Date : 06 Mei 2023

DAILY REPORT Location : PT. Smelting


Page : 83
CONSTRUCTION WORK OF NEW FILE STORAGE BUILDING
START DATE 13 Pebruari 2023
FINISH DATE 14 Oktober 2023
WORK LOCATION/PLANT Change House Area PT. Smelting, Gresik
PTS (M/U Dept.) PTS (General Affair Dept.) CV. RM (Engineer) CV. RM (Spv.)
PERSON IN CHARGE
Mr. Cholisuddin Mr. Indra Junor Ir. Yudi Yulianto Suparlan

NUMBER OF WORKER SPV Foreman Safety Worker TOTAL


Penyelenggaraan SMK3 1 1
Pekerjaan Beton 1 11 12
DAY SHIFT FROM : 8 AM TO : 3 AM

STATUS
TODAY ACTIVITIES, NEXT ACTIVITIES,
Item Pek. Ttl. Project
• Pek. SMK3 Konstruksi 3,00% 0,057% • Melanjutkan Penyelenggaraan SMK3 Konstruksi
• Pek. Kolom pedestal PD 30/30 95,00% 0,047% • Pekerjaan Pemeliharaan Beton
• Pek. Balok RG 1 B 35/50 95,00% 0,329% • Pekerjaan Pembersihan sisa beton
• Pek. Balok RG 1 AB 35/50 95,00% 0,204%
• Pek. Balok RG 2 B 30/50 95,00% 0,517%
• Pek. Plat Lantai, T = 20 cm elv.5,09 95,00% 2,085%
• Pek. Beton Rabat 95,00% 0,293%
• Pek. Mobilisasi Dan Demobilisasi 30,00% 0,416%
Progress of today : 3,948%
Progress of until yesterday : 20,335%
TOTAL : 24,283%

Prepared by : Checked by : Approved by :

Sulistiyo Yudi Yulianto Suparlan M. Riefky Fakhruddin


(Engineering Spv.) (Production Spv.) (Project Manager)