Professional Documents
Culture Documents
Method Statement For Underground Piping & Puddles Installation
Method Statement For Underground Piping & Puddles Installation
7200040907-JWWF-GC-060 Rev 00
OWNER: MARAFIQ
P.O. # 7200040907
Owner/Client: MARAFIQ
P.O. # 7200040907
PROJECT: EXPANION OF IWTP-8 STAGE-4 DBO
OWNER: MARAFIQ
Table of Content
SECTION DESCRIPTION PAGE
1.0 PROJECT DESCRIPTION 3
11.0 TRAINING 27
OWNER: MARAFIQ
The Expansion project contract is based on a Design, Build and Operate (DBO) concept broken down into an Engineering,
Procurement and Construction (EPC) part and an Operation and Maintenance (O&M) part. The EPC project duration will be
for 36 months from Commencement Date, while the O&M period of the contract will be for 5 years from Initial Acceptance of
the Works from MARAFIQ.
For further details, refer Document No. MSCF-1-PC-057 Attachment D EPC Scope of Work of Contract
The SSEM will provide design and construction drawings, supervision of work, labor, construction plant and equipment,
materials, tools, Quality control and coordination to execute the works in accordance with the relevant design drawings,
Standards and specifications.
1.1.1 PURPOSE
This document describes the buried installation of Glass Reinforced Plastic pipes and fittings manufactured by Future Pipe
Industries (Vendor as Reference) It is to be used in conjunction with the Glass Reinforced Plastic Product Data, Method
statements, etc. and is intended to assist the installer in understanding the requirements and procedures for the successful
installation of Glass Reinforced Plastic pipes and fittings.
This manual shall be carefully read by the Contractor responsible for laying the pipe as well as the pipeline Design
Engineer. This information should be considered as a guide. The Engineers or other personnel involved in pipeline design
or laying shall establish by themselves the procedures best suited to the actual site conditions. Sound engineering
practices should always be followed.
1.1.2 SCOPE
This Method Statement is applicable to Expansion of IWTP-8 Stage-4 DBO Project. This document address the usual
circumstances that may be encountered in the field. Unique situations requiring special considerations are not addressed
and should be resolved in coordination with the manufacturer.
Instructions in this document are complete to the extent possible. However, Future Pipe Industry’s experienced
Representatives or Engineers can opt for an alternative or optimum solution for the issues not addressed in this document.
The scope can be used for all types of underground piping under this project but not limited to GRP piping only. Reference
shall taken from project IFC drawings. The Latest techniques, industry standards and sound engineering practices shall
always be followed.
Future Pipe Industries Engineers or Representatives shall be consulted for any clarifications or statements made in this
document.
Definition of words used in these instructions:
- The word “shall” indicates a requirement.
- The word “should” indicates a recommendation.
OWNER: MARAFIQ
(Vendor to be confirmed) will provide the Field Services for the Fiberglass Piping system to the Client on a full-time basis
throughout the agreed duration in the Client's purchase order.
The Field Service Representative is made available to validate the work executed by the Client in the following areas:
handling, storage, bedding, laying, jointing, backfilling, and site testing procedures necessary to achieve a satisfactory
installation of the Fiberglass system supplied by vendor, are following the applicable guidelines at the time of installation.
The Client's responsibility is to make available the documents listed in this scope package to its installation crews and
ensure that they are familiar with these documents and their contents.
The Installation Contractor should also consider any supplementary Installation Instructions published for specific
applications not covered in this document as valid documents for the work execution.
It is the responsibility of the Contractor to follow and implement the published installation instructions, manuals, and any
additional advice given verbally or in writing by the Field Service Representative.
Any failures occurring on-site related to installation, from a client's failure and/or its Contractor, a subcontractor, to follow
and implement the company's written installation instructions and any additional advice or recommendations given by the
company's field Service Representative. It is explicitly agreed by the Client that the role of vendor representative is strictly
to validate that the work executed by the Client is in line with the standard procedures of vendor, applicable at that time. By
placing an order for a Field Service Representative, the Client explicitly accepts the role and responsibility of the vendor
Field Service Representative as defined herein.
All work done in the scope of contractor will be executed in accordance, but not limited, with the following documents. Where
specifications are not clear or covered by these documents the client will be informed and applicable documents will be
provided by the client in order to have clarity on requirements that should be achieved.
• ASTM D1586 Standard Method for Penetration Test and Split Barrel
Sampling of Soils
• AWWA C950 Standard Specification for Fiberglass pipes
• AWWA-M45 MANUAL FIBERGLASS PIPE DESIGN
• ASTM D2487 Classification of soil for Engineering Purpose
OWNER: MARAFIQ
• BS8010 Part 2.5:89 Pipe Lines on Land-Design Construction & installation of GRP
pipelines
• BS8010 part 3:93 Pipe Lines-Sub- Sea: Design, Construction & Installation
• Contractual Requirements and Specification per IFC package and other contractual documents.
SSEM Saudi Services for Electro Mechanic Works Co. (Closed Joint Stock Company)
PMC Project Management Consultant
ISO International Organization for Standardization
OEM Original Equipment Manufacturer
EPC Engineering, Procurement and Construction
O&M Operation & Maintenance
IFC Issue for Construction
PM Project Manager
CM Construction Manager
QMS Quality Management System
QA Quality Assurance
QC Quality Control
Contractor The main Contractor of Project
Sub-contractor Construction Sub-Contractor
ITP Inspection & Test Plan
RFI Request for Inspection
NCR Non-Conformance Report
GRP Glass Reinforced Plastic
HSE Health Safety and Environment
MSDS Material Safety Data Sheets
PPE Personal Protective Equipment
PTW Permit to Work
DN / PN Design Pressure / Nominal Pressure
OWNER: MARAFIQ
Organization Chart
CONSTRUCTION MANAGER
AHMED IBRAHEEM
QA/QC MANAGER
MOHAMMED ISMAIL ELDEEB SAFETY MANAGER
NADJME
PTW COORDINATOR
TBA
All actionable responsibilities mentioned in this section for each position will be completed and available on
site from start to completion of the scope of work.
The Construction manager will be responsible for the overall implementation and monitoring of all the
activities involved in the work.
OWNER: MARAFIQ
The site Civil engineer shall be overall responsible for piping excavations and trench work. He shall
also supervise dewatering subcontractor. He shall be assisted by Mechanical Piping engineer for
design requirements. Civil engineer shall also plan for shoring wherever needed. He shall have in-
depth knowledge about the practical methodology for the installation of underground piping
procedures and planning schedule on site. He must have knowledge about civil excavation work. He
will do proper planning and coordination in order to ensure that piping and fittings shall rest on sand
bedding and backfilled after testing with desired performance and efficiency as per contractual
requirements and IFC drawings.
The required (RFIs) will be submitted to the MARAFIQ/ILF. He will proactively coordinate with the
material engineer and issue appropriate internal (Site Instructions) when he sees that performance of
earth works deviate from the approved method of statement or project specifications.
5.7 COORDINATOR
OWNER: MARAFIQ
Responsible for taking all necessary steps to prepare, authorize, and issue the Permit to Work after
assessing the work and work site and/or area hazards and the controls to address these hazards.
6.1 LOWERING
Manual lowering of small diameter pipes into the trench can be executed by at least two men. It is
recommended that the weight carried by one man do not exceed 20 kg. Pipes weighing up to 120 kg
can be lowered by means of two ropes The ropes must be anchored to stakes as indicated in Figure.
1.
FIGURE- 1
OWNER: MARAFIQ
Mechanical lowering is used for larger diameter pipes, especially when combined with pipe assembly in the trench.
Two straps or slings can be used from an excavator boom if no separate lifting equipment is available as per Fig.2.
Figure- 2
Note: - Project specific handling and storage method statement shall be referred for more details of handling and storage
techniques
6.2.1.2 The trench excavations should not be too far ahead of the pipe-laying team to ensure a better control of the
trench and for safety reasons. The excavated soil should be placed on one side of the trench leaving the other side clear
for equipment and pipe handling. If the trench consists of various layers of soils, these should be placed separately to
use the stone- free granular material for back-filling.
OWNER: MARAFIQ
be smaller than 300 mm. If mechanical compacting equipment is used, the minimum space between the pipes and trench
wall or adjacent pipe shall not be less than width of the widest piece of equipment plus 150mm.
FIRGURE - 3
6.2.4 Pipes Crossing
Where two Glass Reinforced, Plastic pipes are crossing each other as shown in figure 4, the minimum vertical distance
between the two pipes shall be at least the average of the radius of the two pipes, in any case this distance should not be
less than 300 mm.
Figure - 4
should be established based on an evaluation of specific project conditions, such as pipe diameter and stiffness, soil
type and stiffness, and live load type and magnitude.
Project specific AWWA-M45 calculation shall be referred and installation parameters to be strictly adhered for each
Doc No. 7200040907-JWWF-GC-060 Rev 00
project. P.O. # 7200040907
If a risk of pipe flotation occurs, the minimum cover should be 1 pipe diameter. If a specific analysis is made of the
PROJECT: EXPANION OF IWTP-8 STAGE-4 DBO
OWNER: MARAFIQ
buoyant force of an empty pipe compared to the submerged weight of soil over the pipe, this minimum cover may be
reduced.
In the presence of permanent traffic loads, a minimum cover above pipes shall always be maintained. A detailed
engineering should be carried out and installation parameters as per AWWA-M45 calculation shall be strictly followed.
In case of high ground water table, a minimum cover depth equal to 0.8 times the pipe diameter of granular soil (minimum
dry density of 1300 Kg/m3) must be provided to prevent Glass Reinforced Plastic pipes from floating. Always ensure that
this minimum cover is available before turning off dewatering systems.
I) Sleeve pipe.
The below details are considered as a guideline, prior to apply these methods, site team to align with Engineering team to
collect the relevant details of the protection slabs.
I) Sleeve Pipe.
The Glass Reinforced Plastic pipe is nested inside a sleeve pipe. To avoid direct contact between both pipes, spacers
are used to center the GRP pipe inside the sleeve pipe (Figure- 5). The annular space between the two pipes is grouted.
The sleeve pipe should be longer than the width of the road.
OWNER: MARAFIQ
This protection slab is specially designed and dimensioned to minimize the transfer of wheel load on the pipe
and divert the load away from the pipe (Figure-6). The plate has a rebate which a
The Height (H) between the pipe and concrete protection slab will be based on the actual burial depth at site.
OWNER: MARAFIQ
The straps should be of flat material of minimum 25 mm width and strong enough to withstand flotation uplift
forces. The distance between straps should not exceed 4 meters, with a minimum of two strap per section length. The
straps should be tightened to prevent pipe uplift, but should not be over-tightened to avoid additional pipe deflection.
Therefore, the straps should be loose when pouring of concrete reached the pipe springing level. And after the poured
concrete get hardened. Then pouring shall be directly compacted till reaching the pipe crown
The pipe should be supported in such a way that the concrete can easily flow completely around and fully underneath the
pipe. Also, the supports should result in an acceptable pipe shape (less than 3% deflection and no bulges or flat areas).
The concrete must be placed in stages allowing sufficient time between layers for the cement to set and no longer exert
buoyant forces
Doc No. 7200040907-JWWF-GC-060 Rev 00 P.O. # 7200040907
6.4 BACKFILL AND INSTALLATION SELECTION
PROJECT: EXPANION OF IWTP-8 STAGE-4 DBO
OWNER: MARAFIQ
The installation type and choice of Pipe Embedment Zone material is normally specified by the design engineer, based
on the specified pipe stiffness class, maximum burial depths, depth of water table, wheel load, and native soil conditions.
Note: - Project specific AWWA-M45 calculation shall be referred for each project.
If the native soil meets the specifications in tables 1, the same soil may be used in the Pipe Embedment Zone.
6.4.2 Migration
When backfill materials such as gravels and crushed rocks are placed in a trench adjacent to a finer native material, the
finer material may migrate into the coarser material under the flow pressure force of the ground water table. Migration
can also occur when selected sand is used as backfill in a trench where the native soil is coarser.
Significant hydraulic gradients may arise in the pipeline trench during construction, when water levels are controlled by
various pumping or well-pointing methods.
Gradients may also arise after construction, when permeable underdrain or when the open graded embedment materials
act as a “French” drain under high ground water levels. Migration can result in significant loss of pipe support and
increasing pipe deflections that may eventually exceed the design limits of the Glass Reinforced Plastic pipe.
The gradation and relative size of the embedment and adjacent native soils must be compatible to minimize migration. In
general, where significant ground water table is above the foundation or bedding level and when the native soil is a finer
than the backfill, avoid using open graded materials such as crushed rocks and gravel, unless a geotextile filter fabric is
used to line the trench.
The following gradation criteria may be used to restrict the migration of finer material into a coarser material under a
hydraulic gradient.
• D15 I d 85 < 5 where Dis is the sieve opening size passing 15 percent by weight of the coarser material and ds is
the sieve opening size passing 85 percent by weight of the finer material.
• D so / d50 < 25 where D so is the sieve opening size passing 50 percent by weight of the coarser material and is
the sieve opening size passing 50 percent by weight of the finer material. (This criterion doesn’t apply if the
coarser material is well graded)
The fabric shall be stabilized against ultra violet light, inert to commonly encountered chemicals in the in-situ soil and
Doc No. 7200040907-JWWF-GC-060 Rev 00 P.O. # 7200040907
saline water.
PROJECT: EXPANION OF IWTP-8 STAGE-4 DBO
OWNER: MARAFIQ
Minimum property requirements should be as per the international standards and the end user requirements. Figure-9
represent the usage of geotextile to prevent the intermixing of dissimilar soil layers
Geotextile filter fabric shall be lined at the bottom, sides and top of the pipe embedment zone. This can be same
as a gift wrapping method along with the backfill material.
Figure 10: Placing the geotextile to line the trench bottom and sides.
OWNER: MARAFIQ
```
OWNER: MARAFIQ
Blow counts,
N
>50 30-50 15-30 8 - 15 4-8 2-4 1-2
(ASTMD
1586)
Cohesive Soils Very Hard Hard Very Stiff Stiff Medium Soft Vety Soft
OWNER: MARAFIQ
OWNER: MARAFIQ
Pipes shall be lowered into position after checking the proper levels and alignment of the pipeline. Pipes shall be laid
perfectly horizontal and avoid resting the pipe ends on sand piles to avoid any steps between the pipes that will result
the coupler insertion difficult.
6.4.8 Pipe Embedment Zone
The selected backfill material should be evenly placed and properly compacted on both sides of the pipes. Appropriate
hand or mechanical tamping shall be carried out by the Contractor to achieve the specified degree of compaction
required by the selected installation type. During the first one or two lifts (lift height shall not exceed 250mm), special
care should be taken to place and compact the backfill material under the pipe haunches (Figure-16). The best way to
achieve this compaction is to do it manually with the help of a wooden board. This is one of the most important
installation steps and should be executed with care. Failure to place and to compact the backfill material under the pipe
haunches may cause deformation, localized loads and over deflection of the pipes (Figure-17)
OWNER: MARAFIQ
Notes:
1. Trench wall inclined shall be as per the soil characteristics and angle of repose.
2. Foundation thickness must be in line with the Geo-technical recommendations.
3. The first two lifts ate the pipe zone embedment shall not exceed 250mm.
Pipes joined in the trenches should not be left for long periods without back-filling as some joints may rupture due to
daily expansion and contraction of the pipes due to ambient temperature fluctuation. However, if the pipes are
sufficiently restrained to prevent movement, the joints may be left exposed for an easy visual inspection during the field
hydro-test. These joints must be back-filled immediately after the test to avoid damages.
The Contractor should note that the compaction of clean and mixed sands is best achieved when the material is at its
optimum moisture content. While the wetting of sand is recommended prior to compaction, trench flooding should be
avoided to prevent pipes from floating.
Following the first two layers where the backfill has been sufficiently placed, compaction should proceed from the sides
of the trench towards the pipe. The Pipe Embedment Zone backfill should proceed in 150 to 300 mm lifts depending on
backfill type (see section 6.1). For Gravel backfill 300mm lifts are permitted. The Pipe Embedment Zone backfilling, and
compaction should continue until the backfill reaches at least 15 cm above the pipe crown. For pipes, larger than 1000
mm in diameter, back-filling the Pipe Embedment Zone should continue to 300 mm above the pipe crown.
After completion of backfilling in the Pipe Embedment Zone, native material excavated from the trench may be used to
complete backfilling to final grade. No compaction is required in these final backfilling layers except where specified by
the Engineer, or in the case of traffic or other high external loads over the pipe where settlement of the native backfill is
to be avoided.
Caution:
Sand layers of more than 300 mm cannot be compacted properly and may result in loss or reduced support for the
pipes. The best compaction results are achieved with wet sand near its optimum moisture content. Flooding of the
trench must be avoided as pipe floatation may occur. A minimum of 1 pipe diameter of granular backfill is normally
required to prevent Glass Reinforced Plastic pipes from floating.
For backfill material such as Gravel (Class I) and Sand (Class II) a 200kg plate vibrator is required to compact the backfill
in 15cm layers, and a 500kg plate vibrator is required to compact the backfill in 30cm layers. For Class-Ill and Class-IV
backfill materials a 500kg plate vibrator is required to compact the backfill for both lift cases. Before using plate vibrator
OWNER: MARAFIQ
Refer to the relevant method statements to perform the jointing activity. It is the installation contractor's responsibility to
make the necessary method statements available to the installation team members.
Outside rigid structures (i.e. water reservoirs, pumping station, thrust blocks, valve chambers, manholes etc.)
To connect the pipes to a line fitting such as bends or tees inside thrust blocks.
Standard short lengths of pipes shall be planned by the Contractor. Standard short pipe length can be 1.5XND with a
minimum of 500mm and a maximum of 2000mm. The length (L) may follow in between a range as per the below on a
case-to-case basis.
L=Smaller of 2m or 2XND
OWNER: MARAFIQ
Figure-18-Standard Installation
Cautions:
The expected settlement for massive concrete structure shall be calculated by the geotechnical engineer to determine
the number of short pipes & couplers required to withstand the settlement without excessive loads onto the pipes.
Backfilling around the concrete structures shall be thoroughly compacted with the same selected backfilling material. It
is the engineering team to decide the most suitable option to be followed based on their analysis.
OWNER: MARAFIQ
Figure-20
Figure - 21
OWNER: MARAFIQ
Figure - 22
Exposed length of fitting shall be considered while designing the thrust volume (minimum distance as shown into
OWNER: MARAFIQ
Hybrid system is a technique in which a combination of restrained and non-restrained piping system is
being employed to eliminate the use of thrust blocks. It is an ideal system where dimension constrain exists
due to limited space availability such as in plant piping. It is recommended to carry out a detailed
engineering to determine the minimum required restrained lengths to be used at the locations of direction
changes, Tees, Reducers, End caps, etc.
OWNER: MARAFIQ
Work will be performed in accordance with the APPROVED documents; IFC Drawing for Building, Tanks,
Foundation and other structural elements, planning schedule will be updated for delivery and shifting of
material. All lead mechanical engineer site mechanical engineer and material engineer shall have a 3-
weeks look ahead schedule of GRP stock inventory.
SSEM will provide the following equipment throughout the project; quantities will be determined by actual
site/Store demand. Equipment will be inspected prior utilizing.
All records relevant to the above procedure will be retained by the Quality Control department in the site
office, for the duration of the project, before being handed over to the Contractor in accordance with the
requirements of the contract documents. Copies of all records will be made and transferred to the
Contractor Office where they will be retained for the guarantee period of the contract.
OWNER: MARAFIQ
Approved MR I/ RFI
IFC
Approved Material Receiving RFI
11.0 TRAINING