Professional Documents
Culture Documents
5537 MS
5537 MS
5537 MS
This paper was presentedat the 19th Annual OTC in Houston, Texas. April 27-30, 1987. The material is subject to correction by the author. Permission
to copy is restricted to an abstract of not more than 300 words.
For a molecule to leave the surface of a The vacuum plant is attached to the
liquid it must overcome these holding pipeline and the pressure is reduced by
forces, this requires an increase in pumping out the air. As the pressure
molecular energy levels. reduces, evaporation of the water within the
The basis of any drying technique is to pipeline will commence. Each unit volume
change the liquid (in this case water) into extracted from the pipeline will contain a
a gas and then transport this gas from the quantity of water vapour, the result being
system, this necessitates evaporation. that the net quantity of gaseous water
vapour is reduced. This reduction brings
PARTIAL VAPOUR PRESSURE about a reduction in the vapour pressure in
In the case of air in the atmospheric the pipeline, which is in turn made good by
state containing water vapour the Total evaporation to restore the vapour pressure
Pressure of the atmosphere is made up of to the original level determined by the
partial pressures as expressed by Dalton's pipeline temperature. When the remnant air
law of partial pressures. in the pipeline is removed the pipeline
pressure is determined by the vapour
WATER CONTENT HEASURMENT pressure generated by the boiling of the
This is expressed as a dew point since water.
the temperature at which dew will form is a When the water has been evaporated the
measure of the vapour content of the pressure will then fall as the quantity of
atmosphere. water vapour being evaporated is unable to
The dew-point figure refers to the support the vapour pressure in line with the
quantity of water which is present in a GAS temperature.
as a vapour. This vapour is behaving as a The transition between the air-vapour
gas and is NOT in the form of liquid mix at the initial pump down of the pipeline
droplets. is easily determined, however the transition
The alternative method of expressing the from full boiling vapour pressure to the
quantity of water vapour in a gas is to reduced vapour pressure as the pipeline
state the water content in terms of parts becomes dry is less distinct in some cases.
per million by volume (ppmv) or parts per
million by weight (ppmw). PUMP DOWN TIME CALCULATION
The relationship between these values
and the absolute quantities as defined by The standard formula for the pump down
the ratio of partial pressures and molecular time of a vacuum system is shown below:
weights. This can lead to confusion when the
vacuum consisting of water vapour only is
considered since the answer to each (ppmv)
and (ppmw) is equal to 1000000. where:
T = the time in hours to lower pressure
EVAPORATION OF A LIQUID from PI to P2
The molecules of a liquid are held V = volume of the system <cu.m.>
together by the inter-molecular forces such S = pumping speed of the pump <cu.m.lhr>
that these forces exceed those which give P1 = initial pressure of the system <m.bar>
rise to random motion. See REF7. In liquids P2 = final pressure of the system <m.bar>
with a degree of molecular order an entropy
change is required when the liquid is There is a modification required to this
evaporated to the completely random gaseous formula when a limiting pressure due to
state. "outgassing" or liquid vapour pressure is
By considering the evaporation cycle and present.
the interpretation of entropy changes
necessary for the cycle it can be shown that
the vapour pressure of a substance is only a
function of its absolute temperature and its where:
latent heat of evaporation. Pg = outgassing or vapour pressure <m.bar>
Where:
Dt = drying time <hrs>
From this relationship it can be seen that
Ai = internal area of pipeline <sq.m>
the effective pumping speed down the pipe is
Wr = water removal rate <gms/hr>
a function of the conductance of the pipe
and the pump speed.
It is necessary however to consider
If the conductance is equal to the pumping
pumping pressure losses in the line and take
speed then the effective pumping speed is
account of how these significantly affect
half of the pump speed.
the actual performance of the vacuum pump.
When the conductance is very high compared
Since the actual time taken to dry cannot be
to the pump speed then the effective pumping
calculated unless the actual quantity of
speed tends to be equal to the pump speed.
water is known, it may be suggested that
As the conductance reduces to say half the
this calculation of extension of time caused
pump speed the effective pumping speed is a
by pressure loss is merely academic.
third of the pump speed.
However, an understanding of the effects of
The calculation of pipeline conductance is
pressure loss whilst vacuum pumping is
therefore of considerable importance in the
crucial not only from a technical view point
assessment of the pumping performance and
vis-a-vis interpretation of data and
hence the rate at which any drying operation
explanation of phenomena but also from a
will proceed.
commercial view point as to equipment
sizing; it is often the case that increasing There are various sources of information
on the subject of conductance. The earliest
the vacuum pump spread volumetric capacity
(which is expensive) will have no effect on source used was C.M.van Atta, see REFS.
the drying time. Thus it is essential that This gave a simple formula for the
conductance of a pipe which is shown in
pressure loss forecasts are made, and
equally important that they are checked and modified form here for air at 15C:
reconciled against field experience.
The vapour pressure was depressed by the Dewatering and foam pig runs time = 10 days
T.E.G. causing the vacuum process to be less
efficient. It appears that a standard vacuum The condition of the foam pigs after
drying operation would have reduced the swabbing the line was not as expected. Later
overall time. In addition the weather pigs arrived with low water content. The
dependency of vessels etc. does not affect weight increase was high compared to the
the operation of platform based vacuum prescribed acceptance criteria. This
PWPS -
The water extraction rate is calculated
acceptance criteria was arrived at
agreement with any empirical information.
by
from the input vapour density (from Often in pipeline activity it is necessary
dew-point) and the pumping speed. It was to have acceptance criteria, but without
seen that vapour pressure was less than empirical data these criteria must be
total pressure throughout. This represents a subject to change and restatement.
considerable quantity of air being pumped. The acceptance criteria was that two
The fact that the lowest pressure obtainable sucessive foam pigs having less than a 5%
was only 1.5 mbarA at location N and 1.7 increase in weight, would show a damp pipe.
mbarA at location T was perhaps symptomatic The object was to ensure loose water
of an in-leakage. pick-up. This criteria was not met, however
Subsequent procedures have paid a great the pigs were only damp. The future criteria
deal of attention to leakage detection. The was set to being 10% of the water carrying
vacuum pumps should pump 99% water vapour capacity of the pig.
during evaporation. However the pipeline
pressure is below the evaporation pressure The vacuum drying equipment was designed to
for the pipe temperature so the process is be hooked up with the minimum of delay.
operating. Location 1 the 3 no. single stage ejectors
The final dew-point achieved was better were fitted on to the pipe-manifold.
than -15C. These ejectors would assist in the initial
pull down to the evaporation pressure. This
CONTRACT 2 (01107183 to 03/06/83) was in view of the low displacement values
The location of the contract was sub sea of the vacuum pumps above 100 mbarA.
from platform (location 1) to platform To prevent pools of water forming in the
(location 2). The climate is tropical. pipe the most rapid pull-down time was
The pipeline details: requested.
Length: 44.126 km
Max depth: 70.Om At location 2 the two vacuum pump sets were
Inside Diameter: 28.87 in connected through a special monitoring spool
Volume of pipeline: 18607 cu.m. to the pipeline. This monitoring spool
Internal area of pipe: 101577 sq.m. allows the dew point meters to be in the
Temperature: 25C main vapour stream and be easily maintained.
The results show that the soak test was Total installed vacuum pump capacity:
satisfactory as there was no pressure rise, Nominal pump speed 7600 cu.m.lhr.
hence no water was evaporating at low
pressure. The air purge demonstrated that The dewatering and foam pigging took 13
the pipeline water vapour was displaced days. The initial dewater train had 4 no.
after four days and the pipeline would pigs. A total of 12 foam pigs were used.
transmit gas without showing an increased
dew-point. The subsequent pull down did not The foam pigs extracted 609.2 kg of water
plateau at pipe temperature vapour pressure
indicating a dry system. Foam pigs Nos 11 to 17 delivered 510.5 kg of
Thus three independent dryness tests water in 25 hours. The extraction rate for
demonstrated that the system was acceptable, foam pigs was 20.4 kglhr.
the ultimate dryness being below -20C
dew-point. After a 24 day delay. for reinstatemnet, the
It is possible that the three days spent vacuum drying procedure was started.
on the foam pigging operations did not
extract as much water as an equivalent time Estimated vacuum drying times:
spent on the vacuum drying procedure. In Quantity of water (100gmlsq.m) = 12951 kg
the light of subsequent investigations it Expected evaporating pressure = 31.77 mbarA
may well be that the use of foam pigs will Time to pull down to s.v.p. = 2.05 days
not be recommended in view of the efficiency Time to evaporate 12951 kg = 5.64 days
obtained. Time to draw down to -10C d.p. = 3.17 days
Total drying time = 10.86 days
CONTRACT 3 (21108186 to 11109186 8
06110186 to 25110186) The operational timings for vacuum drying
The location of the contract was sub sea are shown as follows:
from platform (location E) to platform
(location F). The climate is tropical. Pressure draw down to evaporation = 4 days
The pipeline details: Pressure from 36 to 33 mbarA = 2 days
Length : 52.800 km Pressure from 33 to 4.5 mbarA = 2 days
Max depth: 80. Om Air purge 8 down to 0.26 mbarA = 2 days
Inside Diameter: 30.624in Soak test at 2.6 to 2.68 mbarA = 3 days
Volume of pipeline: 25052 cu.m. Pressure from 2.68 to 0.38 mbarA = 5 days
Internal area of pipe: 128928 sq.m. Total vacuum drying time = 18 days
Temperature: 25C
Water evaporated by vacuum was 11238kg.
PROCEDURE ADOPTED The estimated water (based on 100gmlsq.m)
Vacuum drying following dewatering and foam was 12900kg. The foam pigs removed 609kg of
pig swabbing water thus giving a total of 11847kg water
The dewatering and vacuum equipment was to be accounted for. The estimated
placed on location F. 100gmlsq.m value would seem reasonable based
To avoid ball valve contamination the on these results.
dewatering and foam pigging was undertaken This result when compared to the
with the top side pipe work removed. The Contract 2 quantity would support the
top-side pipe work was reassembled and presence of excess water in the top-side
vacuum drying started. This pipeline is pipework. Contract 3 has these sections
running in a broadly parallel situation to removed prior to dewatering.
contract 2. The evaporation vacuum extraction rate
is 1268 kglday or 52.8kgIhr. Overall
Equipment used on pipeline: including the last days in this particular
Location E. case the extraction rate is 591kglday or
Temporary pig trap. 24.6kglhr. This overall vacuum drying rate
Monitoring equipment is better than the foam pigging rate.
The water pick-up by the foam pigs is
Location F. not as good as the best pick-up rate for
Dewatering compressors: vacuum drying.
2 No. Diesel compressors 1200cfm 290 psi
Temporary pig launcher. The final dew-point was better than -30C.
Vacuum pumps: CONTRACT 4 (12103186 to 09/04/86)
2 No. combination sets, each comprising: The location of this contract was sub-sea
1 No. Rotary oil sealed piston pumps from onshore (location BC) to platform
500 cu.m.lhr displacement (location SP). The climate is European
1 No. Roots booster pump continental shelf - winter.
Nom.capacity 1800 cu.m.Ihr. The pipeline details:
2 No. combination sets, each comprising: Length: 107.000 km
1 No. ES7500 rotary piston pump )lax depth: profile variable
450 cu.mlhr displacement Inside Diameter: 28.684in
1 No. M 4 2 0 0 roots booster Volume of pipeline: 44541 cu.m.
Nominal capacity 2000 cu.m.lhr. Internal area of pipe: 244724 sq.m.
Temperature: 3C
10 COMMISSIONING GAS PIPELINES USING THE VACUUM DRYING HETHOD OTC5537
The actual trials which took place did not (4):Selecting Humidity Sensors for
necessarily address this problem since the Industrial Purposes Handbook:
"pool" of T.E.G. mixture was placed in a General Eastern Instruments Corporation.
discreet location and not spread as one Watertown.Mass.02172.Jun 1978
might expect in a swabbed pipeline.
(5):The Gaseous Phase: W.H.Thorning.John
The original objective of drying water bound Murray London 1974 ISBN 0 7195 2954 9.
into a rust or mill scale was not undertaken
due to shortage of time on the test site. I t (6):Physical Chemistry. Walter J. Moore.
may be appropriate to discuss this problem Longman 1972 ISBN 0 582 44234 6.
at this stage since it is a practical
difficulty that will occur. (7):Principles of Physical Chemistry for
Biology and Pharmacy. Prof.L.Saunders
CONCLUSIONS D.Sc..F.R.I.C.:Oxford University Press
The vacuum drying method has been operated 1971:ISBN 0 19 8597706 1
more sucessfully in the last few years than
may have been the case previously. The (8): Vacuum Manual:L.Holland,
application of more rigorous check W.Steckelmacher,L J.Yarwood:1974:Spon
procedures has ensured that dryness is London:ISBN 0 419 10740 1
proved.
1)The soak test is the best check (9):The Design of High Vacuum Systems:
available to find any remnant water. C.M.van Atta: Kinney Vacuum Corp.
2)Air purging at higher pressures can Boston: 1960
assist in moving mist from the pipeline.
3)The use of foam pigs will not replace (10):Vacuum Technology its Foundations
pipeline cleaning as a method of Formulae and Tab1es:Leybold-HeraeusGMBH
pre-preparation for vacuum drying. Postfach 510 760. D-5000 Koln 51
4)The running of a cleaningldewatering W-Germany.
train followed by tight swabbing pigs does
appear to give a good start to vacuum
drying.
5)If a fully dry pipeline is required then
the use of a T.E.G. swab will not give the
desired results. However T.E.G. may be
useful in one way pipelines, such as
reinjection lines in order to control future
dew-point levels.
6)To obtain low dew-points it is necessary
to use pumps with a good low pressure
characteristic.
7)Research is necessary to investigate the
effects of side-wall contained moisture,
with a view to reducing the vacuum drying
times .