Download as pdf or txt
Download as pdf or txt
You are on page 1of 12

International Journal of Civil Engineering (2018) 16:1329–1340

https://doi.org/10.1007/s40999-017-0261-0

RESEARCH PAPER

Critical Tendon Bond Length for Prestressed Ground Anchors in Pullout


Performance Tests Conducted in Sand
Hakki O. Ozhan1 · Erol Guler2

Received: 3 March 2017 / Revised: 25 September 2017 / Accepted: 5 October 2017 / Published online: 13 November 2017
© Iran University of Science and Technology 2017

Abstract
In this study, pullout performance tests were conducted on five prestressed ground anchors having different tendon bond
and unbonded lengths. The tendon bond lengths of the tested anchors varied from 4 to 10 m, whereas the unbonded lengths
were in the range of 8–16 m. The tests were performed separately on a dense, gravelly sandy soil slope with an inclination
of 90° in Cottbus, Germany. The anchors were inclined downwards at an angle of 15° below the horizontal. The results
indicated that three of the five anchors did not satisfy the acceptance criteria as outlined in DIN 4125 Standards. According
to the acceptance criteria, the line that was composed of the elastic displacements of the unbonded length had to remain
between two specific limit lines. Although the elastic displacements of the unbonded tendons were taken into account for
the acceptance of the anchors, the length of the unbonded tendon did not have a significant effect on stability. The anchors
having unbonded lengths of 8, 13, and 15 m failed, whereas the anchors with unbonded length of 9 and 16 m were accepted
after the termination of the performance tests. However, the tendon bond length was proved to be an important parameter
that contributed to the acceptance of the tested anchors. Test results indicated that anchors having tendon bond lengths longer
or shorter than 6 m were rejected.

Keywords  Anchor tendon coefficient · Performance test · Prestressed ground anchor · Tendon bond length · Unbonded
length

1 Introduction walls, slopes, dams, bridges, and foundations or to resist


wind-produced uplift forces [2–4]. Moreover, the ground
Ground anchors offer economical solutions to temporary or anchors are used for stabilization of landslides and resistance
permanent stability problems. The service life of a ground of overturning by reducing the horizontal displacements
anchor used for a temporary application usually varies from of the structures [2]. Ground anchors are also preferred to
2 to 5 years depending on the duration of the construction braced systems to expand the working space and to increase
project, whereas permanent ground anchors are used for the efficiency of construction. Therefore, anchors reduce
the whole life of the permanent structure [1]. Designed to construction time and cost [5].
withstand lateral and uplift forces, the ground anchors are In practice, ground anchors can generally be classified
temporarily used as a part of deep excavation support sys- into two main groups: prestressed anchors that are formed
tems or permanently used to strengthen and protect retaining by tensioning the anchors and passive anchors that are unten-
sioned and mobilized with the displacement of the retained
structure. A prestressed ground anchor is a structural ele-
* Hakki O. Ozhan
hakki.ozhan@altinbas.edu.tr ment embedded in grout filled drill holes and is used to
transmit an applied tensile load into the ground. In general,
Erol Guler
eguler@boun.edu.tr the anchor is prestressed to protect the soil against tensile
overloads [6]. The decision of whether to use prestressed
1
Department of Civil Engineering, Altinbas University, anchors or passive anchors depends on several factors such
Mahmutbey Dilmenler Cad. No: 26 Bagcilar, Istanbul, as the level of displacements of the anchor, the nature of the
Turkey
rock in which the anchor is to be embedded and the risk of
2
Department of Civil Engineering, Bogazici University, corrosion [7]. Main advantages of using a prestressed anchor
Bebek, 34342 Istanbul, Turkey

13
Vol.:(0123456789)

1330 International Journal of Civil Engineering (2018) 16:1329–1340

instead of a passive anchor are the significant reduction in The tendon includes the prestressing steel element
the displacements of the anchor due to the application of (strands or bars), corrosion protection, and sheath. The
a prestress load, and the transfer of a permanent stabiliz- sheath is a tube that protects the prestressing steel in the
ing force on the surrounding ground due to prestressing and unbonded length from corrosion. The grout is a Portland
monitoring the performance of the anchor during prestress- cement-based mixture that provides both load transfer from
ing [7]. Many structures deliver significant tension loads to the tendon to the ground and corrosion protection for the
the foundations. In such cases, prestressed anchors are used tendon [14].
between the structures and the foundations to transfer the Anchorage of structures and stabilization of slopes
tension loads [8–11]. require the use of tendons made of prestressed strands or
Besides the usage of prestressed ground anchors in soils, bars with a high yield point. Bars composed of low-quality
prestressed anchor tendons might also be installed in struc- steel are suitable only for short anchors with a short service
tural members made of concrete. The use of prestressed steel life, such as those used in securing rock surfaces in small
strands as the tensional reinforcement in concrete T-beams underground excavations or in applications where prestress-
has demonstrably improved the mechanical properties of the ing is not preferred. The use of strands instead of bars has
structural members [12]. become popular in spite of their greater cost. When a tendon
Prestressed ground anchors are also preferred for hydrau- composed of prestressed strands is used, there is less danger
lic purposes. Prestressed anchor cables with a tensile of prestressing loss as a result of ground creep when com-
strength capacity of 1395 MPa were used as a part of the pared to a tendon composed of prestressed bars [15].
composite lining system in shield tunnels for water convey- The minimum tendon bond length has to be taken as 3 m
ance [13]. to enable the tendon bond length to be located beyond the
A typical prestressed ground anchor is composed of potential active zone [1, 2]. The unbonded length has to
anchorage, unbonded length, and tendon bond length, as be taken as greater than 3 m for bar tendons and 4.5 m for
shown in Fig. 1 [2]. The anchorage is formed by the com- strand tendons to avoid unacceptable load reductions due to
bination of the anchor head, bearing plate, and trumpet that seating losses during load transfer and prestress losses due to
transmits the prestressing force from the prestressing steel creep in the prestressed tendon of the anchor or the soil [2].
(bar or strand) to the ground or the supported structure. Hsu and Chang (2007) performed pullout tests on vertical
The unbonded length is the prestressing steel that is free to anchors embedded in a gravelly soil layer [5]. According to
elongate elastically and transfer the resisting force from the the results, the ultimate load of an anchor increased from
tendon bond length to the structure. During anchorage test- 215 to 883 kN as the tendon bond length increased from
ing, the elastic displacements are measured at the unbonded 1.5 to 5.82 m. Briaud et al. [16] also conducted pullout and
length of an anchor that is not bonded to the grout or soil creep tests on prestressed anchors with tendon bond lengths
[2]. The tendon bond length is the prestressing steel that of 4.6 and 9.2 m, respectively, embedded in stiff clay. Results
is bonded to the grout and is capable of transmitting the indicated that anchors with shorter tendon bond length had
applied tensile load into the ground [14]. higher ultimate strength and lower creep rate. Moreover,
anchors with shorter tendon bond length transferred the load
further away from the structure [16].
Fiber-reinforced polymer (FRP) anchors with tendon
bond strengths in the range of 10–15 MPa are used to pro-
vide higher pullout capacities. Ozbakkaloglu and Saatcioglu
[17] performed pullout tests on FRP anchors with diameters
of 12.7, 15.9, and 19.1 mm, embedment lengths differing
from 25 to 100 mm, and angle of inclination varying from
15° to 45°. According to the results, tendon bond strength
decreased with increasing embedment length, anchor diam-
eter, and angle of inclination [17]. Zhang et al. [18] also
performed pullout tests on several FRP prestressed ground
anchors. The results indicated that all the tested anchors with
1-m tendon bond length had acceptable tensile and creeping
behavior that controlled the long-term tensile capacity of the
tested anchors. Furthermore, more than 0.45-m increase in
tendon bond length appeared to have negligible effect on the
tensile capacity of the anchors [18].
Fig. 1  Components of a prestressed ground anchor [2]

13
International Journal of Civil Engineering (2018) 16:1329–1340 1331

Vukotic et al. [19] conducted pullout tests on single bore Table 1  Engineering properties of the soil in which the anchors were
multiple anchors (SBMA) to investigate the contribution installed in
of tendon bond length to the pullout capacity of the tested Type Slope Unit Internal Standard Anchor
anchor. SBMA were cement pressure grouted anchors pro- inclina- weight frictional penetra- inclina-
duced by prestressing the strand tendons that were embed- tion (°) (kN/m3) angle (°) tion test tion below
(SPT) horizontal
ded in a single borehole in soil or rock. These anchors had value (°)
sufficient short unit anchor lengths to cause a reduction in
debonding. The results indicated that tendon bond lengths Gravelly 90 20 40 48 15
dense
longer than 10 m did not improve the pullout capacity sig-
sand
nificantly [19].
Before being put into service in the field, the ground
anchors have to be loaded up to a limited level and the load/
deformation behavior has to be determined by conduct- Additional grout was injected under high pressure into the
ing performance tests, proof tests, or extended creep tests initial grout, which caused an enlargement in the grout body.
[1]. All these tests are performed by considering excessive Engineering parameters relating to the tested anchors
deformations due to anchor loading. The ground anchors are and the segmental anchor lengths are listed in Table 2. Four
subjected to incremental loading and unloading sequences in strands each with seven multiple-wire strand tendons were
performance tests where the deformations of the anchors are used in each test. Jacking over length of an anchor was the
recorded [20]. The acceptance criteria for performance tests part of the tendon that was not stressed. This length was
are based on allowable elastic movements of the unbonded measured as the distance between the anchor head and
length and creep of the anchor. After acceptance, the anchor the concrete bearing plate where the hydraulic jack was
is loaded up to a critical value and then locked-off [1]. installed. As can be seen in Table 2, overall lengths of the
The objective of this study was to investigate the effects anchors differed from 17 to 27 m, while the tendon bond
on stability of both tendon bond length and unbonded length lengths were in the range of 4–10 m.
of the prestressed ground anchors that were embedded in
dense sand. For this reason, pullout performance tests were 2.2 Test Procedure
performed on five prestressed ground anchors in accordance
with DIN 4125, by applying loading and unloading cycles First, the alignment load of about 10% of the tendon yield
that were in the range of 100–750 kN. In these tests, elas- strength was applied. Then, the load was increased, respec-
tic and plastic displacements of the unbonded tendons were tively, in the range of 50–75–100–125–150% of the design
measured, and load–displacement behaviors of the anchors load to determine the residual displacements. A design load
were obtained. The tendon bond lengths of the five tested of 500 kN was applied in all of the anchor tests [21].
anchors were 6, 6, 10, 4, and 8 m, respectively, while these The factor of safety was defined as the ratio of the ulti-
anchors had unbonded lengths of 9, 16, 15, 13, and 8 m. mate capacity to the working load, and it was usually taken
as 1.5 and 1.3 for permanent and temporary usages, respec-
tively [1, 20]. The maximum test load for a permanent
ground anchor had to be applied as 1.5 times of the design
2 Experimental Program load based on at rest earth pressure assumption. According
to this statement, the ultimate load, named as the planned
2.1 Material Properties testing force, was calculated as 750 kN. For cohesionless
soils, each load increment was maintained for a period of
The engineering properties of the soil in which the anchors 15 min to 2 h.
were embedded are listed in Table 1. The tests were per- A hydraulic jack was used to stress the anchors as
formed in compliance with DIN 4125 [21]. The anchors that shown in Fig. 2. Wooden blocks were placed between the
were used in this project were post-grouted ground anchors hydraulic jack and the concrete bearing plates to level the
consisting of strand tendons and high-pressure grouted clamping of the anchor tendon and the hydraulic jack.
boreholes. The rotary method was chosen for drilling with Afterwards, the displacements of the unbonded tendon
a roller bit and a thick flush that was convenient for sand. were measured using a dial gauge fixed to a tripod, as
The boreholes with diameters of 140 mm were long enough shown in Fig. 3. First, stressing the tendon was maintained
to accommodate the tendons. Each test had two injection by applying the alignment load that was taken as 100 kN,
phases where post-grouting took place during the second and then, the anchor was loaded up to 250 kN [21]. There
injection phase. Applied grout injection pressures were was an observation period of 15 min to measure the total
taken as greater than 1 MPa during all injection phases. movements of the unbonded tendon in the 1st, 2nd, 5th,

13

1332 International Journal of Civil Engineering (2018) 16:1329–1340

Overall anchor
length (mm)

19,000
18,000
17,000
24,000
27,000
Jacking over
length (mm)

2000
2000
2000
2000
2000
length (mm)
Unbonded

16,000
15,000
13,000
8000
9000
Tendon bond
length (mm)

Fig. 2  Hydraulic jack used for stressing an anchor


10,000
6000
6000

4000
8000
Total tendon
area ­(mm2)

560
560
560
560
560
Tendon area per
strand ­(mm2)

140
140
140
140
140
Table 2  Engineering parameters and anchor lengths of the prestressed ground anchors
Elasticity modu- Number of
strands

4
4
4
4
4
lus (N/mm2)

Fig. 3  Dial gauge used for measuring the displacements of the tendon


190,600
190,600
191,900
191,900
191,900

10th, and 15th minutes as outlined in DIN 4125. Then, the


tendon was unloaded down to the alignment load and the
Factor of

plastic (residual) displacement of the unbonded tendon


safety

was measured. The difference between the total movement


1.5
1.5
1.5
1.5
1.5

measured on 15th minutes and the residual displacement


was taken as the elastic displacement. The tendon was
load (kN)
Design

loaded up to 375 kN and the total displacements of the


500
500
500
500
500

unbonded tendon were measured in the 1st, 2nd, 5th, 10th,


and 15th minutes. Then, the tendon was unloaded down
to 100 kN and the plastic and elastic displacements of
Alignment
load (kN)

the unbonded tendon were measured again. This proce-


100
100
100
100
100

dure was pursued by performing reloading and unloading


cycles until the planned testing force; 750 kN was reached.
However, the observation period was taken as 60 min by
Anchor-5
Anchor-1
Anchor-2
Anchor-3
Anchor-4

taking readings in the 1st, 2nd, 5th, 10th, 15th, 30th, 45th,
and 60th minutes for 500 and 625 kN and 120 min by

13
International Journal of Civil Engineering (2018) 16:1329–1340 1333

taking readings in the 1st, 2nd, 5th, 10th, 15th, 30th, 45th, the strands, lt was the tendon bond length (mm), lf was the
60th, 90th, and 120th minutes for 750 kN [21]. Subse- unbonded length (mm), and lj was the jacking over length
quently, the tendon was unloaded down to the alignment (mm) of the tested anchor.
load, and the final residual and temporary displacements As can be seen in Figs. 4b, 5b, 6b, 7b, and 8b, limit line b
of the tendon were measured. Elastic displacements for was taken as the lower limit line of the elastic displacements,
500 and 625 kN were measured by subtracting the plastic and according to DIN 4125, b was calculated as follows:
displacements from the total displacements measured in Fi − Fa
the 60th minute of the reloading cycle. However, the total b = 0.8 (l + l ). (2)
E × As f j
displacement readings were taken in the 120th minute of
the reloading cycle to calculate the elastic displacement Theoretical line c was the imaginary elastic extension line
for 750 kN [21]. and it was located between limit lines a and b, as shown in
As shown in Figs. 4b, 5b, 6b, 7b, and 8b, limit line a Figs. 4b, 5b, 6b, 7b, and 8b. Comparison between the elastic
was taken as the upper limit line of the elastic displace- displacements of the unbonded tendon was made by also
ments and according to DIN 4125, a was calculated as taking the theoretical line c into consideration. The elastic
follows: displacements had to be located not far away from line c.
Fi − Fa
(
lt
) According to DIN 4125, c was calculated as follows:
a= l +l + , (1)
E × As f j 2 Fi − Fa
c= (l + l ). (3)
E × As f j
where Fi (kN) was the working load, Fa (kN) was the align-
ment load, E was the elasticity modulus (N/mm2) of the R and S points were two specific points located on
tendon steel, As ­(mm2) was the total tendon surface area of load–displacement graphs where the x axis consisted of

(a) Load (kN) (b) 100


Elastic Displacements
50 150 250 350 450 550 650 750 850
Plastic Displacements
0 90 Limit Line a
Displacement of unbonded tendon after each unloading cycle (mm)

Limit Line b
Theoretical Line c
80
10

70
Displacement of unbonded tendon (mm)

20
60

30
50
S

40 40

30
50

20
60
10

70 R Load (kN)
0
0 100 200 300 400 500 600 700 800 900

80 -10

-20

Fig. 4  a Loading–unloading–reloading phases for Anchor-1; b elastic and plastic displacements of unbonded tendon for Anchor-1

13

1334 International Journal of Civil Engineering (2018) 16:1329–1340

(a) Load (kN) (b) 130


50 150 250 350 450 550 650 750 850 Elastic Displacements
0 120 Plastic Displacements
Limit Line a
10 110 Limit Line b
Theoretical Line c

Displacement of unbonded tendon after each unloading cycle (mm)


20 100

30 90
Displacement of unbonded tendon (mm)

40
80
S
50
70

60
60

70
50

80
40

90
30

100
20
110
10
120 R Load (kN)
0
0 100 200 300 400 500 600 700 800 900
130
-10

-20

Fig. 5  a Loading–unloading–reloading phases for Anchor-2; b elastic and plastic displacements of unbonded tendon for Anchor-2

force values and the y axis consisted of displacement values, displacements were measured by a dial gauge that was
as shown in Figs. 4b, 5b, 6b, 7b, and 8b. According to DIN located at the anchor head. Plastic displacements were cal-
4125, point R was located on the load axis and point S was culated by subtracting the deformations measured when
the intersection of the line passing through R and S points the tendon was unloaded down to the alignment load from
and the lower limit line b. The line that passed through R the deformations measured when the tendon was loaded or
and S points could be taken as the minimum limit line for the reloaded up to the desired value. On the other hand, the
elastic displacements. R (x, y) and S (x, y) were calculated elastic displacements were the temporary deformations of
as follows: the unbonded part of the anchor tendon.
Elastic and plastic displacements of the unbonded tendon
R(x, y) = (0.15 × FS × Fd + Fa , 0) = (212.5, 0) (4) were measured during and at the end of the tests. The loca-
tions of the elastic displacements had to remain between
l f + lj
( )
S(x, y) = 0.75 × FS × Fd + Fa , 0.6 × FS × Fd , limit line a and limit line b to decide that the anchor would
E × As be put into service: otherwise, the anchor would be rejected
(5)
[21].
where Fd (kN) was the design load and FS was the factor of Elongation of the bonded tendon, named as creep, was
safety. As given in Eq. 4, point R was zero on the displace- considered to be significant when an anchor was tested in a
ment axis which means that it was located on the load axis cohesive soil. The anchors tested in this study were embed-
with the value of 212.5. As given in Eq. 5, point S had the ded in dense sand; and for this reason, creep of the anchors
value of 662.5 on the load axis. was not taken into consideration.
The plastic displacements were the residual deforma- The acceptance or rejection of the anchors was deter-
tions of the unbonded part of the anchor tendon and these mined based on the allowable elastic displacements of the

13
International Journal of Civil Engineering (2018) 16:1329–1340 1335

(a) Load (kN) (b) 140


50 150 250 350 450 550 650 750 850 Elastic Displacements
0 130 Plastic Displacements
Limit Line a
120 Limit Line b
Theoretical Line c

Displacement of unbonded tendon after each unloading cycle (mm)


10 110

100
20
90
Displacement of unbonded tendon (mm)

80
30
70 S

40 60

50

50 40

30
60
20

10
70 Load (kN)
R
0
0 100 200 300 400 500 600 700 800 900
80 -10

-20

Fig. 6  a Loading–unloading–reloading phases for Anchor-3; b elastic and plastic displacements of unbonded tendon for Anchor-3

unbonded tendon [21]. If an elastic displacement value were located between limit lines a and b, which resulted
was located outside the limit lines a and b and the line that in the acceptance of both Anchor-1 and Anchor-2. How-
passed through points R and S, it would be concluded that ever, the elastic displacement lines for both Anchor-3 and
the related anchor lengths did not satisfy the acceptance Anchor-5 were not located between limit lines a and b as
criteria. However, all of the elastic displacements could be shown in Figs. 6b and 8b. Most of the portions of the elastic
located below the lower limit line b and above the line that displacement lines were below the lower limit line b and
passed through points R and S. In this case, the anchor was the lines that passed through points R and S. According to
neither accepted nor rejected; but further anchor tests such these results, both Anchor-3 and Anchor-5 were rejected and
as proof tests or extended creep tests, which were out of they could not be put into service. As can be seen in Fig. 7b,
the scope of this study, had to be performed on that anchor. Anchor-4 was also rejected due to the fact that the elastic
Although not used for anchor acceptance, plastic displace- displacement line was located above the upper limit line a;
ment was an indicator of the stress–strain behavior of the but not between limit lines a and b.
ground–grout bond of the anchor [2]. When an anchor was The elastic and plastic displacements of the unbonded
accepted after the termination of the performance test, then, tendon measured after each unloading cycle for each tested
this anchor could be put into service. anchor are listed in Table 3. The maximum elastic displace-
ment of an accepted anchor (Anchor-1) was measured almost
the same as that of a rejected anchor (Anchor-3). As listed
3 Test Results and Discussion in Table 3, Anchor-1 had a maximum elastic displacement
of 62.96 mm, whereas the maximum elastic displacement
Figures 4a, 5a, 6a, 7a, 8a show the load–displacement behav- of Anchor-3 was measured as 63.34 mm. Similar results
ior of the tested prestressed ground anchors in the field. As were obtained for another accepted anchor (Anchor-2) and
can be seen in Figs. 4b and 5b, the elastic displacement lines a rejected anchor (Anchor-4). The elastic displacement

13

1336 International Journal of Civil Engineering (2018) 16:1329–1340

(a) Load (kN) (b) 120


50 150 250 350 450 550 650 750 850 Elastic Displacements
0 110 Plastic Displacements
Limit Line a
10 Limit Line b
100

Displacement of unbonded tendon after each unloading cycle (mm)


Theoretical Line c
20
90
30
Displacement of unbonded tendon (mm)

80
40

50 70

S
60 60

70 50

80
40
90
30
100
20
110

10
120
R
Load (kN)
130 0
0 100 200 300 400 500 600 700 800 900
140 -10

-20

Fig. 7  a Loading–unloading–reloading phases for Anchor-4; b elastic and plastic displacements of unbonded tendon for Anchor-4

of Anchor-2 and Anchor-4 was measured as 110.73 and Based upon the results of the performance tests in this
116.08 mm, respectively, as can be seen in Table 3. These study, three out of five anchors did not satisfy the accept-
results indicated that a correlation between the elastic dis- ance criteria. Although all of the anchors were produced
placements of the unbonded tendons and the acceptance under strict quality control measures, field tests proved
criteria could not be established. that some of these anchors still had problems. Hence, it
The plastic displacements for all the tested anchors varied can be concluded that every single anchor must be sub-
almost linearly during the performance tests and the maxi- jected to a field performance test to decide whether the
mum displacements obtained at 750 kN were in the range anchor satisfies the acceptance criteria or not, before being
of 10.89–16.31 mm as listed in Table 3. Due to the linear put into service.
variation of the plastic displacements, it might be concluded As listed in Table 4, both Anchor-1 and Anchor-2 had a
that creeping of the tendon did not occur. These displace- tendon bond length of 6 m, although there was a significant
ment values were found to be higher than those obtained in difference between their unbonded lengths. The unbonded
pullout tests conducted on prestressed ground anchors that length of Anchor-1 was 9 m, whereas that of Anchor-2 was
were embedded in a rock [22]. According to the results of 16 m.
the pullout tests performed by Ren et al. [22], the maxi- Like the comparison between Anchor-1 and Anchor-2,
mum plastic displacement was measured as approximately Anchor-3 and Anchor-5 also had significantly different
1.25 mm at a load of 300 kN [22]. Obtaining higher perma- unbonded lengths when compared to each other. Anchor-3
nent deformations for the anchors tested in dense sand could had an unbonded length of 15 m, whereas the unbonded
be attributed to the lower elasticity modulus and internal length of Anchor-5 was 8 m. However, the tendon bond
frictional angle of the sand when compared to those of the lengths of these two anchors were greater than those of
rock. Anchor-1 and Anchor-2. Anchor-3 had a tendon bond length

13
International Journal of Civil Engineering (2018) 16:1329–1340 1337

(a) Load (kN) (b) 90


50 150 250 350 450 550 650 750 850
Elastic Displacements
0
Plastic Displacements
80
Limit Line a
Limit Line b

Displacement of unbonded tendon after each unloading cycle (mm)


70 Theoretical Line c

10

60
Displacement of unbonded tendon (mm)

50
20
S
40

30
30

20

40 10

Load (kN)
R
0
0 100 200 300 400 500 600 700 800 900

50 -10

-20

Fig. 8  a Loading–unloading–reloading phases for Anchor-5; b elastic and plastic displacements of unbonded tendon for Anchor-5

of 10 m, whereas the tendon bond length of Anchor-5 was


8 m as listed in Table 4.
According to these results, a correlation between ten-
Table 3  Elastic and plastic displacements measured at the applied don bond length and elastic displacements of the unbonded
loads tendon could be established. For the anchors with tendon
Applied load (kN) 250 375 500 625 750 bond lengths greater than 6 m, elastic displacements were
measured below limit line b. Measuring temporary deforma-
Anchor-1
tions below limit line b might be attributed to the insufficient
 Elastic displacement (mm) 12.38 24.12 38.83 49.23 62.96
attachment of the unbonded tendon to the soil. Because of
 Plastic displacement (mm) 5.1 6.86 9.39 12.77 13.92
this, the unbonded tendon could not transfer the resisting
Anchor-2
force from the tendon bond length to the structure.
 Elastic displacement (mm) 26.76 48.06 69.27 89.88 110.73
It was stated that horizontal tensile stresses that were
 Plastic displacement (mm) 3 4.81 8.79 14.75 16.31
located around the unbonded tendon of ground anchors
Anchor-3
embedded in a rock could cause microcracking of the rock
 Elastic displacement (mm) 14.22 25.18 41.11 56.38 63.34
surface. Moreover, shear stress developing around the
 Plastic displacement (mm) 3.22 5.34 8.34 11.13 12.05
unbonded tendon could result in shear failure of the rock
Anchor-4
[23]. These results indicated that critical stresses developing
 Elastic displacement (mm) 24.72 49.88 73.65 89.92 116.08
around the unbonded tendon of an anchor in a rock could
 Plastic displacement (mm) 5.23 7.19 9.9 13.15 14.21
cause failure of the anchor.
Anchor-5
Anchor-4 was another anchor that was rejected and
 Elastic displacement (mm) 8.39 12.73 17.56 28.88 37.93
could not be put into service due to the fact that the elas-
 Plastic displacement (mm) 3.51 5.1 6.92 8.23 10.89
tic displacement line of this anchor was located above

13

1338 International Journal of Civil Engineering (2018) 16:1329–1340

Table 4  Correlation between Tendon bond Unbonded Anchor Maximum elastic displace- Acceptance in
anchor lengths and acceptance length, lt length, lf tendon coef- ment of the unbonded tendon performance
in performance tests (mm) (mm) ficient, ct (mm) test

Anchor-1 6000 9000 0.67 62.96 Yes


Anchor-2 6000 16,000 0.38 110.73 Yes
Anchor-3 10,000 15,000 0.67 63.34 No
Anchor-4 4000 13,000 0.31 116.08 No
Anchor-5 8000 8000 1 37.93 No

the upper limit line a. Tendon bond length and unbonded important correlation that could be established between the
length of Anchor-4 were 4 and 13 m, respectively. anchor lengths and anchor acceptance was the tendon bond
Based upon this result, a correlation between tendon length. Furthermore, a correlation between ct and the maxi-
bond length and elastic displacements of the unbonded mum elastic displacements of the unbonded tendon could
tendon could also be established. For the anchors with also be established. As ct increased, the elastic displace-
tendon bond lengths under 6 m, the elastic displacements ments decreased.
were located above limit line a. These excessive displace- Actually, a range for the tendon bond length could not
ments might have been the result of the mobilization of be established due to the test results. The only tendon bond
the shear and horizontal tensile stresses in dense sand length value that resulted in acceptance of the anchors was
around the unbonded tendon. Due to these stresses, cracks 6 m. Anchor-4 was rejected with a tendon bond length of
that could result in the failure of the structure might have 4 m. However, Briaud et al. (1998) stated that anchors hav-
occurred in the soil [23]. ing 4.6 m tendon bond length that were embedded in stiff
A coefficient that was derived by dividing the tendon clay performed better than anchors having 9.2 m tendon
bond length by the unbonded length was used to inves- bond length in terms of stability [16].
tigate the effect of bonded and unbonded portions of an On the other hand, Littlejohn (1980) stated that a pre-
anchor on the acceptance criteria. This coefficient (ct) was stressed ground anchor with a tendon bond length of 6 m
named as anchor tendon coefficient: that was embedded in gravelly dense sand had an ultimate
load carrying capacity of almost 825 kN [24]. In our study,
lt
ct = , (6) Anchor-1 and Anchor-2 also had a tendon bond length of
lf
6 m. They were embedded in dense sand and they with-
where ct value for Anchor-1, Anchor-2, Anchor-3, Anchor-4, stood a load of 750 kN, which was smaller than the ultimate
and Anchor-5 was calculated as 0.67, 0.38, 0.67, 0.31, and capacity value indicated by Littlejohn (1980). However,
1, respectively, as listed in Table 4. Based upon this result, an increase in tendon bond length up to 9 m caused only
a logical correlation could not be established between c t a slight increase in the ultimate load carrying capacity of
values and the acceptance criteria for the tested anchors. the anchor. The maximum load that the anchor withstood
For example, ct for an accepted anchor (Anchor-1) and for was measured as approximately 1000 kN, and then, even
a rejected anchor (Anchor-3) was the same as 0.67. On the a slight increase in tendon bond length did not cause any
other hand, ­ct for a rejected anchor (Anchor-4) was lower further increase in load carrying capacity [24]. According to
than 0.67, whereas ­ct for another rejected anchor (Anchor-5) the results of the theoretical study performed by Littlejohn
was higher than 0.67 as listed in Table 4. These results indi- (1980), using tendon bond lengths greater than 6.7 m did
cated that evaluation of tendon bond length and unbonded not improve the load carrying capacity of the prestressed
length together did not have any significant effect on the ground anchor embedded in a dense soil having an SPT
acceptance criteria for the tested anchors, although the limit value of 50. Furthermore, permanent displacement of an
lines for determining the acceptance of the anchors were anchor having a tendon bond length of 6.7 m was found to
mostly related to the unbonded length rather than the tendon be approximately 15 mm at a load of 750 kN [24]. Some
bond length. As can be seen in Table 4, there was no correla- of the results obtained from our study were consistent with
tion either between the unbonded length of the anchors and this result. The plastic displacements measured from the two
the acceptance criteria. The range of the unbonded length for anchors (Anchor-1 and Anchor-2) with tendon bond lengths
the rejected anchors differed from 8 to 15 m, whereas that for of 6 m that were embedded in dense sand having an SPT
the accepted anchors was from 9 to 16 m. According to the value of 48, were 13.92 and 16.31 mm, respectively, at a
results of the performance test as listed in Table 4, the most load of 750 kN. Moreover, the anchors with tendon bond
lengths greater than 6 m (Anchor-3 and Anchor-5), were

13
International Journal of Civil Engineering (2018) 16:1329–1340 1339

rejected and it could be concluded that these anchors did not could not be put into service had tendon bond lengths of 10,
show any improvement in terms of load carrying capacity, 4, and 8 m, respectively.
as also stated by Littlejohn [24]. Anchor tendon coefficient (ct) was expressed as the ratio
According to the results shown in Table 4, a reduction in of the tendon bond length to the unbonded length. As ct
bond length obviously reduced the pullout resistance and, increased, the elastic displacements of the unbonded tendon
therefore, reduced the stability of the anchor. Due to the ten- decreased. However, no correlation was established between
don bond length smaller than 6 m, the grouted tendon could ­ct and acceptance criteria.
not transmit the tensile stresses to the soil properly, which As outlined in DIN 4125, when the tendon bond length
might have resulted in the failure of the anchor. However, was greater than 6 m, the elastic displacements were insuf-
the result of the performance tests indicated that an increase ficient and located below limit line b. Contrarily, when the
in bonded length also caused a reduction in stability. Based tendon bond length was smaller than 6 m, the elastic dis-
upon the test results, the tendon bond length had to be taken placements were excessive and located above limit line a.
as 6 m to provide the pullout resistance of the tested anchor. In conclusion, it might be stated that first, the location of
As stated by Littlejohn [24], vertical tensile stresses mobi- a prestressed ground anchor had to be determined where the
lized in the soil around the tendon bond length might have bonded section of an anchor had to be embedded beyond a
been the reason for the insufficient elastic displacements failure surface in the ground. After this condition was sat-
measured from Anchor-3 and Anchor-5. Due to an increase isfied, the length of the tendon bond had to be strictly fol-
in tendon bond length, the vertical tensile stresses might lowed as 6 m in the field. According to the results, a tendon
have increased and afterwards, cracks could occur in the soil bond length greater than 6 m could be unbeneficial in terms
and the anchor could fail. of both stability and cost. Using a tendon bond length of
According to the results, the prestressed steel section of 6 m would be the optimum solution for prestressed ground
the anchor that transferred the applied load to the ground anchors embedded in dense sand by considering the location
should be manufactured with a critical length of 6 m to meet of elastic displacements of the unbonded tendon as outlined
the acceptance criteria for the anchor [12]. Based upon the in DIN 4125.
results, the elastic deformations of the unbonded tendon did However, the number of the anchors on which perfor-
not play a significant role on the stability of the anchor. mance tests were conducted might be increased to evaluate
It might be concluded that the temporary deformations the detailed effects of tendon bond length and unbonded
in the tendon of an anchor could be tolerated. However, length on the stability of the tested anchor. Additional field
the length of the grouted section of an anchor should be tests, such as proof tests or extended creep tests, might also
no longer than the critical value, 6 m, although the tendon be performed on the rejected anchors to decide whether they
bond length was embedded behind a possible failure surface would be put into service or not.
in the ground.
Acknowledgements  The authors sincerely thank Prof. Dr. Lutz
Wichter from Geotechnical Engineering Department of Brandenburg
Technical University for providing the prestressed ground anchors and
4 Conclusions the equipment for conducting the pullout performance tests.

Pullout performance tests were performed on five pre-


stressed ground anchors in the field. Three of the tested
anchors did not satisfy the acceptance criteria. The accepted References
anchors could be put into service in the field. However, the
rejected anchors could cause stability problems and must not 1. Newton BJ (2012) Earth retaining systems using ground anchors,
be used in the field. memo to designers 5–12. Caltrans Engineering Manuals, p 25
2. Sabatini PJ, Pass DG, Bachus RC (1999) Geotechnical engineer-
The results indicated that unbonded length of the tested ing circular no. 4—ground anchors and anchored systems. Fed-
anchors did not play a significant role on the acceptance eral Highway Administration FHWA- IF-99-015, Washington DC,
criteria in terms of stability. The anchors with an unbonded p 281
length of 9 and 16 m could be put into service, whereas the 3. Hinks JL, Burton IW, Peacock AR, Gosschalk EM (1990) Post-
tensioning Mullardoch Dam in Scotland. Water Power & Dam
anchors with an unbonded length of 15, 13, and 8 m were Constr 42(11):12–15
rejected. 4. Bruce DA (1993) The stabilization of concrete dams by post-
According to the results, tendon bond length of the tested tensioned rock anchorages: the state of American practice.
anchors was found to be a significant parameter in terms Anderson LR (ed) Geotechnical specifications publication, no.
35, geotechnical practice in dam rehabilitation. ASCE, New York,
of stability. The critical length of the tendon bond was pp 320–332
measured as 6 m. Anchors tested with tendon bond lengths 5. Hsu SC, Chang CM (2007) Pullout performance of vertical
greater or smaller than 6 m were rejected. The anchors that anchors in gravel formation. Eng Geol 90(1–2):17–29

13

1340 International Journal of Civil Engineering (2018) 16:1329–1340

6. Gerwick BC (2008) Construction of prestressed concrete. In: 16. Briaud JL, Powers WF, Weatherby DE (1998) Should grouted
Nawy EG (ed) Concrete construction engineering handbook, vol anchors have short tendon bond length? J Geotech Geoenviron
11. CRC Press, Boca Raton, pp 1–62 Eng ASCE 124(2):110–118
7. Benmokrane B, Chekired M, Xu H, Ballivy G (1995) Behavior of 17. Ozbakkaloglu T, Saatcioglu M (2009) Tensile behavior of FRP
grouted anchors subjected to repeated loadings in field. J Geotech anchors in concrete. J Compos Constr ASCE 13(2):82–92
Eng ASCE 121(5):413–420 18. Zhang B, Benmokrane B, Chennouf A, Mukhopadhyaya P, El-
8. Ostermayer H (1975) Construction, carrying behaviour and creep Safty A (2001) Tensile behavior of FRP tendons for prestressed
characteristics of ground anchors. Proceedings of Institution of ground anchors. J Compos Constr ASCE 5(2):85–93
Civil Engineers, London, pp 141–151 19. Vukotic G, Galindo JG, Soriano A (2013) The influence of bond
9. Hobst L, Zajic J (1977) Anchoring in rock. Developments in geo- stress distribution on ground anchor fixed length design. Field
technical engineering, 13. Elsevier Scientific, Amsterdam trial results and proposal for design methodology. In: Proceed-
10. Hanna TH (1982) Foundations in tension: ground anchors (series ings of the 18th international conference on soil mechanics and
on rock and soil mechanics). Trans Tech Publications, McGraw- geotechnical engineering, Paris, pp 2119–2122
Hill, New York 20. OPSS 942 (2009) Construction specification for prestressed soil
11. Schnabel H Jr (1982) Tiebacks in foundation engineering and and rock anchors. Ontario provincial standard specification, p 26
construction. McGraw-Hill Book Company, New York 21. DIN 4125 (1990) Ground anchorages; temporary and permanent
12. Cao G, Zhang W, Hu J, Zhang K (2017) Experimental study anchorages; design, construction and testing, Deutsches Institut
on the long-term behaviour of RBPC t-beams. Int J Civ Eng. für Normung
doi:10.1007/s40999-017-0227-2 22. Ren FF, Yang ZJ, Chen JF, Chen WW (2010) An analytical analy-
13. Yang F, Cao S, Qin G (2017) Performance of the prestressed com- sis of the full-range behaviour of grouted rockbolts based on a
posite lining of a tunnel: case study of the Yellow River crossing tri-linear bond-slip model. Constr Build Mater 24(3):361–370
tunnel. Int J Civ Eng. doi:10.1007/s40999-016-0124-0 23. Showkati A, Maarefvand P, Hassani H (2016) An analytical solu-
14. Wichter L, Meininger W (2000) Verankerungen und vernage- tion for stresses induced by a post-tensioned anchor in rocks con-
lungen im grundbau (anchors and soil nails in geotechnical con- taining two perpendicular joint sets. Acta Geotech 11:415–432
structions), 1st edn. Ernst & Sohn, Berlin, p 215 24. Littlejohn GS (1980) Design estimation of the ultimate load-hold-
15. Ozhan HO (2004) The effect of tendon bond length of prestressed ing capacity of ground anchors. Ground Eng Found Publ, Essex,
ground anchors to the stability of anchored retaining systems. M. pp 25–39
Sc. Thesis, Bogazici University, Istanbul, p 184

13

You might also like