Professional Documents
Culture Documents
Rab Mebeler (12.199)
Rab Mebeler (12.199)
a . RUANG PEMULASARAN
- Meja Pemulasaran 3,00 unit 10.872.025,95 32.616.077,85
- Vertical blind 5,50 m² 575.577,84 3.165.678,14
SUB TOTAL RUANG JENAZAH 59.718.485,40
3 . RUANG KANTIN KARYAWAN
a . AREA MAKAN
- Meja Kantin 12,00 unit 1.598.827,35 19.185.928,15
- Kursi makan 48,00 unit 931.887,94 44.730.621,05
- Meja washtafel 3,00 unit 4.111.270,32 12.333.810,95
b . RUANG ADMINISTRASI
- Meja kerja staf 1,00 unit 2.740.846,88 2.740.846,88
- Kursi Kerja staf 1,00 unit 1.644.508,13 1.644.508,13
- Lemari Arsip 1,00 unit 9.867.048,76 9.867.048,76
- Vertical blind 3,52 m² 575.577,84 2.026.034,01
d . RUANG PENERIMAAN
- Meja kerja staf 1,00 unit 2.740.846,88 2.740.846,88
- Kursi Kerja staf 1,00 unit 1.644.508,13 1.644.508,13
- Lemari Arsip 1,00 unit 9.867.048,76 9.867.048,76
- Vertical blind 3,52 m² 575.577,84 2.026.034,01
e . AREA LOCKER
- Locker 16,00 unit 2.740.846,88 43.853.550,05
g . AREA MASAK
- Pantry Master 1,00 ls 411.127.031,71 411.127.031,71
b . RUANG SATPAM
- Meja Counter Satpam 1,00 set 5.116.247,51 5.116.247,51
- Meja kerja staf 1,00 unit 2.740.846,88 2.740.846,88
- Kursi Kerja staf 3,00 unit 1.644.508,13 4.933.524,38
- Meja Tamu 1,00 unit 1.644.508,13 1.644.508,13
- Kursi Tamu 4,00 unit 931.887,94 3.727.551,75
- Locker 3,00 unit 2.740.846,88 8.222.540,63
- Vertical blind 2,20 m² 575.577,84 1.266.271,26
SUB TOTAL RUANG PUBLIK 55.100.158,41
5 . OFFICE
a . BAGIAN KEUANGAN
- Meja kerja Manager 1,00 unit 6.029.863,13 6.029.863,13
- Kursi Kerja Manager 1,00 unit 2.284.039,07 2.284.039,07
- Kursi hadap Manager 2,00 unit 1.461.785,00 2.923.570,00
- Meja kerja staf 4,00 unit 2.740.846,88 10.963.387,51
- Kursi Kerja staf 4,00 unit 1.644.508,13 6.578.032,51
- Lemari Arsip 1,00 unit 8.222.540,63 8.222.540,63
- Vertical blind 5,28 m² 575.577,84 3.039.051,02
b . BAGIAN UMUM
- Meja kerja Manager 1,00 unit 6.029.863,13 6.029.863,13
- Kursi Kerja Manager 1,00 unit 2.284.039,07 2.284.039,07
- Kursi hadap Manager 2,00 unit 1.461.785,00 2.923.570,00
- Meja kerja staf 4,00 unit 2.740.846,88 10.963.387,51
- Kursi Kerja staf 4,00 unit 1.644.508,13 6.578.032,51
- Lemari Arsip 1,00 unit 8.222.540,63 8.222.540,63
- Vertical blind 5,28 m² 575.577,84 3.039.051,02
c . BAGIAN SDM
- Meja kerja Manager 1,00 unit 6.029.863,13 6.029.863,13
- Kursi Kerja Manager 1,00 unit 2.284.039,07 2.284.039,07
- Kursi hadap Manager 2,00 unit 1.461.785,00 2.923.570,00
- Meja kerja staf 3,00 unit 2.740.846,88 8.222.540,63
- Kursi Kerja staf 3,00 unit 1.644.508,13 4.933.524,38
- Lemari Arsip 1,00 unit 8.222.540,63 8.222.540,63
- Vertical blind 5,28 m² 575.577,84 3.039.051,02
SUB TOTAL OFFICE 115.736.096,61
6 . REKAM MEDICE
a . STAF ADM
- Meja kerja staf 2,00 unit 2.740.846,88 5.481.693,76
- Kursi Kerja staf 2,00 unit 1.644.508,13 3.289.016,25
b . RUANG ARSIP
- Roll Opack 5,00 set 219.267.750,25 1.096.338.751,24
SUB TOTAL REKAM MEDICE 1.105.109.461,25
7 . GUDANG FARMASI
a . STAF ADM
- Meja kerja staf 1,00 unit 2.740.846,88 2.740.846,88
- Kursi Kerja staf 1,00 unit 1.644.508,13 1.644.508,13
b . RAK FARMASI
- Rak Farmasi 16,00 unit 7.235.835,76 115.773.372,13
SUB TOTAL GUDANG FARMASI 120.158.727,14
8 . RUANG ENGINEERING
a . STAF ADM
- Meja kerja staf 3,00 unit 3.882.866,41 11.648.599,23
- Kursi Kerja staf 3,00 unit 2.329.719,85 6.989.159,54
- Lemari Arsip 3,00 unit 13.978.319,08 41.934.957,23
SUB TOTAL RUANG ENGINEERING 60.572.716,01
9 . PARKIR MOBIL
- Meja kerja staf 1,00 unit 2.740.846,88 2.740.846,88
- Kursi Kerja staf 1,00 unit 1.644.508,13 1.644.508,13
SUB TOTAL PARKIR MOBIL 4.385.355,00
10 . BPJS LOUNGE
a . RUANG TUNGGU
- Meja Counter 2,00 set 9.455.921,73 18.911.843,46
- Sofa 3 Seater 3,00 unit 4.385.355,00 13.156.065,01
- Sofa 1 Seater 6,00 unit 1.827.231,25 10.963.387,51
- Meja Sofa 2 3,00 unit 1.781.550,47 5.344.651,41
B. LANTAI 1
1 . RUANG TRIASE
a . RUANG COUNTER TRIASE
- Meja Counter 1,00 set 9.455.921,73 9.455.921,73
- Kursi Kerja staf 2,00 unit 1.644.508,13 3.289.016,25
- Kursi Tunggu 4 sseater 2,00 set 4.385.355,00 8.770.710,01
- Wall Panel 10,44 m² 1.087.202,59 11.350.395,09
- Droop seilling + indirect lamp 15,00 m² 493.352,44 7.400.286,57
b . NURSE STATION
- Meja Counter 1,00 set 9.455.921,73 9.455.921,73
- Kursi Kerja staf 2,00 unit 1.644.508,13 3.289.016,25
- Backdroop panel + Signage + Lamp 8,40 m² 1.534.874,25 12.892.943,71
- Vertical blind 11,10 m² 493.352,44 5.476.212,06
c . RUANG DOKTER
- Meja Kerja Dokter 1,00 set 4.385.355,00 4.385.355,00
- Kursi Kerja Dokter 1,00 unit 1.827.231,25 1.827.231,25
- Kursi Hadap Dokter 2,00 unit 822.254,06 1.644.508,13
- Lemari Arsip 1,00 unit 8.222.540,63 8.222.540,63
- Sofa 2 seater 1,00 unit 4.385.355,00 4.385.355,00
d . RUANG PERAWAT
- Lemari Arsip 1,00 unit 8.222.540,63 8.222.540,63
- Sofa 2 seater 1,00 unit 4.385.355,00 4.385.355,00
d . RUANG TINDAKAN
- Bed Pasien K1 12,00 unit 10.415.218,14 124.982.617,64
- Tirai Pembatas + Hanging rail 70,20 m² 274.084,69 19.240.745,08
SUB TOTAL RUANG TRIASE 248.676.671,80
2 . RUANG RADIOLOGI
a . RUANG ADMINISTRASI
- Meja Kerja staf 1,00 unit 2.740.846,88 2.740.846,88
- Kursi Kerja staf 1,00 unit 1.644.508,13 1.644.508,13
- Kursi Hadap staf 2,00 unit 685.211,72 1.370.423,44
- Lemari Arsip 1,00 unit 8.222.540,63 8.222.540,63
b . RUANG KONSULTASI
- Meja Kerja staf 1,00 unit 2.740.846,88 2.740.846,88
- Kursi Kerja staf 1,00 unit 1.644.508,13 1.644.508,13
- Kursi Hadap staf 2,00 unit 685.211,72 1.370.423,44
c . RUANG TUNGGU
- Kursi Tunggu 4 sseater 2,00 set 5.481.693,76 10.963.387,51
- Wall Panel 7,20 m² 931.887,94 6.709.593,16
- TV LED 42'' 1,00 unit 6.166.905,48 6.166.905,48
SUB TOTAL RUANG RADIOLOGI 43.573.983,67
3 . LOBBY
a . RUANG ADMINISTRASI
- Meja Registrasi 1 1,00 set 8.880.343,89 8.880.343,89
- Kursi Kerja staf 7,00 unit 1.644.508,13 11.511.556,89
- Kursi Hadap staf 6,00 unit 913.615,63 5.481.693,76
- Meja Kerja staf 4,00 unit 2.740.846,88 10.963.387,51
- Kursi Kerja staf 4,00 unit 1.644.508,13 6.578.032,51
- Lemari Arsip 4,00 unit 8.222.540,63 32.890.162,54
- Backdroop panel + Signage + Lamp 25,20 m² 1.534.874,25 38.678.831,14
b . RUANG TUNGGU
- Kursi Tunggu 4 sseater 8,00 set 5.481.693,76 43.853.550,05
- Sofa 1 Seater 8,00 unit 2.740.846,88 21.926.775,02
- Sofa 3 Seater 4,00 unit 6.578.032,51 26.312.130,03
- Meja Sofa 2 4,00 unit 1.644.508,13 6.578.032,51
- Vertical blind 49,00 m² 575.577,84 28.203.314,38
- Lantai Marmer 325,00 m² 1.644.508,13 534.465.141,23
- Hanging Lamp decorative 12,00 unit 959.296,41 11.511.556,89
c . LOBBY LIFT
- Wall Panel Lift 45,00 m² 1.644.508,13 74.002.865,71
- Wall Panel 10,80 m² 931.887,94 10.064.389,74
- Droop seilling + indirect lamp 12,00 m² 255.812,38 3.069.748,50
d . TENANT
- Interior dan furniture Tenant 50,00 m² 6.395.309,38 319.765.469,11
e . COFFE
- Counter Coffe 1,00 set 19.121.975,05 19.121.975,05
- Meja Coffe 6,00 unit 2.192.677,50 13.156.065,01
- Kursi Café 24,00 unit 1.279.061,88 30.697.485,03
- Droop seilling + indirect lamp 30,00 m² 255.812,38 7.674.371,26
- Backdroop panel + Signage + Lamp 11,76 m² 1.534.874,25 18.050.121,20
4 . RUANG POLIKLINIK
a . NURSE STATION
- Meja Registrasi 2 1,00 set 20.556.351,59 20.556.351,59
- Kursi Kerja staf 3,00 unit 1.644.508,13 4.933.524,38
- Backdroop panel + Signage + Lamp 1,00 m² 1.534.874,25 1.534.874,25
- Droop seilling + indirect lamp 7,60 m² 255.812,38 1.944.174,05
c . RUANG TUNGGU
- Kursi Tunggu 4 seater 22,00 set 5.481.693,76 120.597.262,64
- TV LED 42'' 1,00 unit 6.166.905,48 6.166.905,48
f . LAIN - LAIN
- Vertical blind 72,00 m² 575.577,84 41.441.604,80
SUB TOTAL RUANG POLIKLINIK 582.090.462,03
5 . DEPARTEMEN FARMASI
a . COUNTER FARMASI
- Meja counter Farmasi 1,00 set 22.200.859,71 22.200.859,71
- Kursi Kerja staf 3,00 unit 1.096.338,75 3.289.016,25
- Cabinet Display Farmasi 1,00 unit 20.720.802,40 20.720.802,40
- Kursi Tunggu 4 seater 11,00 set 6.578.032,51 72.358.357,58
- Backdroop panel + Signage + Lamp 14,00 m² 1.534.874,25 21.488.239,52
b . KASIR
- Meja Kasir 1,00 set 9.209.245,51 9.209.245,51
- Kursi Kerja staf 2 2,00 unit 1.370.423,44 2.740.846,88
- Backdroop panel + Signage + Lamp 8,96 m² 1.315.606,50 11.787.834,25
c . KEPALA FARMASI
- Meja kerja Manager 1,00 unit 5.024.885,94 5.024.885,94
- Kursi Kerja Manager 1,00 unit 2.284.039,07 2.284.039,07
- Kursi hadap Manager 2,00 unit 1.096.338,75 2.192.677,50
d . MEJA KONSULTASI
- Meja konsultasi 1,00 unit 3.837.185,63 3.837.185,63
- Kursi Kerja staf 2 1,00 unit 1.370.423,44 1.370.423,44
- Kursi Hadap Staf 2 2,00 unit 959.296,41 1.918.592,81
e. RUANG ARSIP
- Lemari Arsip 15,00 unit 9.867.048,76 148.005.731,42
g. LAIN-LAIN
- Vertical blind 6,00 m² 575.577,84 3.453.467,07
SUB TOTA DEPARTEMEN FARMASI 439.117.839,09
6 . DEPARTEMEN FISIOTERAPI
a . RUANG TUNGGU
- Kursi Tunggu 4 sheater 3,00 set 5.481.693,76 16.445.081,27
- Backdroop panel + Signage + Lamp 9,52 m² 1.534.874,25 14.612.002,88
d. LAIN-LAIN
- Vertical blind 48,00 m² 575.577,84 27.627.736,53
SUB TOTA DEPARTEMEN FISIOTERAPI 134.560.598,42
7 . DEPARTEMEN BPJS
a . RUANG CODING BPJS
- Meja kerja Staff 3,00 unit 2.740.846,88 8.222.540,63
- Kursi Kerja Staf 3,00 unit 1.644.508,13 4.933.524,38
- Lemari Arsip 2,00 unit 9.867.048,76 19.734.097,52
8 . DEPARTEMEN LABORATORIUM
a . RUANG KONSULTASI
- Meja Kerja dokter 1,00 set 4.385.355,00 4.385.355,00
- Kursi Kerja Dokter 1,00 unit 1.827.231,25 1.827.231,25
- Kursi Hadap Dokter 2,00 unit 1.096.338,75 2.192.677,50
- Kursi Tunggu 4 seater 2,00 set 6.578.032,51 13.156.065,01
- TV LED 42'' 1,00 unit 6.166.905,48 6.166.905,48
b . BAG ADMINISTRASI
- Meja Kerja Kepala 1,00 set 4.385.355,00 4.385.355,00
- Kursi Kerja Kepala 1,00 unit 1.827.231,25 1.827.231,25
- Kursi Hadap Kepala 2,00 unit 1.279.061,88 2.558.123,75
- Meja kerja Staff 2,00 unit 2.740.846,88 5.481.693,76
- Kursi Kerja Staf 2,00 unit 1.644.508,13 3.289.016,25
- Lemari Arsip 2,00 unit 8.222.540,63 16.445.081,27
c . BAG STAFF
- Meja Kerja staff 1,00 unit 2.740.846,88 2.740.846,88
- Kursi Kerja staff 6,00 unit 1.370.423,44 8.222.540,63
d . RUANG DOKTER
- Meja Kerja dokter 1,00 set 4.385.355,00 4.385.355,00
- Kursi Kerja Dokter 1,00 unit 1.827.231,25 1.827.231,25
- Kursi Hadap Dokter 2,00 unit 1.096.338,75 2.192.677,50
- Sofa 2 seater 1,00 unit 4.385.355,00 4.385.355,00
e . LABORATORIUM KIMIA
- Meja Laboratorium /Racik - Wall bench 5,00 mI 8.313.902,20 41.569.510,98
f . LABORATORIUM URINE
- Meja Laboratorium /Racik - Wall bench 2,90 mI 8.313.902,20 24.110.316,37
g . LABORATORIUM HEMATOLOGI
- Meja Laboratorium /Racik - Island bench 2,00 mI 15.348.742,52 30.697.485,03
- Meja Laboratorium /Racik - Wall bench 3,50 mI 8.313.902,20 29.098.657,69
h. LABORATORIUM FESES,BTA,SPUTUM
- Meja Laboratorium /Racik - Wall bench 7,00 mI 8.313.902,20 58.197.315,38
i . RUANG GUDANG
- Lemari Arsip 6,00 unit 9.867.048,76 59.202.292,57
j. LAIN-LAIN
- Vertical blind 15,84 m² 575.577,84 9.117.153,06
SUB TOTA DEPARTEMEN LABORATORIUM 337.461.472,89
C. LANTAI 2
1 . RUANG LOBBY
a . RUANG TUNGGU
- Kursi Tunggu 4 seater 14,00 set 6.578.032,51 92.092.455,10
- Wall Panel Lift 24,60 m² 1.644.508,13 40.454.899,92
- Wall Panel 24,60 m² 931.887,94 22.924.443,29
- TV 49 inch 24,60 unit 8.222.540,63 202.274.499,60
- Vertical blind 12,00 m² 575.577,84 6.906.934,13
SUB TOTAL RUANG LOBBY 364.653.232,05
2 . BAGIAN HEMODIALISA
a . RUANG HEMODIALISA
- Bed Pasien K3 12,00 unit 10.278.175,79 123.338.109,51
- Meja Registrasi 1 1,00 set 8.880.343,89 8.880.343,89
b . RUANG TUNGGU
- Kursi Tunggu 4 seater 3,00 set 6.578.032,51 19.734.097,52
c . MEJA KONSULTASI
- Meja Konsultasi 1,00 unit 3.837.185,63 3.837.185,63
- Kursi kerja staff 2 1,00 unit 1.370.423,44 1.370.423,44
- Kursi Hadap Staff 2 2,00 unit 1.279.061,88 2.558.123,75
d . RUANG OBAT
- Lemari Arsip 1,00 unit 9.867.048,76 9.867.048,76
e. LAIN-LAIN
- Vertical blind 33,60 m² 575.577,84 19.339.415,57
SUB TOTAL BAGIAN HEMODIALISA 188.924.748,08
3 . BAGIAN ICU
a . RUANG PERIKSA
- Bed Pasien K2 5,00 unit 12.151.087,83 60.755.439,13
- Meja Registrasi 1 1,00 set 8.880.343,89 8.880.343,89
- Kursi Hadap Staff 2 2,00 unit 1.370.423,44 2.740.846,88
b . RUANG DOKTER
- Meja Kerja dokter 1,00 set 4.385.355,00 4.385.355,00
- Kursi Kerja Dokter 1,00 unit 1.827.231,25 1.827.231,25
- Kursi Hadap Dokter 2,00 unit 1.096.338,75 2.192.677,50
- Sofa 2 seater 1,00 unit 4.385.355,00 4.385.355,00
c . RUANG PERAWAT
- Lemari Arsip 1,00 unit 9.867.048,76 9.867.048,76
- Sofa 2 seater 1,00 unit 4.385.355,00 4.385.355,00
d . RUANG ISOLASI
- Bed Pasien K2 1,00 unit 12.151.087,83 12.151.087,83
e. LAIN-LAIN
- Vertical blind 24,00 m² 575.577,84 13.813.868,27
SUB TOTAL BAGIAN ICU 125.384.608,52
4 . RUANG VK
a . RUANG PERIKSA
- Bed Pasien K2 6,00 unit 12.151.087,83 72.906.526,96
- Meja Registrasi 1 1,00 set 8.880.343,89 8.880.343,89
- Meja kerja staff 1,00 unit 2.740.846,88 2.740.846,88
- Kursi Kerja Staff 2 2,00 unit 1.370.423,44 2.740.846,88
- Backdroop panel + Signage + Lamp 10,80 m² 1.534.874,25 16.576.641,92
SUB TOTAL RUANG VK 103.845.206,52
b . RUANG ADM
- Meja kerja staff 1,00 unit 2.740.846,88 2.740.846,88
- Kursi Kerja Staff 2 1,00 unit 1.370.423,44 1.370.423,44
- Lemari Arsip 1,00 unit 6.906.934,13 6.906.934,13
SUB TOTAL RUANG PRE -OP 71.243.746,52
b . RUANG ADM
- Meja kerja staff 1,00 unit 2.740.846,88 2.740.846,88
- Kursi Kerja Staff 2 1,00 unit 1.370.423,44 1.370.423,44
- Lemari Arsip 1,00 unit 6.906.934,13 6.906.934,13
c . RUANG MEETING
- Meja Rapat 1,00 set 12.425.172,51 12.425.172,51
- Kursi Kerja Staff 2 6,00 unit 1.142.019,53 6.852.117,20
- Backdroop panel + Signage + Glasboard 9,60 m² 1.534.874,25 14.734.792,82
e . RUANG PERAWAT
- Meja kerja staff 2,00 unit 2.740.846,88 5.481.693,76
- Kursi Kerja Staff 2 2,00 unit 1.370.423,44 2.740.846,88
- Lemari Arsip 2,00 unit 9.867.048,76 19.734.097,52
- Vertical blind 4,80 m² 575.577,84 2.762.773,65
SUB TOTAL RUANG POST -OP 190.090.521,61
c . KEPALA BAGIAN
- Meja Kerja Manager 1,00 unit 6.029.863,13 6.029.863,13
- Kursi Kerja Manager 1,00 unit 2.740.846,88 2.740.846,88
- Kursi Hadap Manager 2,00 unit 1.827.231,25 3.654.462,50
- Lemari Arsip 1,00 unit 9.867.048,76 9.867.048,76
d . PERAWAT
- Meja kerja staff 2,00 unit 2.740.846,88 5.481.693,76
- Kursi Kerja Staff 2 2,00 unit 1.370.423,44 2.740.846,88
- Lemari Arsip 2,00 unit 9.867.048,76 19.734.097,52
D. LANTAI 3
1 . RUANG MANAGEMENT
a . RUANG DIREKTUR UTAMA
- Meja Kerja Direktur utama 1,00 unit 12.425.172,51 12.425.172,51
- Kursi Kerja Direktur Utama 1,00 unit 4.385.355,00 4.385.355,00
- Kursi Hadap Direktur Utama 2,00 unit 2.192.677,50 4.385.355,00
- Cabinet 1,00 unit 25.325.425,15 25.325.425,15
- Vertical blind 6,00 m² 575.577,84 3.453.467,07
d . RUANG SEKRETARIS
- Meja Kerja Sekretasris 2,00 unit 4.933.524,38 9.867.048,76
- Kursi Kerja Sekretasris 2,00 unit 2.284.039,07 4.568.078,13
- Kursi Hadap Sekretasris 4,00 unit 1.461.785,00 5.847.140,01
- Meja Kerja Rapat Direktur 1,00 unit 16.445.081,27 16.445.081,27
- Kursi Rapat Direktur 6,00 unit 2.284.039,07 13.704.234,39
e . SELASAR
- Backdroop panel + Signage + Lamp 40,00 m² 1.534.874,25 61.394.970,07
SUB TOTAL RUANG MANAGEMENT 396.008.520,33
2 . RUANG PENDUKUNG
a . KANTIN
- Meja Kantin 12,00 unit 1.370.423,44 16.445.081,27
- Kursi Makan 48,00 unit 776.573,28 37.275.517,54
- Pantry 7,50 mI 2.558.123,75 19.185.928,15
- Counter Kantin 7,50 mI 3.837.185,63 28.778.892,22
- Droop seilling + indirect lamp 55,00 m² 255.812,38 14.069.680,64
- Wall Panel 18,00 m² 1.087.202,59 19.569.646,71
b . MUSHOLA
- Bench Pria 3,00 unit 1.644.508,13 4.933.524,38
- Bench Wanita 3,00 unit 1.644.508,13 4.933.524,38
- Vinil Tile Lantai 45,00 m² 479.648,20 21.584.169,16
c . FOYER
- Droop seilling + indirect lamp 35,00 m² 255.812,38 8.953.433,14
- Hanging Lamp Decorative 4,00 unit 959.296,41 3.837.185,63
- Hiasan Dinding 4,00 m² 639.530,94 2.558.123,75
SUB TOTAL RUANG PENDUKUNG 182.124.706,97
3 . RUANG PERAWATAN
a . NURSE STATION
- Meja Counter 1,00 set 11.347.106,08 11.347.106,08
- Kursi Kerja Staff 3,00 unit 1.370.423,44 4.111.270,32
- Backdroop panel + Signage + Lamp 8,40 m² 1.534.874,25 12.892.943,71
E. LANTAI 4
1 . RUANG PERAWATAN KELAS 1
a . NURSE STATION
- Meja Counter 1,00 set 11.347.106,08 11.347.106,08
- Kursi Kerja Staff 3,00 unit 1.370.423,44 4.111.270,32
- Backdroop panel + Signage + Lamp 8,40 m² 1.534.874,25 12.892.943,71
- Droop seilling + indirect lamp 6,70 m² 255.812,38 1.713.942,91
F. LANTAI 5
1 . RUANG PERAWATAN KELAS 1
a . NURSE STATION
- Meja Counter 1,00 set 11.347.106,08 11.347.106,08
- Kursi Kerja Staff 3,00 unit 1.644.508,13 4.933.524,38
- Backdroop panel + Signage + Lamp 8,40 m² 1.534.874,25 12.892.943,71
G. LANTAI 5
1 . RUANG PERAWATAN KELAS VIP
a . NURSE STATION
- Meja Counter 1,00 set 11.347.106,08 11.347.106,08
- Kursi Kerja Staff 3,00 unit 1.644.508,13 4.933.524,38
- Backdroop panel + Signage + Lamp 8,40 m² 1.534.874,25 12.892.943,71