RENCANA ANGGARAN BIAYA (RAB)

PEKERJAAN : PEMBANGUNAN GEDUNG RUANG KULIAH PRODI MERAUKE


LOKASI : KABUPATEN MERAUKE
TAHUN ANGGARAN: 2018

HARGA JUMLAH
NO. URAIAN PEKERJAAN VOLUME SATUAN SATUAN HARGA
(Rp.) (Rp.)
I. PEKERJAAN PENDAHULUAN
1 Pengukuran dan Pemasangan Bouplank 118.00 M' 83,512.55 9,854,480.90
2 Pembersihan Lokasi Pekerjaan 150.00 M2 22,000.00 3,300,000.00
3 Papan Nama Proyek 1.00 Ls 700,000.00 700,000.00
4 Penyediaan Air Kerja di Lapangan 1.00 Ls 2,000,000.00 2,000,000.00
5 Pembuatan Gudang dan Barak Kerja 1.00 Ls 6,951,000.00 6,951,000.00
22,805,480.90
II PEKERJAAN TANAH
1 Galian Tanah Pondasi 131.76 M3 122,265.00 16,109,636.40
2 Urugan Pasir Bawah Pondasi 5.76 M3 627,880.00 3,616,588.80
3 Urugan Pasir Bawah Lantai 18.40 M3 627,880.00 11,552,992.00
4 Urugan Tanah Peninggian Peil Lantai 253.00 M3 379,335.00 95,971,755.00
5 Urugan Tanah Kembali 84.35 M3 72,600.00 6,123,810.00
133,374,782.20
III PEKERJAAN PONDASI DAN BETON
1 Cor Pondasi Lajur 1 : 2 : 3 117.00 M3 2,427,678.69 284,038,406.44
2 Cor Balok sloof 20/25 9.15 M3 9,893,196.94 90,522,752.01
3 Cor Kolom Praktis 15/15 0.32 M3 9,408,848.87 2,963,787.39
4 Cor Kolom 20/20 5.74 M3 9,893,196.94 56,786,950.44
5 Cor Kolom 15/20 0.53 M3 9,893,196.94 5,193,928.39
6 Cor Ring Balk 15/20 0.15 M3 9,408,848.87 1,411,327.33
7 Cor Ring Balk 20/25 11.98 M3 9,408,848.87 112,670,965.17
553,588,117.17
IV PEKERJAAN LANTAI KERAMIK
1 Pasang Lantai Keramik 40 x 40 cm 433.00 M2 304,659.26 131,917,459.04
2 Pasang Lantai Keramik 20 x 20 cm KM/WC 6.00 M2 387,387.83 2,324,326.95
3 Pasang Lantai Keramik Dinding 20 x 25 cm KM/W 20.80 M2 439,675.50 9,145,250.40
4 Cor Lantai dan Rabat 1 : 2 : 3 38.81 M3 1,964,912.13 76,251,558.87
219,638,595.26
V PEKERJAAN PASANGAN DAN PLESTERAN
1 Pasang Batu Bata 1 : 2 44.10 M2 509,118.33 22,452,118.27
2 Pasang Batu bata 1 : 4 413.10 M2 499,150.68 206,199,145.13
3 Plesteran dinding 1 : 2 88.20 M2 88,377.27 7,794,875.43
4 Plesteran dinding 1 : 4 826.20 M2 85,461.48 70,608,270.65
5 Acian dinding dan Lantai Rabat 974.40 M2 50,852.48 49,550,660.78
356,605,070.26
VI PEKERJAAN ATAP DAN KUDA-KUDA
1 Pasang Lisplank Kayu 2/20 125.00 M' 100,237.50 12,529,687.50
2 Kuda-kuda + Skor Angin kayu besi 5/10 4.88 M3 8,795,314.00 42,921,132.32
3 Gording kayu matoa 5/10 4.74 M3 7,538,162.50 35,730,890.25
4 Pasang Reng dan Usuk 435.00 M2 93,407.88 40,632,425.63
5 Atap Multi Roof 435.00 M2 96,873.75 42,140,081.25
6 Nok Multi Roof 96.00 M' 79,543.13 7,636,140.00
181,590,356.95
VII PEKERJAAN KUSEN, PINTU DAN JENDELA
1 Pasang Kusen Pintu dan Jendela 5/10 3.80 M3 10,162,013.13 38,615,649.88
2 Pasang Pintu Panel 6.72 M2 1,002,017.50 6,733,557.60
3 Pasang Pintu Panel dalam dilapis Seng Plat 2.94 M2 1,038,812.09 3,054,107.54
4 Pasang Jendela Ungkit Kaca Ryben 5 mm 30.24 M2 549,653.23 16,621,513.52
5 Pasang Ventilasi Jalusi atas Kayu Besi 2./10 26.60 M2 831,975.38 22,130,544.98
6 Pasang Tralis Jendela 54.00 Unit 850,000.00 45,900,000.00
133,055,373.51
VIII PEKERJAAN PLAFOND
1 Pasang Rangka Plafond 557.00 M2 130,802.38 72,856,922.88
2 Pasang Plafond Gypsun 557.00 M3 148,667.75 82,807,936.75
3 Pasang List Gypsun 327.00 M' 99,625.08 32,577,399.53
188,242,259.15
HARGA JUMLAH
NO. URAIAN PEKERJAAN VOLUME SATUAN SATUAN HARGA
(Rp.) (Rp.)
IX PEKERJAAN INSTALASI LISTRIK
1 Lampu SL 18 Watt 24.00 Bh 476,630.00 11,439,120.00
2 Lampu SL 14 Watt 18.00 Bh 464,378.75 8,358,817.50
3 Instalasi Titik Lampu dan Stop Kontak 50.00 Titik 442,813.25 22,140,662.50
4 Saklar ganda 8.00 Bh 270,820.00 2,166,560.00
5 Saklar tunggal 5.00 Bh 266,736.25 1,333,681.25
6 Stop Kontak 8.00 Bh 270,820.00 2,166,560.00
7 Pasang Limit Listrik 2.00 Bh 176,600.88 353,201.75
8 Penyambungan Listrik PLN 1.00 Unit 7,500,000.00 7,500,000.00
55,458,603.00
X PEKERJAAN PENGUNCI DAN PENGGANTUNG
1 Kunci pintu 2 slaag 6.00 Bh 319,440.00 1,916,640.00
2 Engsel pintu 18.00 Bh 53,105.25 955,894.50
3 Engsel Jendela 108.00 Bh 35,403.50 3,823,578.00
4 Grendel Jendela 54.00 Bh 55,852.50 3,016,035.00
5 Hak Angin 108.00 Bh 50,377.25 5,440,743.00
15,152,890.50
XII PEKERJAAN PLUMBING
1 GIP dia 1/2" plus acesories 12.00 M' 66,852.84 802,234.13
2 Kran Air 2.00 Bh 48,700.44 97,400.88
3 Floor drain 2.00 Bh 75,449.00 150,898.00
4 Pasang Bak Mandi 2.00 Bh 1,476,513.05 2,953,026.11
5 Pek. Pipa PVC Ø 4" 12.00 M' 112,461.90 1,349,542.84
6 Pek. Pas Closet Duduk 2.00 Bh 2,485,588.88 4,971,177.75
7 Pasang Septictank dan Peresapan 1.00 Bh 8,598,138.97 8,598,138.97
18,922,418.66
XIII PEKERJAAN SALURAN
1 Galian Tanah 66.64 M3 122,265.00 8,147,739.60
2 Urugan Pasir 4.17 M3 627,880.00 2,615,120.20
3 Dinding Batu bata 1 : 2 71.40 M2 509,118.33 36,351,048.63
4 Plesteran Got 1 : 2 142.80 M2 88,377.27 12,620,274.51
5 Cor Lantai Got/Saluran 3.57 M3 1,964,912.13 7,014,736.29
66,748,919.23
XIV PEKERJAAN PENGECATAN
1 Cat tembok 974.40 M2 27,316.30 26,617,002.72
2 Cat Plafond 557.00 M2 28,812.30 16,048,451.10
3 Cat kilat kayu 94.00 M2 54,963.70 5,166,587.80
4 Teak Oil Pintu 12.60 M2 55,221.79 695,794.52
5 Residu Kuda-Kuda dan Gording 275.00 M2 27,178.80 7,474,170.00
56,002,006.14
XV PEKERJAAN LAIN-LAIN
1 Pembersihan Akhir 1.00 Ls 2,000,000.00 2,000,000.00
2,000,000.00
REKAPITULASI PEKERJAAN

PEKERJAAN : PEMBANGUNAN GEDUNG RUANG KULIAH PRODI MERAUKE


LOKASI : KABUPATEN MERAUKE
TAHUN ANGGARAN: 2018

NO URAIAN PEKERJAAN JUMLAH HARGA


(Rp.)

I PEKERJAAN PENDAHULUAN 22,805,480.90

II PEKERJAAN TANAH 133,374,782.20

III PEKERJAAN PONDASI DAN BETON 553,588,117.17

IV PEKERJAAN LANTAI KERAMIK 219,638,595.26

V PEKERJAAN PASANGAN DAN PLESTERAN 356,605,070.26

VI PEKERJAAN ATAP DAN KUDA-KUDA 181,590,356.95

VII PEKERJAAN KUSEN, PINTU DAN JENDELA 133,055,373.51

VIII PEKERJAAN PLAFOND 188,242,259.15

IX PEKERJAAN INSTALASI LISTRIK 55,458,603.00

X PEKERJAAN PENGUNCI DAN PENGGANTUNG 15,152,890.50

XII PEKERJAAN PLUMBING 18,922,418.66

XIII PEKERJAAN SALURAN 66,748,919.23

XIV PEKERJAAN PENGECATAN 56,002,006.14

XV PEKERJAAN LAIN-LAIN 2,000,000.00

REAL COST 2,003,184,872.92


PPN 10 % 200,318,487.29
JUMLAH 2,203,503,360.21
DIBULATKAN 2,203,503,000.00
TERBILANG : DUA MILYAR DUA RATUS TIGA JUTA LIMA RATUS TIGA RIBU RUPIAH

Jayapura, Agustus 2018


Penawar
PT.INDAMI STAR

DEMMY S.KAWER
Direktur Utama
ANALISA HARGA SATUAN
PEKERJAAN : PEMBANGUNAN GEDUNG RUANG KULIAH PRODI MERAUKE
LOKASI : KABUPATEN MERAUKE
TAHUN ANGG. : 2018

HARGA SATUAN JUMLAH


NO. URAIAN PEKERJAAN ANALISA SATUAN BAHAN/UPAH HARGA
(Rp) (Rp)
1 2 3 4 5 6
1. 1 M² Pembersihan Lokasi
Pekerja 0.1000 H/o 115,000.00 11,500.00
Mandor 0.0500 H/o 170,000.00 8,500.00

Jumlah 20,000.00
Overhead dan Profit 10.0% 2,000.00
Jumlah Harga Satuan 22,000.00

2. 1 M¹ Pemasangan Bauwplank
Papan Bouwplank 0.0070 M³ 2,475,000.00 17,325.00
Kayu Klas II 0.0120 M³ 2,475,000.00 29,700.00
Paku 0.0200 Kg 22,275.00 445.50
Pekerja 0.1000 H/o 115,000.00 11,500.00
Tukang Kayu 0.1000 H/o 145,000.00 14,500.00
Kepala Tukang Kayu 0.0100 H/o 160,000.00 1,600.00
Mandor 0.0050 H/o 170,000.00 850.00

Jumlah 75,920.50
Overhead dan Profit 10.0% 7,592.05
Jumlah Harga Satuan 83,512.55

3 1 M³ Galian Tanah Biasa (1 M)


Pekerja 0.7500 H/o 115,000.00 86,250.00
Mandor 0.0250 H/o 170,000.00 4,250.00

Jumlah 90,500.00
Overhead dan Profit 10.0% 9,050.00
Jumlah Harga Satuan 99,550.00

4 1 M³ Galian Tanah Biasa (2 M)


Pekerja 0.9000 H/o 115,000.00 103,500.00
Mandor 0.0450 H/o 170,000.00 7,650.00

Jumlah 111,150.00
Overhead dan Profit 10.0% 11,115.00
Jumlah Harga Satuan 122,265.00

5 1 M³ Urugan Kembali Galian Tanah


Pekerja 0.5000 H/o 115,000.00 57,500.00
Mandor 0.0500 H/o 170,000.00 8,500.00

Jumlah 66,000.00
Overhead dan Profit 10.0% 6,600.00
Jumlah Harga Satuan 72,600.00

6 1 M³ Urugan Pasir
Pasir Urug 1.2000 M³ 445,500.00 534,600.00
Pekerja 0.3000 H/o 115,000.00 34,500.00
Mandor 0.0100 H/o 170,000.00 1,700.00

Jumlah 570,800.00
Overhead dan Profit 10.0% 57,080.00
Jumlah Harga Satuan 627,880.00
HARGA SATUAN JUMLAH
NO. URAIAN PEKERJAAN ANALISA SATUAN BAHAN/UPAH HARGA
(Rp) (Rp)
1 2 3 4 5 6
7 1 M³ Pemadatan Tanah Pilihan
Pekerja 0.5000 H/o 115,000.00 57,500.00
Mandor 0.0500 H/o 170,000.00 8,500.00

Jumlah 66,000.00
Overhead dan Profit 10.0% 6,600.00
Jumlah Harga Satuan 72,600.00

8 1 M³ Urugan Pilihan
Urugan/Timbunan Pilihan 1.2000 M³ 259,875.00 311,850.00
Pekerja 0.2500 H/o 115,000.00 28,750.00
Mandor 0.0250 H/o 170,000.00 4,250.00

Jumlah 344,850.00
Overhead dan Profit 10.0% 34,485.00
Jumlah Harga Satuan 379,335.00

9 1 M³ Membuat Beton Mutu f'c : 7,4 Mpa (K100)


Sement PC 230.0000 Kg 1,670.63 384,243.75
Pasir Beton 0.4340 M³ 965,250.00 418,918.50
Kerikil Beton 0.5940 M³ 965,250.00 573,358.50
Air 215.000 Ltr 600.00 129,000.00
Pekerja 1.2000 H/o 115,000.00 138,000.00
Tukang 0.2000 H/o 145,000.00 29,000.00
Kepalla Tukang 0.0200 H/o 160,000.00 3,200.00
Mandor 0.0600 H/o 170,000.00 10,200.00
1,685,920.75
10 1 M³ Membuat Beton Mutu f'c : 7,4 Mpa (K175)
Semen PC (50 Kg) 326.0000 Kg 1,670.63 544,623.75
Pasir Pasang 0.3800 M³ 965,250.00 366,795.00
Kerikil 0.6120 M³ 965,250.00 590,733.00
Air 215.000 Ltr 600.00 129,000.00
Pekerja 1.6500 H/o 115,000.00 189,750.00
Tukang 0.2750 H/o 145,000.00 39,875.00
Kepala Tukang 0.0280 H/o 160,000.00 4,480.00
Mandor 0.0830 H/o 170,000.00 14,110.00
1,879,366.75
11 1 M³ Membuat Beton Mutu f'c : 19,3 Mpa (K225)
Sement PC 371.0000 Kg 1,670.63 619,801.88
Pasir Beton 0.3490 M³ 965,250.00 336,872.25
Batu Kerikil 0.6220 M³ 965,250.00 600,385.50
Air 215.000 Ltr 742.50 159,637.50
Pekerja 1.6500 H/o 115,000.00 189,750.00
Tukang 0.2750 H/o 145,000.00 39,875.00
Kepala Tukang 0.0280 H/o 160,000.00 4,480.00
Mandor 0.0830 H/o 170,000.00 14,110.00
1,964,912.13
12 1 Kg Pembersian dengan Besi Polos
Besi beton Polos 1.0500 Kg 14,850.00 15,592.50
Kawat Ikat 0.0150 Kg 18,562.50 278.44
Pekerja 0.0070 H/o 115,000.00 805.00
Tukang Besi 0.0070 H/o 145,000.00 1,015.00
Kepala Tukang 0.0007 H/o 160,000.00 112.00
Mandor 0.0004 H/o 170,000.00 68.00
17,870.94
16. 1 M² Begisting Balok Sloof
Kayu Begisting 0.0450 M³ 2,475,000.00 111,375.00
Paku Campur 0.3000 Kg 22,275.00 6,682.50
Pekerja 0.5200 H/o 115,000.00 59,800.00
Tukang 0.2600 H/o 145,000.00 37,700.00
Kepala Tukang 0.0260 H/o 160,000.00 4,160.00
Mandor 0.0260 H/o 170,000.00 4,420.00
224,137.50
HARGA SATUAN JUMLAH
NO. URAIAN PEKERJAAN ANALISA SATUAN BAHAN/UPAH HARGA
(Rp) (Rp)
1 2 3 4 5 6
13 1 M² Memasang Begisting Kolom
Kayu Matoa 0.0450 M³ 2,475,000.00 111,375.00
Paku Campur 0.4000 Kg 22,275.00 8,910.00
Multiplek 9 mm 0.3500 Lbr 111,375.00 38,981.25
Pekerja 0.6600 H/o 115,000.00 75,900.00
Tukang 0.3300 H/o 145,000.00 47,850.00
Kepala Tukang 0.0330 H/o 160,000.00 5,280.00
Mandor 0.0330 H/o 170,000.00 5,610.00
293,906.25
14 1 M² Memasang Begisting Balok
Kayu Matoa 0.0400 M³ 2,475,000.00 99,000.00
Paku Campur 0.2000 Kg 22,275.00 4,455.00
Multiplek 9 mm 0.3500 Lbr 111,375.00 38,981.25
Pekerja 0.6600 H/o 115,000.00 75,900.00
Tukang 0.3300 H/o 145,000.00 47,850.00
Kepala Tukang 0.0330 H/o 160,000.00 5,280.00
Mandor 0.0330 H/o 170,000.00 5,610.00
277,076.25
15 1 M² Memasang Begisting Plat Lantai
Kayu Begisting 0.0400 M³ 2,475,000.00 99,000.00
Paku Campur 0.4000 Kg 22,275.00 8,910.00
Balok Kayu 0.0150 M³ 2,475,000.00 37,125.00
Tripleks 9 mm 0.3500 Lbr 111,375.00 38,981.25
Pekerja 0.3200 H/o 115,000.00 36,800.00
Tukang 0.3300 H/o 145,000.00 47,850.00
Kepala Tukang 0.0330 H/o 160,000.00 5,280.00
Mandor 0.0060 H/o 170,000.00 1,020.00
274,966.25
16 1 M³ Membongkar Cetakan
Pekerja 4.0000 H/o 115,000.00 460,000.00
460,000.00
17 1 M³ Cor Pondasi Lajur
Cor Beton 1 Pc : 2 Ps : 3 Kr 1.0000 M³ 1,964,912.13 1,964,912.13
Bekisting 1.0800 M² 224,137.50 242,068.50

Jumlah 2,206,980.63
Overhead dan Profit 10.0% 220,698.06
Jumlah Harga Satuan 2,427,678.69

18 1 M³ Cor Balok Sloof 20/25 (K-225)


Beton K-225 1.0000 M³ 1,964,912.13 1,964,912.13
Pembesian 220.9000 Kg 17,870.94 3,947,690.09
Begisting Sloof 11.4545 M² 224,137.50 2,567,393.18
Pembongkaran Bekisting 1.1170 M³ 460,000.00 513,820.00

Jumlah 8,993,815.40
Overhead dan Profit 10.0% 899,381.54
Jumlah Harga Satuan 9,893,196.94

19 1 M³ Cor Balok Sloof 15 x 20


Cor Beton 1 Pc : 2 Ps : 3 Kr K-175 1.0000 M³ 1,879,366.75 1,879,366.75
Pembesian 197.7000 Kg 17,870.94 3,533,084.34
Bekisting 13.3300 M² 224,137.50 2,987,752.88
Pembongkaran Bekisting 0.3333 M³ 460,000.00 153,295.00

Jumlah 8,553,498.97
Overhead dan Profit 10.0% 855,349.90
Jumlah Harga Satuan 9,408,848.87
HARGA SATUAN JUMLAH
NO. URAIAN PEKERJAAN ANALISA SATUAN BAHAN/UPAH HARGA
(Rp) (Rp)
1 2 3 4 5 6
20 1 M³ Cor Kolom 20/20 (K225)
Beton K225 1.0000 M³ 1,964,912.13 1,964,912.13
Pembesian 237.5010 Kg 17,870.94 4,244,364.68
Begisting 11.4286 M² 224,137.50 2,561,571.43
Bongkar Bekisting 0.5530 M³ 460,000.00 254,380.00

Jumlah 9,025,228.23
Overhead dan Profit 10.0% 902,522.82
Jumlah Harga Satuan 9,927,751.05
21 1 M³ Cor Kolom Praktis 15 x 15 (K225)
Cor Beton (K-225) 1.0000 M³ 1,964,912.13 1,964,912.13
Pembesian 237.5010 Kg 17,870.94 4,244,364.68
Begisting Kolom 11.4286 M² 224,137.50 2,561,571.43

Jumlah 8,770,848.23
Overhead dan Profit 10.0% 877,084.82
Jumlah Harga Satuan 9,647,933.05

22 1 M³ Cor Beton Rinkbalk 15 x 20 (K225)


Beton K225 1.0000 M³ 1,964,912.13 1,964,912.13
Pembesian 196.8119 Kg 17,870.94 3,517,212.30
Begisting 13.3333 M² 224,137.50 2,988,500.00

Jumlah 8,470,624.43
Overhead dan Profit 10.0% 847,062.44
Jumlah Harga Satuan 9,317,686.87

23 1 M² Pasangan Batu Bata


Campuran 1 Pc : 2 Psr
Batu Bata 140.0000 Bh 1,485.00 207,900.00
Sement PC 32.9500 Kg 1,670.63 55,047.09
Pasir Pasang 0.0910 M³ 965,250.00 87,837.75
Pekerja 0.6500 H/o 115,000.00 74,750.00
Tukang Batu 0.2000 H/o 145,000.00 29,000.00
Kepala Tukang Batu 0.0200 H/o 160,000.00 3,200.00
Mandor 0.0300 H/o 170,000.00 5,100.00

Jumlah 462,834.84
Overhead dan Profit 10.0% 46,283.48
Jumlah Harga Satuan 509,118.33

24 1 M² Pasangan Batu Bata


Campuran 1 Pc : 4 Psr
Batu Bata 140.000 Bh 1,485.00 207,900.00
Sement PC 26.5500 Kg 1,670.63 44,355.09
Pasir Pasang 0.0930 M³ 965,250.00 89,768.25
Pekerja 0.6500 H/o 115,000.00 74,750.00
Tukang Batu 0.2000 H/o 145,000.00 29,000.00
Kepala Tukang Batu 0.0200 H/o 145,000.00 2,900.00
Mandor 0.0300 H/o 170,000.00 5,100.00

Jumlah 453,773.34
Overhead dan Profit 10.0% 45,377.33
Jumlah Harga Satuan 499,150.68

25 1 M² Plesteran Dinding 1 : 2
T. 1,5 Cm Camp. 1 Pc : 2 Psr
Sement PC 8.5200 Kg 1,670.63 14,233.73
Pasir Pasang 0.0170 M³ 965,250.00 16,409.25
Pekerja 0.2000 H/o 115,000.00 23,000.00
Tukang Batu 0.1500 H/o 145,000.00 21,750.00
Kepala Tukang Batu 0.0150 H/o 160,000.00 2,400.00
Mandor 0.0150 H/o 170,000.00 2,550.00

Jumlah 80,342.98
Overhead dan Profit 10.0% 8,034.30
Jumlah Harga Satuan 88,377.27
HARGA SATUAN JUMLAH
NO. URAIAN PEKERJAAN ANALISA SATUAN BAHAN/UPAH HARGA
(Rp) (Rp)
1 2 3 4 5 6
26 1 M² Plesteran Dinding 1 : 4
T. 1,5 Cm Camp. 1 Pc : 4 Psr
Sement PC 5.2000 Kg 1,670.63 8,687.25
Pasir Pasang 0.0200 M³ 965,250.00 19,305.00
Pekerja 0.2000 Jam 115,000.00 23,000.00
Tukang Batu 0.1500 Jam 145,000.00 21,750.00
Kepala Tukang Batu 0.0150 H/o 160,000.00 2,400.00
Mandor 0.0150 Jam 170,000.00 2,550.00

Jumlah 77,692.25
Overhead dan Profit 10.0% 7,769.23
Jumlah Harga Satuan 85,461.48

27 1 M² Acian Dinding Batu Tela


Sement PC 3.2500 Kg 1,670.63 5,429.53
Pekerja 0.2000 H/o 115,000.00 23,000.00
Tukang 0.1000 H/o 145,000.00 14,500.00
Kepala Tukang 0.0100 H/o 160,000.00 1,600.00
Mandor 0.0100 H/o 170,000.00 1,700.00

Jumlah 46,229.53
Overhead dan Profit 10.0% 4,622.95
Jumlah Harga Satuan 50,852.48

28 1 M² Pasang Lantai Keramik 40/40


Keramik uk. 40/40 11.0000 Bh 14,850.00 163,350.00
Semen PC 11.3800 Kg 1,670.63 19,011.71
Pasir Pasang 0.0450 M³ 965,250.00 43,436.25
Pekerja 0.2500 H/o 115,000.00 28,750.00
Tukang 0.1250 H/o 145,000.00 18,125.00
Kepalla Tukang 0.0130 H/o 160,000.00 2,080.00
Mandor 0.0130 H/o 170,000.00 2,210.00

Jumlah 276,962.96
Overhead dan Profit 10.0% 27,696.30
Jumlah Harga Satuan 304,659.26

29 1 M² Pasang Lantai Keramik 20/20


Keramik uk. 20/20 26.5000 Bh 8,910.00 236,115.00
Semen PC 10.4000 Kg 1,670.63 17,374.50
Pasir Pasang 0.0450 M³ 965,250.00 43,436.25
Pekerja 0.2700 H/o 115,000.00 31,050.00
Tukang 0.1350 H/o 145,000.00 19,575.00
Kepalla Tukang 0.0140 H/o 160,000.00 2,240.00
Mandor 0.0140 H/o 170,000.00 2,380.00

Jumlah 352,170.75
Overhead dan Profit 10.0% 35,217.08
Jumlah Harga Satuan 387,387.83

30 1 M² Pasang Dinding Keramik 20/25


Dinding Keramik 20 x 25 cm 26.5000 M² 7,425.00 196,762.50
Semen PC 10.0000 Kg 1,670.63 16,706.25
Pasir Pasang 0.0450 M³ 965,250.00 43,436.25
Pekerja 0.7000 H/o 115,000.00 80,500.00
Tukang 0.3500 H/o 145,000.00 50,750.00
Kepalla Tukang 0.0350 H/o 160,000.00 5,600.00
Mandor 0.0350 H/o 170,000.00 5,950.00

Jumlah 399,705.00
Overhead dan Profit 10.0% 39,970.50
Jumlah Harga Satuan 439,675.50
HARGA SATUAN JUMLAH
NO. URAIAN PEKERJAAN ANALISA SATUAN BAHAN/UPAH HARGA
(Rp) (Rp)
1 2 3 4 5 6
31 1 M³ Kusen Pintu dan Jendela
Kayu Besi uk. 5/10 1.0000 M³ 4,950,000.00 4,950,000.00
Paku 1.2500 Kg 22,275.00 27,843.75
Lem Kayu 1.0000 Kg 14,850.00 14,850.00
Pekerja 7.0000 H/o 115,000.00 805,000.00
Tukang 21.0000 H/o 145,000.00 3,045,000.00
Kepalla Tukang 2.1000 H/o 160,000.00 336,000.00
Mandor 0.3500 H/o 170,000.00 59,500.00

Jumlah 9,238,193.75
Overhead dan Profit 10.0% 923,819.38
Jumlah Harga Satuan 10,162,013.13

32 1 M² Pasang Daun Pintu Panil Kayu


Papan Kayu Besi 0.0600 M³ 4,950,000.00 297,000.00
Lem Kayu 0.5000 Kg 14,850.00 7,425.00
Pekerja 1.0000 H/o 115,000.00 115,000.00
Tukang 3.0000 H/o 145,000.00 435,000.00
Kepalla Tukang 0.3000 H/o 160,000.00 48,000.00
Mandor 0.0500 H/o 170,000.00 8,500.00

Jumlah 910,925.00
Overhead dan Profit 10.0% 91,092.50
Jumlah Harga Satuan 1,002,017.50

33 1 M² Pasang Pintu dan Jendela Kaca


Kaca Riben T. 5 mm 1.2000 M² 322,987.50 387,585.00
Papan kayu Besi 0.0240 M³ 4,950,000.00 118,800.00
Lem Kayu 0.3000 Kg 14,850.00 4,455.00
Pekerja 0.8000 H/o 115,000.00 92,000.00
Tukang 2.4000 H/o 145,000.00 348,000.00
Kepalla Tukang 0.2400 H/o 160,000.00 38,400.00
Mandor 0.0400 H/o 170,000.00 6,800.00

Jumlah 996,040.00
Overhead dan Profit 10.0% 99,604.00
Jumlah Harga Satuan 1,095,644.00

34 1 M² Pasang Daun Pintu Panil Kayu Lapis Seng Plat


Papan Kayu Besi 0.0600 M³ 4,950,000.00 297,000.00
Lem Kayu 0.5000 Kg 14,850.00 7,425.00
Seng Plat BJLS 30 0.5300 Lbr 63,112.50 33,449.63
Pekerja 1.0000 H/o 115,000.00 115,000.00
Tukang 3.0000 H/o 145,000.00 435,000.00
Kepalla Tukang 0.3000 H/o 160,000.00 48,000.00
Mandor 0.0500 H/o 170,000.00 8,500.00

Jumlah 944,374.63
Overhead dan Profit 10.0% 94,437.46
Jumlah Harga Satuan 1,038,812.09

35 1 M² Jalusi Kayu Besi 2/10 cm


Papan Kayu Besi 0.0600 M³ 4,950,000.00 297,000.00
Tukang Kayu 2.0000 H/o 145,000.00 290,000.00
Kepala Tukang Kayu 0.2000 H/o 160,000.00 32,000.00
Pekerja 0.6700 H/o 115,000.00 77,050.00
Mandor 0.3350 H/o 170,000.00 56,950.00
Paku 0.1500 Kg 22,275.00 3,341.25

Jumlah 756,341.25
Overhead dan Profit 10.0% 75,634.13
Jumlah Harga Satuan 831,975.38
HARGA SATUAN JUMLAH
NO. URAIAN PEKERJAAN ANALISA SATUAN BAHAN/UPAH HARGA
(Rp) (Rp)
1 2 3 4 5 6
36 1 M² Pasang Jendela Kaca Panel (kaca T. 5 mm)
Kaca Ryben T. 5 mm 1.1000 M² 322,987.50 355,286.25
Lat Kayu 4.1000 Btg 28,875.00 118,387.50
Pekerja 0.0150 H/o 115,000.00 1,725.00
Tukang 0.1500 H/o 145,000.00 21,750.00
Kepalla Tukang 0.0150 H/o 160,000.00 2,400.00
Mandor 0.0008 H/o 170,000.00 136.00

Jumlah 499,684.75
Overhead dan Profit 10.0% 49,968.48
Jumlah Harga Satuan 549,653.23

37 1 M² Rangka Plafond Kayu Klas II


Kayu Klas II 5/10 0.0163 M³ 2,475,000.00 40,342.50
Tukang Kayu 0.3000 H/o 145,000.00 43,500.00
Kepala Tukang Kayu 0.0300 H/o 160,000.00 4,800.00
Pekerja 0.2000 H/o 115,000.00 23,000.00
Mandor 0.0100 H/o 170,000.00 1,700.00
Paku 0.2500 Kg 22,275.00 5,568.75

Jumlah 118,911.25
Overhead dan Profit 10.0% 11,891.13
Jumlah Harga Satuan 130,802.38

38 1 M² Plafond Gypsun
Gypsun 1.0000 Lbr 111,375.00 111,375.00
Paku/Moor 0.1000 Kg 22,275.00 2,227.50
Pekerja 0.0100 H/o 115,000.00 1,150.00
Tukang Kayu 0.1000 H/o 145,000.00 14,500.00
Kepala Tukang Kayu 0.0050 H/o 160,000.00 800.00
Mandor 0.0300 H/o 170,000.00 5,100.00

Jumlah 135,152.50
Overhead dan Profit 10.0% 13,515.25
Jumlah Harga Satuan 148,667.75

39 1 M' Pekerjaan List Gpysun


List Gypsun 1.1000 M' 66,000.00 72,600.00
Paku 0.0300 Kg 22,275.00 668.25
Pekerja 0.0100 H/o 115,000.00 1,150.00
Tukang Kayu 0.1000 H/o 145,000.00 14,500.00
Kepala Tukang 0.0050 H/o 160,000.00 800.00
Mandor 0.0050 H/o 170,000.00 850.00

Jumlah 90,568.25
Overhead dan Profit 10.0% 9,056.83
Jumlah Harga Satuan 99,625.08

40 1 M2 Pasang Reng/Usuk
Seng/Usuk kayu besi 0.0100 M3 4,950,000.00 49,500.00
Paku 0.1500 Kg 22,275.00 3,341.25
Pekerja 0.0100 H/o 115,000.00 1,150.00
Tukang Kayu 0.1000 H/o 145,000.00 14,500.00
Kepala Tukang Kayu 0.1000 H/o 160,000.00 16,000.00
Mandor 0.0025 H/o 170,000.00 425.00

Jumlah 84,916.25
Overhead dan Profit 10.0% 8,491.63
Jumlah Harga Satuan 93,407.88
HARGA SATUAN JUMLAH
NO. URAIAN PEKERJAAN ANALISA SATUAN BAHAN/UPAH HARGA
(Rp) (Rp)
1 2 3 4 5 6
41 1 M³ Konstruksi Kuda - kuda Ky. Besi 5/10
Kayu Besi uk. 5/10 1.1000 M³ 4,950,000.00 5,445,000.00
Paku 5.6000 Kg 22,275.00 124,740.00
Pekerja 4.0000 H/o 115,000.00 460,000.00
Tukang 12.0000 H/o 145,000.00 1,740,000.00
Kepalla Tukang 1.2000 H/o 160,000.00 192,000.00
Mandor 0.2000 H/o 170,000.00 34,000.00

Jumlah 7,995,740.00
Overhead dan Profit 10.0% 799,574.00
Jumlah Harga Satuan 8,795,314.00

42 1 M³ Konstruksi Gording Ky. Matoa 5/10


Kayu Matoa 5/10 1.1000 M³ 2,475,000.00 2,722,500.00
Paku Kayu 3.0000 Kg 22,275.00 66,825.00
Pekerja 6.7000 H/o 115,000.00 770,500.00
Tukang 20.1000 H/o 145,000.00 2,914,500.00
Kepalla Tukang 2.0100 H/o 160,000.00 321,600.00
Mandor 0.3350 H/o 170,000.00 56,950.00

Jumlah 6,852,875.00
Overhead dan Profit 10.0% 685,287.50
Jumlah Harga Satuan 7,538,162.50

44 1 M² Pasang Atap Sakura Roof


Atap Sakura Roof 0.8000 Lbr 66,825.00 53,460.00
Paku Seng 0.0200 Kg 18,562.50 371.25
Plastik 1.0000 M2 18,562.50 18,562.50
Pekerja 0.1200 H/o 115,000.00 13,800.00
Tukang Kayu 0.0600 H/o 145,000.00 8,700.00
Kepala Tukang Kayu 0.0060 H/o 160,000.00 960.00
Mandor 0.0060 H/o 170,000.00 1,020.00

Jumlah 96,873.75
Overhead dan Profit 10.0% 9,687.38
Jumlah Harga Satuan 106,561.13

45 1 M' Nok Atap Sakura Roof


Nok Sakura Roof 0.4500 Lbr 63,112.50 28,400.63
Paku 0.0400 Kg 18,562.50 742.50
Tukang Kayu 0.0700 H/o 145,000.00 10,150.00
Kepala Tukang Kayu 0.0800 H/o 160,000.00 12,800.00
Pekerja 0.1500 H/o 115,000.00 17,250.00
Mandor 0.0600 H/o 170,000.00 10,200.00

Jumlah 79,543.13
Overhead dan Profit 10.0% 7,954.31
Jumlah Harga Satuan 87,497.44

46 1 M' Pasang Listplank uk. 2 x 20 cm


Papan Kayu Besi 0.0108 M³ 4,950,000.00 53,460.00
Paku 0.1000 Kg 22,275.00 2,227.50
Pekerja 0.1000 H/o 115,000.00 11,500.00
Tukang Kayu 0.2000 H/o 145,000.00 29,000.00
Kepala Tukang Kayu 0.0200 H/o 160,000.00 3,200.00
Mandor 0.0050 H/o 170,000.00 850.00

Jumlah 100,237.50
Overhead dan Profit 10.0% 10,023.75
Jumlah Harga Satuan 110,261.25
HARGA SATUAN JUMLAH
NO. URAIAN PEKERJAAN ANALISA SATUAN BAHAN/UPAH HARGA
(Rp) (Rp)
1 2 3 4 5 6
47 1 Bh Pasang Kunci Tanam 2 Slaag
Kunci Tanam Dua Slaag 1.0000 Bh 207,900.00 207,900.00
Pekerja 0.0100 H/o 115,000.00 1,150.00
Tukang 0.5000 H/o 145,000.00 72,500.00
Kepala Tukang 0.0500 H/o 160,000.00 8,000.00
Mandor 0.0050 H/o 170,000.00 850.00

Jumlah 290,400.00
Overhead dan Profit 10.0% 29,040.00
Jumlah Harga Satuan 319,440.00

48 1 Bh Pasang Engsel Pintu Ring Nilon


Engsel Pintu Ring Nilon 1.0000 M¹ 22,275.00 22,275.00
Pekerja 0.0150 H/o 115,000.00 1,725.00
Tukang 0.1500 H/o 145,000.00 21,750.00
Kepala Tukang 0.0150 H/o 160,000.00 2,400.00
Mandor 0.0008 H/o 170,000.00 127.50

Jumlah 48,277.50
Overhead dan Profit 10.0% 4,827.75
Jumlah Harga Satuan 53,105.25

49 1 Bh Pasang Engsel Jendela Ring Nilon


Engsel Jendela Ring Nilon 1.0000 M¹ 14,850.00 14,850.00
Pekerja 0.0100 H/o 115,000.00 1,150.00
Tukang 0.1000 H/o 145,000.00 14,500.00
Kepala Tukang 0.0100 H/o 160,000.00 1,600.00
Mandor 0.0005 H/o 170,000.00 85.00

Jumlah 32,185.00
Overhead dan Profit 10.0% 3,218.50
Jumlah Harga Satuan 35,403.50

50 1 Bh Pasang Grendel Jendela


Kunci Grendel Jendela 1.0000 Bh 14,850.00 14,850.00
Pekerja 0.0500 H/o 115,000.00 5,750.00
Tukang 0.1500 H/o 145,000.00 21,750.00
Kepala Tukang 0.0500 H/o 160,000.00 8,000.00
Mandor 0.0025 H/o 170,000.00 425.00

Jumlah 50,775.00
Overhead dan Profit 10.0% 5,077.50
Jumlah Harga Satuan 55,852.50

51 1 Bh Pasang Hak Angin Jendela


Hak Angin Biasa 1.0000 Bh 18,562.50 18,562.50
Pekerja 0.0150 H/o 115,000.00 1,725.00
Tukang 0.1500 H/o 145,000.00 21,750.00
Kepala Tukang 0.0150 H/o 160,000.00 2,400.00
Mandor 0.0080 H/o 170,000.00 1,360.00

Jumlah 45,797.50
Overhead dan Profit 10.0% 4,579.75
Jumlah Harga Satuan 50,377.25

52 1 M² Pengecatan Tembok Baru


Plamur tembok 0.1100 Kg 29,700.00 3,267.00
Cat Dasar 0.1000 Kg 18,562.50 1,856.25
Cat Tembok 0.2600 Kg 25,987.50 6,756.75
Pekerja 0.0200 H/o 115,000.00 2,300.00
Tukang Kayu 0.0630 H/o 145,000.00 9,135.00
Kepala Tukang 0.0063 H/o 160,000.00 1,008.00
Mandor 0.0030 H/o 170,000.00 510.00

Jumlah 24,833.00
Overhead dan Profit 10.0% 2,483.30
Jumlah Harga Satuan 27,316.30
HARGA SATUAN JUMLAH
NO. URAIAN PEKERJAAN ANALISA SATUAN BAHAN/UPAH HARGA
(Rp) (Rp)
1 2 3 4 5 6
53 1 M² Pengecatan Bidang kayu Baru
Cat Menie 0.2000 Kg 14,850.00 2,970.00
Plamur 0.1500 Kg 29,700.00 4,455.00
Cat dasar 0.1700 Kg 14,850.00 2,524.50
Cat Kilat/Minyak 0.3500 Kg 44,550.00 15,592.50
Pekerja 0.0700 H/o 115,000.00 8,050.00
Tukang 0.1050 H/o 145,000.00 15,225.00
Kepala Tukang 0.0040 H/o 160,000.00 640.00
Mandor 0.0030 H/o 170,000.00 510.00

Jumlah 49,967.00
Overhead dan Profit 10.0% 4,996.70
Jumlah Harga Satuan 54,963.70

54 1 M² Pengecatan Plafond
Cat Tembok 0.4000 Kg 25,987.50 10,395.00
Pekerja 0.0300 H/o 115,000.00 3,450.00
Tukang Kayu 0.0730 H/o 145,000.00 10,585.00
Kepala Tukang 0.0073 H/o 160,000.00 1,168.00
Mandor 0.0035 H/o 170,000.00 595.00

Jumlah 26,193.00
Overhead dan Profit 10.0% 2,619.30
Jumlah Harga Satuan 28,812.30

55 1 M² Pekerjaan Teak Oil Politur dan Vernis


Teak oil / Politur / Vernis 0.1500 Ltr 25,987.50 3,898.13
Dempul 0.0500 Kg 22,275.00 1,113.75
Amplas 0.1000 Lbr 3,712.50 371.25
Kuas 0.0100 Bh 14,850.00 148.50
Pekerja 0.1600 H/o 115,000.00 18,400.00
Tukang Kayu 0.1600 H/o 145,000.00 23,200.00
Kepala Tukang Kayu 0.0160 H/o 160,000.00 2,560.00
Mandor 0.0030 H/o 170,000.00 510.00

Jumlah 50,201.63
Overhead dan Profit 10.0% 5,020.16
Jumlah Harga Satuan 55,221.79

56 1 M² Pekerjaan Residu
Residu 0.4000 Kg 22,275.00 8,910.00
Pekerja 0.0300 H/o 115,000.00 3,450.00
Tukang Kayu 0.0730 H/o 145,000.00 10,585.00
Kepala Tukang 0.0073 H/o 160,000.00 1,168.00
Mandor 0.0035 H/o 170,000.00 595.00

Jumlah 24,708.00
Overhead dan Profit 10.0% 2,470.80
Jumlah Harga Satuan 27,178.80
57 1 TTK Pasang Lampu XL 18 Watt
Lampu XL 18 Watt 1.0000 Bh 48,262.50 48,262.50
Acesories 1.0000 Bh 30,000.00 30,000.00
Kabel Listrik 5.0000 M' 14,107.50 70,537.50
Pekerja 1.0000 H/o 115,000.00 115,000.00
Tukang 1.0000 H/o 145,000.00 145,000.00
Kepala Tukang 0.1000 H/o 160,000.00 16,000.00
Mandor 0.0500 H/o 170,000.00 8,500.00

Jumlah 433,300.00
Overhead dan Profit 10.0% 43,330.00
Jumlah Harga Satuan 476,630.00
HARGA SATUAN JUMLAH
NO. URAIAN PEKERJAAN ANALISA SATUAN BAHAN/UPAH HARGA
(Rp) (Rp)
1 2 3 4 5 6
58 1 TTK Pasang Lampu XL 14 Watt
Balon Lampu XL 14 Watt 1.0000 Bh 37,125.00 37,125.00
Acsesoris 1.0000 Bh 30,000.00 30,000.00
Kabel Listrik 5.0000 M' 14,107.50 70,537.50
Pekerja 1.0000 H/o 115,000.00 115,000.00
Tukang 1.0000 H/o 145,000.00 145,000.00
Kepala Tukang 0.1000 H/o 160,000.00 16,000.00
Mandor 0.0500 H/o 170,000.00 8,500.00

Jumlah 422,162.50
Overhead dan Profit 10.0% 42,216.25
Jumlah Harga Satuan 464,378.75
59 1 TTK Pasang Titik Lampu
Fiting Lampu 1.0000 Bh 14,850.00 14,850.00
Pipa Pralon 1.0000 Bh 7,425.00 7,425.00
Kabel Listrik 6.0000 M' 14,107.50 84,645.00
T. Dos 1.0000 Bh 11,137.50 11,137.50
Pekerja 1.0000 H/o 115,000.00 115,000.00
Tukang 1.0000 H/o 145,000.00 145,000.00
Kepala Tukang 0.1000 H/o 160,000.00 16,000.00
Mandor 0.0500 H/o 170,000.00 8,500.00

Jumlah 402,557.50
Overhead dan Profit 10.0% 40,255.75
Jumlah Harga Satuan 442,813.25

60 1 TTK Pasang Saklar Tunggal


Saklar Tunggal 1.0000 Bh 22,275.00 22,275.00
Kabel Listrik 5.0000 M' 14,107.50 70,537.50
Pipa Kabel Union 1.0000 Btg 7,425.00 7,425.00
Pekerja 0.5000 H/o 115,000.00 57,500.00
Tukang 0.5000 H/o 145,000.00 72,500.00
Kepala Tukang Listrik 0.0500 H/o 160,000.00 8,000.00
Mandor 0.0250 H/o 170,000.00 4,250.00

Jumlah 242,487.50
Overhead dan Profit 10.0% 24,248.75
Jumlah Harga Satuan 266,736.25

61 1 TTK Pasang Saklar Double


Saklar Double 1.0000 Bh 25,987.50 25,987.50
Kabel 5.0000 M' 14,107.50 70,537.50
Pipa Kabel Union 1.0000 Btg 7,425.00 7,425.00
Pekerja 0.5000 H/o 115,000.00 57,500.00
Tukang 0.5000 H/o 145,000.00 72,500.00
Kepala Tukang Listrik 0.0500 H/o 160,000.00 8,000.00
Mandor 0.0250 H/o 170,000.00 4,250.00

Jumlah 246,200.00
Overhead dan Profit 10.0% 24,620.00
Jumlah Harga Satuan 270,820.00

62 1 TTK Pasang Stop Kontak


Stop Kontak 1.0000 Bh 25,987.50 25,987.50
Kabel 5.0000 M 14,107.50 70,537.50
Pipa Kabel Union 1.0000 Btg 7,425.00 7,425.00
Pekerja 0.5000 H/o 115,000.00 57,500.00
Tukang 0.5000 H/o 145,000.00 72,500.00
Kepala Tukang Listrik 0.0500 H/o 160,000.00 8,000.00
Mandor 0.0250 H/o 170,000.00 4,250.00

Jumlah 246,200.00
Overhead dan Profit 10.0% 24,620.00
Jumlah Harga Satuan 270,820.00
HARGA SATUAN JUMLAH
NO. URAIAN PEKERJAAN ANALISA SATUAN BAHAN/UPAH HARGA
(Rp) (Rp)
1 2 3 4 5 6
63 1 Bh Limit Listrik
Limit Listrik 1.0000 Bh 22,275.00 22,275.00
Kabel Instalasi 1.0000 M 14,107.50 14,107.50
Pipa Kabel Union 1.0000 Btg 25,987.50 25,987.50
Tukang 0.5000 H/o 14,107.50 7,053.75
Pekerja 0.5000 H/o 7,425.00 3,712.50
Kepala tukang Listrik 0.7500 H/o 115,000.00 86,250.00
Mandor 0.0080 H/o 145,000.00 1,160.00

Jumlah 160,546.25
Overhead dan Profit 10.0% 16,054.63
Jumlah Harga Satuan 176,600.88

64 1 M¹ Memasang Pipa GIP Medium Ø ½"


Pipa GIP Medium Ø ½" 1.2000 M¹ 22,893.75 27,472.50
Aksesoris (35 % dari Harga Bahan) 8,012.81
Pekerja 0.0540 H/o 115,000.00 6,210.00
Tukang 0.0900 H/o 145,000.00 13,050.00
Kepala Tukang 0.0090 H/o 160,000.00 1,440.00
Mandor 0.0270 H/o 170,000.00 4,590.00

Jumlah 60,775.31
Overhead dan Profit 10.0% 6,077.53
Jumlah Harga Satuan 66,852.84

65 1 M¹ Memasang Pipa PVC Ø 3" AW


Pipa PVC Ø 3 AW 1.2000 Bh 33,412.50 40,095.00
Perlengkapan (35% Harga Pipa) 11,694.38
Pekerja 0.0810 H/o 115,000.00 9,315.00
Tukang 0.1350 H/o 145,000.00 19,575.00
Kepala Tukang 0.0135 H/o 160,000.00 2,160.00
Mandor 0.0040 H/o 170,000.00 680.00

Jumlah 83,519.38
Overhead dan Profit 10.0% 8,351.94
Jumlah Harga Satuan 91,871.31

66 1 M¹ Memasang Pipa PVC Ø 4" AW


Pipa PVC Ø 4 AW 1.2000 Bh 45,478.13 54,573.75
Perlengkapan (35% Harga Pipa) 15,917.34
Pekerja 0.0810 H/o 115,000.00 9,315.00
Tukang 0.1350 H/o 145,000.00 19,575.00
Kepala Tukang 0.0135 H/o 160,000.00 2,160.00
Mandor 0.0041 H/o 170,000.00 697.00

Jumlah 102,238.09
Overhead dan Profit 10.0% 10,223.81
Jumlah Harga Satuan 112,461.90

67 1 M¹ Memasang Pipa PVC Ø 3/4" AW


Pipa PVC Ø 3/4 AW 1.2000 Bh 18,562.50 22,275.00
Perlengkapan (35% Harga Pipa) 6,496.88
Pekerja 0.0540 H/o 115,000.00 6,210.00
Tukang 0.0900 H/o 145,000.00 13,050.00
Kepala Tukang 0.0090 H/o 160,000.00 1,440.00
Mandor 0.0030 H/o 170,000.00 510.00

Jumlah 49,981.88
Overhead dan Profit 10.0% 4,998.19
Jumlah Harga Satuan 54,980.06
HARGA SATUAN JUMLAH
NO. URAIAN PEKERJAAN ANALISA SATUAN BAHAN/UPAH HARGA
(Rp) (Rp)
1 2 3 4 5 6
68 1 M¹ Memasang Pipa GIP Ø 2"
Pipa GIP Ø 2 1.2000 Bh 54,450.00 65,340.00
Perlengkapan (35% Harga Pipa) 0.3500 19,057.50
Biaya Pengelasan Pipa 1.0000 Titik 500,000.00 500,000.00
Pekerja 0.5400 H/o 115,000.00 62,100.00
Tukang 0.0900 H/o 145,000.00 13,050.00
Kepala Tukang 0.0900 H/o 160,000.00 14,400.00
Mandor 0.0270 H/o 170,000.00 4,590.00

Jumlah 678,537.50
Overhead dan Profit 10.0% 67,853.75
Jumlah Harga Satuan 746,391.25

69 1 Bh Memasang Kloset Duduk Porselin


Kloset Duduk Porselin 1.0000 Bh 1,856,250.00 1,856,250.00
Semen Portland 6.0000 Kg 1,670.63 10,023.75
Pasir Pasang 0.0100 M³ 965,250.00 9,652.50
Pekerja 1.0000 H/o 115,000.00 115,000.00
Tukang 1.5000 H/o 145,000.00 217,500.00
Kepala Tukang 0.1500 H/o 160,000.00 24,000.00
Mandor 0.1600 H/o 170,000.00 27,200.00

Jumlah 2,259,626.25
Overhead dan Profit 10.0% 225,962.63
Jumlah Harga Satuan 2,485,588.88

70 1 Bh Memasang Kran Air Ø ½"


Kran Air Ø ½" 1.0000 Bh 25,987.50 25,987.50
Seal Tape 0.0250 Bh 7,425.00 185.63
Pekerja 0.0100 H/o 115,000.00 1,150.00
Tukang 0.1000 H/o 145,000.00 14,500.00
Kepala Tukang 0.0100 H/o 160,000.00 1,600.00
Mandor 0.0050 H/o 170,000.00 850.00

Jumlah 44,273.13
Overhead dan Profit 10.0% 4,427.31
Jumlah Harga Satuan 48,700.44

71 1 Bh Memasang Floor Drain


Floor Drain 1.0000 Bh 50,490.00 50,490.00
Pekerja 0.0100 H/o 115,000.00 1,150.00
Tukang 0.1000 H/o 145,000.00 14,500.00
Kepala Tukang 0.0100 H/o 160,000.00 1,600.00
Mandor 0.0050 H/o 170,000.00 850.00

Jumlah 68,590.00
Overhead dan Profit 10.0% 6,859.00
Jumlah Harga Satuan 75,449.00

72 1 Bh Pasang Septictank dan Peresapan


Pas. Batu Bata 1 : 2 1.7500 M² 509,118.33 890,957.07
Beton bertulang 1 : 2 : 3 k-100 1.7500 M³ 1,685,920.75 2,950,361.31
Pas. Pipa PVC 4" 1.0000 Btg 181,912.50 181,912.50
Plesteran 1 : 3 26.0000 M² 88,377.27 2,297,809.09
Pipa Hawa Gip 2" 1.0000 M' 54,450.00 54,450.00
Pekerja 4.5000 H/o 115,000.00 517,500.00
Tukang 3.0000 H/o 145,000.00 435,000.00
Kepala Tukang 2.1500 H/o 160,000.00 344,000.00
Mandor 0.8500 H/o 170,000.00 144,500.00

Jumlah 7,816,489.97
Overhead dan Profit 10.0% 781,649.00
Jumlah Harga Satuan 8,598,138.97
HARGA SATUAN JUMLAH
NO. URAIAN PEKERJAAN ANALISA SATUAN BAHAN/UPAH HARGA
(Rp) (Rp)
73 1 Bh Pasang Bak Mandi Lapis Keramik
uk.20 x 25 cm
Ubin Porselin 20 x 25 cm 1.0000 M² 8,910.00 8,910.00
Semen PC 0.9500 Kg 1,670.63 1,587.09
Batu Tela 30.0000 Bh 1,485.00 44,550.00
Pasir Pasang 0.9500 M³ 965,250.00 916,987.50
Pekerja 2.5000 H/o 115,000.00 287,500.00
Tukang 0.2500 H/o 145,000.00 36,250.00
Kepala Tukang 0.0250 H/o 160,000.00 4,000.00
Mandor 0.2500 H/o 170,000.00 42,500.00

Jumlah 1,342,284.59
Overhead dan Profit 10.0% 134,228.46
Jumlah Harga Satuan 1,476,513.05
HARGA BAHAN DAN UPAH KERJA

PEKERJAAN : PEMBANGUNAN GEDUNG RUANG KULIAH PRODI MERAUKE


LOKASI : KABUPATEN MERAUKE
TAHUN ANGGARAN : 2018

NO NAMA BAHAN SATUAN HARGA BAHAN


(Rp.)
1 2 3 4
I. DAFTAR HARGA SATUAN BAHAN
A. MATERIAL BATU DAN PASIR
1 Batu Bata Merah Bh 1,485.00
2 Batu Roster Bh 8,167.50
3 Paving Blok Bh 8,910.00
4 Batu Pecah 2/3 M3 965,250.00
5 Pasir Pasang M3 965,250.00
6 Pasir Urug M3 445,500.00
7 Tanah Timbunan M3 259,875.00

B. KELOMPOK BAHAN KAYU


1 Balok Kayu Besi 5 x 10 M3 4,950,000.00
2 Balok Kayu Besi 5 x 5 M3 4,950,000.00
3 Papan Kayu Besi 2 x 20 M3 4,950,000.00
4 Balok Kayu Matoa 5 x 10 M3 2,475,000.00
5 Balok Kayu Matoa 5 x 5 M3 2,475,000.00
6 Papan Kayu Matoa 2 x 20 M3 2,475,000.00
7 Kayu Steger / Buah M3 2,475,000.00
8 Papan Bekisting M3 2,475,000.00
9 Kayu List Kayu Btng 28,875.00
10 List Gpysun M' 66,000.00

C. HARGA KELOMPOK BAHAN TOKO

1 Semen PC 50 Kg Kg 1,670.63
2 Semen Warna Kg 18,562.50
3 Keramik uk. 40 x 40 Bh 14,850.00
4 Keramik uk. 30 x 30 Bh 11,137.50
5 Keramik uk. 20 x 20 Bh 8,910.00
6 Keramik uk. 20 x 25 Bh 7,425.00
7 Keramik uk. 10 x 40 Bh 8,910.00
8 Sakura Roof Lbr 66,825.00
9 Seng Gelombang BJLS 30 mm Lbr 59,400.00
10 Nok Sakura Roof Lbr 63,112.50
11 Seng Plat BJLS 20 mm Lbr 55,687.50
12 Tripleks 3 mm Lbr 63,112.50
13 Gypsun Lbr 111,375.00
14 Teakwood uk. 122 x 144 Lbr 152,212.50
15 Teakwood (Ukuran Pintu) Lbr 111,375.00
16 Kaca Ryben T. 5 mm M2 322,987.50
NO NAMA BAHAN SATUAN HARGA BAHAN
(Rp.)
1 2 3 4
17 Besi Beton Kg 14,850.00
18 Kawat Ikat Kg 18,562.50
19 Pipa GIP dia. 1/2" Btg 137,362.50
20 Pipa GIP dia. 3/4" Btg 196,762.50
21 Pipa GIP dia. 1" Btg 241,312.50
22 Pipa GIP dia. 2" Btg 326,700.00
23 Pipa PVC dia. ½" Btg 29,700.00
24 Pipa PVC dia. 3/4" Btg 40,837.50
25 Pipa PVC dia. 1" Btg 48,262.50
26 Pipa PVC dia. 2" Btg 74,250.00
27 Pipa PVC dia. 3" Btg 133,650.00
28 Pipa PVC dia. 4" Btg 181,912.50
29 Pipa PVC dia. 6" Btg 262,102.50
30 Air Ltr 742.50
31 Sealtipe Bh 7,425.00
32 Stop Kran gip dia. 2" Bh 233,887.50
33 Paku Campur Kg 22,275.00
34 Paku Seng + Ring Karet Kg 18,562.50
35 Paku Tripleks Kg 18,562.50
36 Karet Paku Bh 742.50
37 Cat Tembok Dasar Kg 18,562.50
38 Cat Tembok Kg 25,987.50
39 Cat Kilat Kayu Kg 44,550.00
40 Cat Besi Kg 25,987.50
41 Cat Meni Kayu Kg 14,850.00
42 Minyak Cat (Thineer) Ltr 18,562.50
43 Residu Kg 22,275.00
44 Teak Oil / Politur Ltr 25,987.50
45 Plamur Tembok Kg 29,700.00
46 Dempul Kayu Kg 22,275.00
47 Amplas Lbr 3,712.50
48 Kuas Sedang Bh 14,850.00
49 Lem Kayu Kg 14,850.00
50 Kunci Tanam 2 Slaag Bh 207,900.00
51 Kunci Tanam Silinder Bh 170,775.00
52 Engsel Pintu Psg 22,275.00
53 Engsel Jendela Psg 14,850.00
54 Grendel Jendela Bh 14,850.00
55 Hak Angin Psg 18,562.50
56 Lampu SL Philips 18 watt + Fiting Bh 48,262.50
57 Lampu SL Philips 14 watt + Fiting Bh 37,125.00
58 Kabel Listrik NYM 2 x 2,5 mm M¹ 14,107.50
59 Stop Kontak Bh 25,987.50
60 Saklar Tunggal Bh 22,275.00
61 Saklar Double Bh 25,987.50
62 Limit Bh 22,275.00
63 Donw Ligt Bh 66,825.00
64 Pipa Kabel PVC Btg 7,425.00
NO NAMA BAHAN SATUAN HARGA BAHAN
(Rp.)
1 2 3 4
65 Fiting Lampu Bh 14,850.00
66 T. Dos Bh 11,137.50
67 Klosed Duduk KIA Standar / Sejenis Bh 1,856,250.00
68 Kran Air Bh 25,987.50
69 Floor Drain Stainlees Bh 50,490.00
70 Shell Tape Bh 7,425.00
71 Plastik M2 18,562.50

NO NAMA BAHAN SATUAN HARGA BAHAN


(Rp.)
1 2 3 4
II. DAFTAR HARGA UPAH KERJA
1 Pekerja OH 115,000.00
2 Tukang OH 145,000.00
3 Kepala Tukang OH 160,000.00
4 Mandor OH 170,000.00
time schedule

PEKERJAAN : PEMBANGUNAN GEDUNG RUANG KULIAH PRODI MERAUKE Chart Title


LOKASI : KABUPATEN MERAUKE
TAHUN ANGGARAN: 2018

NO URAIAN PEKERJAAN JUMLAH HARGA BOBOT BULAN 1 BULAN 2 BULAN 3 BULAN 4


(Rp.) (%) 1 2 3 4 1 2 3 4 1 2 3 4 1 2

I PEKERJAAN PENDAHULUAN 22,805,480.90 1.14% 0.57% 0.57%

II PEKERJAAN TANAH 133,374,782.20 6.66% 2.22% 2.22% 2.22%

III PEKERJAAN PONDASI DAN BETON 553,588,117.17 27.64% 6.91% 6.91% 6.91% 6.91%

IV PEKERJAAN LANTAI KERAMIK 219,638,595.26 10.96% 5.48% 5.48%

V PEKERJAAN PASANGAN DAN PLESTERAN 356,605,070.26 17.80% 4.45% 4.45% 4.45% 4.45%

VI PEKERJAAN ATAP DAN KUDA-KUDA 181,590,356.95 9.07% 3.02% 3.02% 3.02%

VII PEKERJAAN KUSEN, PINTU DAN JENDELA 133,055,373.51 6.64% 3.32% 3.32%

VIII PEKERJAAN PLAFOND 188,242,259.15 9.40% 4.70% 4.70%

IX PEKERJAAN INSTALASI LISTRIK 55,458,603.00 2.77% 2.77%

X PEKERJAAN PENGUNCI DAN PENGGANTUNG 15,152,890.50 0.76% 0.76%

XII PEKERJAAN PLUMBING 18,922,418.66 0.94% 0.94%

XIII PEKERJAAN SALURAN 66,748,919.23 3.33% 3.33%

XIV PEKERJAAN PENGECATAN 56,002,006.14 2.80% 1.40% 1.40%

XV PEKERJAAN LAIN-LAIN 2,000,000.00 0.10% 0.10%

BOBOT RENCANA 0.57% 0.57% 2.22% 2.22% 2.22% 6.91% 6.91% 6.91% 11.36% 7.47% 7.47% 21.73% 21.95% 1.50%
KUMULATIF BOBOT RENCANA 0.57% 1.14% 3.36% 5.58% 7.80% 14.71% 21.61% 28.52% 39.88% 47.35% 54.83% 76.56% 98.50% 100.00%

Jayapura, Agustus 2018


Penawar
PT.INDAMI STAR

DEMMY S.KAWER
Direktur Utama