RENCANA ANGGARAN BIAYA

PROYEK : Pembangunan Rumah Sakit Islam Asshobirin


LOKASI : Jl. Raya Serpong KM. 11 Kota Tangerang Selatan
PEKERJAAN : STRUKTUR, ARSITEKTUR, MEP
SUB PEKERJAAN : Mebeleur dan interior
PERIODE :
HARGA
NO URAIAN PEKERJAAN VOLUME
SATUAN TOTAL

IX PEKERJAAN MEBELEUR DAN INTERIOR


A LANTAI SEMIBASEMENT
1 . LAUNDRY
a . RUANG PETUGAS
- Meja kerja staf 1,00 unit 3.197.654,69 3.197.654,69
- Kursi Kerja staf 1,00 unit 1.918.592,81 1.918.592,81

b . AREA KERJA LOUNDRY


- Rak Penyimpanan 1,00 unit 13.813.868,27 13.813.868,27
- Meja kerja Loundry 3,00 unit 7.126.201,88 21.378.605,65
SUB TOTAL LOUNDRY 40.308.721,42
2 . RUANG JENAZAH
a . RUANG KEPALA
- Meja kerja Manager 1,00 unit 6.029.863,13 6.029.863,13
- Kursi Kerja Manager 1,00 unit 2.740.846,88 2.740.846,88
- Kursi Hadap Manager 2,00 unit 1.827.231,25 3.654.462,50
- Kursi Tunggu 3 sheater 1,00 set 4.933.524,38 4.933.524,38
- Kursi Tunggu 4 sheater 1,00 set 6.578.032,51 6.578.032,51

a . RUANG PEMULASARAN
- Meja Pemulasaran 3,00 unit 10.872.025,95 32.616.077,85
- Vertical blind 5,50 m² 575.577,84 3.165.678,14
SUB TOTAL RUANG JENAZAH 59.718.485,40
3 . RUANG KANTIN KARYAWAN
a . AREA MAKAN
- Meja Kantin 12,00 unit 1.598.827,35 19.185.928,15
- Kursi makan 48,00 unit 931.887,94 44.730.621,05
- Meja washtafel 3,00 unit 4.111.270,32 12.333.810,95

- Wall panel 21,60 m² 1.087.202,59 23.483.576,05


- Drop ceilling + indirect lamp 45,00 m² 274.084,69 12.333.810,95
- Hanging Lamp decorative 5,00 unit 959.296,41 4.796.482,04
- TV LED 29 '' 1,00 unit 6.578.032,51 6.578.032,51

b . RUANG ADMINISTRASI
- Meja kerja staf 1,00 unit 2.740.846,88 2.740.846,88
- Kursi Kerja staf 1,00 unit 1.644.508,13 1.644.508,13
- Lemari Arsip 1,00 unit 9.867.048,76 9.867.048,76
- Vertical blind 3,52 m² 575.577,84 2.026.034,01

c . RUANG AHLI GIZI


- Meja kerja staf 1,00 unit 2.740.846,88 2.740.846,88
- Kursi Kerja staf 1,00 unit 1.644.508,13 1.644.508,13
- Kursi Hadap staf 2,00 unit 1.142.019,53 2.284.039,07
- Vertical blind 2,20 m² 575.577,84 1.266.271,26

d . RUANG PENERIMAAN
- Meja kerja staf 1,00 unit 2.740.846,88 2.740.846,88
- Kursi Kerja staf 1,00 unit 1.644.508,13 1.644.508,13
- Lemari Arsip 1,00 unit 9.867.048,76 9.867.048,76
- Vertical blind 3,52 m² 575.577,84 2.026.034,01

e . AREA LOCKER
- Locker 16,00 unit 2.740.846,88 43.853.550,05

f . RUANG ALAT MAKAN


- Rak 1 9,00 ml 2.740.846,88 24.667.621,90

g . AREA MASAK
- Pantry Master 1,00 ls 411.127.031,71 411.127.031,71

h . RUANG ALAT MASAK


- Rak 1 7,50 ml 2.740.846,88 20.556.351,59
SUB TOTAL RUANG KANTIN KARYAWAN 664.139.357,83
4 . RUANG PUBLIK
a . MUSHOLA
- Bench pria 2,00 unit 1.918.592,81 3.837.185,63
- Bench Wanita 2,00 unit 1.918.592,81 3.837.185,63
- Vinil Tile lantai 38,00 m² 447.671,66 17.011.522,96
- Tirai Pembatas + hanging rail 10,08 m² 274.084,69 2.762.773,65

b . RUANG SATPAM
- Meja Counter Satpam 1,00 set 5.116.247,51 5.116.247,51
- Meja kerja staf 1,00 unit 2.740.846,88 2.740.846,88
- Kursi Kerja staf 3,00 unit 1.644.508,13 4.933.524,38
- Meja Tamu 1,00 unit 1.644.508,13 1.644.508,13
- Kursi Tamu 4,00 unit 931.887,94 3.727.551,75
- Locker 3,00 unit 2.740.846,88 8.222.540,63
- Vertical blind 2,20 m² 575.577,84 1.266.271,26
SUB TOTAL RUANG PUBLIK 55.100.158,41
5 . OFFICE
a . BAGIAN KEUANGAN
- Meja kerja Manager 1,00 unit 6.029.863,13 6.029.863,13
- Kursi Kerja Manager 1,00 unit 2.284.039,07 2.284.039,07
- Kursi hadap Manager 2,00 unit 1.461.785,00 2.923.570,00
- Meja kerja staf 4,00 unit 2.740.846,88 10.963.387,51
- Kursi Kerja staf 4,00 unit 1.644.508,13 6.578.032,51
- Lemari Arsip 1,00 unit 8.222.540,63 8.222.540,63
- Vertical blind 5,28 m² 575.577,84 3.039.051,02

b . BAGIAN UMUM
- Meja kerja Manager 1,00 unit 6.029.863,13 6.029.863,13
- Kursi Kerja Manager 1,00 unit 2.284.039,07 2.284.039,07
- Kursi hadap Manager 2,00 unit 1.461.785,00 2.923.570,00
- Meja kerja staf 4,00 unit 2.740.846,88 10.963.387,51
- Kursi Kerja staf 4,00 unit 1.644.508,13 6.578.032,51
- Lemari Arsip 1,00 unit 8.222.540,63 8.222.540,63
- Vertical blind 5,28 m² 575.577,84 3.039.051,02

c . BAGIAN SDM
- Meja kerja Manager 1,00 unit 6.029.863,13 6.029.863,13
- Kursi Kerja Manager 1,00 unit 2.284.039,07 2.284.039,07
- Kursi hadap Manager 2,00 unit 1.461.785,00 2.923.570,00
- Meja kerja staf 3,00 unit 2.740.846,88 8.222.540,63
- Kursi Kerja staf 3,00 unit 1.644.508,13 4.933.524,38
- Lemari Arsip 1,00 unit 8.222.540,63 8.222.540,63
- Vertical blind 5,28 m² 575.577,84 3.039.051,02
SUB TOTAL OFFICE 115.736.096,61
6 . REKAM MEDICE
a . STAF ADM
- Meja kerja staf 2,00 unit 2.740.846,88 5.481.693,76
- Kursi Kerja staf 2,00 unit 1.644.508,13 3.289.016,25

b . RUANG ARSIP
- Roll Opack 5,00 set 219.267.750,25 1.096.338.751,24
SUB TOTAL REKAM MEDICE 1.105.109.461,25
7 . GUDANG FARMASI
a . STAF ADM
- Meja kerja staf 1,00 unit 2.740.846,88 2.740.846,88
- Kursi Kerja staf 1,00 unit 1.644.508,13 1.644.508,13
b . RAK FARMASI
- Rak Farmasi 16,00 unit 7.235.835,76 115.773.372,13
SUB TOTAL GUDANG FARMASI 120.158.727,14
8 . RUANG ENGINEERING
a . STAF ADM
- Meja kerja staf 3,00 unit 3.882.866,41 11.648.599,23
- Kursi Kerja staf 3,00 unit 2.329.719,85 6.989.159,54
- Lemari Arsip 3,00 unit 13.978.319,08 41.934.957,23
SUB TOTAL RUANG ENGINEERING 60.572.716,01
9 . PARKIR MOBIL
- Meja kerja staf 1,00 unit 2.740.846,88 2.740.846,88
- Kursi Kerja staf 1,00 unit 1.644.508,13 1.644.508,13
SUB TOTAL PARKIR MOBIL 4.385.355,00
10 . BPJS LOUNGE
a . RUANG TUNGGU
- Meja Counter 2,00 set 9.455.921,73 18.911.843,46
- Sofa 3 Seater 3,00 unit 4.385.355,00 13.156.065,01
- Sofa 1 Seater 6,00 unit 1.827.231,25 10.963.387,51
- Meja Sofa 2 3,00 unit 1.781.550,47 5.344.651,41

- Wall panel 15,00 m² 931.887,94 13.978.319,08


- TV LED 49'' 1,00 unit 8.770.710,01 8.770.710,01
- Dispenser + meja 1,00 unit 4.659.439,69 4.659.439,69
- Droop seilling + indirect lamp 30,00 m² 219.267,75 6.578.032,51
- Droop seilling + indirect lamp 30,00 m² 219.267,75 6.578.032,51
- hiasan Dinding 4,00 m² 548.169,38 2.192.677,50
- Parfum Dispenser 2,00 unit 246.676,22 493.352,44
- Vertical blind 16,50 m² 575.577,84 9.497.034,43
SUB TOTAL BPJS LOUNGE 101.123.545,57
10 . BPJS LOUNGE
a . LOBBY LIFT
- Wall panel Lift 45,00 m² 1.644.508,13 74.002.865,71
- Wall Panel 10,80 m² 931.887,94 10.064.389,74
- Droop seilling + indirect lamp 12,00 m² 237.540,06 2.850.480,75
SUB TOTAL BPJS LOUNGE 86.917.736,20
11 . PENINGKATAN INTERIOR DISAIN
a . PENINGKATAN INTERIOR DISAIN
- Peningkatan interior disain 1,00 ls 225.693.260,98 225.693.260,98
SUB TOTAL PENINGKATAN INTERIOR DISAIN 225.693.260,98
TOTAL PEKERJAAN MEBELEUR DAN INTERIOR LANTAI BASEMENT 2.638.963.621,81

B. LANTAI 1
1 . RUANG TRIASE
a . RUANG COUNTER TRIASE
- Meja Counter 1,00 set 9.455.921,73 9.455.921,73
- Kursi Kerja staf 2,00 unit 1.644.508,13 3.289.016,25
- Kursi Tunggu 4 sseater 2,00 set 4.385.355,00 8.770.710,01
- Wall Panel 10,44 m² 1.087.202,59 11.350.395,09
- Droop seilling + indirect lamp 15,00 m² 493.352,44 7.400.286,57

b . NURSE STATION
- Meja Counter 1,00 set 9.455.921,73 9.455.921,73
- Kursi Kerja staf 2,00 unit 1.644.508,13 3.289.016,25
- Backdroop panel + Signage + Lamp 8,40 m² 1.534.874,25 12.892.943,71
- Vertical blind 11,10 m² 493.352,44 5.476.212,06

c . RUANG DOKTER
- Meja Kerja Dokter 1,00 set 4.385.355,00 4.385.355,00
- Kursi Kerja Dokter 1,00 unit 1.827.231,25 1.827.231,25
- Kursi Hadap Dokter 2,00 unit 822.254,06 1.644.508,13
- Lemari Arsip 1,00 unit 8.222.540,63 8.222.540,63
- Sofa 2 seater 1,00 unit 4.385.355,00 4.385.355,00

d . RUANG PERAWAT
- Lemari Arsip 1,00 unit 8.222.540,63 8.222.540,63
- Sofa 2 seater 1,00 unit 4.385.355,00 4.385.355,00

d . RUANG TINDAKAN
- Bed Pasien K1 12,00 unit 10.415.218,14 124.982.617,64
- Tirai Pembatas + Hanging rail 70,20 m² 274.084,69 19.240.745,08
SUB TOTAL RUANG TRIASE 248.676.671,80

2 . RUANG RADIOLOGI
a . RUANG ADMINISTRASI
- Meja Kerja staf 1,00 unit 2.740.846,88 2.740.846,88
- Kursi Kerja staf 1,00 unit 1.644.508,13 1.644.508,13
- Kursi Hadap staf 2,00 unit 685.211,72 1.370.423,44
- Lemari Arsip 1,00 unit 8.222.540,63 8.222.540,63

b . RUANG KONSULTASI
- Meja Kerja staf 1,00 unit 2.740.846,88 2.740.846,88
- Kursi Kerja staf 1,00 unit 1.644.508,13 1.644.508,13
- Kursi Hadap staf 2,00 unit 685.211,72 1.370.423,44

c . RUANG TUNGGU
- Kursi Tunggu 4 sseater 2,00 set 5.481.693,76 10.963.387,51
- Wall Panel 7,20 m² 931.887,94 6.709.593,16
- TV LED 42'' 1,00 unit 6.166.905,48 6.166.905,48
SUB TOTAL RUANG RADIOLOGI 43.573.983,67

3 . LOBBY
a . RUANG ADMINISTRASI
- Meja Registrasi 1 1,00 set 8.880.343,89 8.880.343,89
- Kursi Kerja staf 7,00 unit 1.644.508,13 11.511.556,89
- Kursi Hadap staf 6,00 unit 913.615,63 5.481.693,76
- Meja Kerja staf 4,00 unit 2.740.846,88 10.963.387,51
- Kursi Kerja staf 4,00 unit 1.644.508,13 6.578.032,51
- Lemari Arsip 4,00 unit 8.222.540,63 32.890.162,54
- Backdroop panel + Signage + Lamp 25,20 m² 1.534.874,25 38.678.831,14

b . RUANG TUNGGU
- Kursi Tunggu 4 sseater 8,00 set 5.481.693,76 43.853.550,05
- Sofa 1 Seater 8,00 unit 2.740.846,88 21.926.775,02
- Sofa 3 Seater 4,00 unit 6.578.032,51 26.312.130,03
- Meja Sofa 2 4,00 unit 1.644.508,13 6.578.032,51
- Vertical blind 49,00 m² 575.577,84 28.203.314,38
- Lantai Marmer 325,00 m² 1.644.508,13 534.465.141,23
- Hanging Lamp decorative 12,00 unit 959.296,41 11.511.556,89

c . LOBBY LIFT
- Wall Panel Lift 45,00 m² 1.644.508,13 74.002.865,71
- Wall Panel 10,80 m² 931.887,94 10.064.389,74
- Droop seilling + indirect lamp 12,00 m² 255.812,38 3.069.748,50

d . TENANT
- Interior dan furniture Tenant 50,00 m² 6.395.309,38 319.765.469,11

e . COFFE
- Counter Coffe 1,00 set 19.121.975,05 19.121.975,05
- Meja Coffe 6,00 unit 2.192.677,50 13.156.065,01
- Kursi Café 24,00 unit 1.279.061,88 30.697.485,03
- Droop seilling + indirect lamp 30,00 m² 255.812,38 7.674.371,26
- Backdroop panel + Signage + Lamp 11,76 m² 1.534.874,25 18.050.121,20

f . RUANG BERMAIN ANAK


- Permainan Anak 1,00 ls 59.385.015,69 59.385.015,69
SUB TOTAL LOBBY 1.342.822.014,64

4 . RUANG POLIKLINIK
a . NURSE STATION
- Meja Registrasi 2 1,00 set 20.556.351,59 20.556.351,59
- Kursi Kerja staf 3,00 unit 1.644.508,13 4.933.524,38
- Backdroop panel + Signage + Lamp 1,00 m² 1.534.874,25 1.534.874,25
- Droop seilling + indirect lamp 7,60 m² 255.812,38 1.944.174,05

b . NURSE STATION POLY ANAK


- Meja Registrasi 2 1,00 set 20.556.351,59 20.556.351,59
- Kursi Kerja staf 2,00 unit 1.644.508,13 3.289.016,25
- Backdroop panel + Signage + Lamp 10,08 m² 1.534.874,25 15.471.532,46
- Droop seilling + indirect lamp 6,70 m² 255.812,38 1.713.942,91

c . RUANG TUNGGU
- Kursi Tunggu 4 seater 22,00 set 5.481.693,76 120.597.262,64
- TV LED 42'' 1,00 unit 6.166.905,48 6.166.905,48

d . RUANG LOUNGE DOKTER


- Meja Kerja dokter 1,00 set 4.385.355,00 4.385.355,00
- Kursi Kerja Dokter 1,00 unit 1.827.231,25 1.827.231,25
- Kursi Hadap Dokter 2,00 unit 1.096.338,75 2.192.677,50
- Sofa 2 seater 1,00 unit 3.654.462,50 3.654.462,50

e . RUANG PRAKTEK TYPE 1 ( 16 R00M )


- Meja Kerja dokter 16,00 set 4.385.355,00 70.165.680,08
- Kursi Kerja Dokter 16,00 unit 1.827.231,25 29.235.700,03
- Kursi Hadap Dokter 32,00 unit 1.096.338,75 35.082.840,04
- Bed Pasien K1 16,00 unit 11.283.152,98 180.530.447,70

f . RUANG PRAKTEK TYPE 2 ( 2 ROOM )


- Meja Kerja dokter 2,00 set 4.385.355,00 8.770.710,01
- Kursi Kerja Dokter 2,00 unit 1.827.231,25 3.654.462,50
- Kursi Hadap Dokter 4,00 unit 1.096.338,75 4.385.355,00

f . LAIN - LAIN
- Vertical blind 72,00 m² 575.577,84 41.441.604,80
SUB TOTAL RUANG POLIKLINIK 582.090.462,03

5 . DEPARTEMEN FARMASI
a . COUNTER FARMASI
- Meja counter Farmasi 1,00 set 22.200.859,71 22.200.859,71
- Kursi Kerja staf 3,00 unit 1.096.338,75 3.289.016,25
- Cabinet Display Farmasi 1,00 unit 20.720.802,40 20.720.802,40
- Kursi Tunggu 4 seater 11,00 set 6.578.032,51 72.358.357,58
- Backdroop panel + Signage + Lamp 14,00 m² 1.534.874,25 21.488.239,52

b . KASIR
- Meja Kasir 1,00 set 9.209.245,51 9.209.245,51
- Kursi Kerja staf 2 2,00 unit 1.370.423,44 2.740.846,88
- Backdroop panel + Signage + Lamp 8,96 m² 1.315.606,50 11.787.834,25

c . KEPALA FARMASI
- Meja kerja Manager 1,00 unit 5.024.885,94 5.024.885,94
- Kursi Kerja Manager 1,00 unit 2.284.039,07 2.284.039,07
- Kursi hadap Manager 2,00 unit 1.096.338,75 2.192.677,50

d . MEJA KONSULTASI
- Meja konsultasi 1,00 unit 3.837.185,63 3.837.185,63
- Kursi Kerja staf 2 1,00 unit 1.370.423,44 1.370.423,44
- Kursi Hadap Staf 2 2,00 unit 959.296,41 1.918.592,81

e. RUANG ARSIP
- Lemari Arsip 15,00 unit 9.867.048,76 148.005.731,42

f. RUANG PRODUKSI FARMASI


- Meja Laboratorium /Racik - Island bench 3,00 ml 16.445.081,27 49.335.243,81
- Meja Laboratorium /Racik - Wall bench 6,50 ml 8.907.752,35 57.900.390,30

g. LAIN-LAIN
- Vertical blind 6,00 m² 575.577,84 3.453.467,07
SUB TOTA DEPARTEMEN FARMASI 439.117.839,09
6 . DEPARTEMEN FISIOTERAPI
a . RUANG TUNGGU
- Kursi Tunggu 4 sheater 3,00 set 5.481.693,76 16.445.081,27
- Backdroop panel + Signage + Lamp 9,52 m² 1.534.874,25 14.612.002,88

b . RUANG FISIO TYPE 1


- Meja Kerja dokter 3,00 set 4.385.355,00 13.156.065,01
- Kursi Kerja Dokter 3,00 unit 1.827.231,25 5.481.693,76
- Kursi Hadap Dokter 6,00 unit 1.096.338,75 6.578.032,51
- Bed Pasien K1 3,00 unit 11.283.152,98 33.849.458,94

c . RUANG FISIO TYPE 2


- Meja Kerja dokter 2,00 set 4.385.355,00 8.770.710,01
- Kursi Kerja Dokter 2,00 unit 1.827.231,25 3.654.462,50
- Kursi Hadap Dokter 4,00 unit 1.096.338,75 4.385.355,00

d. LAIN-LAIN
- Vertical blind 48,00 m² 575.577,84 27.627.736,53
SUB TOTA DEPARTEMEN FISIOTERAPI 134.560.598,42

7 . DEPARTEMEN BPJS
a . RUANG CODING BPJS
- Meja kerja Staff 3,00 unit 2.740.846,88 8.222.540,63
- Kursi Kerja Staf 3,00 unit 1.644.508,13 4.933.524,38
- Lemari Arsip 2,00 unit 9.867.048,76 19.734.097,52

b . RUANG KONSULTASI BPJS


- Meja kerja Staff 1,00 unit 2.740.846,88 2.740.846,88
- Kursi Kerja Staf 1,00 unit 1.644.508,13 1.644.508,13
- Kursi Hadap Staf 2,00 unit 913.615,63 1.827.231,25
- Lemari Arsip 1,00 unit 9.867.048,76 9.867.048,76
SUB TOTA DEPARTEMEN BPJS 48.969.797,56

8 . DEPARTEMEN LABORATORIUM
a . RUANG KONSULTASI
- Meja Kerja dokter 1,00 set 4.385.355,00 4.385.355,00
- Kursi Kerja Dokter 1,00 unit 1.827.231,25 1.827.231,25
- Kursi Hadap Dokter 2,00 unit 1.096.338,75 2.192.677,50
- Kursi Tunggu 4 seater 2,00 set 6.578.032,51 13.156.065,01
- TV LED 42'' 1,00 unit 6.166.905,48 6.166.905,48

b . BAG ADMINISTRASI
- Meja Kerja Kepala 1,00 set 4.385.355,00 4.385.355,00
- Kursi Kerja Kepala 1,00 unit 1.827.231,25 1.827.231,25
- Kursi Hadap Kepala 2,00 unit 1.279.061,88 2.558.123,75
- Meja kerja Staff 2,00 unit 2.740.846,88 5.481.693,76
- Kursi Kerja Staf 2,00 unit 1.644.508,13 3.289.016,25
- Lemari Arsip 2,00 unit 8.222.540,63 16.445.081,27

c . BAG STAFF
- Meja Kerja staff 1,00 unit 2.740.846,88 2.740.846,88
- Kursi Kerja staff 6,00 unit 1.370.423,44 8.222.540,63

d . RUANG DOKTER
- Meja Kerja dokter 1,00 set 4.385.355,00 4.385.355,00
- Kursi Kerja Dokter 1,00 unit 1.827.231,25 1.827.231,25
- Kursi Hadap Dokter 2,00 unit 1.096.338,75 2.192.677,50
- Sofa 2 seater 1,00 unit 4.385.355,00 4.385.355,00

e . LABORATORIUM KIMIA
- Meja Laboratorium /Racik - Wall bench 5,00 mI 8.313.902,20 41.569.510,98

f . LABORATORIUM URINE
- Meja Laboratorium /Racik - Wall bench 2,90 mI 8.313.902,20 24.110.316,37

g . LABORATORIUM HEMATOLOGI
- Meja Laboratorium /Racik - Island bench 2,00 mI 15.348.742,52 30.697.485,03
- Meja Laboratorium /Racik - Wall bench 3,50 mI 8.313.902,20 29.098.657,69

h. LABORATORIUM FESES,BTA,SPUTUM
- Meja Laboratorium /Racik - Wall bench 7,00 mI 8.313.902,20 58.197.315,38

i . RUANG GUDANG
- Lemari Arsip 6,00 unit 9.867.048,76 59.202.292,57

j. LAIN-LAIN
- Vertical blind 15,84 m² 575.577,84 9.117.153,06
SUB TOTA DEPARTEMEN LABORATORIUM 337.461.472,89

9 . PENINGKATAN INTERIOR DISAIN


a . PENINGKATAN INTERIOR DISAIN
- Peningkatan interior disain 1,00 ls 663.986,76 663.986,76
SUB TOTAL PENINGKATAN INTERIOR DISAIN 663.986,76

TOTAL PEKERJAAN MEBELEUR DAN INTERIOR LANTAI 1 3.177.936.826,86

C. LANTAI 2
1 . RUANG LOBBY
a . RUANG TUNGGU
- Kursi Tunggu 4 seater 14,00 set 6.578.032,51 92.092.455,10
- Wall Panel Lift 24,60 m² 1.644.508,13 40.454.899,92
- Wall Panel 24,60 m² 931.887,94 22.924.443,29
- TV 49 inch 24,60 unit 8.222.540,63 202.274.499,60
- Vertical blind 12,00 m² 575.577,84 6.906.934,13
SUB TOTAL RUANG LOBBY 364.653.232,05

2 . BAGIAN HEMODIALISA
a . RUANG HEMODIALISA
- Bed Pasien K3 12,00 unit 10.278.175,79 123.338.109,51
- Meja Registrasi 1 1,00 set 8.880.343,89 8.880.343,89

b . RUANG TUNGGU
- Kursi Tunggu 4 seater 3,00 set 6.578.032,51 19.734.097,52

c . MEJA KONSULTASI
- Meja Konsultasi 1,00 unit 3.837.185,63 3.837.185,63
- Kursi kerja staff 2 1,00 unit 1.370.423,44 1.370.423,44
- Kursi Hadap Staff 2 2,00 unit 1.279.061,88 2.558.123,75

d . RUANG OBAT
- Lemari Arsip 1,00 unit 9.867.048,76 9.867.048,76

e. LAIN-LAIN
- Vertical blind 33,60 m² 575.577,84 19.339.415,57
SUB TOTAL BAGIAN HEMODIALISA 188.924.748,08

3 . BAGIAN ICU
a . RUANG PERIKSA
- Bed Pasien K2 5,00 unit 12.151.087,83 60.755.439,13
- Meja Registrasi 1 1,00 set 8.880.343,89 8.880.343,89
- Kursi Hadap Staff 2 2,00 unit 1.370.423,44 2.740.846,88

b . RUANG DOKTER
- Meja Kerja dokter 1,00 set 4.385.355,00 4.385.355,00
- Kursi Kerja Dokter 1,00 unit 1.827.231,25 1.827.231,25
- Kursi Hadap Dokter 2,00 unit 1.096.338,75 2.192.677,50
- Sofa 2 seater 1,00 unit 4.385.355,00 4.385.355,00

c . RUANG PERAWAT
- Lemari Arsip 1,00 unit 9.867.048,76 9.867.048,76
- Sofa 2 seater 1,00 unit 4.385.355,00 4.385.355,00

d . RUANG ISOLASI
- Bed Pasien K2 1,00 unit 12.151.087,83 12.151.087,83

e. LAIN-LAIN
- Vertical blind 24,00 m² 575.577,84 13.813.868,27
SUB TOTAL BAGIAN ICU 125.384.608,52

4 . RUANG VK
a . RUANG PERIKSA
- Bed Pasien K2 6,00 unit 12.151.087,83 72.906.526,96
- Meja Registrasi 1 1,00 set 8.880.343,89 8.880.343,89
- Meja kerja staff 1,00 unit 2.740.846,88 2.740.846,88
- Kursi Kerja Staff 2 2,00 unit 1.370.423,44 2.740.846,88
- Backdroop panel + Signage + Lamp 10,80 m² 1.534.874,25 16.576.641,92
SUB TOTAL RUANG VK 103.845.206,52

5 . RUANG PRE -OP


a . RUANG PRE -OP
- Bed Pasien K2 4,00 unit 12.151.087,83 48.604.351,30
- Meja Registrasi 1 1,00 set 8.880.343,89 8.880.343,89
- Kursi Kerja Staff 2 2,00 unit 1.370.423,44 2.740.846,88

b . RUANG ADM
- Meja kerja staff 1,00 unit 2.740.846,88 2.740.846,88
- Kursi Kerja Staff 2 1,00 unit 1.370.423,44 1.370.423,44
- Lemari Arsip 1,00 unit 6.906.934,13 6.906.934,13
SUB TOTAL RUANG PRE -OP 71.243.746,52

6 . RUANG POST -OP


a . RUANG POST -OP
- Bed Pasien K2 5,00 unit 12.151.087,83 60.755.439,13
- Meja Registrasi 1 1,00 set 20.556.351,59 20.556.351,59
- Kursi Kerja Staff 2 2,00 unit 1.370.423,44 2.740.846,88
- Backdroop panel + Signage + Lamp 9,60 m² 1.534.874,25 14.734.792,82

b . RUANG ADM
- Meja kerja staff 1,00 unit 2.740.846,88 2.740.846,88
- Kursi Kerja Staff 2 1,00 unit 1.370.423,44 1.370.423,44
- Lemari Arsip 1,00 unit 6.906.934,13 6.906.934,13

c . RUANG MEETING
- Meja Rapat 1,00 set 12.425.172,51 12.425.172,51
- Kursi Kerja Staff 2 6,00 unit 1.142.019,53 6.852.117,20
- Backdroop panel + Signage + Glasboard 9,60 m² 1.534.874,25 14.734.792,82

d . RUANG LOUNGE DOKTER


- Meja Kerja dokter 1,00 set 4.385.355,00 4.385.355,00
- Kursi Kerja Dokter 1,00 unit 1.827.231,25 1.827.231,25
- Kursi Hadap Dokter 2,00 unit 1.096.338,75 2.192.677,50
- Sofa 2 seater 1,00 unit 4.385.355,00 4.385.355,00
- Vertical blind 4,80 m² 575.577,84 2.762.773,65

e . RUANG PERAWAT
- Meja kerja staff 2,00 unit 2.740.846,88 5.481.693,76
- Kursi Kerja Staff 2 2,00 unit 1.370.423,44 2.740.846,88
- Lemari Arsip 2,00 unit 9.867.048,76 19.734.097,52
- Vertical blind 4,80 m² 575.577,84 2.762.773,65
SUB TOTAL RUANG POST -OP 190.090.521,61

7 . RUANG IBU DAN ANAK


a . NURSE STATION
- Meja Registrasi 1 1,00 set 19.734.097,52 19.734.097,52
- Kursi Kerja Staff 2 3,00 unit 1.370.423,44 4.111.270,32
- Backdroop panel + Signage + Lamp 1,00 m² 1.534.874,25 1.534.874,25

b . RUANG LOUNGE DOKTER


- Meja Kerja dokter 1,00 set 4.385.355,00 4.385.355,00
- Kursi Kerja Dokter 1,00 unit 1.827.231,25 1.827.231,25
- Kursi Hadap Dokter 2,00 unit 1.096.338,75 2.192.677,50
- Sofa 2 seater 1,00 unit 4.385.355,00 4.385.355,00

c . KEPALA BAGIAN
- Meja Kerja Manager 1,00 unit 6.029.863,13 6.029.863,13
- Kursi Kerja Manager 1,00 unit 2.740.846,88 2.740.846,88
- Kursi Hadap Manager 2,00 unit 1.827.231,25 3.654.462,50
- Lemari Arsip 1,00 unit 9.867.048,76 9.867.048,76

d . PERAWAT
- Meja kerja staff 2,00 unit 2.740.846,88 5.481.693,76
- Kursi Kerja Staff 2 2,00 unit 1.370.423,44 2.740.846,88
- Lemari Arsip 2,00 unit 9.867.048,76 19.734.097,52

e . RUANG ISOLASI ( 3 ROOM )


- Bed Pasien K1 3,00 unit 12.151.087,83 36.453.263,48
- Kursi Pasien K1 3,00 unit 1.096.338,75 3.289.016,25
- Vertical blind 15,84 m² 575.577,84 9.117.153,06
- Tirai Pembatas + Hanging rail 39,00 m² 274.084,69 10.689.302,82

f . RUANG PERAWATAN ANAK KELAS VIP ( 2 ROOM )


- Bed Pasien K VIP - unit 22.840.390,65 -
- Meja Pasien K VIP - unit 6.395.309,38 -
- Kursi Pasien K VIP - unit 3.654.462,50 -
- Sofa 2 seater - unit 7.308.925,01 -
- Meja Sofa 2 - unit 2.740.846,88 -
- Medicine Panel 14,40 m² 1.087.202,59 15.655.717,37
- Vertical blind 11,52 m² 575.577,84 6.630.656,77
- Tirai Pembatas + Hanging rail - m² 456.807,81 -

g . RUANG PERAWATAN ANAK KELAS 1 - 2 BED ( 2 ROOM )


- Bed Pasien K 1 2,00 unit 12.151.087,83 24.302.175,65
- Kursi Pasien K 1 2,00 unit 1.370.423,44 2.740.846,88
- Meja Pasien K 1 2,00 unit 2.740.846,88 5.481.693,76
- Medicine Panel 11,52 m² 1.087.202,59 12.524.573,89
- Vertical blind 11,52 m² 575.577,84 6.630.656,77
- Tirai Pembatas + Hanging rail 26,00 m² 319.765,47 8.313.902,20

h . RUANG PERAWATAN ANAK KELAS 3


- Bed Pasien K 3 6,00 unit 9.592.964,07 57.557.784,44
- Vertical blind 5,76 m² 575.577,84 3.315.328,38

i . RUANG PERAWATAN IBU KELAS 1 - 2 BED ( 2 ROOM )


- Bed Pasien K 1 36,00 unit 12.151.087,83 437.439.161,74
- Kursi Pasien K 1 36,00 unit 1.644.508,13 59.202.292,57
- Meja Pasien K 1 36,00 unit 2.740.846,88 98.670.487,61
- Medicine Panel 11,52 m² 1.087.202,59 12.524.573,89
- Tirai Pembatas + Hanging rail 468,00 m² 319.765,47 149.650.239,54
- Vertical blind 11,52 m² 575.577,84 6.630.656,77

J . RUANG PERAWATAN IBU KELAS 3 ( 3 ROOM )


- Bed Pasien K 3 - unit 13.704.234,39 -
- Vertical blind 7,20 m² 575.577,84 4.144.160,48
- Tirai Pembatas + Hanging rail - m² 456.807,81 -
SUB TOTAL RUANG IBU DAN ANAK 1.059.383.364,61
8 . PENINGKATAN INTERIOR DISAIN
a . PENINGKATAN INTERIOR DISAIN
- Peningkatan interior disain 1,00 LS 313.235.383,44 313.235.383,44
SUB TOTAL PENINGKATAN INTERIOR DISAIN 313.235.383,44
TOTAL PEKERJAAN MEBELEUR DAN INTERIOR LANTAI 2 2.416.760.811,34

D. LANTAI 3
1 . RUANG MANAGEMENT
a . RUANG DIREKTUR UTAMA
- Meja Kerja Direktur utama 1,00 unit 12.425.172,51 12.425.172,51
- Kursi Kerja Direktur Utama 1,00 unit 4.385.355,00 4.385.355,00
- Kursi Hadap Direktur Utama 2,00 unit 2.192.677,50 4.385.355,00
- Cabinet 1,00 unit 25.325.425,15 25.325.425,15
- Vertical blind 6,00 m² 575.577,84 3.453.467,07

- Meja Kerja Direktur 1,00 unit 15.348.742,52 15.348.742,52


- Kursi Kerja Direktur 6,00 unit 3.197.654,69 19.185.928,15
- Sofa 3 seater 1,00 unit 6.578.032,51 6.578.032,51
- Sofa 1 seater 2,00 unit 2.740.846,88 5.481.693,76
- Meja Sofa 1,00 unit 1.644.508,13 1.644.508,13
- Vertical blind 6,00 m² 575.577,84 3.453.467,07

b . RUANG RAPAT UTAMA


- Meja Kerja Direktur utama 1,00 unit 15.348.742,52 15.348.742,52
- Kursi Kerja Direktur Utama 12,00 unit 2.740.846,88 32.890.162,54
- Backdroop panel + Signage + Glasboard 11,40 m² 1.534.874,25 17.497.566,47
- Droop seilling + indirect lamp 12,50 m² 255.812,38 3.197.654,69

c . RUANG DIREKTUR ( 2 PAX ))


- Meja Kerja Direktur 2,00 unit 8.907.752,35 17.815.504,71
- Kursi Kerja Direktur 2,00 unit 3.197.654,69 6.395.309,38
- Kursi Hadap Direktur 4,00 unit 1.827.231,25 7.308.925,01
- Cabinet 2,00 unit 25.325.425,15 50.650.850,31
- Vertical blind 6,00 m² 575.577,84 3.453.467,07
- Sofa 3 seater 2,00 unit 6.578.032,51 13.156.065,01
- Sofa 1 seater 4,00 unit 2.740.846,88 10.963.387,51
- Meja Sofa 2,00 unit 1.918.592,81 3.837.185,63

d . RUANG SEKRETARIS
- Meja Kerja Sekretasris 2,00 unit 4.933.524,38 9.867.048,76
- Kursi Kerja Sekretasris 2,00 unit 2.284.039,07 4.568.078,13
- Kursi Hadap Sekretasris 4,00 unit 1.461.785,00 5.847.140,01
- Meja Kerja Rapat Direktur 1,00 unit 16.445.081,27 16.445.081,27
- Kursi Rapat Direktur 6,00 unit 2.284.039,07 13.704.234,39

e . SELASAR
- Backdroop panel + Signage + Lamp 40,00 m² 1.534.874,25 61.394.970,07
SUB TOTAL RUANG MANAGEMENT 396.008.520,33

2 . RUANG PENDUKUNG
a . KANTIN
- Meja Kantin 12,00 unit 1.370.423,44 16.445.081,27
- Kursi Makan 48,00 unit 776.573,28 37.275.517,54
- Pantry 7,50 mI 2.558.123,75 19.185.928,15
- Counter Kantin 7,50 mI 3.837.185,63 28.778.892,22
- Droop seilling + indirect lamp 55,00 m² 255.812,38 14.069.680,64
- Wall Panel 18,00 m² 1.087.202,59 19.569.646,71

b . MUSHOLA
- Bench Pria 3,00 unit 1.644.508,13 4.933.524,38
- Bench Wanita 3,00 unit 1.644.508,13 4.933.524,38
- Vinil Tile Lantai 45,00 m² 479.648,20 21.584.169,16

c . FOYER
- Droop seilling + indirect lamp 35,00 m² 255.812,38 8.953.433,14
- Hanging Lamp Decorative 4,00 unit 959.296,41 3.837.185,63
- Hiasan Dinding 4,00 m² 639.530,94 2.558.123,75
SUB TOTAL RUANG PENDUKUNG 182.124.706,97

3 . RUANG PERAWATAN
a . NURSE STATION
- Meja Counter 1,00 set 11.347.106,08 11.347.106,08
- Kursi Kerja Staff 3,00 unit 1.370.423,44 4.111.270,32
- Backdroop panel + Signage + Lamp 8,40 m² 1.534.874,25 12.892.943,71

b . RUANG PERAWATAN KELAS 2 - 4 BED ( 5 ROOM )


- Bed Pasien K 2 - unit 17.358.696,89 -
- Bed side table K 2 - unit 3.654.462,50 -
- Kursi Pasien K 2 - unit 2.740.846,88 -
- Tirai Pembatas + Hanging rail - m² 456.807,81 -
- Medicine Panel 12,00 m² 1.087.202,59 13.046.431,14
- Vertical blind 48,00 m² 575.577,84 27.627.736,53

c . RUANG PERAWATAN KELAS 2 - 2 BED ( 1 ROOM )


- Bed Pasien K 2 - unit 17.358.696,89 -
- Bed side table K 2 - unit 3.654.462,50 -
- Kursi Pasien K 2 - unit 2.740.846,88 -
- Tirai Pembatas + Hanging rail - m² 456.807,81 -
- Medicine Panel 2,40 m² 1.087.202,59 2.609.286,23
- Vertical blind 9,60 m² 575.577,84 5.525.547,31

d . RUANG ISOLASI (1 ROOM )


- Bed Pasien K1 1,00 unit 12.151.087,83 12.151.087,83
- Kursi Pasien K1 1,00 unit 1.370.423,44 1.370.423,44
- Vertical blind 9,60 m² 575.577,84 5.525.547,31
- Tirai Pembatas + Hanging rail 4,75 m² 319.765,47 1.518.885,98

e . RUANG PERAWATAN KELAS 3 ( 5 ROOM )


- Bed Pasien K 2 10,00 unit 9.592.964,07 95.929.640,73
- Bed side table K 2 10,00 unit 2.558.123,75 25.581.237,53
- Kursi Pasien K 2 10,00 unit 1.370.423,44 13.704.234,39
- Tirai Pembatas + Hanging rail 47,50 m² 319.765,47 15.188.859,78
- Medicine Panel 12,00 m² 1.087.202,59 13.046.431,14
- Vertical blind 48,00 m² 575.577,84 27.627.736,53

f . RUANG ISOLASI (1 ROOM )


- Bed Pasien K1 1,00 unit 12.151.087,83 12.151.087,83
- Kursi Pasien K1 1,00 unit 1.918.592,81 1.918.592,81
- Medicine Panel 2,40 m² 1.087.202,59 2.609.286,23
- Vertical blind 9,60 m² 575.577,84 5.525.547,31
- Tirai Pembatas + Hanging rail 4,75 m² 319.765,47 1.518.885,98
SUB TOTAL RUANG PERAWATAN 312.527.806,12

4 . RUANG PRE FUCTION


- Backdroop panel + Signage + Lamp 24,00 m² 1.534.874,25 36.836.982,04
- Droop seilling + indirect lamp 28,00 m² 255.812,38 7.162.746,51
- Meja Sofa 2 2,00 unit 1.918.592,81 3.837.185,63
- Sofa 1 Seater 6,00 unit 2.740.846,88 16.445.081,27
- Vertical blind 4,80 m² 575.577,84 2.762.773,65
SUB TOTAL RUANG PREPUCNTION 67.044.769,10

5 . PENINGKATAN INTERIOR DISAIN


a . PENINGKATAN INTERIOR DISAIN
- Peningkatan interior disain 1,00 ls 300.940.946,55 300.940.946,55
SUB TOTAL PENINGKATAN INTERIOR DISAIN 300.940.946,55
TOTAL PEKERJAAN MEBELEUR DAN INTERIOR LANTAI 3 1.258.646.749,08

E. LANTAI 4
1 . RUANG PERAWATAN KELAS 1
a . NURSE STATION
- Meja Counter 1,00 set 11.347.106,08 11.347.106,08
- Kursi Kerja Staff 3,00 unit 1.370.423,44 4.111.270,32
- Backdroop panel + Signage + Lamp 8,40 m² 1.534.874,25 12.892.943,71
- Droop seilling + indirect lamp 6,70 m² 255.812,38 1.713.942,91

b . RUANG PERAWATAN KELAS 1 - 2 BED ( 10 ROOM )


- Bed Pasien K 1 20,00 unit 12.151.087,83 243.021.756,52
- Bed side table K 1 20,00 unit 2.558.123,75 51.162.475,06
- Kursi Pasien K 1 20,00 unit 1.370.423,44 27.408.468,78
- Tirai Pembatas + Hanging rail 190,00 m² 319.765,47 60.755.439,13
- Medicine Panel 20,00 m² 1.087.202,59 21.744.051,90

c . RUANG ISOLASI (1 ROOM )


- Bed Pasien K1 1,00 unit 12.151.087,83 12.151.087,83
- Kursi Pasien K1 1,00 unit 1.370.423,44 1.370.423,44
- Tirai Pembatas + Hanging rail 9,50 m² 319.765,47 3.037.771,96
- Medicine Panel 1,00 m² 1.087.202,59 1.087.202,59
SUB TOTAL RUANG PERAWATAN KELAS 1 451.803.940,23

2 . RUANG PERAWATAN KELAS VIP


a . RUANG PERAWATAN KELAS VIP - 1 BED ( 10 ROOM )
- Bed Pasien K VIP - unit
- Kursi Pasien K VIP - unit
- Bed side table K VIP 10,00 unit 2.558.123,75 25.581.237,53
- Meja Pasien K VIP - unit
- Sofa 2 Seater - unit
- Meja Sofa 2 - unit
- Tirai Pembatas + Hanging rail - m²
SUB TOTAL RUANG PERAWATAN KELAS VIP 25.581.237,53

3 . RUANG PRE FUCTION


- Backdroop panel + Signage + Lamp 24,00 m² 1.534.874,25 36.836.982,04
- Droop seilling + indirect lamp 28,00 m² 255.812,38 7.162.746,51
- Meja Sofa 2 2,00 unit 1.644.508,13 3.289.016,25
- Sofa 1 Seater 6,00 unit 2.740.846,88 16.445.081,27
SUB TOTAL RUANG PREPUCTION 63.733.826,07

4 . PENINGKATAN INTERIOR DISAIN


a . PENINGKATAN INTERIOR DISAIN
- Peningkatan interior disain 1,00 ls 161.001.593,93 161.001.593,93
SUB TOTAL PENINGKATAN INTERIOR DISAIN 161.001.593,93

TOTAL PEKERJAAN MEBELEUR DAN INTERIOR LANTAI 4 702.120.597,76

F. LANTAI 5
1 . RUANG PERAWATAN KELAS 1
a . NURSE STATION
- Meja Counter 1,00 set 11.347.106,08 11.347.106,08
- Kursi Kerja Staff 3,00 unit 1.644.508,13 4.933.524,38
- Backdroop panel + Signage + Lamp 8,40 m² 1.534.874,25 12.892.943,71

b . RUANG PERAWATAN KELAS 1 - 2 BED ( 10 ROOM )


- Bed Pasien K 1 20,00 unit 12.151.087,83 243.021.756,52
- Bed side table K 1 20,00 unit 2.558.123,75 51.162.475,06
- Kursi Pasien K 1 20,00 unit 1.370.423,44 27.408.468,78
- Tirai Pembatas + Hanging rail 190,00 unit 319.765,47 60.755.439,13
- Medicine Panel 20,00 unit 1.087.202,59 21.744.051,90

c . RUANG ISOLASI (1 ROOM )


- Bed Pasien K1 1,00 unit 12.151.087,83 12.151.087,83
- Kursi Pasien K1 1,00 unit 1.370.423,44 1.370.423,44
- Tirai Pembatas + Hanging rail 9,50 unit 319.765,47 3.037.771,96
- Medicine Panel 1,00 unit 1.087.202,59 1.087.202,59
SUB TOTAL RUANG PERAWATAN KELAS 1 450.912.251,38

2 . RUANG PERAWATAN KELAS VIP


a . RUANG PERAWATAN KELAS VIP - 1 BED ( 10 ROOM )
- Bed Pasien K VIP 10,00 unit 15.988.273,46 159.882.734,56
- Kursi Pasien K VIP 10,00 unit 2.192.677,50 21.926.775,02
- Bed side table K VIP 10,00 unit 2.558.123,75 25.581.237,53
- Meja Pasien K VIP 10,00 unit 3.197.654,69 31.976.546,91
- Sofa 2 Seater 10,00 unit 4.385.355,00 43.853.550,05
- Meja Sofa 2 10,00 unit 1.644.508,13 16.445.081,27
- Tirai Pembatas + Hanging rail 95,00 unit 319.765,47 30.377.719,57
SUB TOTAL RUANG PERAWATAN KELAS VIP 330.043.644,90
3 . RUANG PRE FUCTION
- Backdroop panel + Signage + Lamp 24,00 m² 1.534.874,25 36.836.982,04
- Droop seilling + indirect lamp 28,00 m² 255.812,38 7.162.746,51
- Meja Sofa 2 2,00 unit 1.644.508,13 3.289.016,25
- Sofa 1 Seater 6,00 unit 2.740.846,88 16.445.081,27
SUB TOTAL RUANG PRE FUCTION 63.733.826,07
4 . PENINGKATAN INTERIOR DISAIN
a . PENINGKATAN INTERIOR DISAIN
- Peningkatan interior disain 1,00 ls 156.090.116,56 156.090.116,56
SUB TOTAL PENINGKATAN INTERIOR DISAIN 156.090.116,56

TOTAL PEKERJAAN MEBELEUR DAN INTERIOR LANTAI 5 1.000.779.838,91

G. LANTAI 5
1 . RUANG PERAWATAN KELAS VIP
a . NURSE STATION
- Meja Counter 1,00 set 11.347.106,08 11.347.106,08
- Kursi Kerja Staff 3,00 unit 1.644.508,13 4.933.524,38
- Backdroop panel + Signage + Lamp 8,40 m² 1.534.874,25 12.892.943,71

b . RUANG PERAWATAN KELAS VIP - 1 BED ( 10 ROOM )


- Bed Pasien K VIP 10,00 unit 15.988.273,46 159.882.734,56
- Kursi Pasien K VIP 10,00 unit 2.192.677,50 21.926.775,02
- Bed side table K VIP 10,00 unit 2.558.123,75 25.581.237,53
- Meja Pasien K VIP 10,00 unit 3.837.185,63 38.371.856,29
- Sofa 2 Seater 10,00 unit 4.385.355,00 43.853.550,05
- Meja Sofa 2 10,00 unit 1.644.508,13 16.445.081,27
- Tirai Pembatas + Hanging rail 95,00 unit 319.765,47 30.377.719,57

c . RUANG ISOLASI (1 ROOM )


- Bed Pasien K1 1,00 unit 12.151.087,83 12.151.087,83
- Kursi Pasien K1 1,00 unit 1.370.423,44 1.370.423,44
- Tirai Pembatas + Hanging rail 1,00 unit 319.765,47 319.765,47
- Medicine Panel 1,00 unit 1.087.202,59 1.087.202,59
SUB TOTAL RUANG PERAWATAN KELAS VIP 380.541.007,79

2 . RUANG PRE FUCTION


- Backdroop panel + Signage + Lamp 24,00 m² 1.534.874,25 36.836.982,04
- Droop seilling + indirect lamp 28,00 m² 255.812,38 7.162.746,51
- Meja Sofa 2 2,00 unit 1.370.423,44 2.740.846,88
- Sofa 1 Seater 6,00 unit 2.740.846,88 16.445.081,27
SUB TOTAL RUANG PRE FUCTION 63.185.656,70
3 . RUANG SERBA GUNA
- Folding table 80,00 unit 2.238.358,28 179.068.662,70
- Stacking chair 160,00 unit 1.004.977,19 160.796.350,18
SUB TOTAL RUANG SERBA GUNA 339.865.012,88

4 . PENINGKATAN INTERIOR DISAIN


a . PENINGKATAN INTERIOR DISAIN
- Peningkatan interior disain 1,00 ls 220.536.345,74 220.536.345,74
SUB TOTAL PENINGKATAN INTERIOR DISAIN 220.536.345,74

TOTAL PEKERJAAN MEBELEUR DAN INTERIOR LANTAI 6 1.004.128.023,11


TOTAL JUMLAH ( A+B+C+D+E+F+G ) 12.199.336.468,88
DI BULATKAN 12.199.336.000,00