Name: Sharmaine C.

Legaspi
Title: Workshop No.1
Project: Measurement for Concrete & Formworks

S/N Description Location Length (mm) Width (mm) Height (m) MultiplierConcrete Volume (m^3)
Formworks (m^2) Remarks

A Beams
1.1 Beam 1 Grid 4/A1-B1 7750 300 0.375 1 0.87 6.04
1.2 Beam 2 Grid 4/B1-C1 7250 300 0.375 1 0.82 5.66
1.3 Beam 3 Grid 4/C1-D1 7250 300 0.375 1 0.82 5.66
1.4 Beam 4 Griid 3/A1-B1 7750 300 0.525 1 1.22 8.45
1.5 Beam 5 Grid 3/B1-C1 7475 300 0.525 1 1.18 8.16
1.6 Beam 6 Grid 3/C1-D1 7575 300 0.525 1 1.19 8.27
1.7 Beam 7 Grid 2/A1-B1 8000 300 0.525 1 1.26 8.72
1.8 Beam 8 Grid 2/B1-C1 7475 300 0.525 1 1.18 8.16
1.9 Beam 9 Grid 2/C1-D1 7575 300 0.525 1 1.19 8.27
1.1 Beam 10 Grid 1/A1-B1 7500 300 0.375 1 0.84 5.85
1.11 Beam 11 Grid 1/B1-C1 7750 300 0.375 1 0.87 6.04
1.12 Beam 12 Grid 1/ C1-D1 7250 300 0.375 1 0.82 5.66
1.13 Beam 13 Grid A1/4-3 4750 300 0.375 1 0.53 3.79
1.14 Beam 14 Grid A1/3-2 7500 300 0.375 1 0.84 5.85
1.15 Beam 15 Grid A1/2-1 6000 300 0.375 1 0.68 4.73
1.16 Beam 16 Grid B1/4-3 4500 300 0.525 1 0.71 5.04
1.17 Beam 17 Grid B1/3-2 7000 300 0.525 1 1.1 7.67
1.18 Beam 18 Grid B1/2-1 6500 300 0.525 1 1.02 7.14
1.19 Beam 19 Grid C1/4-3 5250 300 0.525 1 0.83 5.83
1.20 Beam 20 Grid C1/3-2 7000 300 0.525 1 1.1 7.67
1.21 Beam 21 Grid C1/2-1 7500 300 0.525 1 1.18 8.19
1.22 Beam 22 Grid D1/4-3 4500 300 0.375 1 0.51 3.6
1.23 Beam 23 Grid D1/3-2 7000 300 0.375 1 0.79 5.48
1.24 Beam 24 Grid D1/2-1 6500 300 0.375 1 0.73 5.1
Subtotal (Beams) 22.28 155.03

B Slabs
Slab 1 Grid 1-4/A1-D1 24000 22000 0.225 1 118.8 20.7
Soffit Area Grid 1-4/A1-D1 24000 22000 528 No deduction for beam soffit
Less: 2C1 Grid 4/A1 1000 250 0.225 -1 -0.06
2C2 Grid 4/B1 1000 250 0.225 -1 -0.06
2C3 Grid 4/C1 1000 250 0.225 -1 -0.06
2C4 Grid 4/D1 1000 250 0.225 -1 -0.06
2C5 Grid 3/A1 1000 250 0.225 -1 -0.06
2C6 Grid 3/B1 1000 350 0.225 -1 -0.08
2C7 Grid 3/C1 1000 350 0.225 -1 -0.08
2C8 Grid 3/D1 1000 250 0.225 -1 -0.06
2C9 Grid 2/A1 1000 250 0.225 -1 -0.06
2C10 Grid 2/B1 1000 350 0.225 -1 -0.08
2C11 Grid 2/C1 1000 350 0.225 -1 -0.08
2C12 Grid 2/D1 1000 250 0.225 -1 -0.06
2C13 Grid 1/A1 1000 250 0.225 -1 -0.06
2C14 Grid 1/A1 1000 250 0.225 -1 -0.06
2C15 Grid 1/B1 1000 250 0.225 -1 -0.06
2C16 Grid 1/C1 and D1 1000 250 0.225 -1 -0.06
2C17 Grid 1/C1 and D2 1000 250 0.225 -1 -0.06
2C18 Grid 1/C1 and D3 1000 250 0.225 -1 -0.06
2C19 Grid 1/D1 1000 250 0.225 -1 -0.06
Subtotal (Slab) 117.58 548.7

C Columns
1 2-C1 Grid 4/A1 1000 250 3 1 0.75 7.50
2 2-C2 Grid 4/B1 1000 250 3 1 0.75 7.50
3 2-C3 Grid 4/C1 1000 250 3 1 0.75 7.50
4 2-C4 Grid 4/D1 1000 250 3 1 0.75 7.50
5 2-C5 Grid 3/A1 1000 250 3 1 0.75 7.50
6 2-C6 Grid 3/B1 1000 350 3 1 1.05 8.10
7 2-C7 Grid 3/C1 1000 350 3 1 1.05 8.10
8 2-C8 Grid 3/D1 1000 250 3 1 0.75 7.50
9 2-C9 Grid 2/A1 1000 250 3 1 0.75 7.50
10 2-C10 Grid 2/B1 1000 350 3 1 1.05 8.10
11 2-C11 Grid 2/C1 1000 350 3 1 1.05 8.10
12 2-C12 Grid 2/D1 1000 250 3 1 0.75 7.50
13 2-C13 Grid 1/A1 1000 250 3 1 0.75 7.50
14 2-C14 Grid 1/A1 1000 250 3 1 0.75 7.50
15 2-C15 Grid 1/B1 1000 250 3 1 0.75 7.50
16 2-C16 Grid 1/C1 1000 250 3 1 0.75 7.50
17 2-C17 Grid 2/D1 1000 250 3 1 0.75 7.50
18 2-C18 Grid 1/D1 1000 250 3 1 0.75 7.50
19 2-C19 Grid 1/D1 1000 250 3 1 0.75 7.50
Subtotal (Column) 15.45 144.90

D Footings/Pile Cap
1 PC 1 Grid A1/4 1500 500 0.5 1 0.38 2
2 PC 2 Grid A1/3 1500 500 0.5 1 0.38 2
3 PC 3 Grid A1/ Near 2 1500 500 0.5 1 0.38 2
4 PC 4 Grid A1/1 1500 500 0.5 1 0.38 2
5 PC 5 Grid B1/4 700 1900 1039 0.5 1 1.34 3.2
1900 700 0.5 1
6 PC 6 Grid B1/3 500 500 0.5 1 0.13 1
7 PC 7 Grid B1/2 700 1900 1039 0.5 1 1.34 3.2
1900 700 0.5 1
8 PC 8 Grid B1/1 1500 500 0.5 1 0.38 2
9 PC 9 Grid C1/4 700 1900 1039 0.5 1 1.34 3.2
1900 700 0.5 1
10 PC 10 Grid C1/3 500 500 0.5 1 0.13 1
11 PC 11 Grid C1/2 500 500 0.5 1 0.13 1
12 PC 12 Grid C1/1 1500 500 0.5 1 0.38 2
13 PC 13 Grid D1/4 1500 500 0.5 1 0.38 2
14 PC 14 Grid D1/3 1500 500 0.5 1 0.38 2
15 PC 15 Grid D1/2 700 1900 1039 0.5 1 1.34 3.2
1900 700 0.5 1
16 PC 16 Grid D1/1 1500 500 0.5 1 0.38 2
17 PC 17 Grid 1/ Near A1 1500 500 0.5 1 0.38 2
18 PC 18 Grid 1/ Near D1 1500 500 0.5 1 0.38 2
19 PC 19 Near D1/ Near 2 1500 500 0.5 1 0.38 2
Subtotal (Footings/Pile Cap) 10.31 39.80

E Starter Column
1 2-SC1 Grid 4/A1 1000 250 1.8 1 0.45 4.5
2 2-SC2 Grid 4/B1 1000 250 1.8 1 0.45 4.5
3 2-SC3 Grid 4/C1 1000 250 1.8 1 0.45 4.5
4 2-SC4 Grid 4/D1 1000 250 1.8 1 0.45 4.5
5 2-SC5 Grid 3/A1 1000 250 1.8 1 0.45 4.5
6 2-SC6 Grid 3/B1 1000 350 1.8 1 0.63 4.86
7 2-SC7 Grid 3/C1 1000 350 1.8 1 0.63 4.86
8 2-SC8 Grid 3/D1 1000 250 1.8 1 0.45 4.5
9 2-SC9 Grid btw 1-2/A1 1000 250 1.8 1 0.45 4.5
10 2-SC10 Grid 2/B1 1000 350 1.8 1 0.63 4.86
11 2-SC11 Grid 2/C1 1000 350 1.8 1 0.63 4.86
12 2-SC12 Grid 2/D1 1000 250 1.8 1 0.45 4.5
13 2-SC13 Grid 1/A1 1000 250 1.8 1 0.45 4.5
14 2-SC14 Grid 1/btw A1-B1 1000 250 1.8 1 0.45 4.5
15 2-SC15 Grid 1/B1 1000 250 1.8 1 0.45 4.5
16 2-SC16 Grid 1/btw C1-D1 1000 250 1.8 1 0.45 4.5
17 2-SC17 Grid btw 1-2/btw 1000 250 1.8 1 0.45 4.5
18 2-SC18 Grid 1/btw C1-D1 1000 250 1.8 1 0.45 4.5
19 2-SC19 Grid 1/D1 1000 250 1.8 1 0.45 4.5
Subtotal (Starter 9.27 86.94
Column)
F Lean Concrete
1 LC A1/4 to D1/1 24000 22000 0.05 1 26.4 -

Subtotal (Lean Concrete) 26.4 -

GRAND TOTAL 201.27 447.18