R - ITP - EARTHING RESISTOR - T4344466RevO - F001
R - ITP - EARTHING RESISTOR - T4344466RevO - F001
SUPPLIER/VENDOR DOCUMENTATION
Document Title:
ITP FOR INSTALLATION AND TESTING OF
NEUTRAL GROUNDING RESISTORS
Vendor/Supplier Doc Vendor/Supplier
Number: 545-9118-27 Revision: A
Tag/Item Number(s): N/A
Unit: 0-2000; 1-2100; 1-2200; 1-2300; 1-2400;
PCWBS: GZ00
2-2100; 2-2200; 2-2300; 2-2400
KF HAN AM 29-06-2009
Status of Submission (tick applicable box before submission)
Contractor Date
Review Code and Status Initials/Signature signed
Purchase Order
Number 0012MH128
(continued)
Tag/Item Number(s)
(continued)
NA
ITP FOR
INSTALLATION & TESTING OF NUETRAL GROUNDING RESISTORS
Proj. Contr
Date By Chkd Appr. Status Revision reason for issue description
Rev. Rev
Linde Project ID: 1110 A05M Linde Project Code: PEARL QATAR
Shell Project No.: HP-3000-QAT Contractor name:
Unit: 0-2000; 1-2100; 1-2200; 1-2300; 1-2400;
Contractor Project No.: 5887 2-2100; 2-2200; 2-2300; 2-2400
Linde Engineering
INDEX
545-GN-9005-Form3
02.01 01 Material Reciept And Inspection Report N/A
-MRIR
N/A
03 SUPPORTING DOCUMENTS
545-GN-9002 REQUEST FOR INSPECTION – QUALITY
03.01 01 N/A
FORM_1 RECORD_ QR-101A
NOTE :
1) INSPECTIONS SHALL BE CALLED IN USING FORM NO.#3. DOC # 545-GN-9002 (SEE 03.02) REQUEST FOR
INSPECTION TO CLIENT WITH 24 HRS NOTICE OR SHALL BE SUBMITTED BEFORE THE END OF PREVIOUS
DAY OFFICE HOUR. HOWEVER IN CASE OF URGENCY THE NOTICE PERIOD MAY BE VERY SHORT
DEPENDING ON SITE SITUATIONS.
2) DEFICIENCIES IN THE INSPECTED ITEMS SHALL BE RECORDED USING PUNCH LIST FORM (SEE 02.04) IT
SHALL BE DUELY SIGNED BY THE QK INSPECTOR AND CLIENT INSPECTOR.
CONTRACT NO: 0012 MH 128 QK PROJECT NO.: 545 PROJECT DOC NO: T-4.344.466_Rev.O
CONFORMANCE TO IFC
DRAWINGS & MRIR Forms 545-
VISUAL INSPECTION, OSD
SPECIFICATION, GN-9005 Form 3 &
1.1 FREE SUPPLIED MATERIALS MC, QCI REPORTS, FREE FROM DAMAGE H W S
CERTIFICATES AND FAT FAT Report
ETC.
DOCUMENTS &
DEP
CONFORMANCE TO IFC
DRAWINGS & MRIR Forms 545-
QKZ SUPPLIED MATERIALS SPECIFICATION, GN-9005 Form 3 &
1.2 MC, QCI VISUAL INSPECTION H S S
CERTIFICATES AND FAT FAT Report
DOCUMENTS.
DEP
CONTRACT NO: 0012 MH 128 QK PROJECT NO.: 545 PROJECT DOC NO: T-4.344.466_Rev.O
CONTRACT NO: 0012 MH 128 QK PROJECT NO.: 545 PROJECT DOC NO: T-4.344.466_Rev.O
Designation: QA/QC ENGINEEER Designation: QA/QC MANAGER Designation: PROJECT MANAGER Designation:
06
CIVIL ELECT INST MECH COMMS PLUMB OTHER
CONSTRUCTION
07 NAME
SIGNATURE
DATE QA / QC INSPECTOR
PROJECT INFORMATION
PROJECT: PEARL GTL PROJECT QATAR - E&I -AIR SEPARATION UNIT
LINDE PROJ NO: 5887 QK PROJECT NO: 545 CONTRACT NO: IP - 092
ITP NUMBER:
CIVIL/STRUCTURAL
ITP ACTIVITY NO.:
*
INSPECTION TYPE:
MECHANICAL *W – Witness, H – Hold in the box, R-Review, S-Surveillance
ELECTRICAL
INSTRUMENTATION
WELDING/PIPING
PREFAB BUILDING
OTHERS REF :
INSPECTION RESULT
Result of inspection is:
Comments:
2. CHECK LIST(In the field check off ; acceptable items only, note deviations/defects under“REMARKS”and mark non-applicable items N/A
Checked By/Date
4. INSPECTION COMPLETED/ACCEPTED
QKZ:
Name (Print): _________________________________ Signature: ________________________________ Date:__________________
LINDE:
Name (Print): _________________________________ Signature: ________________________________ Date:__________________
JK/ QSGTL:
Name (Print): _________________________________ Signature: ________________________________ Date:__________________
NOTE: The Layout Of This Form Shall Not Be Changed Without Permission From COMPANY QA/QC Manager
INSTRUMENT DETAILS
TYPE OF TEST EQUIPMENT :
MANUFACTURER :
SERIAL NO :
CALIBRATION DATE :
CALIBRATION DUE DATE :
TEST VOLTAGE :
LINDE
Name (Print): Signature: Date:
JK/QSGTL
Name (Print): Signature: Date:
Test
Test Voltage: Cal. Date:
Equipment
Notes!!!
1. Use 500 volt test set for 600 volt equipment and below, 2500 volt tests set for equipment rated over 600 volts.
2. Resistor must be disconnected from ground/earth and neutral during Insulation Resistance (megger) and DC Overpotential Tests.
4. Apply DC Overpotential Test between terminals and ground for the complete device. (The voltage applied between the terminals of
each assembly and its grounded enclosure shall be twice the rated AC voltage plus 1000 V when rated 600 V or less, or 2.25 times the
rated AC voltage plus 2000 V when rated over 600 V for 1 Minute.) This test is a Pass/ Fail test based purely on withstand alone.
6. Check to assure that the center tap ratio is correct, when CT is supplied with resistor.
INSPECTION COMPLETED/ACCEPTED
NAME SIGNATURE DATE
QKZ
Name(Print):
LINDE
Name(Print):
JK/QGSTL
Name(Print):
Completion
Scheduled
Issued By
Inspector
Category
Verify By
QK_QC
Action
Sl No.
Name
Area
Date
Disc
No.
Description Remarks