THE MODEL AND HISTORICAL DATA 

   Average  Method of calculation of average demand based on 
Average Demand used in  Demand based  load duration curve = average of values at 3000 and 
model (from UCTE one  on the load  6000 hours 
day value)  duration curve 
NL  16.30  9 

 
FIGURE 34 LOAD DURATION CURVE FOR NETHERLANDS 

BE  12.60  9 

 
FIGURE 35 LOAD DURATION CURVE BELGIUM 

FR  79.40  60 

 
FIGURE 36 LOAD DURATION CURVE FOR FRANCE 
 

DE  74.00  50 

 
FIGURE 37 LOAD DURATION CURVE FOR GERMANY 

As is clear from the values, the values used in the model are higher than what is reflected from the past load 
duration curves. This could be attributed to two factors – 
• The values in the study are older, only till 2005. If we consider the annual increase there would be 
some convergence of the values. 
• The value snapshot considered by UCTE, i.e. Referecne value on the 3rd Wednesday of January, 2007 
at 11:00, might not reflect the reality as well. 

However the values still are reflective of the trend, and have been achieved at the same instance of time in the 
past. Hence it is much better reflective of reality than the average values reflected in the data from duration 
curves.  

6.4 PRICE OF ELECTRICITY WITHOUT IMPORTS AND EXPORTS 
To  test  the  correctness  of  the  supply  curve  and  the  demand  data  it  was  decided  to  compare  the  results  of 
price  calculated  from  the  simulation  model  without  inter‐country  trades  and  the  past  prices  from  the  day 
ahead  markets  in  APX,  BelPEX,  PowerNext  and  EEX.  This  data  was  tough  to  gather  too.  However  it  was 
collected for 24 hours and for the past two years from the respective power exchanges. The data analysis of 
the data yielded the statistics given in the  Figure 38 Comparision of wholesale price of electricity based on the 
model and actual past data from the power exchanges for year 2005‐07 The software SAS and MS Excel were 
utilized for the analysis. The results can be found in the appendix A.4.  

 
Chapter: Validation and Verification of model 

FIGURE 38 COMPARISION OF WHOLESALE PRICE OF ELECTRICITY BASED ON THE MODEL AND ACTUAL PAST DATA FROM THE 
POWER EXCHANGES FOR YEAR 2005‐07 

As can be seen for NL and BE the prices calculated from the model are much higher than the actual day ahead 
prices.  However  for  Germany  and  France  it  is  much  closer  to  the  reality.  Other  observation  is  the  fact  that 
mean of prices in Germany is actually higher than the mean in Netherlands and Belgium, which might not be 
true. This could be attributed to the fact that a lot of values from the data set for EEX were missing for some 
reason. The prices in NL and BE are expected to  be higher as all the generation is assumed to  be local, and 
that would mean it would be expensive. In real life prices in NL and BE are lower because of cheaper imports 
from Germany and France.  

  59 
 
60  Flow‐based Market Coupling 
 

To  get  better  perspective  on  the  prices  it  was  decided  to  compare  the  prices  to  the  futures  prices,  which 
showed better correlation. 

6.5 VALIDATION OF PTDF VALUES FROM POWER WORLD 
The  basic  tool  for  congestion  management  in  FMC  is  Power  Transfer  Distribution  Factor  (PTDF)  which 
assesses sensitivity of a given line flow to the changes in nodal generations and demands. PTDF factors are 
used  to  measure  the  impacts  of  a  commercial  transaction  on  the  physical  power  flows  in  the  critical 
transmission  lines/  or  interfaces.  Based  on  the  values  of  PTDFs,  transactions  are  curtailed  and  increased  in 
order to relieve lines overloads. Due to the phenomenon of loop flows in a meshed network, PTDF calculation 
requires the full network information. This next section is based on the paper by (Zhou and Bialek 2005) 

TABLE 14 PTDF VALUE COMPARISON FROM POWER WORLD MODEL TO ACTAUL PUBLISHED VALUES 

 
 

“In order to test the applicability of the UCTE network model under various dispatch conditions, the 
published  PTDF  values  were  compared  with  the  calculated  ones.  Although  not  all  PTDF  values  are 
publicly  available,  some  of  the  PTDFs  in  the  UCTE  network  were  obtained  from  European 
5
Commission  reports   (Haubrich  and  Fritz  1999).  As  our  study  was  focused  on  the  cross‐border 
congestions, we were interested only in the values of PTDFs on cross‐country interfaces rather than 
individual  PTDFs  for  all  internal  lines  within  each  country.  Tables  II–IV  give  the  PTDF  factors  (in 
6
percent)  on  the  crossborder  interfaces  for  the  transactions  from  Belgium  to  Italy ,  North  France  to 
7
the  Netherlands  and  France  to  Italy ,  respectively.  The  correlation  factors  are  97%,  91%  and  95%, 
proving very good agreement between the expected and actually calculated values.” 

6.6 CONCLUSIONS 
The  conclusions  from  the  validation  and  verification  yielded  confidence  into  the  data.  The  data  from  the 
studies were lower for the marginal costs and average prices seen on the spot markets. Main reason for this is 
that  the  plants  right  now  in  operation  have  been  in  operation  for  long  and  have  already  paid  for  their 
investments.  It  is  profitable  to  just  bid  on  the  marginal  costs  in  the  market.  However  the  data  which  was 

                                                                         
5
http://europa.eu.int/comm/energy/en/elec_single_market/index_en.html
6
Net Transfer Capacities (NTC) and Available Transfer Capacities (ATC) in the Internal Market of Electricity
in Europe (IEM) –Information for User, ETSO, 2000.
7
http://europa.eu.int/comm/energy/en/elec_single_market/index_en.html
 

collected  was  mostly  for  newly  installed  or  planned  plants  in  the  cost  sheet.  Hence  the  supply  curve  was 
shifted towards higher costs in the model. This was the main difference. Also the demands have risen in the 
present case – higher than the once in the published reports from 2004 and 2005. Considering these facts it is 
possible to justify the values that were considered in the model. Also counting the fact that the model is built 
to give approximate values and is mainly built for the purpose of understanding the behavior of FMC – it was 
justified to use the data. 

   

Chapter: Validation and Verification of model 

  61 
 
62  Flow‐based Market Coupling 
 

   
 

   

Section 3: Results 

Here  the  results  from  the  model  are 


presented and conclusion are drawn 

Chapter: Validation and Verification of model 

  63 
 
64  Flow‐based Market Coupling 
 

   
 

7 RESULTS 
 

This chapter is divided into two main sections. First section would detail the results from the base case. The 
second part would detail the results from the scenarios. 

7.1 BASE CASE 
The base case was run with the values which have already been discusses in Chapter 5(Structure of Simulation 
Model).  

The model is run first without coupling, i.e. all the markets calculate MCP without any imports or exports. The 
results of the calculations are given below in the table. 

 
FIGURE 39  MCP, EQUILIBRIUM DEMAND AND SURPLUS CALCULATION WITHOUT MARKET COUPLING 

The  prices  in  Belgium  are  the  highest,  followed  by  Netherlands.  France  with  its  huge  installation  of  nuclear 
energy  has  the  cheapest  energy  prices.  Germany  is  also  substantially  lower  priced  compared  to  NL  and  BE 
because of coal installations.  

The second step was to run the solver in excel to minimize the net cost of generation by varying the imports 
and exports into each country. 

7.1.1 PRICE OF ELECTRICITY    

 
Prices (euros/MWh)
7.1.1.1 E LECTRICITY  P RICES  P RICES  
€ 60.00 
From the end consumer viewpoint the 
€ 50.00  most important indicator is the price of 
electricity. It must be considered that this 
€ 40.00  graph only gives the price of wholesale 
electricity; however it contributes 
€ 30.00 
substantially to the final electricity price. 
As can be seen after flow based market 
€ 20.00 
coupling Dutch and Belgian customers 
€ 10.00  would earn the benefit.  

€‐
NL BE FR DE
P* P'
 
Chapter: Results 

  65 
 
66  Flow‐based Market Coupling 
 

 
Prices Change (euros/MWh)
7.1.1.2 C HANGE IN  P RICES  
€ 2.00 
As already said Dutch and Belgium see 
substantial decrease in electricity prices. 
€‐ The biggest gainer is Netherlands with 
NL BE FR DE almost € 8, Belgium also has reduced 
€ (2.00)
prices but not as much reduction as seen in 
€ (4.00) Netherlands ‐ € 6. It must also be stated 
here that the benefit driven by countries 
€ (6.00)
shows a very strong dependence on the 
€ (8.00)
slope of calculated supply curve. Hence it is 
very important to get the supply curves as 
€ (10.00) accurate as possible. This was the reason 
∆ Price behind creating a costing model for all the 
technologies and obtaining real world data 
 
to populate the matrices.  

7.1.2 ELECTRICITY DEMAND   

 
7.1.2.1 C ONSUMPTION  P ER  C OUNTRY  
Electricity Demand
The consumption does not change so 
(GW)
90.00
much in the countries. However as 
expected, the countries in which prices 
80.00
went up – namely Germany and France, 
70.00
the consumption decreased. This is true 
60.00 because of the assumption of elastic 
50.00 demand curve. Netherlands and Belgium 
40.00 saw more consumption because of falling 
30.00 prices. 
20.00

10.00

0.00
NL BE FR DE
Q* Qd
 
 
Import‐Export (‐ve means import)
7.1.2.2 I MPORTS AND  E XPORTS  
The high price countries import from the 
5.00% low electricity priced countries. 
Netherlands imports almost 17%(this 
0.00% number is comparable to what 
NL BE FR DE Netherlands imports currently at about 
20%) of its net consumption. Belgium is 
‐5.00%
able to import only 12%. However current 
values are based mostly on explicit 
‐10.00% contacts, trading on Power exchanges is 
still limited. However if all electricity is 
‐15.00% traded over the power exchange and 
calculations are done according to implicit 
‐20.00%
flow based coupling method with objective 
% Demand Imported
function being the total cost of generation 
then the scenario might change to what is 
  shown in the figure. 
 

7.1.3 WELFARE D ATA    

 
Consumer Surplus (Meuros/hour)
7.1.3.1 C ONSUMER  S URPLUS  
$10.00
The consumer surplus has a marginal 
Millions

$9.00
increase in importing countries mainly 
$8.00
because of reduced prices and also 
$7.00
increased demand. Change in consumer 
$6.00
surplus in exporting countries is relatively 
$5.00
small because of their large size and large 
$4.00
spare installations for generation. 
$3.00
$2.00
$1.00
$0.00
NL BE FR DE
Consumer Surplus Consumer Welfare(FMC)
 

 
Producer Surplus (Meuros/hour)
7.1.3.2 P RODUCER  S URPLUS  
€ 1.40 
Producer surplus did see a substantial 
Millions

€ 1.20  reduction in the quantity. This was visible 
in both the importing countries and 
€ 1.00 
exporting countries. Importing countries 
€ 0.80  would hurt the local generating 
companies. At the same time the 
€ 0.60 
exporting countries would benefit their 
€ 0.40  local generators as they would now be able 
€ 0.20 
to sell outside of their territory and earn 
benefit. 
€‐
NL BE FR DE
Producer Surplus Producer Welfare(FMC)
 

 
Net Welfare (Meuros/hour)
€ 12.00  7.1.3.3 N ET  W ELFARE  
Millions

Net Welfare for all countries remained 
€ 10.00  almost the same. The benefit earned by 
the consumers was countered by the loss 
€ 8.00 
to the generators in the importing 
€ 6.00  countries and was reversed in case of 
exporting countries. In general overall for 
€ 4.00 
the local economy the benefit is almost 
€ 2.00  negligible. 

€‐
NL BE FR DE
Net Welfare Net Welfare (FMC)
 
Chapter: Results 

  67 
 
68  Flow‐based Market Coupling 
 

 
Distribution of Welfare
7.1.3.4 D ISTRIBUTION OF  W ELFARE  
10.00%
Looking at percentage is interesting when 
5.00%
considering welfare. This would decide the 
0.00%
amount of opposition that the proposal 
‐5.00% NL BE FR DE
would face from various actors. As can be 
‐10.00% clearly seen that the Producers in 
‐15.00% Netherlands would oppose this move, and 
‐20.00% so would the producers in Belgium. 
‐25.00% However the remaining actors would be 
‐30.00% more or less neutral to the change. 
‐35.00%

% ∆ Consumer Surplus
% ∆ Producer Surplus
% ∆ Net Welfare
 

7.1.4 INTERCONNECTOR CAPACITY UTILIZATION   

 
% Utilization
7.1.4.1 %   U TILIZATION OF CAPACITY  
As already said, the utilization on the BE‐
FR and DE‐NL border is the highest. These 
150.00%
would be the tie‐lines that would need to 
100.00% be reinforced in order to attain the copper 
50.00% plate or a successful competitive and liquid 
0.00%
market in the north‐west European region. 
However it must be noticed that this 
‐50.00% BE‐FR BE‐NL DE‐FR DE‐NL
utilization % is of the physical available 
‐100.00% capacity and not the NTC values.  
‐150.00%

Net Utilization

 
Utilization of Interconnector Capacity
7.1.4.2 A CTUAL  F LOWS  
Considering the tie‐line capacity utilization 
factor is important. As can be seen BE‐FR 
6.00   
5.00    and DE‐NL are completely used. This is 
4.00    what would be expected as well. Only 
3.00    when two of the four interconnectors have 
2.00   
been fully utilized there could be no 
1.00   
‐ additional flow from any direction possible 
‐1.00    BE‐FR BE‐NL DE‐FR DE‐NL and hence it would lead to a closed 
‐2.00    constraint. 
‐3.00   

Forward Unused Capacity 
Forward Flow
Reverse Unused Capacity 
Reverse Flow  

   
 

7.1.5 CONCLUSIONS FROM BASE CASE 
On the whole FMC is effective in bringing down the net cost of generation for the whole north‐west European 
region.  In  terms  of  net  welfare  every  country  gained  except  France,  where  there  was  no  change  observed. 
From  the  perspective  of  energy  prices,  they  went  down  significantly  for  Netherlands  and  Belgium,  though 
there was a very insignificant increase in the prices in Germany and France. The interconnectors on BE‐FR and 
DE‐NL  borders  were  completely  utilized  to  their  limits.  Overall  it  seems  to  be  an  efficient  system  for 
optimization of market value and better usage of the interconnector capacity. Hence it can be concluded that 
FMC would lead to regional gains if implemented in the North West European region. The detailed numbers 
from the analysis are attached in the appendix A.9 and A.10  

Next  step  was  to  compare  FMC  with  NTC  based  Market  coupling  method  which  is  already  implemented 
between  NL,  BE  and  FR.  However  there  was  issue  of  defining  the  contract  path  with  addition  of  Germany. 
Germany offers a parallel or loop flow, which can not be defined using a contract path, as the flows resulting 
from execution of a contract between France and Netherlands would pass through Germany and the German 
TSO  should  be  paid  for  its  marginal  value.  This  makes  definition  of  contract  path  complex.  As  there  are  no 
documents of how the system would define contract path – if not basing them on PTDFs – it was decided to 
base them on assumptions. For testing if FMC is better than Market Coupling, three different contract paths 
were  defined  –  clockwise,  anti‐clockwise  and  50%  division.  The  results  of  the  analysis  would  be  discussed 
below. 

7.2 CURRENT SITUATION VS FMC 
As  already  discussed  in  chapter  2.2  Trilateral  Market  Coupling,  the  current  situation  in  the  North  West 
European region already has coupled markets. In order to be able to comment on the additional benefits that 
FMC entails ‐ it was necessary to make comparison with the current system. Hence a modification was made 
to the model with following parameter values. 

Chapter: Results 

 
FIGURE 40 TRADED VOLUMES FOR FMC AND TRILATERAL MARKET COUPLING COMPARISION 

  69 
 
70  Flow‐based Market Coupling 
 

The explicit trades as mentioned in the picture above lead to already some change in the demand and prices 
in the countries as compared to the base case of no coupling at all. A new optimization problem was now set 
for the trilateral market coupling countries – NL, BE and FR. The optimization objective function was set to be 
minimization  of  generation  cost  and  not  net  welfare  (present  system  employs  Net  welfare,  for  justification 
see  chapter  of  methodology).  The  results  from  the  optimization  were  plotted  against  the  results  from  the 
base case without any coupling and FMC to clearly delineate the effects.  

Prices (euros/MWh) Prices Change Electricity Demand


€ 60.00 Compared to no coupling (GW)
(euros/MWh) 90.00
€ 50.00 € 2.00
80.00

€- 70.00
€ 40.00
NL BE FR DE 60.00
€ (2.00)
€ 30.00 50.00

€ (4.00) 40.00
€ 20.00
30.00
€ (6.00)
20.00
€ 10.00
€ (8.00) 10.00
€- 0.00
€ (10.00)
NL BE FR DE NL BE FR DE
∆ Price(MC) ∆ Price(FMC)
P*(No Coupling) P'(MC) P'(FMC) Q*(No Coupling) Qd(MC) Qd(FMC)
   

Import-Export (-ve means Consumer Surplus Producer Surplus


import) (euros/hour) (euros/hour)
$10.00 € 1.40
5.00% $9.00
€ 1.20
$8.00
0.00% € 1.00
$7.00
NL BE FR DE $6.00 € 0.80
-5.00% $5.00
€ 0.60
$4.00
-10.00% € 0.40
$3.00
$2.00 € 0.20
-15.00% $1.00
€-
$0.00 NL BE FR DE
-20.00% NL BE FR DE Producer Surplus(No Coupling)
% Demand Imported(MC)
Consumer Surplus(No Coupling) Producer Surplus(MC)
% Demand Imported(FMC)
Consumer Surplus(MC) Producer Surplus(FMC)
   

 
 

Distribution of Welfare Utilization of % Utilization


Interconnector Capacity
0.14%

0.12%
6.00 150.00%
0.10% 5.00
100.00%
4.00
0.08%
3.00 50.00%
2.00
0.06% 0.00%
1.00
BE-FR BE-NL DE-FR DE-NL
0.04% - -50.00%
(1.00) BE-FR BE-NL DE-FR DE-NL
0.02% -100.00%
(2.00)
(3.00) -150.00%
0.00%
NL BE FR DE
Forward Unused Capacity (MC)
% ∆ Net Welfare(MC)
Forward Flow(MC) Net Utilization (MC)
% ∆ Net Welfare(FMC) Reverse Unused Capacity (MC)
Net Utilization(FMC)
Reverse Flow(MC)
     
FIGURE 41 RESULTS FROM SIMULATION MODEL FOR CURRENT STATE OF TRADE IN NORTH WEST EUROPEAN REGION 

Conclusions 

As  can  be  clearly  seen  above  FMC  is  more  beneficial  as  compared  to  present  implementation  of  trilateral 
market  coupling  between  NL,  BE,  FR  and  explicit  auctions  between  NL,  DE  and  DE,  FR.  Clearly  there  are 
benefits for Netherlands – there is almost € 2 per MWh further drop in prices with FMC. For Belgium there is 
almost  no  difference.  Germany  sees  higher  prices  with  FMC  as  it  is  able  to  sell  more  in  the  market  and 
substitute  the  trades  which  were  otherwise  going  from  France.  There  is  also  a  net  gain  the  welfare  of  the 
region. The percentages are small however it should be considered that the initial values of consumer surplus 
were  high  due  to  the  inelastic  nature  of  the  demand  function.  It  can  be  concluded  on  basis  of  the  above 
mentioned results the FMC would indeed lead to gains both in national and regional levels. Though it should 
also  be  kept  in  mind  that  there  was  a  very  insignificant  drop  in  welfare  within  France,  mainly  because 
Germany replaced some of its export benefits with introduction of FMC. 

7.3 COMPARISON OF FMC WITH MARKET COUPLING 
The  next  step  was  to  compare  the  claim  of  FMC  with  Market  coupling  The  following  situations  were 
simulated. 

 
Chapter: Results 

  71 
 
72  Flow‐based Market Coupling 
 

 
FIGURE 42 FLOW DIRECTION FOR COMPARISION OF FMC WITH NTC BASED MARKET COUPLING 

The results are attached in the appendix A.11  

The results can be discussed from perspective of any of the involved countries, and actors. As already stated 
the problem owner being the Ministry of Economic Affairs this report would aim to analyze the results from 
their perspective.  

   
 

1. Consumer Perspective:  Wholesale MCP after inter‐country trading 

FMC  MC Clockwise 

The end consumers, in this case the 
Prices Change (euros/MWh) Prices Change (euros)
domestic  users,  care  only  about  the  € 1.50 
price  to  electricity  that  is  charge  to  € 2.00  € 1.00 
them.  From  the  results  of  the  € 0.50 
€‐
analysis the Dutch customers would  €‐
NL BE FR DE
pay  least  in  case  of  NTC  based  € (2.00) € (0.50) NL BE FR DE

market  coupling  with  equally  € (1.00)


€ (4.00)
distributed  assumption  on  the  € (1.50)

contract  paths(€8.18  /MWh),  € (6.00) € (2.00)

followed  closely  by  the  results  from  € (8.00)


€ (2.50)

Flow‐based  market  coupling  based  € (3.00)

on  actual  PTDF  values  (€8.21  € (10.00) € (3.50)

/MWh).  However  the  difference  is  ∆ Price ∆ Price

not  significant  only  at  the  second     


decimal value (€0.03) which could be 
neglected.  Basically  both  FMC  and  MC Anti‐Clockwise  MC Distributed 
distributed  contract  Market 
coupling gave same results on Dutch  Prices Change (euros) Prices Change (euros)
€ 3.00  € 2.00 
market prices.  However  considering 
prices in Belgium do not get benefit  € 2.00 
€‐
in case of distributed contract based  € 1.00  NL BE FR DE
market coupling (a drop of less than   €‐
€ (2.00)

€2)  –  which  dropped  substantially  NL BE FR DE


€ (1.00) € (4.00)
with FMC (almost a drop of € 6). The 
€ (2.00)
results  from  anti‐clockwise  and  € (6.00)
clockwise Market coupling are much  € (3.00)

different  from  the  other  two  cases.  € (8.00)


€ (4.00)
As  can  be  seen  that  prices  fall  by 
€ (5.00) € (10.00)
about € 4 in Netherlands 
∆ Price ∆ Price

   

2. Effects on Welfare Distribution:  

Welfare  distributions can  be  predicted  on basis of above  graphs, the importing  countries saw the consumer 


surplus  going  up  while  at  the  same  time  exporting  countries  saw  consumer  surplus  going  down  because  of 
slightly higher prices. Also to be noted is the fact in general it is observed that the Net Welfare change for all 
countries is always positive but is only a small percentage. More information and graphs can be looked up in 
the appendix A.11.3 
Chapter: Results 

  73 
 
74  Flow‐based Market Coupling 
 

3. Dependence on imports:  Imports and exports for each of the partners involved in market 
coupling after equilibrium 

FMC  MC Clockwise 

To an extent the amount of imports 
Import‐Export (‐ve means  Import‐Export (‐ve means 
decide the level of dependence that  import) import)
the  country  has  on  its  trade  5.00% 6.00%
partners.  From  the  perspective  of 
4.00%
the supra‐national aspirations this is  0.00%
2.00%
good.  However  thinking  of  the  NL BE FR DE

energy  independence  and  self  ‐5.00%


0.00%
sufficiency  –  too  much  imports  ‐2.00%
NL BE FR DE
‐10.00%
create  a  sense  of  insecurity  in  the 
‐4.00%
local  market.  In  the  long  term  they 
‐15.00%
may  create  incentives  for  the  ‐6.00%

generators  to  move  the  generation  ‐20.00% ‐8.00%


plants  in  the  countries  with  lower  % Demand … % Demand …

cost  of  generation,  thus  causing     


further erosion of spare capacity and 
could  lead  to  higher  volatility  in  the  MC Anti‐Clockwise  MC Distributed 
markets.  In  case  of  FMC  Holland 
ends up importing almost 15% of its  Import‐Export (‐ve means  Import‐Export (‐ve means 
total  demand  from  outside.  This  is  import) import)
8.00% 10.00%
actual  in‐line  with  the  present 
6.00%
imports – which stand at around 15‐ 5.00%
4.00%
20%.  Other  interesting  thing  to 
2.00% 0.00%
notice  is  the  fact  that  France 
0.00% NL BE FR DE
become the sole exporter in  case of  ‐5.00%
‐2.00% NL BE FR DE
MC.  This  should  not  be  very 
‐4.00% ‐10.00%
surprising  given  the  fact  that  ‐6.00%
electricity  is  the  cheapest  in  this  ‐15.00%
‐8.00%
country  and  the  objective  function  ‐10.00% ‐20.00%
for  the  current  simulation  is  % Demand … % Demand …
minimization  of  the  oveall  cost  of     
generation. 

 
4. Effect on local demand 

It  was  also  noted  that  demand  changes  only  slightly  for  each  case  this  could  be  attributed  to  the  fact  that 
demand function is almost inelastic. The slope of demand function in NL and BE is of the order of 1000, hence 
there is not much change in  the demand  with  increasing  or decreasing  prices. This is in line with the reality 
too. For details refer to appendix  

   
 

 
5. Tie‐Line capacity  % utilization of the interconnector utilization 
utilization 
FMC  MC Clockwise 

To  make  decisions  about 


% Utilization % Utilization
investment  into  grid  expansion  it  is 
150.00% 80.00%
very  important  for  the  government 
60.00%
to  look  at  the  actual  picture  of  100.00% 40.00%
congestion.  The  results  from  the  20.00%
50.00%
analysis  of  capacity  usage  under  0.00%
different  market  methods  were  0.00% ‐20.00% BE‐FR BE‐NL DE‐FR DE‐NL
largely  different.  This  probably  also  BE‐FR BE‐NL DE‐FR DE‐NL ‐40.00%
‐50.00% ‐60.00%
shows  that  there  would  exist 
‐80.00%
gaming  opportunities  for  the  actors  ‐100.00%
‐100.00%
with  large  market  power  both 
‐150.00% ‐120.00%
generators  and  large  consumers.  In 
Net  Net 
case  of  FMC  the  most  congested  Utilization Utilization
borders  are  BE‐FR  and  DE‐NL.  Is     
should  be  noted  that  France  sort  of 
determines  which  tie‐lines  would  MC Anti‐Clockwise  MC Distributed 
get  congested  because  of  low 
prices.  In  case  of  MC  clockwise  the  % Utilization % Utilization
BE‐FR  tie  line  gets  congested  150.00%

because France is exporting  to both 
100.00% 150.00%
Belgium  and  Netherlands.  It  is  also 
100.00%
trying  to  export  to  Germany,  thus  50.00%
50.00%
the  DE‐FR  tie‐line  also  gets 
0.00% 0.00%
congested.  Similar  is  the  case  with 
BE‐FR BE‐NL DE‐FR DE‐NL BE‐FR BE‐NL DE‐FR DE‐NL
‐50.00%
anti‐clockwise  flow  but  with  ‐50.00%

reversed signs. MC distributed leads  ‐100.00%
‐100.00%
to  appearance  of  three  congested  ‐150.00%

lines, i.e. all tie lines except the DE‐ ‐150.00%

NL  tie‐line.  For  details  refer  Net  Net 


Utilization Utilization
appendix A.11     

7.3.1.1 C ONCLUSIONS  
In the highly meshed interconnected transmission networks in Europe programmed exchanges and physical 
flows  differ  often  considerably.  They  would  be  closely  connected  to  the  power  flows  through  the  cross 
borders only in the ideal case of a peninsular system and its neighbor if both were interconnected through a 
single tie line, in case of market coupling in between Netherlands, Belgium and France there are no parallel 
paths  hence  it  is  a  good  approximation  to  peninsular  system  with  the  neighbors  lying  in  a  straight  line. 
However, in a widely interconnected network like for example the UCTE network the power flow through the 
cross border tie lines between two neighbor areas A and B may be interpreted as a superposition of a direct 
flow,  which  is  related  to  exchanges  between  A  and  B  and  a  parallel  flow,  which  is  related  to  all  the  other 
exchanges in the meshed network and to the location of generations and loads in the several grids. Therefore 
Chapter: Results 

there would be a parallel flow even if all the exchanges in the interconnected system were set at zero. With 
introduction of Germany into the market coupling there would be large implications due to transit and loop 
flows on the values of ATC and NTCs. These transit flows cannot be handled by the NTC based MC.  

  75 
 
76  Flow‐based Market Coupling 
 

FMC leads to substantial drop in prices for both NL and BE. The drop is almost twice as much as achieved by 
using  MC  (clockwise  and  anti‐clockwise).  MC  with  distributed  also  did  perform  well  if  considering  only  the 
prices  in  Netherlands,  however  from  a  regional  perspective  FMC  would  be  more  suitable.  FMC  also  makes 
best possible use of the interconnector capacity, the interconnector % utilization ratios in other cases is not 
really the physical limit usage – but some approximate flow based on the commercial exchange that does not 
take  care  of  parallel  flows  occurring  due  to  transactions  between  other  countries.  Hence  it  is  possible  to 
conclude  that  FMC  comes  across  as  an  ideal  method  for  managing  inter‐country  electricity  trade  and 
congestion  management.  It  leads  to  the  best  use  of  actual  interconnector  capacity  and  hence  also  optimal 
trade volumes. 

Next part of the study would focus on the different scenarios that has either been planned in the future or are 
expected  to  happen  in  the  near  future.  Effect  of  FMC  on  these  scenarios  would  be  discussed  in  the  next 
section. 

7.4 SCENARIOS 
Scenarios were developed in consultation with the Ministry of Economic Affairs and suggestions from experts 
in the  field.  The scenarios were mainly  on policy and  investment options that can  be  employed. Increase of 
generation capacity, increase of transmission capacity, effect of carbon markets and the effect of loop flows 
because of wind generation in Germany have been investigated. 

7.4.1 INCREASE GENERATION CAPACITY IN NETHERLANDS  
There is presently no coal production in the Netherlands. All of their coal mining operations were closed down 
following the discovery of large indigenous reserves of natural gas in the early 1970s. Most of the coal reserves 
are  in  the  southern  and  east  central  parts  of  the  country,  and  recoverable  reserves  are  estimated  (as  of 
January 2005) at about 500 million short tons. The Netherlands currently ranks as the world's 32nd greatest 
coal  consumer  (and  11th  in  the  EU),  accounting  for  about  0.3%  of  the  world's  (and  about  1.9%  of  the  EU's) 
total  annual  coal  consumption  (Source:  EIA/DOE).  With  the  volatility  that  has  been  seen  in  the  Natural  Gas 
and Oil markets recently there is a renewed interest in Netherlands in investments in coal based power plants. 
Two  different  scenarios  were  tested  in  the  current  research  –  first  with  creation  of  5000  MW  additional 
capacity and second with additional capacity of 10 GW. The results would be discussed next. 

   
 

7.4.1.1 I NSTALLATION OF  5000   MW  COAL BASED POWER PLANTS  


 

NL Supply Curve
€ 80.00 
y = 2.439x
€ 70.00  R² = 0.848
€ 60.00 
Price (euros/MWh)

€ 50.00 
€ 40.00 
€ 30.00 
€ 20.00 
€ 10.00 
€‐
0.00 5.00 10.00 15.00 20.00 25.00 30.00
Generation Capacity (GW)
NL Supply Curve Linear (NL Supply Curve)
 
FIGURE 43 NEW SUPPLY CURVE WITH ADDITIONAL 5 GW OF HARD COAL BASED POWER PLANT 

The change induced in the model due to increased generation capacity is outlined above, the supply curve of 
NL changes and the slope becomes flatter. The market results from this change are presented in the figure 
below: 

Prices (euros/MWh) Import-Export % Tie-Line Utilization


(-ve means import)
10.00% 150.00%
€ 60.00

5.00%
€ 50.00 100.00%
0.00%
€ 40.00 NL BE FR DE 50.00%
-5.00%

€ 30.00 -10.00% 0.00%


BE-FR BE-NL DE-FR DE-NL
-15.00%
€ 20.00 -50.00%
-20.00%
€ 10.00 -100.00%
-25.00%

€- -30.00% -150.00%
NL BE FR DE

P* (w/o Coupling) P' (FMC Base) % Demand Imported (FMC Base) Net Utilization (FMC Base)
P* P' % Demand Imported Net Utilization
     

 Figure 44 Price change in NL, Imports and % tie line utilization for scenario with installation of 5000 MW coal 
based generation in NL 
Chapter: Results 

The prices in the Dutch electricity market would drop substantially with installation of extra 5000MW, even in 
absence  of  any  market  coupling  ‐  prices  drop  to  almost  €  40  per  MWh.  However  there  are  still  substantial 
benefits from FMC. If FMC was introduced in the present sate the prices would drop form € 51.83 to €43.62 

  77 
 
78  Flow‐based Market Coupling 
 

per MWh. Then if government decides to invest in 5000 MW coal based power plants, then the prices would 
drop further to € 37.14.  NL is also the country that derives most benefit in from FMC with the highest price 
drop  of  €  6.48  per  MWh,  followed  by  Belgium  €  5.55  per  MWh.  Also  Belgium  begins  to  import  more  from 
other  countries;  it  now  imports  almost  23%  of  its  demand  from  outside,  while  Netherlands  has  shown  an 
opposite trend with imports now standing at around 7%. There is also reversal of flow on the Dutch Belgian 
flow.  In  FMC  base  case  the  flow  was  mostly  from  Belgium  to  Netherlands  due  to  cheaper  imports  coming 
from France, however now the flows are from Netherlands to Belgium, as electricity in Netherlands is being 
supplied more locally. It goes on to prove that NL becomes much more independent of the imports – it’s also 
shown  in  the  figure  above.  However  it  must  to  noted  that  still  Netherlands  is  a  net  importer  –  despite 
investing  so  largely  in  the  coal  based  plants.  The  detailed  results  for  the  analysis  are  given  in  the  appendix 
A.12 

One  important  aspect  that  should  be  kept  in  mind  is  that  installation  of  coal  based  power  plants  though 
brings down the prices – they would also push the renewable energy technologies out of business for most of 
the  time  in  a  year.  This  should  be  considered  by  the  ministry  before  taking  such  a  step.  The  renewable 
technologies would need government support to  be able to remain competitive and be able to survive‐ this 
might offset some of the benefits of installing more coal based power plants. 

7.4.1.2 I NSTALLATION OF  10,000   MW  COAL BASED POWER PLANTS  

NL Supply Curve
€ 80.00 
€ 70.00  y = 1.951x
R² = 0.826
€ 60.00 
Price (euros/MWh)

€ 50.00 
€ 40.00 
€ 30.00 
€ 20.00 
€ 10.00 
€‐
0.00 5.00 10.00 15.00 20.00 25.00 30.00 35.00
Generation Capacity (GW)

NL Supply Curve Linear (NL Supply Curve)
 
FIGURE 45 NEW SUPPLY CURVE WITH ADDITIONAL 10,000 MW OF HARD COAL BASED POWER PLANTS 

The change induced in the model due to increased generation capacity is outlined above, the supply curve of 
NL changes and the slope becomes flatter. The market results from this change are presented in the figure 
below: 
 

Prices (euros/MWh) Import-Export % Utilization


(-ve means import)

€ 60.00 10.00% 150.00%

5.00%
€ 50.00 100.00%
0.00%
€ 40.00
NL BE FR DE 50.00%
-5.00%
€ 30.00
-10.00% 0.00%

€ 20.00 -15.00% BE-FR BE-NL DE-FR DE-NL


-50.00%
-20.00%
€ 10.00
-25.00% -100.00%
€-
-30.00%
NL BE FR DE -150.00%

P* (w/o Coupling) P' (FMC Base) % Demand Imported (FMC Base) Net Utilization (FMC Base)

P* P' % Demand Imported Net Utilization


     

FIGURE 46 PRICE CHANGE IN NL, IMPORTS AND % TIE LINE UTILIZATION FOR SCENARIO WITH INSTALLATION OF 10,000 MW 
HARD COAL BASED GENERATION IN NL 

The most striking observation from this scenario is that Netherlands becomes a net exporter. Belgium is the 
only country which is importing now from both Netherlands and also France and a small amount of exports 
from  Germany.  Belgium  prices  drop  down  and  also  it  is  importing  now  almost  quarter  of  its  demand  from 
other countries. The Netherlands ends up exporting electricity amounting to 5% of its local demand. Also the 
producer  surplus  in  the  Netherlands  increases  –  mainly  attributed  to  the  fact  that  the  prices  go  up  and 
electricity is being exported to other countries. Another interesting observation is that Germany is almost out 
of the loop. This could mainly be because of presence of low cost countries in the neighborhood of Belgium, 
and  no  direct  connection  between  Germany  and  Belgium.  This  could  however  change  if  there  were  to  be 
integration of networks in Luxemburg, allowing Germany to trade electricity directly to Belgium over that tie‐
line.  Presently  the  flows  from  Germany  to  Belgium  have  to  pass  through  either  France  or  Netherlands  and 
hence  have  lower  value.  Also  worth  noting  is  the  local  prices  of  electricity  in  Netherlands  drops  down  to  € 
33.14 per MWh, which is marginally lower than the local prices in Germany which stand at € 33.75 per MWh. 
The detailed results for the analysis are given in the appendix A.13 

However it should also be noted that if there was no market coupling and Netherlands was to install 10,000 
MW  coal  based  power  plants  than  the  local  prices  will  drop  down  to  €32.39  per  MWh,  and  actually  there  is 
increase in prices due to coupling‐ as there is exports to Belgium leading to a small increase in prices. Hence 
there is no clear cut benefit with installation of 10,000MW and FMC together – if only considering the national 
interests of Netherlands. Just going for installation of 10,000MW would give the benefits. 

• Conclusion 

Installation of additional coal based capacity in Netherlands has strong impact on the local prices and status 
of Netherlands as  being an net importer of electricity.  However it should  be noted that installation of large 
capacity  brings  down  the  benefit  that  Netherlands  was  deriving  out  of  FMC,  actually  with  installation  of 
+10,000 MW of coal based power plants – Netherlands became a net exporter. However one thing that was 
not considered here was the carbon prices. The price benefit that has been calculated was based on variable 
Chapter: Results 

cost of electricity generation – but without any carbon prices. It is possible that with inclusion of carbon prices 
(and  assuming  that  it  would  rise  from  the  present  levels  of  less  than  a  euro  per  ton  of  CO2  emission)  the 

  79 
 
80  Flow‐based Market Coupling 
 

variable cost would go up. Also from the purely environmental and health perspective government needs to 
investigate the implications such an huge change in generation mix might have on the country. 

7.4.2 INCREASED TIE‐LINE CAPACITY 
Tennet is working on a new direct Dutch‐German 1‐2 GW power interconnnector from Doetinchem to Wesel, 
planned to come onstream 2012, which could physically complete an integrated north‐west European power 
market. It was considered important to look at the effect FMC would have on the electricity market landscape 
after  installation  of  the  new  transmission  capacity.  Two  scenarios  were  modeled  to  study  the  effects  –  first 
with installation of 2000 MW and the second with installation of 5000 MW on the DE‐NL borders. The section 
below first describes the process of setting up the model, which was similar for both cases. The second part 
details the results. 

The new transmission line would have effect on two aspects of the model – first it could induce changes in the 
PTDFs  as  there  is  now  an  additional  path  available  for  the  current  to  pass  through  and  second  that  the 
interconnector  capacity  now  is  more  hence  there  could  be  more  exchange  of  electricity  between  the 
countries, leading to better convergence of the prices. Both these aspects were taken into consideration for 
studying  the  effect  on  new  transmission  line  on  the  electricity  markets  in  north‐west  European  region.  The 
new line was assumed to be installed between Gronau in Germany and Hengelo in Netherlands (referred to as 
Gronau    Hengelo,  from  here  on).  The  line  is  parallel  to  already  existing  transmission  line  between  the  two 
stations. The technical details for the transmission line that were entered into Power World model are given 
below. 

TABLE 15 PARAMETERS FOR THE NEW TRANSMISSION LINE BETWEEN DE‐NL 

  TieLine Records   
  Series Reactance  Meter MW  Meter Mvar  Status  Lim MVA  MW Loss  Mvar Loss 
1.  0.00726  393.3  ‐149.5  Closed  2000  0  11.7 
2.    0.00283  590.1  ‐239.8  Closed  5000  0  10.43 
The values of series reactance were picked to be similar to the ones of existing lines of similar capacities from 
within the model.  

 
FIGURE 47 THE DIALOG IN POWERWORLD TO SET UP THE VALUES OF PARAMETERS FOR THE TRANSMISSION LINE 
 

After  installing  a  new  transmission  line  as  described  above,  the  PowerWorld  model  is  run  to  get  the  new 
values of the PTDF’s. The new values compared to the previous values are shown below. 

TABLE  16  COMPARISION  OF  THE  PTDF  VALUES  BEFORE  AND  AFTER  INSTALLATION  OF  2000  MW  TRANSMISSION  LINE 
BETWEEN DE‐NL 

   Base Case  With 2000 MW transmisison line between DE‐NL 

  NL→NL  BE→NL  FR→NL  DE→NL  NL→NL  BE→NL  FR→NL  DE→NL 

BE→FR  0  0.196  ‐0.484  ‐0.244  0  0.197  ‐0.484  ‐0.242 

BE→NL  0  0.804  0.484  0.244  0  0.803  0.484  0.242 

DE→FR  0  ‐0.138  ‐0.272  0.107  0  ‐0.138  ‐0.272  0.106 

DE→NL  0  0.196  0.516  0.756  0  0.197  0.516  0.758 

The  first  observation  is  that  there  is  no  significant  variation  between  the  values.  There  is  only  a  very  minor 
change  in  the  values  at  the  DE‐NL  border.  However  even  that  is  at  the  third  decimal  point.  It  can  thus  be 
assumed that installation of a 2000 MW line between DE‐NL is an insignificant event considering the whole 
network. It can safely be concluded that PTDF values are not very sensitive to such changes. However it is still 
not clear what effect this small change in PTDF can have on the outcomes of the market module.  

Next  step  was  to  increase  the  tie‐line  capacity  in  the  market  module  by  2000  MW,  followed  by  the 
calculations of the final results. The line was assumed to be bi‐directional; hence the capacity was increased in 
both directions. 

 
FIGURE 48 NEW TIE‐LINE CAPACITY VALUES 

   
Chapter: Results 

  81 
 
82  Flow‐based Market Coupling 
 

7.4.2.1 B ETWEEN  G ERMANY AND  N ETHERLANDS  (+2000   MW) 


Prices (euros/MWh) Import-Export % Utilization
(-ve means import)

15.00% 150.00%
€ 60.00

10.00%
€ 50.00 100.00%
5.00%

€ 40.00 0.00% 50.00%

NL BE FR DE
-5.00%
€ 30.00 0.00%
-10.00% BE-FR BE-NL DE-FR DE-NL
€ 20.00
-15.00% -50.00%

€ 10.00 -20.00%
-100.00%
-25.00%
€-
-30.00% -150.00%
NL BE FR DE
% Demand Imported (FMC Base) Net Utilization (FMC Base)
P* (w/o Coupling) P' (FMC Base) P* P' % Demand Imported Net Utilization
     
FIGURE 49 RESULTS FROM FMC AFTER INSTALLATION OF 2000 MW TRANSMISSION LINE BETWEEN DE‐NL 

The  change  in  prices  in  the  Netherlands  is  high  –  it  drops  by  €  4.62  compared  to  case  in  which  FMC  is 
implemented  in  present  situation.  It  shows  that  there  is  sensitivity  of  the  FMC  market  results  on  the 
transmission  capacity.    Also  Germany  becomes  the  only  exporter,  despite  lower  prices  in  France.  The 
explanation  to  this  also  lies  in  how  FMC  operates,  Netherlands  only  has  an  interconnector  capacity  of  1350 
MW  with  Belgium,  that  so  that  means  maximum  amount  of  electricity  that  can  come  from  France  to 
Netherlands  through  Belgium  is  1350  MW.  Additionally  the  interconnector  between  France  and  Germany 
allows  only  1700MW  to  flow  from  France  to  Germany.  Hence  there  isn’t  a  possibility  of  large  imports  into 
Netherlands from France, because of congestion on BE‐FR tie‐line. When the interconnector on Germany and 
Netherlands border gets more capacity installed then Germany is able to deliver large amounts of electricity 
and 10% of that flows through the parallel path, DE‐> FR‐> BE‐> NL. Hence looking at the whole system it is 
more beneficial to dispatch the generators in Germany and not France. This should be kept in mind – the FMC 
results have strong dependence on topology of the system. Any change on one tie‐line can lead to completely 
different results, which are not intuitive to the sense of dispatching the cheapest generators.  

The increased transmission capacity allows more flow from Germany to both Belgium and Netherlands which 
allow these two countries to get the benefit. The prices in Belgium also drop by almost € 8, compared to the 
drop of € 6, in the base case. The net welfare for all countries is positive. For France the change is almost zero. 
The details of the results can be checked from the appendix A.14 

Also  still  there  is  congestion  on  the  DE‐NL  and  BE‐FR  border.  That  shows  that  there  could  be  additional 
benefits with increasing the capacity of the DE‐NL border further. A case was also run with increasing BE‐FR 
tie line capacity, as that is also congested, in both the base case and current case. 
 

Prices Change (euros) Prices Change (euros) % Utilization


FMC Base ‐ FMC Scenario FMC Base ‐ FMC Scenario

€ 3.00  € 3.00 

€ 2.00  € 2.00  150.00%

€ 1.00 
€ 1.00  100.00%
€‐
€‐ 50.00%
NL BE FR DE
NL BE FR DE € (1.00)
€ (1.00) 0.00%
€ (2.00)
BE-FR BE-NL DE-FR DE-NL
€ (2.00) -50.00%
€ (3.00)
€ (3.00) -100.00%
€ (4.00)

€ (4.00) € (5.00) -150.00%

€ (5.00) € (6.00)

∆ Price ∆ Price Net Utilization (FMC Base)

Net Utilization
     
FIGURE  50  PRICE  CHANGE  AFTER  FIGURE  51  PRICE  CHANGE  WITH  FIGURE  52  UTILIZATION  OF  FLOW  LINE 
INSTALLATION OF +2000MW ON NL‐DE  INSTALLATION  OF  +2000MW  ON  BE‐FR  WITH  +2000  MW  ON  BE‐FR  LINE, 
TIE‐LINE  TIE LINE  COMAPRE TO FIGURE 45 

The  detailed  results  are  attached  in  the  appendix  A.15.  It  can  be  seen  that  clearly  the  benefit  now  shifts  to 
Belgium as an importer and to France as an exporter. France becomes the sole exporter and Germany is also 
importing small amount of capacity from France. 

7.4.2.2 B ETWEEN  G ERMANY AND  N ETHERLANDS  (+5000   MW) 


The case was setup using the same steps as above. The results are discussed below. 

TABLE  17  COMPARISION  OF  THE  PTDF  VALUES  BEFORE  AND  AFTER  INSTALLATIONOF  5000  MW  TRANSMISSION  LINE 
BETWEEN DE‐NL 

  Base Case  With 5000 MW transmission line between DE‐NL 

  NL→NL  BE→NL  FR→NL  DE→NL  NL→NL  BE→NL  FR→NL  DE→NL 

BE→FR  0  0.196  ‐0.484  ‐0.244  0  0.197  ‐0.482  ‐0.241 

BE→NL  0  0.804  0.484  0.244  0  0.803  0.482  0.241 

DE→FR  0  ‐0.138  ‐0.272  0.107  0  ‐0.138  ‐0.273  0.106 

DE→NL  0  0.196  0.516  0.756  0  0.197  0.518  0.759 

Again the same observation is made about the effect of a new transmission line on the PTDFs, it is very small, 
affecting only the third  decimal value. This time the  value of interconnector transmission capacity  between 
DE‐NL was increased by 5000 MW, taking it up to 7500 MWs. The results of the FMC would be discussed next. 
Chapter: Results 

  83 
 
84  Flow‐based Market Coupling 
 

Prices (euros/MWh) Import-Export % Utilization


(-ve means import)
€ 60.00

15.00%
€ 50.00
10.00% 150.00%

5.00% 100.00%
€ 40.00
0.00% 50.00%
€ 30.00 NL BE FR DE
-5.00%
0.00%
-10.00% BE-FR BE-NL DE-FR DE-NL
€ 20.00 -50.00%
-15.00%
-100.00%
€ 10.00 -20.00%
-150.00%
-25.00%
€-
-30.00%
NL BE FR DE
% Demand Imported (FMC Base) Net Utilization (FMC Base)
P* (w/o Coupling) P' (FMC Base) P* P' % Demand Imported Net Utilization
     
FIGURE 53 RESULTS FROM FMC AFTER INSTALLATION OF 5000 MW TRANSMISSION LINE BETWEEN DE‐NL 

As  can  be  seen  the  results  are  identical  to  the  results  of  2000  MW  case,  prices  change  and  imports  into 
Netherlands are almost the same. This shows that congestion is now no longer on the NL‐DE border. The only 
congestion now is on BE‐FR line. As can be seen in the first case two of the interconnectos are congested BE‐
FR and DE‐NL. In the case of increased capacity on the DE‐NL border further, the congestion shifts to BE‐NL 
border.  More details on the model can be found in the appendix A.16 

The  case  was  also  run  with  increasing  the  border  capacity  on  DE‐NL  border  by  10,000  MW,  however  the 
results resembled the results from additional 5000 MW case, as the congestion is not on that border anymore. 
See Appendix A.17 

7.4.3 DISCUSSION ON SENSITIVITY OF PTDFS 
As seen from the two  cases, first with  installation of +2000MW and then with +5000MW, the  PTDFs do not 
change  substantially.  The  effect  is  seen  only  at  the  third  decimal  place.  This  could  also  be  expected  mainly 
because the  whole  of UCTE network is considered here and an additional 1000’s of  MWs only have a minor 
impact the topology of the network. Hence it could be assumed that there would not be major changes in the 
PTDFs with small changes in the network. 

Next it is also important to see what small differences can have on the market results. To check the impact of 
PTDF on the solutions case with PTDFs of 5000 MW, and tie‐line capacity on NL‐DE border of additional 2000 
MWs.  Now  the  results  could  be  compared  to  the  results  of  model  with  the  PTDFs  from  2000  MW  and 
additional capacity of 2000 MW on DE‐NL border (A.14). There was no remarkable change with between the 
two. 
 

Prices Change (euros) % Utilization


FMC Base - FMC Scenario 150.00%
€ 3.00
€ 2.00 100.00%
€ 1.00
50.00%
€-
€ (1.00) NL BE FR DE 0.00%
€ (2.00) BE-FR BE-NL DE-FR DE-NL
-50.00%
€ (3.00)
€ (4.00) -100.00%

€ (5.00)
-150.00%
∆ Price Net Utilization (FMC Base) Net Utilization
 
FIGURE 54 PRICE CHANGE AND % UTILIZATION FROM +2000MW ON DE‐NL BORDER AND PTDF'S ALSO FROM +2000MW CASE 

Prices Change (euros/MWh) % Utilization


FMC Base - FMC Scenario
€ 3.00

€ 2.00 150.00%
€ 1.00 100.00%
€- 50.00%
€ (1.00) NL BE FR DE 0.00%
€ (2.00) -50.00% BE-FR BE-NL DE-FR DE-NL

€ (3.00) -100.00%
€ (4.00) -150.00%
€ (5.00)

∆ Price
Net Utilization (FMC Base) Net Utilization
 
FIGURE  55  PRICE  CHANGE  AND  %  UTILIZATION  OF  INTERCONNECTOR  FROM  +2000MW  CAPACITY  ON  DE‐NL  BORDER  AND 
PTDFS FROM +5000MW  

The above two figure show that there is no difference between the results. It is possible that under extreme 
change of values the results would change as seen in the comparison of FMC with MC in section 7.3. However 
there is no significant dependence on the PTDF’s for minor changes as seen here. Hence though PTDF’s play a 
very  important  role  in  deciding  the  market  outcome  –  they  are  also  not  very  sensitive  to  small  changes  in 
transmission capacity, neither do small changes in PTDF’s lead to large changes in the market outcomes. 

• Conclusion 

Tie line capacity has strong effect on the prices in a country. As was seen with installation of 2000MW on the 
DE‐NL  border  and  BE‐FR  border,  the  prices  change  is  higher  with  installation  of  more  capacity  on  the 
congested  tie‐lines.  However  it  was  also  noted  that  installation  of  additional  5000MW  has  very  small 
additional benefit for the region. The tie line is not fully utilized and hence is not recommended. 

PTDFs play an  important role in the market  outcome from the FMC.  However  calculation of  PTDFs depend 


only  on  the  topology  of  the  network.  UCTE  is  composed  of  the  highly  meshed  system  of  24  European 
countries  consisting  of  some  200,000  km  of  400  and  220  kV  lines.  Installation  of  a  new  tie  line  between 
countries like NL and DE, have small impact on the topology of the system as a whole. Hence there is only a 
Chapter: Results 

minor change on the PTDFs with installation of new tie‐line. Secondly, though the markets do depend on the 
PTDFs, the dependence is not as strong so as to get affected by change on PTDFs in its third decimal. Hence it 

  85 
 
86  Flow‐based Market Coupling 
 

is possible to be certain that the TSOs won’t be able to guide the market results as much. Markets could still 
be efficient, though they might be owned by TSOs, as in case of NL.  

Next part of scenario analysis would focus on studying the effect of Carbon Market which has been evolving 
over  the  recent  past.  As  already  discusses  in  the  development  of  model  –  the  cost  sheet  included  carbon 
pricing into it. However it was decided in the model thus far not to consider them. In the next section carbon 
prices and its effect on the market results would be studied. 

7.4.4 EFFECT OF CARBON MARKET 
The  European  Union  Emission  Trading  Scheme  (or  EU  ETS)  is  the  largest  multi‐national,  greenhouse  gas 
emissions trading scheme in the world and was created in conjunction with the Kyoto Protocol. It commenced 
operation  in  January  2005  with  all  25  (now  27)  member  states  of  the  European  Union  participating  in  it.  It 
contains  the  world's  only  mandatory  carbon  trading  program.  The  program  caps  the  amount  of  carbon 
dioxide that can be emitted from large installations, such as power plants and carbon intensive factories and 
covers almost half of the EU's Carbon Dioxide emissions  

FIGURE  56  CONTRIBUTION  OF  ELECTRICITY  AND  HEAT  GENERATION  TOWRDS  TOTAL  CARBON  EMISSIONS 
(HTTP://WWW.DEFRA.GOV.UK/ENVIRONMENT/CLIMATECHANGE/TRADING/EU/INDEX.HTM). 

As shown above in the Figure 57 electricity and heat generation accounts for 24% of total emissions within EU 
(EEA  2006)  and  also  the  fact  the  prices  of  Carbon  have  been  very  volatile  over  the  past  two  years  since 
introduction of trading. The prices of Carbon credits since its introduction have been given below in Figure 57. 
The  prices  started  at  around  €  8  per  tonne  of  emission,  it  increased  within  the  next  18  months  to  a  high  of 
more than € 30 per tonne and then suddenly dropped in April 2006, since then it has been tumbling down to 
below € 1 recently. 

 
FIGURE 57 DEVELOPMENT OF CARBON PRICES IN EU, INCLUDING THE CRASH IN APRIL 2006 (SOURCE: POINT CARBON) 

Carbon  prices  add  to  the  variable  cost  of  generation  of  electricity  based  on  fossil  fuels.  Considering  the 
importance  coal  and  natural  gas  play  in  the  energy  portfolios  of  the  north‐west  European  countries  it  was 
 

important to study the  effect that carbon prices can have on the merit orders and hence the  energy export 


and import. On basis of the values for carbon credits given four different scenarios were defined.  

• 15 €/ton of CO2 
• 20 €/ton of CO2 
• 30 €/ton of CO2 
• 50 €/ton of CO2 

The details of the results are attached in the appendix A.19. Some of the interesting observations would be 
discussed below.  

7.4.4.1 E FFECT OF  C ARBON  P RICING ON  M ERIT  O RDER  


The merit order did not change with increasing the prices from € 0.00 till € 20. Till then the merit order was 
same as the base case. Only when the prices for carbon rise to €30 there is a change in the merit order. CHP‐
Gas becomes cheaper compared to Lignite coal and hard coal based power plants. At the extreme end of the 
spectrum with the prices rising up to € 50 the Gas based plants become cheaper than the Lignite based power 
plants.  This  is  mainly  an  issue  for  Germany  as  they  have  19.33  GW  installed  capacity  based  on  Lignite.  This 
also reflects in the electricity prices in Germany after introduction of carbon pricing. 

TABLE 18 IMPACT OF CARBON PRICING ON THE MERIT ORDER BASED ON FUEL AND ENERGY TECHNOLOGY TYPE (THE ITEMS 
MARKED WITH OLIVE ARE THE ONCE THAT MOVED) 

Environmental  Price  of Carbon Emission (€/tonne) 
  Preference  Base Case  15  20  30  50 
Merit Order  H  H  H  H  H  H 
   W  W  W  W  W  W 
   N  N  N  N  N  N 
   CHP‐B  HC  HC  HC  CHP‐G  CHP‐G 
   O  LC  LC  LC  HC  HC 
   CHP‐G  CHP‐G  CHP‐G  CHP‐G  LC  G 
   G  G  G  G  G  O 
   HC  O  O  O  O  LC 
   LC  CHP‐B  CHP‐B  CHP‐B  CHP‐B  CHP‐B 
           
Key            
Hydro  H         
Wind  W         
Nuclear  N         
CHP Natural Gas  CHP‐G         
Hard Coal Condensation  HC         
Lignite Condensation  LC         
Natural Gas Combined Cycle  G         
Oil  O         
CHP Biomass  CHP‐B         
 

This is also reflected in the changing equation of the supply curve. The demand curve was assumed to be the 
Chapter: Results 

same  as  before,  to  ensure  that  the  results  can  be  compared  to  each  other.  The  demand  curve  changes  are 
shown in Figure 58. 

  87 
 
88  Flow‐based Market Coupling 
 
 

 
FIGURE 58 EFFECT OF CARBON PRICING ON THE MERIT ORDER WITHIN NORTH‐WEST EUROPEAN REGION 

The  biggest  change  is  observed  within  Netherlands  and  Germany.  France  has  large  installations  of  nuclear 
and is predominantly unaffected by the prices. It is interesting to see the operating point of the market as well 
the average demand for the north‐west European region. 
Chapter: Results 

   

  89 
 
90  Flow‐based Market Coupling 
 

TABLE 19 AVERAGE DEMAND IN NORTH‐WEST EUROPEAN REGION (UCTE SYSTEM ADEQUACY REPORT 2007‐20) 

   Average Demand 
  GW 
NL  16.30 
BE  12.60 
FR  79.40 
DE  74.00 
The average demand within France can be satisfied by its installed capacity of Hydro, Wind and Nuclear and is 
thus  almost  not  affected  by  the  carbon  pricing.  However  the  results  of  FMC  could  shed  more  light  into  the 
details.  

Prices Change Import-Export % Utilization


(euros/MWh) (-ve means import)
FMC Base - FMC Scenario
€ 6.00
5.00%

150.00%
€ 5.00
0.00%
100.00%
€ 4.00 NL BE FR DE
50.00%
-5.00%
€ 3.00 0.00%
BE-FR BE-NL DE-FR DE-NL
-10.00% -50.00%
€ 2.00
-100.00%
€ 1.00 -15.00%
-150.00%

€-
-20.00%
NL BE FR DE
% Demand Imported (FMC Base) Net Utilization (FMC Base)
∆ Price
% Demand Imported Net Utilization
     

CO2 Price € 15 per ton 

Prices Change Import-Export % Utilization


(euros/MWh) (-ve means import)
FMC Base - FMC Scenario
€ 7.00
5.00%

€ 6.00 150.00%

0.00%
100.00%
€ 5.00
NL BE FR DE
50.00%
€ 4.00 -5.00%
0.00%
€ 3.00 BE-FR BE-NL DE-FR DE-NL
-10.00% -50.00%
€ 2.00
-100.00%

€ 1.00 -15.00%
-150.00%

€-
-20.00%
NL ∆BE FR DE
% Demand Imported (FMC Base) Net Utilization (FMC Base)
Price
% Demand Imported Net Utilization
     

CO2 Price € 20 per ton 
 

Prices Change Import-Export % Utilization


(euros/MWh) (-ve means import)
FMC Base - FMC Scenario
€ 12.00
10.00%

150.00%
€ 10.00
5.00%
100.00%
€ 8.00
0.00% 50.00%
NL BE FR DE
€ 6.00 0.00%
-5.00%
BE-FR BE-NL DE-FR DE-NL
-50.00%
€ 4.00
-10.00%
-100.00%
€ 2.00
-15.00% -150.00%

€-
-20.00%
NL BE FR DE
% Demand Imported (FMC Base) Net Utilization (FMC Base)
∆ Price
% Demand Imported Net Utilization
     

CO2 Price € 30 per ton 

Prices Change Import-Export % Utilization


(euros/MWh) (-ve means import)
FMC Base - FMC Scenario
€ 20.00
5.00%
€ 18.00
150.00%
€ 16.00
0.00% 100.00%
€ 14.00 NL BE FR DE
50.00%
€ 12.00
-5.00%
€ 10.00 0.00%

€ 8.00 BE-FR BE-NL DE-FR DE-NL


-10.00% -50.00%
€ 6.00
-100.00%
€ 4.00
-15.00%
-150.00%
€ 2.00

€-
-20.00%
NL BE FR DE
% Demand Imported (FMC Base) Net Utilization (FMC Base)
∆ Price
% Demand Imported Net Utilization
     

CO2 Price € 50 per ton 

FIGURE 59 RESULTS FROM FMC AFTER CONSIDERING CARBON PRICING 

As expected, after implementation of Carbon pricing in the FMC model, the price of electricity in the markets 
would go up. Belgium sees the highest price change for prices increasing to €15 and €20 per ton, compared to 
the FMC base  case with no  carbon pricing.  The second most affected  country is Netherlands. With € 15 per 
ton, there is an increase of around € 4.50 per MWh in Netherlands, and an increase of €5 in Belgium. In general 
every country sees a price increase of around €4‐€5 per MWh. Still Germany is exporting and the congested 
tie‐lines are NL‐DE and BE‐FR. 
Chapter: Results 

With  the  price  of  carbon  going  up  to  €  20  per  ton  of  CO2  the  pattern  of  results  is  similar.  Though  now  the 
prices increase in the region is higher – around €5.50 to €6.50. The highest increase in again seen in Belgium 

  91 
 
92  Flow‐based Market Coupling 
 

and followed by Netherlands at € 6.00. It  can  be seen that because these countries depend strongly on the 


imports they see slightly higher increases in prices as compared to the exporters. Germany is still exporting. 

When the prices hit €30, the scenarios begin to change. Germany sees a very high increase in electricity price 
– of around €1 per MWh, followed by Belgium at around € 9 per MWh. The lowest price change is now seen in 
Netherlands  at  around  €7  per  ton.  Though  still  Germany  is  exporting,  mainly  the  reason  for  that  is  good 
interconnector that it has with Netherlands and higher flow capacity from DE‐> FR(5000MW), as compared to 
FR‐> DE (1700MW).  Hence Germany has a good access to the  high price areas (NL and BE, as compared to 
France.  

With further increase in price ‐ € 50 per ton of CO2, the picture looks much different. Now the German prices 
shoot up by € 18 per MWh, followed by France at around €14. Netherlands sees a price increase of around € 8 
per MWh, which is the lowest among all countries.  

The detailed results for each case from every perspective can be checked in the appendix A.19 

• Conclusion 

It can be concluded from the above results that CO2 pricing though has strong effects on regional price levels. 
Netherlands  is  amongst  the  least  affected  countries  when  it  comes  to  price  changes  induced  by  carbon 
pricing. With lower prices (around €15) there was an increase of around €4, and with higher prices (€50) there 
was a change of around €8. However other countries – most importantly Belgium saw bigger price changes 
and Germany gets badly affected when the prices go high.  

7.4.5 DECOUPLING OF GERMAN SYSTEM INTO NORTH AND SOUTH BLOCK  
Germany was required to be split up into north and south zones in order to study the effect that loop flows 
have on the north west European electricity system, that occur due to wind generation in North of Germany 
and  consumption  in  the  southern  industrial  demand  area  within  Germany.  The  PowerWorld  model  for  the 
UCTE was used for this purpose. Two new areas were defined out of the current single area. The division was 
made along the line shown in Figure 60. The new areas were then used to calculate new set of PTDF’s for the 
region. Figure 61 shows the flows after splitting of Germany. 

These  new  PTDF  values  would  be  used  to  understand  the  effect  that  these  loop  flows  have  on  the 
interconnector congestion in the North West European region. 
 

 
FIGURE 60 THE DIVISIONOF GERMANY INTO NORTH AND SOUTH BLOCK 

 
Chapter: Results 

 
FIGURE 61 FLOWS AFTER SPLITTING GERMANY INTO NORTH AND SOUTH BLOCKS 

  93 
 
94  Flow‐based Market Coupling 
 

7.4.5.1 E FFECT OF  W IND GENERATION IN  G ERMANY  (15,000   MW  FROM  NÆS) 


Current installation  of  wind  generation in Germany is around  21  GW, it is  expected to rise to  29 GW  by the 
year  2010  (www.ucte.org).  Wind  is  highly  intermittent  and  German  laws  enforce  that  all  wind  generation 
should  be  accepted  into  the  grid.  Figure  62  shows  the  share  of  wind  power  in  the  net  generation  within 
Germany. 

 
FIGURE 62 ANNUAL SHARE OF DAILY WIND POWER IN RESPECTIVE DAILY PEAK DEMAND ON E‐ON GRID (GERMANY) 

With  the  fast  extension  of  wind  capacities  especially  in  Northern  Germany  congestion  management  has 
become a serious issue in the North‐Western European electricity grid. Due to power distribution through the 
entire European integrated network (UCTE grid) according to relative line impedances, Germany’s neighbors 
to  the  North  West,  namely  Benelux  countries,  are  affected  by  unintended  but  inevitable  cross  border  flows 
congesting their grids. With the intended expansion of offshore wind capacities in the German North Sea, this 
problem is bound to aggravate. 

TABLE 20 PTDF VALUES AFTER SPLITTING GERMANY INTO NORTH AND SOUTH BLOCK 

Interface  % PTDF 

BE→FR  9.4 
BE→NL  ‐9.4 

DE‐S→FR  ‐0.90 

DE‐N→NL  9.4 

DE‐N→DE‐S  77.4 

As can be seen from the table above 9.4% of all electricity that is supposed to go from DE‐N to DE‐S actually 
takes its path through NL. Hence if 20,000 MW of electricity has to go from DE‐N to DE‐S during a storm in 
the northern part and operation of the wind generation, 9.4% of this would pass through the DE‐N‐NL tie line. 
2500 MW is the capacity, NTC value of this interface. Therefore 1880 MW of this 2500 MW would already be 
used  up  because  of  German  wind  energy.  This  would  leave  only  620  MW  for  making  trade  with  other 
countries (in the direction DE‐> NL). Also there would be less capacity on the BE‐NL border and also on BE‐FR 
border and also on FR‐DE border. BE‐NL border has only a capacity of 1350 MW, it cannot transfer 1880 MW 
through.  Hence  BE‐NL  interconnector  would  already  be  congested.  Hence  there  is  no  possibility  of  making 
 

any trade with any other country. The prices in the countries would stay equal to the prices that would occur 
without coupling of networks. 

Hence  it  is  concluded  that  there  is  significant  effect  that  loop  flows  from  a  large  market  (like  Germany  and 
France)  could  have  on  interconnector  usage  between  smaller  market  like  Netherlands  and  Belgium.  Loop 
flows because of German wind power are enough to congest the interconnector within other countries. Next 
section would discuss the effect of FMC on loop flows because of wind. 

7.4.5.2 FMC  AND  L OOP  F LOWS  


The  relatively  large  loop  flows  through  the  Netherlands  and  Belgium  and  France  as  shown  in  the  previous 
discussion  due  to  wind  generation  within  Germany  and  the  law  within  Germany  to  consider  these  flows  as 
local clearly ignores the physics of the interconnected network.  

FMC in present state is not able to deal with the loop flows.  

 
FIGURE  63  THE  DIFFERENCE  BETWEEN  TRANSIT  AND  LOOP  FLOWS  (GREEN  ARROWS  MARK  THE  TRANSIT  FLOWS,  GREY 
ARROWS MARK THE LOOP FLOWS) 

As  can  be  seen  from  the  Figure  63,  the  green  arrows  mark  the  transit  flows  that  occur  due  to  commercial 
exchange of electricity between Germany and France (from Germany to France).Please note that there would 
be direct flow over the DE‐FR interconnector as well, which is not show in the image above. These flows that 
occur in the interconnectors between DE‐NL, NL‐BE and BE‐FR because of commercial flow from DE‐>FR are 
termed  as  transit  flows.  These  flows  are  all  accounted  for  by  using  the  PTDFs  approach  –  during  market 
coupling. 

The loop flows on the other hand the flows that happen in the whole system due to flows which are assumed 
to be local. As can be seen in the picture above, the flow from Germany north to south would also utilize the 
networks in NL, BE and FR. However there was no commercial exchange, and hence it was not considered in 
the  calculation  during  FMC.  Hence  FMC  would  not  resolve  the  issues  of  loop  flows  from  Germany.  Also 
interesting is the fact that any other country in North West European region shares its border with every other 
country, unlike Germany; hence the issue of loop flows in case of other countries is much smaller. 

The  only  possible  solution  to  this  issue  is  either  to  consider  Germany  as  two  price  areas,  two  independent 
markets. If that is the case, then the FMC would be between 5 market areas, and all the flows which are now 
considered  local to Germany would  be from  Germany north to south. These flows  can  then  be taken  in the 
FMC algorithm. The markets would become more efficient and transparent in that situation. 

This is a suggestion and might not be acceptable to German policy makers. This however is an important issue 
to be discussed with the German TSOs and PXs – in case there can be some other arrangement that can be 
Chapter: Results 

worked out. 

   

  95 
 
96  Flow‐based Market Coupling 
 

8 ACTOR ANALYSIS   
 

Till  now  the  report  focused  on  understanding  FMC  and  its  distributive  effects  on  the  involved  countries. 
However, it is important at this point to realize the fact that FMC would have to be implemented in a multi‐
actor  environment  many  of  whom  might  have  conflicting  interests.  The  last  sections  showed  that  FMC  is 
indeed an economically efficient method for cross‐border congestion management – it makes most optimal 
use of the available transmission capacity while respecting the physical limits of the lines. 

This section would focus on researching the actors that would be involved in the process. First step would be 
to look at the context in which the present system would be implemented – i.e. very high level understanding 
of the market place. Consequently, the section would detail the various actors in the electricity market arena. 
After the listing is complete, their interests and positions would be listed. Based on their positions and needs a 
framework for analysis of assessing the acceptability of FMC would be outlined. Finally the chapter would end 
with detailing the FMC’s effect on the positions of the involved actors. 

8.1 GENERAL OVERVIEW 
The  four  countries  in  focus  here  are  significantly  different  from  other  in  terms  of  size,  population  and 
electricity demand and supply characteristics. The table below details some of the important features of the 
markets  under  consideration.  The  smaller  countries  NL  and  BE  are  also  the  importers.  Net  imports  for  NL 
were  the  highest,  underlining  the  importance  imports  have  for  the  country.  France  is  the  largest  exporter. 
Germany consumes the highest amount of electricity amongst the four and also produces the highest amount 
per year. However the difference in generation between DE and FR are not huge. 

TABLE 21 GENERAL CHARACTERISTICS OF THE NORTH WEST EUROPEAN ELECTRICITY MARKET 

  Installed  Annual Electricity  Growth Forecast 


Area  Population 
Generation  Generation  2007‐20 

  sq km    GW  TWh  % 

NL  41,526  16,570,613  22.1  115  1.8 

BE  30,528  10,392,226  16.33  88  1.4 

FR  643,427  63,713,926  116.36  482  0.9 

DE  357,021  82,400,996  122.59  563  0.3 

  Annual Electricity  Annual Electricity 
Electricity Imports  Electricity Exports 
Consumption  Generation 

  TWh  TWh  TWh  TWh 

NL  115.766  94.306  27.346  5.886 

BE  92.643  82.391  18.946  8.694 

FR  486.187  549.688  8.437  71.938 


 

DE  554.787  570.507  49.407  65.127 

8.2 STRUCTURE OF THE ELLECTRICITY MARKETS 

 
AIN 
FIGURE 64 THE ELECTRICITY VALUE CHA

The electricity value chain can be described under the following headers: 

1. Generation: Refers to geneeration of electricity from coal, gas, nuclear, hydro orr other sources 
2. Electricity Trading: Generaators sell energy via market places to sales companies or major resellers. At 
places where the generatio on companies are not yet unbundled some generatio on units go directly to 
the sales of the generationn company. The price paid by the sales units is determmined in the market 
place. 
3. Sales: Private persons and industries sign delivery agreements with the differen nt actors at the sales 
stage. Prices are regulatedd via various kinds of agreements between sales comp panies and customers. 
4. Transmission: The nationaal grids are large high‐voltage networks that transporrt large volumes of 
electricity over long distan
nces. National grids are for most part owned by state..   
5. Distribution: Regional and local electricity networks transport electricity to the  end customer. There 
are some large companies coexisting with regional and local network companiees.  The networks are 
operated by separate legal entities, regardless if they are owned by major poweer utilities, 
municipalities or other players. 
6. Market Places: Electricity i is traded on electricity exchanges or in the OTC markket. Actors such as 
producers, resellers and veery large industrial companies trade on the electricityy exchanges. Some 
major actors are both prod ducers and suppliers, and act as both buyer and sellerr on the electricity 
exchange. In the OTC market which is outside the exchange, actors trade directtly with one another. 
Pricing in the OTC market  often reflects expectations regarding the electricity e exchange’s wholesale 
price. The import export between national borders take place depending on diffference in the 
wholesale prices between  countries.  
7. Regulators: Electricity marrkets have inherent issues of monopoly and economies of scale there is a 
requirement of monitoring g and control from an external agency. Each country h  has an agency 
committed to making energy markets work as effectively as possible by implem menting various 
regulatory instruments. Th his entails safeguarding access to networks, maintain ning sufficient 
transparency (access to essential information) and protecting consumers again nst potential 
malpractices resulting fromm the (inherent) dominant position of providers. 
Chapter: Actor Analysis 

In the restructured environment, th here are increasing market actor demands for better  power system security 
and  quality.  On  the  other  hand,   market 
m actors  also  demand  an  increase  in  the  pow
wer  system  limits  and 
transfer capacities. These demandss work in opposite directions.  Considering that the reesearch deals with four 

  97 
 
98  Flow‐based Market Coupling 
 

countries a detailed list of actors would be prepared. The next section would present the list of all the actors 
NL, BE, FR and DE. 

8.3 LIST OF ACTORS 
TABLE 22 LIST OF ALL RELEVANT ACTORS FOR THE NORTH WEST EUROPEAN REGION 

  NL  BE 
Regulator  Dienst  uitvoering  en  toezicht  Energie  Commission  de  Regulation  de  l’Electricite  et  du  Gas 
(DTe)  (CREG) 
     
Power Exchnage  APX  BelPex 
     
Generation  Large Scale Generation:  Electrabel SA 
  Delta   
  Electrabel   
  E.ON   
  Essent   
  Nuon   
     
Trade  Generation and Supply  Generation and Supply 
  APX  Belpex 
  Imports/Exports  Imports/Exports 
  Long Term Contracts  Long Term Contracts 
     
Transmission  Tennet  ELIA 
     
Distribution  Cogas  Private companies: 1 
  Delta  Municipality companies: 4 
  Eneco  Mixed Inter‐municipality companies: 15 
  Essent  Pure Inter‐municipality companies: 8 
  NRE Network   
  Nuon   
  ONS   
  Rendo   
  Westland Energie   
     
Retail, B2B  Cogas  Many 
  Delta   
  Eneco   
  Energiebedrijf.com   
  Essent   
  Intergas   
  NRE Network   
  Nuon   
  ONS   
  Rendo   
  Westland Energie   
 

   
 

  FR  DE 
Regulator  Commission de Régulation de l’Electrité  Bundesnetzagentur  für  Elektrizität,  Gas, 
Telekommunikation,  Post  und  Eisenbahnen 
(BNetzA) 

     
Power Exchnage  Powernext  European Energy Exchange (EEX) 
     
Generation  Electricite de France  Berliner Kraft und Licht AG  
  Energie du Rhône   E.ON Energie AG  
  Société Nationale d’Electricité et de Thermique  ENBW Energie‐Versorgung Schwaben 
  Société Hydroélectrique du Midi (SHEM)  Hamburgische Elec‐werke AG  
  Electrabel (Suez Group)  Neckarwerke Suttgart AG (NWS) 
    RWE Energie AG  
    STEAG AG  
    Vattenfal Europe AG 
     
Trade  Generation and Supply  Generation and Supply 
  Powernext  EEX 
  Imports/Exports  Imports/Exports 
  Long Term Contracts  Long Term Contracts 
     
Transmission  Reseau de Transport Electricite (RTE)  EnBW Transportnetze AG 
    E.ON Netz GmbH 
    RWE Transportnetz Strom GmbH 
    Vattenfall Europe Transmission GmbH 
     
Distribution  Electricité de France (EDF)  More than 900 distribution companies 
  Electricité de Strasbourg (ES)   
  Gaz et Electricité de Grenoble (GEG)   
  Usine d’Electricité de Metz (UEM)   
  Vialis (Colmar)   
     
Retail, B2B  Energie du Rhône‐ sales RWE PLUS   Citiworks 
  ENDESA France Electrabel (via SHEM)   E.ON Sales & Trading 
  CNR (Main shareholder Electrabel 49,97)   EDF Trading 
  SNET (Main share holder Endesa 65%)  Electrabel Deutschland 
  Total (via Gas and Power North Europe)  EnBW Ges. für Stromhandel 
  Vattenfall Europe  Endesa Trading 
    Enercity Trade 
    EOS Avenis 
    GETEC Energie 
    MVV Energiehandel 
    NUON Energy Trade & Wholesale 
    RWE Trading 
    Trianel European Energy Trading 
More details on the actors can be found in attached appendix A.20. 
Chapter: Actor Analysis 

It is true that most of these actors have different interests and goals. However it is possible to consider them 
under groups –generators, consumers, traders, regulator, system operators and power exchanges. Their class 
interests  are  similar,  though  it  would  be  in  favor  of  their  own  citizens  or  industries.  The  next  section  would 
look at the interests of these groups. 

  99 
 
100  Flow‐based Market Coupling 
 

8.4 INTERESTS 
8.4.1 GENERATORS 
Generators wish to maximize their profits. It is possible to achieve in two ways – by volume or by price. Price is 
usually decided by the market (assuming little or no market power with the generators), and hence cannot be 
changed  at  will  by  the  generator.  Hence  most  important  measure  is  how  much  of  the  installed  capacity  is 
being utilized at any given instance. Another parameter that can be monitored is the producer surplus. 

8.4.2 CONSUMERS 
Consumers  can  also  be  categorized  further  into  domestic  and  industrial.  However  it  can  be  said  that  all 
consumers  want  the  price  of  electricity  to  be  low.  This  is  also  reflected  in  the  consumer  surplus,  but 
considering that perception also has a role to play in the consumer satisfaction it was decided to consider the 
change in price as the indicator for consumers preference towards a system. 

8.4.3 REGULATOR  
Regulator is a government agency committed to making energy markets work as effectively as possible. This 
entails safeguarding access to networks, maintaining sufficient transparency (access to essential information) 
and protecting  consumers against potential malpractices resulting from the (inherent) dominant position of 
providers.  Consumer  surplus  is  important  from  their  perspective  as  this  reflects  how  beneficial  the  energy 
markets are to the end consumer. 

8.4.4 GOVERNMENT 
The government has an high level goal of ensuring goodwill of people. They have to listen to both producers 
and consumers at the same time. At times these two goals contradict each other. However it was decided to 
consider net welfare as a measure of acceptance for a market method.  

Another  issue  that  government  is  concerned  with  is  the  correct  investment  signals.  When  a  flow‐based 
transmission  model  is  used  for  regional  capacity  allocation  purposes,  the  market  will  choose  the  most 
economically efficient cross‐border trades by itself. The flow‐based method will reveal, in a transparent way, 
the location of the limiting constraint. This facilitates an efficient investment foundation for the transmission 
infrastructures in the entire region. 

8.4.5 TRADERS 
From the market actor’s point of view, it is desirable to be able to trade with any other actor in any system and 
to rapidly react to changed market conditions. In cases with limited transmission capacity, knowledge about 
the  actual  transfer  capacity  and  consequences  for  own  decisions  are  required.  Such  information  should  be 
simple  enough  to  be  understood  without  too  detailed  knowledge  about  the  dependence  and  interactions 
between the transmission corridors 

8.4.6 TSO 
The TSOs define the available transfer capacity between regions before the market operators (MO) calculate 
the balance prices and exchange volumes. The given transfer capacities will therefore impact the output from 
the  activities  of  the  market  participants.  The  TSOs  are  constantly  under  pressure  to  give  as  much  transfer 
capacity as possible. Since the transfer limit calculations directly affect the market actors, the TSOs are to a 
larger extent requested to justify any limits. Different flow conditions may cause different system phenomena 
to be  limiting even  on the same set of lines. The  different transfer limits will  vary and  for an overall system 
optimization the set of limits cannot be calculated accurately in advance. With heavy power transfer between 
neighboring control areas, the consequences of incidents are more wide‐spread. System wide information is 
needed  for  transfer  limit  calculation  and  information  exchange  between  SOs  are  very  important  for  the 
quality of the results. 
 

8.4.7 POWER EXCHANGES 
The  power  exchanges  play  an  increasing  important  role  in  the  electricity  markets  post  liberalization.  True 
competition  can  only  be  introduces  if  all  market  participants  trade  energy  via  an  implicit  market.  The  main 
interest of PX is to maximize their profits by maximizing market participation and hence fostering liquidity. If 
the new system is likely to increase the inter‐country trade taking place via the power exchanges then it can 
be said that the PX would support it. The secondary aims of power exchanges are  

• increasing competition by creating price transparency and implementing the European single 
electricity market. 
• supporting the liberalization of the different European Electricity Systems 
• dealing with the issue of international trading, with special emphasis on providing a market solution 
to the congestion problems. 
TABLE 23 INTERESTS OF THE ACTORS AND THE QUANTIFYING/QUALIFYING PARAMETER 

Actors  Interest  Importance  Quantifying Parameter 

Generators  Profits  Minimization  of  cost  of  % change in producer surplus 


generation 
 

       % of installed capacity utilized 

Consumers  The electricity price    % Change in electricity price 

Regulator  For  a  more  fair  and  efficient  To ensure fair operation  % Change in Consumer surplus 


system  of market 

Government  Welfare of the citizens    % Change in Net Welfare 

Traders  Profit  To ensure that arbitrage  Complexity of system 


possibilities do not exist 

   Also they like complexity      

   More  risk,  more  opportunity      


to arbitrage and earn profits 

Power  Profits  through  maximization  Design  of  market  Liquidity 


Exchanges  of traded volume  algorithms 

     Facilitate  the  whole    


integration process 

TSO  System Security  Ensure  reliability  of  Security margin 


system 

       Method of calculation 
Chapter: Actor Analysis 

8.5 POSITION OF ACTORS 
The TSO, regulators, government, traders and consumers have already been covered in detail in the sections 
on interests and market structure. The other interesting players that need to be further detiled are PXs and 
the strategic generation companies. 

  101 
 
102  Flow‐based Market Coupling 
 

8.5.1 POWER EXCHANGES 
Currently  there  are  4  power  exchanges  in  North  West  European  region  –  one  in  each  country.  The  largest 
power  exchange  is  in  Germany  (EEX).  It  handles  both  spot  and  futures  market  for  electricity.  Belpex  is  the 
newest one of the lot. The start of the day‐ahead trade of electricity on Belpex started from 21st of November 
2006.  The  Powernext,  Belpex  and  APX  are  participants  in  setting  up  market  coupling  between  the  three 
countries. Integration of EEX would be crucial for success of FMC. The figure below details the current trades 
and prices on the four exchanges. 

APX NL
Spot Price Yearly Average (€/MWh):: € 57.3
Electricity Volumes [spot] (TWh): 19
NL

DE
Belpex
Spot Price Yearly Average (€/MWh): 46.0
Electricity Volumes [spot] (TWh): 1 EEX
BE Spot Price Yearly Average (€/MWh): 50.8
Electricity Volumes [forward] (TWh): 1044
Electricity Volumes [spot] (TWh): 89

Powernext
Spot Price Yearly Average (€/MWh): 47.2
Electricity Volumes [forward] (TWh): 83 FR
Electricity Volumes [spot] (TWh): 30

 
FIGURE 65 PRESENT POSITION OF THE POWER EXCHANGES 

8.5.2 GENERATORS 
The North‐West electricity market represents 1,1 million GWh of electricity consumption, 42% of the EU 25 
8
electricity  market .  There  are  many  generation  companies  in  operation  in  the  region.  The  detailed  list  and 
statistics  could  be  looked  up  in  the  previous  section  on  the  list  of  actors  or  the  appendix  A.20.  For  the 
regulator  and  the  government  of  Netherlands  it  is  important  to  understand  who  the  possible  monopolists 
would  be  in  the  regional  market  after  integration.  Hence  The  most  important  players  in  the  market  were 
identified and data was collected. 

TABLE 24 SHARE OF GENERAION COMPANIES IN THE TOTAL GENERATION WITHIN NORTH WEST EUROPEAN REGION 

Country  Firms  capacity  % share in  % share in four 


national market  countries 
    MWe     
         
Netherlands   E.ON Energie AG   1813  10%  0% 
  Electrabel SA   4563  26%  2% 
  Essent Energy Production BV   3305  18%  1% 
  Nuon (Reliant)   3578  20%  1% 
         
Belgium   Electrabel SA   12587  83%  6% 
         
                                                                         
8
http://www.ergeg.org/portal/page/portal/ERGEG_HOME/ERGEG_RI/ERI/Central-West
 

France   Comp Nationale Du Rhone   3068  3%  1% 


  Electricite de France  102089  90%  38% 
         
Germany   Berliner Kraft und Licht AG   1096  1%  0% 
  E.ON Energie AG   28743  24%  11% 
  ENBW Energie‐Versorgung  9360  8%  4% 
  Hamburgische Elec‐werke AG   4150  3%  2% 
  Neckarwerke Suttgart AG (NWS)  2181  2%  1% 
  RWE Energie AG   25625  21%  10% 
  STEAG AG   4302  4%  2% 
  Vattenfal Europe AG   11688  10%  4% 

 
FIGURE  66  MAIN  STRATEGIC  ACTORS  FOR  THE  NORTY‐WEST  EUROPEAN  REGION  (FROM  VATTENFALL  ANNUAL  REPORT 
2006) 

Looking at the above figures it is visible that EDF, E.ON, RWE, Electrabel and EnBW are the biggest players 
even  within  the  regional  markets.  Hence  is  was  important  to  look  into  the  detail  of  what  their  present 
situation  was  within  the  region.  The  next  section  would  detail  the  information  on  these  companies.  Essent 
was  also  considered  in  the  analysis  being  the  big  local  company  to  see  how  it  compares  with  the  bigger 
European giants. 

8.5.3 TSOS 
Using  the  PTDF  capacity  model  increases  planning  certainty  for  TSOs  and  creates  the  possibility  of 
distributing  cross‐border  capacities  following  the  submission  of  bids,  taking  into  account  the  willingness  to 
pay for power in the various zones and the load flows resulting from the market result. However at the same 
time they would be forced by the regulator and power exchanges to reduce the reliability margin. Hence they 
could be both for and against FMC. 

   
Chapter: Actor Analysis 

  103 
 
104  Flow‐based Market Coupling 
 

8.6 STRATEGIC GENERATORS  
 
TABLE 25 DETAILS ABOUT THE MOST STRATEGIC PLAYERS IN THE NORTH WEST EUROPEAN MARKET 

  E.ON   RWE   EnBW  


Country   Germany   Germany   Germany  
Listing info   Listed (free float: 85%)   Listed (free float: 67%)   Listed (EDF owns 45.01%)  
Electricity sales 2005,  404 (of which, Europe 367)   299   107  
TWh  
Number of customers,  Electricity: 22 Gas: 8   Electricity: 20 Gas: 10   Electricity: 5 Gas: 0.4  
millions  
Primary products   Electricity, gas (upstream,  Electricity, gas. (Water  Electricity, gas, (heat, 
downstream)   operations are being  waste, water)  
divested)  
Primary markets   Central and Eastern Europe, UK,  Germany, UK, Central and  Germany, Central and 
Nordic countries, Italy   Eastern Europe   Eastern Europe  
Strategies   • To be the world's leading  • Focus on electricity and  • Focus on core business  
power and gas company   gas   • Strengthen the German 
• Integrate and strengthen  • Focus on core markets   operations. Ambition to 
electricity and gas operations   • Divestment of water  be number three in 
• Expand in gas production   operations in the USA  German energy market  
• Organic growth   and the UK   • Advance positions in 
• Focus on new markets, such  • Organic growth  Central and Eastern 
as Russia and Italy  Europe  
• Focus on value creation 
 
 
  EDF   Essent  
Country   France   Netherlands  
Listing info   Listed in 2005 (85%‐owned by French state)   Unlisted  
Electricity sales 2005,  628   49  
TWh  
Number of customers,  Electricity: 40 (Of which, Europe 37)   Electricity: 2.5 Gas: 1.9  
millions  
Primary products   Electricity, gas   Electricity, gas, heat  
Primary markets   France, UK, Germany, Italy, Eastern Europe  Netherlands, Germany, Belgium  
(Asia, USA and Africa)  
Strategies   • Strengthen positions in Western and  • Aspiration to become a leading utility in 
Central Europe   northwestern Europe  
• Divest non‐core businesses (e.g., Brazilian  • Safeguard the company's independence 
assets)   and handle demands on transmission grid 
• Improve productivity and reduce costs   undbundling. (In early 2007, plans were 
• Invest in gas assets in order to be able to  announced for a merger with the Dutch 
offer customers both electricity and gas  company Nuon)  
• Look for collaboration with other 
companies in northwestern Europe, 
primarily in the Netherlands 
 
It would be important for DTE and the Dutch ministry of economic affairs to closely monitor the behaviour of 
EDF, E.ON, RWE, Electrabel and EnBW. The local company Essent is holding almost 20% of the local market 
though from a regional perspective it is a very small player.  
 

8.7 QUESTIONS RAISED BY THE ACTORS 
Also  during  discussions  many  questions  were  raised  by  the  involved  parties.  Which  though  have  not  been 
answered in the report are still worth mentioning here. 

8.7.1 REGULATOR  
• How would you calculate the transmission capacities, when 7 different TSO’s are involved? 
• What about the aspects of information exchange & Transparency? 
• The sensitivity of the system is very important. 
8.7.2 TSO 
• How  would  it  be  able  to  work  out  one  technical  model  when  7  TSO’s  with  different  standards  on 
information have to collaborate? 
• Would it lead to a more conservative estimate than the present margins? 
• What information is secret and what is open? One solution is creation of a supranational body that 
controls the system. 
• Going to one supra‐national TSO might jeopardize their existence 
• TSOs always want to maximize the reserve to be safe. Negotiations may be get one sided – if system 
is very sensitive to the information that TSO’s have monopoly over. 
• Wish  to  have  more  power  on  allocation  of  capacity.  Should  the  importance  of  Power  Exchange  be 
more or less? 
• Issues of uncertainty about the future 
8.7.3 POWER EXCHANGE 
• Currently PXs are partly owned by the TSOs, would it be still feasible under FMC? 
• Is there a need of a central auction office as suggested in OMC? 
• If there is a central office, what happens to their existence? 

8.8 RESULTS FROM FMC 
The  final  section  of  the  actor  analysis  chapter  would  populate  the  interests  matrix  that  was  composed 
previously  with  results  from  the  FMC  base  case.  The  FMC  base  case  was  already  discussed  in  detail  in  the 
chapters on methodology and results.  

TABLE 26 ACTORS PERCEPTION OF FMC 

Actors Quantifying Parameter Netherlands Belgium France Germany


Generators % change in producer surplus ‐29.18% ‐20.86% 3.52% 6.30%
% of installed capacity utilized 62.06% 68.64% 69.43% 62.24%
Consumers % Change in electricity price ‐15.85% ‐11.04% 1.74% 3.10%
Regulator % Change in Consumer surplus 1.56% 1.58% ‐0.53% ‐0.83%
Government % Change in Net Welfare 0.12% 0.09% 0.00% 0.01%
Traders Complexity of system
Power Exchanges Liquidity
TSO Security margin
Method of calculation  

As  can  be  seen  from  the  table,  the  Dutch  consumers,  regulators  and  government  should  be  pro  FMC.  The 
Chapter: Actor Analysis 

generators would lose some business due to cheaper imports from France and Germany. Belgium should also 
be  supportive  of  the  idea  as it  has  gained  in  almost  every  front.  In  France  there  was  a small  increase  in  the 
prices  (1.74%)  but  it  was  compensated  by  additional  income  from  exports.  The  net  welfare  gains  in  France 
remained almost zero. German generators would be supportive, and not the consumers – though there would 

  105 
 
106  Flow‐based Market Coupling 
 

be an microscopic positive change in the net welfare. The net welfare does not show such large change mainly 
because the gain to the consumers is compensated by loss to the producers and vice‐versa. 

At the same time it must be noted that FMC of ETSO‐Europex proposal, offer more security to the producers 
and consumers since the implicit auction mechanism will  ensure congested  lines to  be fully utilized. On the 
other  hand,  explicit  auctions  of  “options”  of  international  exchange  flows  do  not  offer  the  same  security  to 
TSOs,  since  the  owner  of  the  “options”  can  decide  at  the  last  moment  not  to  use  it.  Hence  from  this 
perspective FMC should be favored by all producers, consumers and TSOs. 

8.9 CONCLUSIONS 
In  the  conclusion  it  can  be  said  that  the  negotiation  arena  is  very  complicated  with  large  number  of  actors. 
Multiple  actors  with  varied  interests  and  the  system  under  consideration  is  complex  –  hence  it  would  be  a 
problem  to  get  everyone  to  agree  on  any  issue.  The  most  important  consideration  identified  was  that  of 
strategic behavior from large generation companies. The large French and German generators might be able 
to have monopoly position in the North West European region. It is important to check the behavior. Other 
important  aspect  is  of  co‐operation  between  the  7  TSO’s,  each  with  own  system  codes  and  standards.  The 
success of the implementation rests almost entirely on the success of the integration of the technical models 
– as PTDFs play a very important role in the convergence and results of the market. Also the technical model 
is required to calculate Fmax and Fref the most important constraints governing the market outcome. 

   
 

 
  Section 4: Market Design Issues 

  The final section of the report sums up 
the  research  by  identifying  and 
 
delineating  the  risks  and  issues 
  associated  with  implementation  of  a 
new  market  design  in  a  multi‐actor 
    setting.  The  main  focus  would  hinge 
around  the  institutional  and 
informational aspects 

Chapter: Actor Analysis 

  107 
 
108  Flow‐based Market Coupling 
 

   
 

9 MARKET DESIGN ISSUES 
 

Although,  ETSO  and  EuroPEX  agreed  on  FMC  as  one  way  of  cross‐border  congestion  management,  the 
proposal provides a list of still outstanding issues, such as the development of a simplified transmission model 
and  its  consequences,  the  development  of  the  coordinating  algorithms,  the  definition  of  performance 
measure  etc.  There  is  need  to  dig  further  into  what  we  do  not  know  and  what  we  need  to  know  aspect  of 
market  design  like  FMC.  Having  answered  some  of  the  economical  and  technical  questions  in  the  previous 
chapters  now  the  focus  is  shifted  towards  looking  more  at  the  issues  that  need  to  be  addressed  in  case 
government decides to go ahead with FMC. 

9.1 LEGAL AND ORGANIZATIONAL ISSUES 
Implementing  any  sound  market  based  mechanism  in  coupling  separate  markets  raises  some  crucial 
9
organizational and legal issues whose answers are necessary prerequisites : 

• Compatible legal framework must be enforced in each market to be coupled in order to ensure fair 
th
conditions to all players (11  Florence Forum requirement for Switzerland) 
• China  walls  must  be  installed  in  every  remaining  vertically  integrated  firm  (especially  with 
large German producers and French behemoth EDF) 
• Non  discriminatory  behavior  of  TSOs  and  MOs(PXs)  must  be  guaranteed  and  externally 
audited 
• The discrepancies of the current transparency of each market to be coupled must be reduced 
• To  avoid  the  apparition  of  “gaming”  opportunities  for  the  better  informed  market  actors, 
the market transparency must be levelised in the whole integrated market. For more refer 
to chapter on actor analysis. 
• To  improve  the  use  of  interconnectors  and  reveal  market  prices  (or  one  common  price, 
when the interconnectors are not congested) reflecting the actual situation of the electrical 
system,  the  publication  of  information  has  to  be  improved  and  harmonized  as  regards 
notably: 
• Access grid data: Forecasted interconnection capacities, forecasted and real‐time load 
level 
• Generation  data:  Forecasted  availability  of  generation  units,  actual  generation  by 
market time unit 

9.2 TECHNICAL ISSUES 
Implementing  the  ETSO/EUROPEX  model  raises  some  important  technical  issues  that  will  take  time  to  be 
fully solved: 

•  The insufficient coordination between TSOs 
• The  global  approach  model  to  determine  the  capacities  requires  a  very  strong  operational 
coordination  and  a  very  detailed  information  exchange  process  between  all  the  involved 
Chapter: Market design issues 

TSOs (technical systems actually exist but are they fully used?) 
•  The determination of the PTDFs matrix 
• What is the optimal zonal segmentation of the regional network? 
•  The interaction between TSOs and PXs 

                                                                         
9
http://ec.europa.eu/energy/electricity/florence/doc/mini_fora/milan/cre_issues.pdf

  109 
 
110  Flow‐based Market Coupling 
 

• It  is  not  yet  demonstrated  how  it  can  work  in  order  to  guarantee  simultaneously  efficient 
trade and operational safety of the grid 
• The determination and the operational working of the PXs’ clearing algorithm 
• Harmonization of the respective time schedules for bidding, harmonization of the respective 
PX’s legal statute, etc. 
• If  more  than  two  PXs  are  involved,  the  complexity  of  the  clearing  algorithm  is  strongly 
increased (cf. Belpex project with 3 PX) 
• The current unequal level of liquidity of the existing PXs 
• In some regions, almost all the market players expressed their strong  concerns about  the potential 
impact  on  the  wholesale  PXs  prices  of  allowing  PXs  to  manage  suddenly  a  large  amount  of 
interconnection capacities 

The most recent ETSO paper (Regional Flow‐based allocations State‐of‐play, March 2007, www.etsonet.org) 
has outlined the following issues in its paper: 

9.3 MARKET RELATED ISSUES 
9.3.1 TRANSPARENCY TOWARDS THE MARKET 
In an NTC‐based allocation mechanism, an Available Transmission Capacity (ATC) is given to the market, and 
the  market  actors  send  their  bids  for  parts  of  this  capacity  to  the  allocation  entity.  In  case  of  flow‐based 
allocation,  there  is  no  such  thing  as  an  ATC  between  two  control  areas.  What  is  available  is  the  maximum 
allowable flow on certain branches (Fmax) and an estimate of the flow that is already present at those branches 
prior  to  the  allocation  (Fref).  Although  evolving  from  an  NTC‐based  market  coupling  to  flow‐based  market 
coupling is rather smooth for market participants (they are still buying energy from and selling energy to their 
local  power  exchanges),  this  is  a  completely  different  situation  when  evolving  from  NTC‐based  explicit 
auctions towards flow‐based explicit auctions. In fact, the main challenge  of flow‐based allocation  is to find 
the proper balance between safeguarding the network security on the one hand and facilitating the market, 
by providing a transparent allocation mechanism, on the other hand. 

9.3.2 ECONOMIC SIGNALS TO MARKET PARTICIPANTS AND SHARING OF CONGESTION INCOME 
Market  actors  with  commercial  exchanges  between  two  adjacent  control  areas  with  uncongested  tie  lines, 
can  contribute  to  congestions  somewhere  else  in  the  grid.  One  of  the  main  advantages  of  flow‐based 
allocation in a regional setting, is that this effect is taken into account during the allocation phase. In this way, 
low‐priced bids between two control areas of which the interconnections are not congested have to compete 
with,  amongst  others,  the  high‐priced  bids  between  two  control  areas  with  congested  interconnections, 
according to their contribution to the congestion. 

9.3.3 LIABILITIES OF TSOS AND POSITION OF INDIVIDUAL REGULATORY AUTHORITIES  
In  principle  (given  the  physical  laws  of  the  system)  any  commercial  transaction  will  use  capacity  on  each 
interconnection of the interconnected system. Virtually, one could imagine that if a certain TSO offers 0 MW 
(or an unrealistically low capacity) on some interconnections in order to cope with congestions in its Control 
Area  or  on  its  interconnections,  all  additional  transactions  in  the  whole  region  and  all  capacities  would  be 
blocked  simultaneously.  Appropriate  revenue  distribution  methods  among  TSOs  and  proper  political, 
regulatory, and TSO coordination should prevent such situations to occur. 

9.4 TECHNICAL IMPLEMENTATION ISSUES 
9.4.1 REGIONAL  BASE CASE 
To calculate the flow‐based  parameters (PTDF, Fmax, Fref)  as accurately as possible, a common model of the 
grid,  with  predicted  generation  and  load  should  be  prepared.  A  part  of  the  maximum  allowed  flow  on  the 
 

critical  branches  is  already  used  (i.e.  prior  to  the  allocation)  by  so‐called  already‐occupied  flows  that  can 
consist of the following components: 

• ‘natural  flows’  (cross‐border  physical  flows  that  will  always  occur,  even  when  there  is  no 
scheduled commercial exchanges between areas); flows that result from sources/sinks that 
are located in a single control area 
• commercial exchanges resulting from firm nominations in previous auction rounds 
• flows caused by exchanges between sources and sinks that are not located in the region that 
is participating in the flow‐based allocation 
• flows caused by exchanges between areas where the source is located in the region that is 
participating in the flow‐based allocation whereas the sink is outside, and vice versa.  

The base case should be representative for the situation/day/time at which the actual allocation should take 
place.  It  is  evident  that  there  is  a  lot  of  uncertainty  involved  in  creating  such  a  base  case.  To  quantify  this 
uncertainty, a thorough testing should be applied. 

9.4.2 PHASE‐SHIFTING TRANSFORMERS 
Some  of  the  phase  shifters  installed  at  his  moment,  or  to  be  installed  in  the  (near)  future,  are  applied  in 
interconnections.  Phase‐shifting  transformers  offer  the  possibility  to  control  the  active  power  flow  through 
the  interconnection  in  which  it  is  installed.  Naturally  this  has  an  impact  on  the  flows  in  the  vicinity  of  the 
phase  shifting  transformer  too.  Therefore,  the  flow‐based  parameters  (PTDF,  Fref)  are  influenced  by  the 
operation of phase shifters. In the 'classical' formulation of the flow‐based allocation, the allocated quantity is 
the only control variable to optimize the market value. A limited range of tap positions of phase shifters could 
be used as an additional control variable. 

9.4.3 NETWORK REPRESENTATION 
Currently  a  control  area  is  represented  by  a  single  node  that  is  connected  to  neighboring  areas  by  a  single 
cross‐border transmission link. It is evident that this is only a rough approximation of the physical reality. The 
translation of the grid in the representation that will be used during the flow‐based allocation is a key issue for 
the TSOs. The grid representation must be such that the network security is guaranteed, even in the case of 
contingencies,  but  still  results  in  a  transparent  mechanism  for  the  market  actors.  Thorough  testing  should 
reveal  for  the  TSOs  whether  a  chosen  grid  representation  in  the  flow‐based  allocation  is  sufficient  to 
safeguard the network security. 

9.4.4 GENERATION REPRESENTATION  
The  exact  distribution  of  generation  within  an  area  is  not  known  exactly  ex‐ante.  This  means  that  TSOs  or 
auction  offices  cannot  know  which  power  plant  will  be  used  to  serve  a  requested  capacity  towards  another 
area. This is one of the major sources of uncertainty when estimating and assessing future grid situations. 

9.4.5 DEFINITION OF FLOW‐GATE CAPACITY (FMAX) 
This issue is closely related with the network representation that has been chosen. In case that the network is 
represented as a single node that is connected to neighboring areas by a single cross‐border transmission link 
the  maximum  allowed  flow  between  two  price  areas  is  referred  to  as  border  capacity  (BC)  or  flow‐gate 
Chapter: Market design issues 

capacity.  Such  a  border  capacity  is  an  aggregated  value  and  has  no  direct  relationship  with  the  physical 
capacity of a transmission line. Hence computation of the Fmax is an issue. In present case the border capacity 
is the aggregated value of the cross‐border flows when maximum exchange between two neighboring, taking 
the n‐1 security into account, is applied.  

In case that a more refined  model, that allows multiple  nodes per TSO or control area, is implemented, the 


Fmax  on  the  critical  branches  interconnecting  those  nodes  can  be  made  explicit  therefore  adding  more 
accuracy and transparency to the system. 

  111 
 
112  Flow‐based Market Coupling 
 

9.4.6 TYPE OF BIDS 
In  a  market‐coupling  environment,  bids  for  the  purchase  or  sale  of  energy  refer  to  the  market  participant’s 
price area. In an explicit auction environment, in case of bilateral bids, the market participant specifies both 
the source and the sink. In case of a flow‐based allocation mechanism, in a regional setting, it is even possible 
that market actors specify a source and sink in, electrically, non‐neighboring countries. 

9.5 POSSIBLE SOLUTIONS 
The  legal  and  organizational  issues  need  to  be  resolved  by  dialogue  between  the  involved  countries.  One 
possible  solution  could  be  formation  of  a  supra  national  entity  (similar  to  the  one  proposed  by  Germany’s 
Open Market Coupling market design) that serves as auctioning office. Also to sort out the need of sharing of 
information and transparency between TSO’s there can be two solutions:  
• Setting  up  of  a  supra  national  entity.  It  would  be  an  effective  solution  however  may  not  be 
acceptable  to  the  TSO’s.  A  supra  national  entity  would  diminish  their  importance  and  might  in  the 
long run jeopardize their existence. However it is possible to implement this with clear cut discussion 
on duties and responsibilities at national and regional level. 
• Technology:  Information  technology  lowers  transaction  cost.  Recent  rapid  technological  advances 
should  be  able  to  settle  the  issue  of  complexity.  In  the  past  few  years,  rapid  developments  of 
advanced  metering,  two‐way  communications  and  Internet‐based  information  technologies  have 
clearly set the trend for lowering market transaction costs. Right technology solutions might be able 
to alleviate, if not completely solve the issue of information sharing and transparency. 
 
In conclusion it can be said that the shift from current system to the new system would not be easy, however 
considering the benefits it should be  worth it. Further  integration  plans with UK and  Norway would also be 
bolstered from this experience with integration with German market. 
   
 

10 CONCLUSIONS  
 

What  are  the  impediments  to  and  implications  of  implementing  Flow‐based  Market  Coupling  as  a 
Congestion Management Mechanism in the North West European Countries? 

Current research was undertaken to provide answer to the above mentioned question. The basic underlying 
mechanism of operation of FMC was studied – using a neo‐classical economic approach. Once the operation 
was understood a model was created to study its impacts on national and regional level. Then model was used 
to understand the effects on national and regional levels for different “what if “scenarios.  

The research hinged around development of decision support model which would enable the policy maker, in 
case of present research the Ministry of Economic Affairs of The Netherlands, to understand the implications 
of FMC to Dutch electricity supply.  

A decision‐support model for evaluating the “implications of” implementing Flow‐based Market Coupling for 
alleviating the issue of interconnector congestion among European countries was created as the outcome of 
research efforts. 

Second  part  of  the  question  was  on  understanding  “impediments  to”  implementing  FMC.  This  was  studied 
using the actor analysis and literature survey on market design. 

The conclusions are divided into sub sections to discuss each part individually: 

10.1 SYSTEM BEHAVIOR 
• How sensitive is the system for the choice of a specific set of PTDFs? 

PTDFs play an important role in the market outcome from the FMC. However calculation of PTDFs 
depends only on the topology of the network. UCTE is composed of the highly meshed system of 24 
European countries consisting of some 200,000 km of 400 and 220 kV lines. Installation of a new tie 
line between countries like NL and DE, have small impact on the topology of the system as a whole. 
Hence there is only a minor change on the PTDFs with installation of new tie‐line. Secondly, though 
the  markets  do  depend  on  the  PTDFs,  the  dependence  is  not  as  strong  so  as  to  get  affected  by 
change on PTDFs in its third decimal. Hence it is possible to be certain that the TSOs won’t be able to 
guide the market results. Markets could still be efficient, though PXs might be owned by TSOs, as in 
case of NL.  

• What is the effect of constraints on the system? Could it lead to a less optimal outcome with respect 
to optimizing market value? 
Fmax  has  an  important  role  to  play  in  the  market  coupling  algorithm.  Congestion  of  one  line  has 
impact  on  the  whole  region.  DE‐NL  tie  line  constraint  also  has  impact  on  the  welfare  gains  within 
Belgium and  congestion  on  BE‐FR tie‐line has impact on  welfare gain in NL. Though this issue was 
not  represented  in  the  simulations  that  well,  mainly  because  of  presence  of  one  low  price  country 
next  to  a  high  priced  country  (DE  for  NL  and  FR  for  BE).  However  it  becomes  more  and  more 
important to consider regional perspective for planning further investment in transmission capacity 
(section 7.4.2). The system could lead to less optimal outcomes compared to the hypothetical case of 
Chapter: Conclusions 

implementing FMC in the current situation only with very extreme low values for tie‐line capacities. 
With the current values, the outcomes lead to benefit for all countries, in terms of welfare. The prices 
were lowered significantly in NL and BE because of imports. There was a marginal increase in prices 
in FR and DE markets because of exports. 

  113 
 
114  Flow‐based Market Coupling 
 

Policy makers may want to reserve a minimum amount of capacity on certain flow gates with respect 
to  the  investments  they  made  regarding  those  flowgates  in  the  past  or  with  respect  to  security  of 
supply. It should be mentioned here that if countries reserve huge capacity on a certain flow gate – 
this might prevent other countries from importing as well (refer A.11.2). While at the same time drop 
of prices in their own countries might not drop as much, as there is no netting of flows on a reserved 
capacity. So reserving capacity on interconnector is not a good idea if the markets are working well, 
it disables the markets from performing well. 

• What will be the net benefit of future network investments on available interconnector capacity and 
the Dutch electricity price level? 

Tie line capacity has strong effect on the prices in a country. As was seen with installation of 2000MW 
on the DE‐NL border and BE‐FR border, the prices change is higher with installation of more capacity 
on  the  congested  tie‐lines.  However  it  was  also  noted  that  installation  of  additional  5000MW  has 
very  small  additional  benefit  for  the  region.  The  tie  line  is  not  fully  utilized  and  hence  is  not 
recommended. 

o What would be the effect on the price level within Netherlands? 

The prices drop till the capacity is increase to a little above 2000MW on the Dutch German 
border after which it does not have any significant effect anymore. 

o Would it lead to more transits and loop flows? 

Loop flows were not modeled implicitly in the model, so it is not possible to predict effect on 
them. It is not possible to resolve individual transit flows through the interconnectors, as the 
simulation  only  gives  the  net  sum  of  all  flows  over  the  interconnector.  However  the  net 
flows occurring over the interconnectors increase with increasing interconnector capacity – 
hinting  at  higher  transit  flows.  However  it  must  be  noted  again  that  transit  flows  are  not 
necessary  eating  up  the  capacity  ‐  with  FMC  they  also  ease  up  the  congestion  if  they  are 
flowing in opposite direction to the congestion. 

o How would the actors perceive this change? 

The  effect  of  net  capacity  is  different  of  different  actors.  The  generators  in  exporting 
countries  like  FR  and  DE  would  be  for  it,  and  so  would  be  the  consumers  in  importing 
countries.  Consumers  in  FR  and  DE  should  have  only  marginal  interest  in  the  issue  as  the 
price change for them is minimal. The generators in NL and BE would be concerned because 
of dropping prices and hence they might not be dispatched. 

10.2 SECURITY OF SUPPLY 
• What is the risk that FMC would lead to a net reduction of the import capacity? 

Import capacity as concept does not exist in FMC. Fmax is defined for each tie‐line, but it is possible to 
the  transactions  to  net  over  this  line  and  lead  to  higher  imports  than  what  Fmax  value  is.  It  is  not 
possible to answer this question on basis of the current research, as it requires also consideration of 
Fref..The data is required to answer these questions further; it depends on the long term (monthly and 
yearly) contracts and consideration of other natural flows that occur in the system. Further work with 
a more detailed model and  Monte‐Carlo simulation might be able to shed some light on this issue. 
(section 9.4.1)   

• How may FMC interfere with security of supply in the Dutch electricity system?  
 

Security  can  be  defined  in  terms  of  availability  and  reliability.  The  reliability  aspect  cannot  be 
answered from the present research – it depends on information sharing between PXs and TSOs in 
North  West  European  region.  However  it  is  possible  to  talk  about  the  availability  aspect.  As  seen 
from  all  simulation  results,  Netherlands  becomes  dependant  on  the  foreign  imports.  Hence  in  the 
long  term  high  priced  local  generators  would  either  have  to  shut  down  or  move  their  generation 
capacity  to  other  countries  –  FR  and  DE.  However  this  risk  of  dependence  can  be  mitigated  by 
diluting  dependence  on  one  particular  country.  Interconnections  with  Norway  and  UK  would 
mitigate the effect of market power from a single large exporting country. 

10.3 WELFARE EFFECTS 
• What could be the effect of such system on national welfare as the system optimizes regional welfare 
in terms of market value? 

It was seen in all the run cases that Net Welfare for each country goes up (except for marginal drop in 
France).  However  it  must  also  be  mentioned  here  that  the  objective  function  was  minimization  of 
total cost of generation and not net welfare. It is possible that results would change with a different 
objective function. Refer to section 7.2 Current Situation vs FMC. 

• What is the effect of the presence of four national systems on the distribution of the welfare for each 
of the four systems? 

The  effect  on  not  welfare  was  not  very  pronounced,  because  net  welfare  was  sum  of  increasing 
producer  surplus  and  decreasing  consumer  surplus  or  vice‐versa.  However  there  were  substantial 
changes  in  producer  and  consumer  surplus.  The  producers  in  exporting  countries  derived  surplus 
gains from FMC and so did the consumers in importing countries – compared to the current situation. 

• How  many  incentives  will  FMC  give  to  increase  electricity  production  from  renewable  energy 
sources? 

This is an important question to be answered; till date renewable technologies are expensive when 
compared to conventional methods of electricity generation. Even with extremely high carbon prices 
(€50  per  ton  –  which  is  extreme  compared  to  the  current  carbon  prices  which  are  hovering  at  less 
than a euro per ton) most of demand was satisfied by conventional sources. Though it does lower the 
dependence on polluting technologies like Lignite based condensation plants, effect on dispatch of 
renewable sources is very marginal. Hydro  is almost always dispatched, but it is not present within 
Netherlands. Wind is intermittent and cannot be described on this high level model. Bio‐mass based 
technologies  are  too  expensive  and  would  require  support  of  government  to  be  able  to  make 
profitable business.  

10.4 IMPLEMENTATION ISSUES 
• What is the effect on transparency? 

The  FMC  is  based  on  PTDFs  and  the  maximum  allowable  flow  on  certain  branches  (Fmax)  and  an 
estimate of the flow that is already present at those branches prior to the allocation (Fref).  

Although  evolving  from  an  NTC‐based  market  coupling  to  flow‐based  market  coupling  is  rather 
Chapter: Conclusions 

smooth  for  market  participants  (they  are  still  buying  energy  from  and  selling  energy  to  their  local 
power  exchanges),  this  is  a  completely  different  situation  when  evolving  from  NTC‐based  explicit 
auctions  towards  flow‐based  explicit  auctions,  especially  between  Germany  and  Netherlands,  and 
also on Germany and France border. In fact, the main challenge of flow‐based allocation is to find the 

  115 
 
116  Flow‐based Market Coupling 
 

proper  balance  between  safeguarding  the  network  security  on  the  one  hand  and  facilitating  the 
market, by providing a transparent allocation mechanism, on the other hand. 

The PTDFs need to be calculated by close cooperation of involved TSOs. PTDFs are not very sensitive 
to changes of an order of magnitude 1000MWs, hence it is not possible to impact them significantly 
single‐handedly  for  any  TSO.  PTDF’s  play  an  important  role  in  the  market  outcomes  and  hence 
should be closely guarded by the respective regulating authorities. 

From  transparency  point  of  view  –  the  authorities  should  request  publication  of  the  following 
parameters: 

a. Optimization  Parameters:  Publication  of  the  optimization  algorithm  details  namely  the 
objective  function,  constraints  and  process  for  resolution  of  non‐convergence  of  the 
optimization process. 
b. Prior  to  trade  publications:  Publication  of  PTDF  and  border  capacities  for  the  day  ahead 
trade 
c. Post trade publications: Publications of market outcomes from the day ahead market. 

• Would  some  kind  of  European  central  decision  making  unit  be  required?  (e.g.  to  decide  about  the 
distribution of capacity on the national borders). 

It is important to have higher degree of co‐operation between the involved actors. Hence it is a good 
option to form a central agency to take care of issues on the regional level. A central arena to address 
only the issue  of FMC can  be set up to  be able to address the issues  on national  level.  For decision 
making in complex networks – it is important to have a guiding authority to direct the negotiations. 

Overwhelmed with the complexity of the problem relative to the current understanding and success 
of the Market Coupling, the actors might fall into defensive positions and might not coordinate well. 
There is no common hierarchy to define an authority to set overall direction and resolve differences 
in such situation.  The first step of the agency would be to study in detail the impact and implications 
– which could be better performed with access to real data. Subsequently follow up with the ideas to 
address each issue that pops up from the analysis – like distribution of congestion rent, payment to 
the actors that make loss by partially taxing those who get the benefit. This way it would be possible 
to  earn  acceptance  from  all  actors  towards  FMC.  It  can  be  seen  that  theoretically  FMC  is  a  better 
system  at  utilizing  the  system,  and  hence  obstacles  to  its  implementation  need  to  be  resolved 
through  negotiation  and  collaboration  –  a  central  agency  solely  devoted  to  this  end  would  be  an 
intelligent move to speed up the process in a neutral and comprehensive way. 

• What about gaming opportunities because of strategic actors? 

There are large generation companies in France and Germany, which also own part of transmission 
lines.  They  own  significant  %  of  generation  while  considering  regional  generation  in  North  West 
European  region  (namely  Electricite  de  France,  E.ON  Energie  AG,  RWE  Energie  AG).  These 
companies  could  abuse  this  market  power  in  a  coupled  environment.  It  is  important  for  the 
regulatory  and  competition  agencies  to  observe  their  behavior.  It  is  also  imperative  to  decouple 
these companies from the transmission ownership to level the playing field.   

   
 

11 LIMITATIONS AND RESEARCH RECOMMENDATIONS 
 

The final chapter would discuss the limitations of the current study and possible areas that can be researched 
further. 

11.1 LIMITATIONS OF THE STUDY 
This  study  focused  on  the  impact  of  FMC  on  the  North  West  European  considering  the  effect  on  electricity 
prices, welfare and use of installed generation and tie‐line capacity. It aspired to offer answers to the effect 
that FMC would have on the various actors and on national and regional level. It also aimed to understand the 
network of actors that would be affected by implementation of this system. It aimed to give study whether 
FMC  would  deliver  what  it  promised  and  what  the  possible  caveats  may  be.  However  there  were  issues  of 
information. It is not possible to get detailed information on many aspects of the mode – as the information is 
not public. Cost of generation data required for obtaining the supply curves is considered as classified, as their 
bidding behavior depends on it. Information of Fmax and Fref  is not calculated or published yet. The PTDFs are 
also  not  available  from  the  public  source.  Even  the  data  on  demand  and  supply  that  is  available  is  highly 
volatile  within  every  time  frame  –  be  it  within  a  day,  varies  from  season  to  season  and  from  country  to 
country. Hence, during the deployment of this study required making several assumptions. Second issue was 
the  available  time  at  hand;  in  the  short  time  available  for  the  study  it  was  only  possible  to  cover  certain 
aspects and not all.  These assumptions led to several limitations, and have been mentioned within the model 
methodology section. 

The  whole  analysis  was  based  on  average  behavior  of  the  system.  It  was  important  as  the  general 
observations cannot be based on one set of demand and supply bids and offers. The results are variable and 
volatile  –  using  such  analysis  could  not  have  provided  the  insights  that  were  required.  The  model  does  not 
give exact results for the markets. The objective function that was used was minimization of generation cost 
and not maximization of net welfare – though both aim towards a similar aim, i.e. maximization of consumer 
surplus. It is possible that real results may vary from those of the model.  

It is also important to note that there are two parameters that need to be considered before making decisions 
–  mean  behavior  and  variance.  Though  mean  behavior  was  studied  in  the  report  and  it  gives  insights  into 
operation  of  the  markets,  there  were  no  discussions  of  the  range  or  variance.  Basing  the  policy  on  mean 
behavior is not recommended, as depicted in the quote below 

“Consider the case of the statistician who drowns while fording a river that he calculates is, on average, 
Chapter: limitations and Research recommendations 

three feet deep. If he were alive to tell the tale, he would expound on the “flaw of averages,” 

‐ Sam Savage, Consulting professor at Stanford University 

Though behavior of system could be understood by assuming averages, it is also true that FMC can give very 
different  solutions  for  different  values  as  seen  in  the  analysis.  Hence  there  is  a  need  to  further  understand 
these effects for all possible variations in of the variables that affect the market output. 

11.2 RESEARCH RECOMMENDATIONS 
Since the scope of a project  is always limited, several proposals can  be made  for the future  continuation  of 
this project. 

• Research further with real data from the agencies. 
• Dynamic simulation of the system to obtain the median and mean results from the markets. 

  117 
 
118  Flow‐based Market Coupling 
 

• Study of the variance and volatility which occur in the results for variation in the input variables. 
• Investment analysis using the cost data that is available to study how investment decisions on future 
generation capacity would be affected by FMC. 
• A detailed actor analysis 

   
 

 
 

A APPENDIX 
   

Chapter: Appendix 

  119 
 
120  Flow‐based Market Coupling 
 

   
 

A.1 COST OF ELECTRICITY GENERATION MODEL 

 
FIGURE 67 THE COMMON DATA FOR COST OF ELECTRICITY 

 
FIGURE 68 FIXED COST DATA FOR ELECTRICITY GENERATION 

 
2  Flow‐based Market Coupling 
 

FIGURE 69 VARIABLE COST DATA FOR ELECTRICITY GENERATION ALONG WITH EMISSION COSTS 

 
TU Delft  3 
Flow‐based Market Coupling 
 

 
FIGURE 70 FORMULATION FOR THE CAPITAL COST CALCULATIONS 

 
4  Flow‐based Market Coupling 
 

 
FIGURE 71 FORMULAITON OF THE VARIABLE AND TOTAL COST 
 

A.2 DATA SOURCES AND ASSUMPTIONS FOR COST OF ELECTRICITY GENERATION 
MODEL 
 

TABLE 27. TOTAL COST OF GENERATION FOR DIFFERENT TECHNOLOGIES BASED ON VATTENFALL 2006. 

Total  cost,  3.7‐4.4  4.4‐6.6  Hard coal: 5.0‐5.6 


€ cents/kWh  (4,4‐6,6)  BLignite: 4.9‐5.5 
  Nuclear power  Hydro power  Coal condensing 
(hard coal, lignite) 
Advantages  • Good fuel  • High efficiency  • Good fuel availability from 
availability  • No emissions to air or  politically stable regions and 
• No CO2 emissions  water  an effective world market for 
in electricity  • Water (and thus  hard coal. The world's coal 
generation  energy) can be stored  reserves are expected to last 
• Easy to regulate  at least 250 years 
generation 
Disadvantages  • Long construction  • Highly dependent on  • Relatively long construction 
time and high  water supply  time 
technological  • Major intrusion on  • High environmental impact, 
complexity results  nature that changes  mainly through CO2 
in high cost of  landscape  emissions. Lignite CO2 
capital  • Few exploitation  emissions are roughly 30% 
• Safety concerns  objects  higher than for hard coal 
• Final storage of  • High investment cost 
spent nuclear fuel is 
an unsolved issue in 
many countries 

Cost example*  Generation capacity:  Generation capacity:  Generation capacity: 700 MW 


1,600 MW Annual  Small scale: up to 10 MW  Annual generation Hard coal: 
generation: 12 TWh  (in EU) Large scale: up to  4.2 TWh Lignite: 5.25 TWh 
440 MW Normal 
generation: approx. 4,000 
hrs/year 
Fixed  cost,  mainly  3.2‐3.9 (incl. tax on  4.4‐6.6 incl. tax,  Hard coal: 1.9‐2.3 (incl. 
cost  of  capital,  €  nuclear capacity of  operation and  operation and maintenance) 
cents/kWh  0.4)  maintenance  Lignite: 2.0‐2.6 (incl. operation 
and maintenance) 
Variable  cost  (mainly  0.5  0  Hard coal: 3.1‐3.3 
fuel,  including  CO2  (incl. cost for final  (No value has been  Lignite: 2.9‐2.9 
emission  allowances,  storage of 0.2)  assigned to the so‐called 
€ cents/kWh)  water value) 
 

Total cost,  5.6‐6.5  6.0‐6.6  7.3‐9.1 


€ cents/kWh 
  Natural gas combined  Combined heat and  Wind power 
cycle  power from biofuels 
Advantages  • Lower environmental  • Low environmental  • No emissions to the air 
impact and higher  impact from large,  or water 
efficiency than coal  modern facilities 
and oil  • CO2‐neutral 
• Low investment cost 

 
6  Flow‐based Market Coupling 
 

Disadvantages  • Concerns over fuel  • The market for biofuels  • Higher need for 


availability (the largest  is still undeveloped in  balancing power due to 
reserves are in  many countries, and  the unpredictability of 
politically unstable  conflicts with other  wind‐based electricity 
regions)  uses for the fuel can  generation 
• High and  arise  • Stability of the 
unpredictable fuel cost  • Particle emissions from  electricity grid can be 
(major price  poorly equipped  adversely affected with 
fluctuations)  facilities  a high share of wind 
• Environmental impact  power in the system 
(emissions of CO2,  • Requires subsidies 
among other things)  • Landscape aesthetics 

Cost example*  Generation capacity: 400  Generation capacity: 30  Generation capacity: 110 


MW   MW electricity and 80 MW  MW Annual generation: 
Annual generation: 2.4  heat Annual generation:  0.33 TWh Pertains to an 
TWh  0.14 TWh electricity and  offshore wind power farm 
0.36 TWh heat 
Fixed cost, mainly  1.1‐1.3  4.6‐5.1  7.3‐9.1 (including 
cost of capital, €  maintenance costs of 
cents/kWh  approx. 1.7) 
Variable cost (mainly  4.5‐5.2  1.4‐1.5  0 
fuel, including CO2 
emission allowances, 
€ cents/kWh) 
 

Data Sources

Cost of electricity technologies

Nuclear EU POLICY AND CARBON EMISSION TRADING:


Natural Gas
Combined
Cycle IMPLICATIONS FOR THE ENERGY MARKET
Hard Coal
Condensation
Lignite
Condensation Risto TARJANNE
Wind Lappeenranta University of
Technology

Federal Energy Regulatory Commission, FERC Form 1, "Annual Report of Major Electric
Hydro Utilities, Licensees and Others."

Oil Projected costs of generating electricity 2005 update book


CHP Natural
Gas

Hoogwijk, M., D. van Vuuren, et al. (2007). "Exploring the impact on cost and electricity
production of high penetration levels of intermittent electricity in OECD Europe and the
CHP Biomass USA, results for wind energy." Energy 32(8): 1381-1402.
TU Delft  7 
Flow‐based Market Coupling 
 

Installed Generation Capacity

Own
calculations
based on UCTE SYSTEM ADEQUACY: 2007 - 2020 FORECAST
http://www.iaea.org/inisnkm/nkm/aws/eedrb/data/NL-elic.html

CO2 Emission Data


Projected costs of generating electricity 2005 update book

Comparative Data for Validation

http://www.vattenfall.com/annual-reports/vf_com/2006/filter.asp?filename=page_013.html
Wietze et al.(2006)

Assumptions

Cost
1. Fixed cost os all CHP plants is same
2. Variable cost from CHP plants is same as the variable cost of normal plants based on the same fuel type
3. Variable cost for CHP-G, CHP-O and O are based on proportional increase in the data for 2000 based
on W. Lise et al, Energy Policy 34 (2006)
4. Oil prices have almost doubled since 2000, hence the data from W. Lise et al, Energy Policy (2006) was
doubled to get the variable cost data for oil based plants
5. The variable cost range and the fixed cost range for oil are then back calculated from the Total Cost data
and the variable cost data
6. CHP natural gas and CHP oil have similar fixed cost structure as the natural gas combined cycle.

Capacity
1. Based on installed generation in each country on the 3rd Wednesday for the month of July in year 2007.
2. The distribution into CHP is not mentioned in the UCTE adequacy database, hence it is based on the W.
Lise et al, Energy Policy 34 (2006). Assuming that more growth has taken place in CHP
generation since 2001 - it was assumed that the data for conventional plants stayed at the same level as
2001. Using this assumption the remaining data could be calculated
3. Oil and mixed-oil and gas plants were assumed to have cost profile of the fuel oil based plants
4. The non-attributable sources of generation under the fossil fuel geeneraion were added to the Hard Cola
Condensation plants capacity.
5. Renewable sources other than wind were assumed to be the CHP-Biomass based plants.
6. CHP-Oil data was used from W. Lise et al, Energy Policy 34 (2006)
7. All Gas based plants, i.e. combine, closed and open, were assumed to follow the cost structure of a
combined cycle plant.
 

   

 
8  Flow‐based Market Coupling 
 

A.3 NATIONAL SUPPLY CURVES 

 
FIGURE 72 DATA POINTS FOR THE MERIT CURVE (SUPPLY CURVE) 

NL Supply Curve

€ 80.00
y = 3.183x
R² = 0.831
€ 70.00

€ 60.00
Price (euros/MWh)

€ 50.00

€ 40.00

€ 30.00

€ 20.00

€ 10.00

€-
0.00 5.00 10.00 15.00 20.00 25.00

Generation Capacity (GW)


NL Supply Curve Linear (NL Supply Curve)
 

FIGURE 73 SUPPLY CURVE FOR NETHERLANDS 
TU Delft  9 
Flow‐based Market Coupling 
 
BE Supply Curve
€ 80.00

€ 70.00 y = 4.217x
R² = 0.829
€ 60.00
Price (euros/MWh)

€ 50.00

€ 40.00

€ 30.00

€ 20.00

€ 10.00

€-
0.00 2.00 4.00 6.00 8.00 10.00 12.00 14.00 16.00 18.00

Generation Capacity (GW)


BE Supply Curve Linear (BE Supply Curve)
 
FIGURE 74 ELECTRICITY SUPPLY CURVE FOR BELGIUM 

FR Supply Curve
€ 80.00

€ 70.00 y = 0.392x
R² = 0.603
€ 60.00
Price (euros/MWh)

€ 50.00

€ 40.00

€ 30.00

€ 20.00

€ 10.00

€-
0.00 20.00 40.00 60.00 80.00 100.00 120.00 140.00

Generation Capacity (GW)


FR Supply Curve Linear (FR Supply Curve)
 

FIGURE 75 ELECTRICITY SUPPLY CURVE FOR FRANCE 

 
10  Flow‐based Market Coupling 
 

DE Supply Curve
€ 80.00

€ 70.00

€ 60.00
y = 0.452x
Price (euros/MWh)

R² = 0.788
€ 50.00

€ 40.00

€ 30.00

€ 20.00

€ 10.00

€-
0.00 20.00 40.00 60.00 80.00 100.00 120.00 140.00

Generation Capacity (GW)


DE Supply Curve Linear (DE Supply Curve)
 
FIGURE 76 ELECTRICITY SUPPLY CURVE FOR GERMANY 

 
 

 
FIGURE 77 EQUATION OF THE SUPPLY CURVES (LINEAR REGRESSION ON THE MERIT ORDER CURVES) 

   
TU Delft  11 
Flow‐based Market Coupling 
 
A.4 AVERAGE HISTORICAL MARKET PRICE OF ELECTRICITY 

 
FIGURE 78 DISTRIBUTION OF MCP FOR NETHERLANDS APX, YEAR 2006‐07 

FIGURE 79 DISTRIBUTION OF MCP FOR BELGIUM BELPEX, YEAR 2006‐07 

 
12  Flow‐based Market Coupling 
 

FIGURE 80 DISTRIBUTION OF MCP FOR FRANCE POWERNEXT, YEAR 2006‐07 

 
FIGURE 81 DISTRIBUTION OF MCP FOR GERMANY EEX, SEPTEMBER 06 – JUN. 07 

 
TU Delft  13 
Flow‐based Market Coupling 
 
TABLE 28 CONSOLIDATED MCP DATA FOR CENTRE WEST EUROPEAN REGION FOR 2006‐07 

   N  Mean  Std Dev  Range  Median  Mode  Q3‐Q1 

  Samples  €/MWh   €/MWh  €/MWh  €/MWh  €/MWh  €/MWh 

NL  4728  36.48  37.22  949.99  30.13  40  18.91 

BE  4765  35.38  38.32  949.99  30.21  30  17.92 

FR  2029  24.9  11.45  99.92  23.1  23.01  12.9 

DE  4271  38.89  19.8  263.73  35  20  25.65 

   

 
14  Flow‐based Market Coupling 
 

A.5 DEMAND WORKSHEET FROM MARKET MODULE 

 
FIGURE 82 DEMAND WORK SHEET VALUES 

FIGURE 83 DEMAND WORKSHEET FORMULATION 

   
TU Delft  15 
Flow‐based Market Coupling 
 
A.6 TIE LINE CAPACITIES 
 

Reference actual capacities of the tie‐lines without reliability margins (n‐1) and (n‐2) corrections 
       

Germany ↔ Netherlands   

 Tie lines    UN   Capacity [MVA]    Net Tie Line Capacity 


   kV  MVA  MVA 
 Conneforde ↔ Meeden    380  1320   
 Diele ↔ Meeden    380  1320   
 Gronau ↔ Hengelo    380  1,300   
 Gronau ↔ Hengelo    380  1,300   
 Rommerskirchen ↔ Maasbracht    380  1580   

 Siersdorf ↔ Maasbracht    380  1580  8400 


       
   Capacity restricted by phase shifting transformer in Gronau 
       

Belgium ↔ Netherlands   

 Tie lines    UN   Capacity [MVA]    Net Tie Line Capacity 


   kV  MVA  MVA 
 Zandvliet ↔ Borssele    380  450   
 Zandvliet ↔ Geertruidenberg    380  1476   
 Meerhout ↔ Maasbracht    380  1320   

 Lixhe ↔ Maasbracht    380  1320  4,566 


       
   Capacity restricted by phase shifting transformer in Borssele 
       
       
Maximum Allocable Capacity  3600 MW     
Long term contracts   1500 MW     
       
       

France ↔ Germany 

 Tie lines      UN   Capacity  Net Tie Line Capacity 


   kV  MVA  MVA 
 Vigy ↔ Uchtelfangen (RWE Net)    380  1170   
 Vigy ↔ Uchtelfangen (RWE Net)    380  1170   
 Muhlbach ↔ Eichstetten (EnBW)    380  1790   

 Vogelgrun ↔ Eichstetten (EnBW)    220  470  4600 


       
       

 
16  Flow‐based Market Coupling 
 

France ↔ Belgium   

Tie lines    UN  Capacity  Net Tie Line Capacity 


  kV  MVA  MVA 
 Chooz ↔ Jamiolle    220  290   
 Lonny ↔ Achene    380  1490   
 Avelin ↔ Avelgem    380  1350   

 Moulaine ↔ Aubange    220  330  3460 


       
   Limited by 220/150 kV transformer in Jamiolle, on 150 kV side 
 

TABLE 29 TIE LINE CAPACITY VALUES 

   Reverse Capacity  Forward Capacity 

   GW  GW 

BE‐FR  1.7  2.5 

BE‐NL  1.35  1.35 

DE‐FR  1.7  5 

DE‐NL  2.5  2.5 

  
 
Data Sources 

1. Website of Tennet, RTE, RWE, Elia and TSO auction website

    
TU Delft  17 
Flow‐based Market Coupling 
 
A.7 POWER TRANSFER DISTRIBUTION FACTORS FOR NORTH‐WEST EUROPEAN 
REGION  
 

PTDFs                        
                   

Sensitivity Matrix                    
                   
           NL→NL  BE→NL  FR→NL  DE→NL     
  BE  →  FR  0  0.196  ‐0.484  ‐0.244     
  BE  →  NL  0  0.804  0.484  0.244     
  DE  →  FR  0  ‐0.138  ‐0.272  0.107     
  DE  →  NL  0  0.196  0.516  0.756     
                   

PTDF Matrix                       
                   
                   
        Commercial Exchange          
           BE→NL  FR→NL  DE→NL  FR→BE  DE→BE  DE→FR 
  BE  →  FR  0.196  ‐0.484  ‐0.244  0.31  ‐0.44  0.24 

  BE  →  NL  0.804  0.484  0.244  0.31  ‐0.56  ‐0.24 

  DE  →  FR  ‐0.138  ‐0.272  0.107  ‐0.69  0.245  0.379 

  DE  →  NL  0.196  0.516  0.756  0.31  0.56  0.24 

  Physical Flow                
 
 
Data Sources  
Own calculation using PowerWorld using the model from (Qiong and Bialek 2005)   

 
18  Flow‐based Market Coupling 
 

A.8 ELECTRICITY DAY‐AHEAD MARKET MODULE 

A.8.1 CONSTRAINTS  
 
Flow Based Coupling Optimization Constraints 

             

 Constraint 1: Maximum flow through the tie‐line is less than the capacity 

             

Net Calculated 
    Backward Capacity      Forward Capacity 
Flow 

    GW    GW    GW 

  BE‐FR  ‐1.7  <=  ‐1.70  <=  2.5 

  BE‐NL  ‐1.35  <=  ‐0.77  <=  1.35 

  DE‐FR  ‐1.7  <=  0.49  <=  5 

  DE‐NL  ‐2.5  <=  2.50  <=  2.5 

             

 Constraint 2: Net Exchange should equal to zero. As there is no storage of electricity 

             

Average  Installed  Absolute 


    Net Exchange   
Demand  Generation  Exchange 

    GWh  GW  GW  GW   

  NL  ‐1.731485945  16.30  22.104  1.731485945   

  BE  ‐2.468514055  12.6  16.329  2.468514055   

  FR  0.797380188  79.4  116.36  0.797380188   

  DE  3.402619812  74  122.5862568 3.402619812   

Net 
  Net Exchange  0.00      8.4 
Exports/Imports 

  

A.8.2 OBJECTIVE FUNCTION 
 
Minimization of Overall Generation Costs 
 
 

A.9 ELECTRICITY DAY‐AHEAD MARKET RESULTS 

Equilibrium without Market Coupling  
             
Price and 
  Quantitiy     Surplus          
  GW  €/MWh  €/hr  €/hr  €/hr  € 
  Q*  P*  Consumer Surplus  Producer Surplus  Net Welfare  Cost of generation 
NL  16.30   €                        51.83    €            1,186,403.81    €                 422,447.10    €                    1,608,850.91    €                         422,447.10  
BE  12.60   €                        53.13    €            1,131,078.79    €                 334,745.46    €                    1,465,824.25    €                         334,745.46  
FR  79.40   €                        30.97    €            2,640,974.19    €              1,229,350.20    €                    3,870,324.39    €                      1,229,350.20  
DE  74.00   €                        33.45    €            1,884,908.00    €              1,237,576.00    €                    3,122,484.00    €                      1,237,576.00  
        Net Welfare   €               10,067,483.54    €                   3,224,118.76  
 

Market Equilibrium under flow based constraints after Market Coupling       
                   
Price and 
  Quantitiy           Surplus            
  GW  GW  €  €  €/hr  €/hr  €/hr      
Consumer  Producer  Net Welfare  Cost of 
  Qd  Qs  P'  P'  Welfare(FMC)  Welfare(FMC)  (FMC)  generation   
NL  16.75  15.02   € 47.77    € 47.77    €  1,253,510.43    €  358,855.69    €  1,612,366.13    € 358,855.69    
BE  13.16  10.70   €  45.10    €  45.10    €  1,234,552.22    € 241,186.19    €  1,475,738.40    €  241,186.19    
FR  79.15  79.94   €  31.18    €  31.18    €   2,624,152.32    € 1,246,256.67    €   3,870,408.99    €  1,246,256.67    
DE  72.65  76.05   € 34.38    €  34.38    €  1,816,831.37    €  1,307,232.14    €  3,124,063.52    €  1,307,232.14    
Net Welfare   €   Total Cost of 
  181.72  181.72        (FMC)  10,082,577.03    €  3,153,530.69   Generation (FMC) 
 

 
20  Flow‐based Market Coupling 
 

A.10 CAPACITY UTILIZATION RESULTS 
Reverse  Forward 
Reverse  Forward  Reverse Unused  Forward Unused 
  Reverse Flow  Forward Flow  Capacity  Capacity  Net Utilization 
Capacity  Capacity  Capacity  Capacity 
Utilization  Utilization 
  GW  GW  GW  GW  GW  GW       
BE‐FR  ‐1.7  2.5  (1.70)  ‐  0.00  2.50  ‐100%  0%  ‐100.00% 

BE‐NL  ‐1.35  1.35  (0.77)  ‐  (0.58)  1.35  ‐57%  0%  ‐56.93% 

DE‐FR  ‐1.7  5  ‐  0.49  (1.70)  4.51  0%  10%  9.76% 

DE‐NL  ‐2.5  2.5  ‐  2.50  (2.50)  (0.00)  0%  100%  100.00% 


 

   
TU Delft  21 
Flow‐based Market Coupling 
 
A.11 COMPARISON OF MARKET COUPLING WITH FLOW‐BASED MARKET COUPLING 
A.11.1 BASE CASE FLOW‐BASED MARKET COUPLING  

   

 
22  Flow‐based Market Coupling 
 

A.11.2 BASE CASE FLOW‐BASED MARKET COUPLING WITH NL RESERVING 1500MW ON DE‐NL BORDER  

 
TU Delft  23 
Flow‐based Market Coupling 
 
A.11.3 MARKET COUPLING   

A.11.3.1 C ONTRACT PATH :   C LOCKWISE  

 
   

 
24  Flow‐based Market Coupling 
 

A.11.3.2 C ONTRACT PATH :   A NTI  C LOCKWISE  

 
 
 

   
TU Delft  25 
Flow‐based Market Coupling 
 
A.11.3.3 C ONTRACT  P ATH :  DISTRIBUTION  (50   C LOCKWISE ‐50   A NTI  C LOCKWISE ) 
 

 
 
 
 
 
 

 
26  Flow‐based Market Coupling 
 

A.11.3.4 C OMPARATIVE  C APACITY  U TILIZATION  R ESULTS  


Base Case Flow‐based market coupling  Contract path: Anti Clockwise 

 
 

Contract path: Clockwise  Contract Path: Equal distribution 

   
TU Delft  27 
Flow‐based Market Coupling 
 
A.12 RESULT OF FMC AFTER INSTALLATION OF 5000MW OF COAL BASED POWER PLANTS IN NL 

   

 
 
 
 
 
   

 
28  Flow‐based Market Coupling 
 

A.13 RESULT OF FMC AFTER INSTALLATION OF 10,000 MW OF COAL BASED POWER PLANTS IN NL 

   

 
TU Delft  29 
Flow‐based Market Coupling 
 
A.14 RESULT OF FMC AFTER INSTALLATION OF 2000 MW TRANSMISSION CAPACITY BETWEEN DE‐NL 

   

 
 

   

 
30  Flow‐based Market Coupling 
 

A.15 INCREASE TIE LINE CAPACITY BETWEEN FR‐BE +2000MW  

   

   
TU Delft  31 
Flow‐based Market Coupling 
 
A.16 RESULT OF FMC AFTER INSTALLATION OF 5000 MW TRANSMISSION CAPACITY BETWEEN DE‐NL 

   

 
 

 
32  Flow‐based Market Coupling 
 

A.17 RESULT OF FMC AFTER INSTALLATION OF 10,000 MW TRANSMISSION CAPACITY BETWEEN DE‐NL 

   

 
 

 
TU Delft  33 
Flow‐based Market Coupling 
 
A.18 RESULT OF FMC AFTER INSTALLATION OF 2000 MW TRANSMISSION CAPACITY BETWEEN DE‐NL WITH PTDF FROM 5000 MW CASE 

   

 
 

   

 
34  Flow‐based Market Coupling 
 

A.19 EFFECT OF CARBON MARKET   
A.18.1 FMC RESULTS WITH EMISSION PRICE OF 15 €/TON OF CO2 

   

 
 

   
TU Delft  35 
Flow‐based Market Coupling 
 
A.18.2 FMC RESULTS WITH EMISSION PRICE OF 20 €/TON OF  CO2 

   

 
 

 
36  Flow‐based Market Coupling 
 

A.18.3 FMC RESULTS WITH EMISSION PRICE OF 30  €/TON OF  CO2 

   

 
 

 
TU Delft  37 
Flow‐based Market Coupling 
 
A.18.4 FMC RESULTS WITH EMISSION PRICE OF 50 €/TON OF  CO2 

   

 
 

 
 
 
 
 
 

 
 

A.20 LIST OF ACTORS 
A.19.1 NETHERLANDS 
 
• Transmission system operator 
o TenneT  is  since  1998  acting  as  TSO  for  the  Netherlands.  It  is  responsible  for  providing 
system services for the whole system and transmission services on the 220‐ and 280 kV‐level 
in the whole country. Transmission services on lower voltage levels are provided by some 20 
network  operators.  In  2004  TenneT  has  taken  over  the  transmission  service  of  a  regional 
network company and its aim is to become the transmission operator for all voltages above 
110kV. During 2005 the operational activities of the regional control‐centre of the acquired 
network were integrated in the national‐control centre of TenneT. 
 
• Main generators 
o The  main  generators  in  Netherlands  market  are  E.ON  Energie  AG,  Electrabel  SA,  Essent 
Energy Production BV, Nuon (Reliant). 
 
• Distributors 
o There  are  a  large  number  of  suppliers  of  electrical  energy.  However,  some  merging  has 
taken place among the distributors. The biggest suppliers on the moment are NUON, Essent 
and Eneco 
 
• Power Exchange 
o The  Amsterdam  based  APX  (Power  NL)  is  the  first  independent  internet  based  power 
exchange in  continental Europe. Since  May 1999 when  it  began, APX’s Day‐Ahead  Market 
has  provided  its  members  with  standardised  products  and  flexible  block  orders  to  sell  and 
purchase  electricity  in  the  Netherlands.  APX  also  offers  a  continuous  trading  facility  for 
Intraday  and  Strips  Markets  in  the  Netherlands.  APX  is  the  central  counterparty  in  all 
electricity  trades,  retaining  anonymity  for  all  members  throughout.  APX  also  offers 
benchmark data and provides industry indices. 
 
• Main traders & other players 
o A  very  important  player  is  the  Amsterdam  Power  Exchange,  which  operates  a  day‐ahead 
market and an adjustment market. Furthermore, some brokers are active and all producers 
and suppliers may act as trader, directly or via the APX. 
 
• Regulator 
o Dienst uitvoering en toezicht Energie (DTe) 
 

   

 
TU Delft  39 
Flow‐based Market Coupling 
 
A.19.2 BELGIUM  
 
• Transmission system operator:  
o The  high‐voltage  network  is  operated  by  ELIA,  an  independent  public  limited  company 
founded  in  June  2001  in  order  to  comply  with  the  federal  requirements  of  independence. 
ELIA  former  shareholders  (Electrabel  and  SPE)  reached  an  agreement  with  the  Federal 
Government on the shareholder structure. 
 
• Main generators 
o Electrabel (Net generation capacity: about 13 165 MW in Belgium) 
o SPE (Gen. capacity: 1 500 MW in Belgium) 
o RWE (from 2005 with 50% of 385 MW at BASF Antwerp) 
o Essent (from 2006 with 120 MW at INEOS Antwerp) 
 
• Distributors 
o The former distribution companies (mainly inter‐municipal companies) have been appointed 
as operator of the distribution network for their respective territory. In order to comply with 
the regional legal requirements, they transferred their sales activities to another company, 
when their customers will become eligible. 
 
o Number of distribution system operators 
ƒ Private companies 1 
ƒ Municipality companies 4 
ƒ Mixed Inter‐municipality companies(a) 15 
ƒ Pure Inter‐municipality companies 8 
 
• Power Exchange 
o Belpex (Belgian Power Exchange) is a day‐ahead spot exchange for the delivery and off‐take 
of  electricity  on  the  Belgian  hub.  Belpex  is  coupled  with  its  two  neighbours,  APX  in  the 
Netherlands  and  Powernext  in  France.    The  partners  of  Belpex  are  APX  (Dutch  Power 
Exchange),  Powernext  (French  Power  Exchange),  RTE  (French  Transmission  System 
Operator) and TenneT (Dutch Transmission System Operator), under the leadership of Elia 
System  Operator.  Endowed  with  a  3  million  euro  equity  capital,  Belpex  shares  are  owned 
initially by APX (10%), Elia (60%), Powernext (10%), RTE (10%) and TenneT (10%). Belpex is 
the  Belgian  Power  Exchange  for  anonymous,  cleared  trading  in  day‐ahead  electricity, 
providing the market with a transparent reference price. 
 
• Main traders & other players 
o Many 
 
• Regulator 
o Commission de Regulation de l’Electricite et du Gas (CREG) 
 
   

 
40  Flow‐based Market Coupling 
 

A.19.3 FRANCE  
 
• TSO 
o RTE 
o The single French  Transmission System Operator RTE is responsible for the operation  and 
maintenance of the French EHV and HV networks between 400kV and 63kV. 
 
• Main generators 
o The four main generating companies in France are: 
ƒ Electricité  de  France  (EDF):  Turnover  34400M€,  installed  capacity‐102GW, 
generation‐482TWh, employees‐117000, 
ƒ Energie  du  Rhône  (former  CNR):  Turnover  459  M€,  installed  capacity‐3GW, 
generation‐12,5TWh, employees 1060, 
ƒ Société Nationale d’Electricité et de Thermique (SNET): Turnover 810M€, installed 
capacity‐2,5GW, generation‐8,7TWh, employees‐1074, 
ƒ Société  Hydroélectrique  du  Midi  (SHEM):  Turnover  75M€,  installed  capacity‐
0,8GW, generation‐2 TWh, employees‐220, 
 
• Number of distributors 
o Based  on  the  French  Act  of  15  June  1906,  the  public  distribution  of  electricity  has  been 
placed  under  the  responsibility  of  local  territorial  administrations  (councils,  regions,  or 
public joint ventures). The management of these local public utilities has been either given 
to a public operator (today EDF for 93% of the local councils) or are managed directly by the 
local councils through communal subsidiaries, which may work together within syndicates. 
 
o Electricité de France (EDF) 
ƒ Turnover  electricity‐34400M€,  sales  in  distribution‐~316  TWh,  employees‐117000 
[80000 in the distribution sector], customers‐31000000 
 
o Beside  EDF,  there  are  in  France  22  municipal  distribution  companies.  The  4  main 
distributors are: 
ƒ Electricité de Strasbourg (ES) 
• Turnover  electricity‐~415M  €,  sales  electricity  ~6  TWh,  employees‐1363, 
customers‐435000 living in 376 communal entities 
ƒ Gaz et Electricité de Grenoble (GEG) 
• Turnover electricity‐59M€, sales electricity ‐8 TWh, employees‐448 
ƒ Usine d’Electricité de Metz (UEM) 
• Turnover  electricity‐135M€,  sales  electricity  ~1,7TWh,  employees‐500, 
customers‐140000, 
ƒ Vialis (Colmar) 
• Turnover  electricity‐53M€,  sales  electricity  –0,4TWh,  employees‐259, 
customers‐36650, 
 
• Power Exchange 
o The  introduction  of  a  power  exchange  (Powernext)  in  France  is  a  direct  response  to  the 
opening up of the European electricity markets. The 1996 European Directive, applied into 
the French Law on the 10th of February 2000, create an opportunity to launch a feasibility 
study  of  the  French  electricity  organised  market  for  partners  including  BNP‐Paribas,  ELIA 
(Belgium  Transmission  System  Operator),  EDF,  Electrabel,  RTE  (French  Transmission 
System Operator), Société Générale and TotalFinaElf under the leadership of Euronext . The 
conclusions of the one year study led to the incorporation of Powernext SA on 30/07/01. 
   
TU Delft  41 
Flow‐based Market Coupling 
 
 
• Main traders & other players (exchanges etc.) 
o The other actors selling to eligible customers on the French market are: 
ƒ Energie du Rhône‐ sales on the French market outside EDF‐1,5TWh 
ƒ RWE PLUS sales on the French market –1TWh 
ƒ ENDESA France sales on the French market‐ 0,6TWh 
ƒ Electrabel (via SHEM) sales on the French Market 2TWh 
ƒ CNR (Main shareholder Electrabel 49,97%)‐sales on the French Market 12,5TWh 
ƒ SNET (Main share holder Endesa 65%)‐sales on the French market 8,7TWh 
ƒ Total (via Gas and Power North Europe)‐sales on the French market 9,5TWh 
ƒ HEW (now Vattenfall Europe)‐sales on the French market 3TWh 
 
• Regulator 
o Commission de Régulation de l’Electrité 
 
 
 

   

 
42  Flow‐based Market Coupling 
 

A.19.4 GERMANY 
 

• Transmission system operator 
o 4 German Transmission System Operators bear responsibility for their control areas and the 
German system  
o (EnBW Transportnetz AG 
o E.ON Netz GmbH 
o RWE Transportnetz Strom GmbH 
o Vattenfall Europe Transmission GmbH 
 
• Main generators 
o Main generating companies are (A growing number of IPPs enter into the German market) 
ƒ RWE 
ƒ E.ON 
ƒ Vattenfall 
ƒ EnBW 
 
• Distributors 
o In Germany, there exist more than 900 Distribution System Operators. 
 
• Power Exchange 
o EEX 
o The European Energy Exchange AG (EEX) currently operates spot and derivatives markets in 
power, CO2 emission allowances, coal and gas. It is rapidly expanding its range of services 
with the aim of establishing EEX as Europe’s leading, multi‐product energy exchange. EEX is 
a  product  of  the  recent  liberalisation  in  energy  markets  and  is  already  Europe’s  biggest 
energy  exchange  in  terms  of  both  membership,  with  over  170  trading  members  from  19 
countries,  and  growth  in  trading  volume.  It  is  fully  regulated  and  can  already  claim  to  be 
truly  pan‐European,  with  the  majority  of  its  members  based  outside  Germany.  Traders’ 
confidence in EEX and its clearing system is underlined by the rapid growth in the volume of 
open interest in power futures ‐ more than 300 Terawatt hours in December 2006, valued at 
around € 17bn. 
 
 
• Main traders & other players 
o Citiworks,  E.ON  Sales  &  Trading,  EDF  Trading,  Electrabel  Deutschland,  EnBW  Ges.  für 
Stromhandel,  Endesa  Trading,  Enercity  Trade,  EOS  Avenis,  GETEC  Energie,  MVV 
Energiehandel,  NUON  Energy  Trade  &  Wholesale,  RWE  Trading,  Trianel  European  Energy 
Trading, Vattenfall Trading Services 
 
• Regulator 
o Bundesnetzagentur  für  Elektrizität,  Gas,  Telekommunikation,  Post  und  Eisenbahnen 
(BNetzA) 

 
   
TU Delft  43 
Flow‐based Market Coupling 
 
BIBLIOGRAPHY 
 

Averch,  H.  and  L.  L.  Johnson  (1962).  "Behavior  of  the  firm  under  regulatory  constraint."  The  American 
Economic Review 52: 1053‐1069. 
   
Bhattacharya,  K.,  M.  H.  J.  Bollen,  et  al.  (2001).  Operation  of  restructured  power  systems.  Boston,  Kluwer 
Academic Publishers. 
   
Borenstein,  S.  (2001).  The  trouble  with  electricity  markets  (and  some  solutions),  University  of  California  at 
Berkeley. 
   
Budhraja, V. (2003). "Harmonizing Electricity Markets with the Physics of Electricity." The Electricity Journal 
16(3): 51‐58. 
   
Chao,  H.  P.,  S.  Peck,  et  al.  (2000).  "Flow‐gate  Transmission  Rights  and  Congestion  Management."  The 
Electricity Journal 13(8): 38‐58. 
   
Christie,  R.  D.,  B.  F.  Wollenberg,  et  al.  (February  2000).  Transmission  management  in  the  deregulated 
environment. Proceedings of the IEEE. 
   
Congestion  Management  Guidelines  (2006).  amending  the  Annex  to  Regulation  (EC)  No  1228/2003  on 
conditions for access to the network for cross‐border exchanges in electricity. 
   
Conscentec and Frontier Economics (June 2004) Analysis of Cross‐Border Congestion Management Methods 
for the EU Internal Electricity Market.  Volume, 138 DOI:  
   
Crampes, C. and J. J. Laffont (2001). "Transport pricing in the electricity industry." Oxford Review of Economic 
Policy 17(3): 313‐328. 
   
Crew, M. A. and P. R. Kleindorfer (1985). "Governance Structures for Natural Monopoly." Journal of Behavioral 
Economics 14(0): 117‐140. 
   
Day,  C.  J.,  B.  F.  Hobbs,  et  al.  (2002).  "Oligopolistic  Competition  in  Power  Networks:  A  Conjectured  Supply 
Function Approach." IEEE Trans. Power Systems 17(3): 597‐607. 
   
De  Jong,  H.  M.  and  R.  A.  Hakvoort  (2007).  "Congestion  Management  in  Europe:  Taking  the  Next  Step.  9th 
IAEE  European  Energy  Conference  “Energy  Markets  and  Sustainability  in  a  Larger  Europe”,  June  10‐12, 
Florence, Italy. 
 
De Vries, L. J. and R. A. Hakvoort (2000b). "An Economic Assessment of Congestion Management Methods 
for Electricity Transmission Networks." Journal of Network Industries 3(4): 425‐466. 
   
Directive 96/92/EC Directive of the European Parliament and of the Council of 19 December 1996 concerning 
common rules for the internal market in electricity., Official Journal of the European Union. L 27: 20‐29. 
   

 
44  Flow‐based Market Coupling 
 

Directive 2003/54/EC European Parliament and of the Council of 26 June 2003 concerning common rules for 
the internal market in electricity and repealing Directive 96/92, (OJ 2003 L 176/37). 
   
EEA  (2006).  Greenhouse  gas  emission  trends  and  projections  in  Europe  2006.  Copenhagen,  European 
Environment Agency. 
   
ENERGY  SECTOR  INQUIRY  (2006).  EUROPEAN  COMMISSION,  Competition  DG;  Energy,  Basic  Industries, 
Chemicals and Pharmaceuticals; Energy, Water. 
   
ETSO (May 2006). An Overview of Current Cross‐Border Congestion Management Methods in Europe: 31. 
   
ETSO  and  EuroPEX  JWG  (2004).  Flow‐based  Market  Coupling  ‐  A  joint  ETSO‐EuroPEX  Proposal  for  Cross‐
Border Congestion Management and Integration of Electricity Markets in Europe. 
   
Gheorghe, A. V., M. Masera, et al. (2006). Critical Infrastructures at Risk. Dordrecht, Springer. 
   
Glachant,  J.‐M.  and  V.  Pignon  (2002).  Nordic  electricity  congestion's  arrangement  as  a  model  for  Europe  : 
physical constraints or operators' opportunism? [Cambridge, Mass.], Massachusetts Institute of Technology, 
Center for Energy and Environmental Policy Research. 
   
 
Harvey, S. M., W. W. Hogan, et al. (1996) Transmission Capacity Reservations and Transmission Congestion 
Contracts.  Volume,  DOI:  
   
Haubrich, H. J. and W. Fritz (1999). Study on Cross‐Border Electricity Transmision Tariffs. . Aachen, Germany. 
   
Hogan, W. W. (1992). "Contract networks for electric power transmission." Journal of Regulatory Economics 
4: 211‐242. 
   
Hunt, S. (2002). Making competition work in electricity. New York, John Wiley & Sons, Inc. 
   
Kirschen, D. S. and G. Strbac (2004). Fundamentals of power system economics London, Wiley, 2004  
   
Knops, H. P. A., L. J. De Vries, et al. (2001). "Congestion management in the European electricity system: an 
evaluation of the alternatives." Journal of Network Industries 2(3‐4): 311‐351. 
   
Lise,  W.,  V.  Linderhof,  et  al.  (2006).  "A  game  theoretic  model  of  the  Northwestern  European  electricity 
market‐‐market power and the environment." Energy Policy 34(15): 2123‐2136. 
   
OECD "Projected Costs of Generating Electricity 2005 Update ": 232. 
   
PJM (2006) Cost Development Guidelines. PJM Manual Volume,  DOI:  
   
Qiong, Z. and J. W. Bialek (2005). "Approximate model of European interconnected system as a benchmark 
system to study effects of cross‐border trades." Power Systems, IEEE Transactions on 20(2): 782‐788. 
   
Regulation  (EC)  No.  1228/2003  (2003).  "of  the  European  Parliament  and  of  the  Council  of  26  June  2003  on 
conditions for access to the network for cross‐border exchanges of electricity on conditions for access to the 
network  for  cross‐border  exchanges  in  electricity."  THE  EUROPEAN  PARLIAMENT  AND  THE  COUNCIL  OF 
THE EUROPEAN UNION L 176/1. 
   
Samuelson, P. A. and W. D. Nordhaus (2005). Economics. New Delhi, Tata McGraw Hill. 
   
Stoft, S. (2002). Power System Economics: Designing Markets for Electricity Piscataway (NJ), IEEE Press. 
   
UCTE (2007). UCTE System Adequacy Forecast 2007 ‐ 2020. Brussels, UCTE. 
   
TU Delft  45 
Flow‐based Market Coupling 
 
Vattenfall (2006). ANNUAL REPORT 2006. Stockholm: 122. 
   
Vries, L. J. d. (2004). Securing the public interest in electricity generation markets : the myths of the invisible 
hand  and  the  copper  plate  Faculty  of  Technology  Policy  and  Management.  Delft,  Delft  University  of 
Technology. Doctorate: 353. 
   
Yan, H. H. (1999). PTDF and TLR from a power marketer's perspective. 
   
 
Zhou, Q. and J. W. Bialek (2005). "Approximate Model of European Interconnected System as a Benchmark 
System to Study Effects of Cross‐Border Trades." IEEE TRANSACTIONS ON POWER SYSTEMS5 20(2): 7. 
   
 
 
   

 
46  Flow‐based Market Coupling 
 

WEBSITES 
 

www.wikipedia.com  
general reading on subjects of interest 

www.etso‐net.org 
Updates on TSOs and policy  

http://ec.europa.eu/energy/electricity/florence/index_en.htm 
Directives and regulations 

www.europex.org  
EuroPEX information 

http://ksghome.harvard.edu  
General information on latest research on electricity markets 

http://www.nordel.org  
Nord pool market; 
 
http://www.bundesnetzagentur.de/enid/27adb19a3f820ac2e4acd1a2a23b07ff,2a066e5f7472636964092d0934
343230/Special_topics/Open_Market_Coupling_32p.html  
Economic and legal analysis of congestion management methods in EU. 

http://www.vattenfall.com/annual‐reports/vf_com/2006/filter.asp?filename=page_013.html  
Vattenfall's Annual Report 2006 ‐ What does new electricity generation cost? 
 
http://www3.vattenfall.com/annual_report_2005/filter.asp?filename=page_011.html  
Vattenfall 2005 ‐ The European electricity market 
 
EEDRB‐Netherlands‐Installed Capacity of Electrical Plants 
 
http://epp.eurostat.ec.europa.eu/portal/page?_pageid=0,1136239,0_45571447&_dad=portal&_schema=PORT
AL  
EUROPA ‐ Eurostat ‐ Environment and energy 
 
http://www.ucte.org/  
[www.ucte.org] :: Home 
 
http://www.ucte.org/publications/library/e_default_2007.asp  
[www.ucte.org] :: Publications : Library : 2007 
 
http://www.apxgroup.com/  
TU Delft  47 
Flow‐based Market Coupling 
 
APX Group 
 
http://www.powernext.fr/modules.php?op=modload&name=PwnStat&file=index&req=stat&bid=129&cld1=1
31&cld2=132&cld3=‐1&graph=Day&graphtype=spot  
Powernext.fr 
 
http://ec.europa.eu/comm/competition/sectors/energy/inquiry/index.html  
EUROPA ‐ DG Competition 
 
http://www.dauphine.fr/cgemp/Equipe/CV/CVBoisseleauPUBLI.htm  
Dr François Boisseleau thesis on “The role of power exchanges for the creation of a single European electricity 
market: market design and market regulation” 

You might also like