REPORT BORED PILE CHILLER COOLING TOWER

UPDATED : 20 MARET 2023

BORE PILE BORING DEPTH CASING LENGTH STEEL REBAR LENGTH VOLUME CONCRETE
NO PILE NUMBER CASTING DATE REMARK
DIAMETER (MM) (METER) (METER) (METER) (M3)
1 1 400 14 12 12.64 02.03.2023 2.5 Rebar goes down 2 meter after casing pulled out
2 36 400 14 12 12.64 02.03.2023 2.5 Rebar goes out after casing pull out. Point failed
3 30 400 12 12 12.64 04.03.2023 2.25 Rebar goes down 0.64 meter after casing pulled out
4 16 400 12 12 12.64 04.03.2023 2.25 Rebar goes down 2 meter after casing pulled out
5 38 400 12 12 12.64 04.03.2023 2 Concrete less 3 meter from ground level. Point failed
6 35 400 12 12 12.64 04.03.2023 2 Rebar goes down 2 meter after casing pulled out
7 10 400 14.5 15 14.64 06.03.2023 3 Rebar goes down 0.30 meter after casing pulled out
8 33 400 16 15 14.64 06.03.2023 3
9 34 400 14.6 15 14.64 07.03.2023 3
10 37 400 14.5 15 14.64 + 1 07.03.2023 3 Rebar goes down 0.64 meter after casing pulled out
11 24 400 14.5 15 14.64 + 1 07.03.2023 3
12 31 400 14.5 15 14.64 + 1 07.03.2023 3 Rebar goes down 1.5 meter after casing pulled out
13 22 600 25.5 (from top casing) 15 25.14 19.03.2023 10

Progress Work 20.03.2023 :


1 Pile ID number 39 Intal casing length 15 meter, boring depth reach 25,5 meter from top of casing. Because of heavy rain at 15.00 PM until 18.00 PM steel rebar cannot put inside because the hole collapse.
2 Pile ID number 40 Instal casing length 15 meter, tomorrow will recheck coordinat point.
3 Batching plant from WIKA and Waskita Precast cannot suply concrete because of heavy rain
4 Balanced concrete 98.5 m3
5 Estimate concrete needed after change design = 181.5m3 (280-98.5)
6 Need to make new concrete PO
7 Start Work at 09.30 AM
8 Heavy Rain at 15.00 PM -18.00 PM
AFI'S MANPOWER :
1. Bor Operator : Donis
2. Crane Operator : Quntum
3. Ecavator Operator : Kamal
4. Safety Officer : Joni
5. Mechanic : Tugiyo
6. Welder : Namo
7. Concreting Crew : Safrudin
8. Concreting Crew : Dedi S
9. Concreting Crew : Dendi
10. Bor Machine Rigger : Haris
11. Rebar Fabrication Crew : Rofik
12.Rebar Fabrication Crew : Edi
13. Supervisor : Cecep Musofa
14. Flagman : Lito
15. Second Welder :Syamsul