PROYEK DERMAGA Persiapan Pengadaan SPP Pengadaan Concrete Spun Pile (CSP) Ø600mm t=100mm L=32m

Start: Thu 3/2/23 ID: 1 Start: Thu 3/2/23 ID: 2 Start: Thu 3/2/23 ID: 3 Start: 3/2/23 ID: 4
Finish: Sat 4/1/23 Dur: 31 days Finish: Fri 3/31/23 Dur: 30 days Finish: Fri 3/31/23 Dur: 30 days Finish: 3/31/23 Dur: 30 days
Comp: 2% Comp: 15% Comp: 15% Res: Pengadaan Concrete Spun Pile (CSP) Ø600mm t=100mm L=3

TRESTLE
Start: Mon 3/6/23 ID: 6
Finish: Sat 4/1/23 Dur: 27 days
Comp: 0%

Page 1
Pengadaan Concrete Spun Pile (CSP) Ø600mm t=100mm L=31m berikut Transport ke Lokasi & Positioning
Start: 3/14/23 ID: 5
Finish: 3/31/23 Dur: 18 days
Res: Pengadaan Concrete Spun Pile (CSP) Ø600mm t=100mm L=31m berikut Transport ke Lokasi & Positioning T[1,488 m1]

Pemancangan Segment 7 Grid 3 Grid 2


Start: Mon 3/6/23 ID: 7 Start: Mon 3/6/23 ID: 8 Start: Mon 3/6/23 ID: 17 Start: Tue 3/7/23 ID: 13
Finish: Sat 4/1/23 Dur: 27 days Finish: Mon 3/13/23
Dur: 8 days Finish: Tue 3/7/23 Dur: 2 days Finish: Thu 3/9/23 Dur: 3 days
Comp: 0% Comp: 0% Comp: 0% Comp: 0%

Segment 6 Segment 5
Start: Sun 3/12/23ID: 41 Start: Wed 3/15/23ID: 62
Finish: Thu 3/16/23Dur: 5 days Finish: Sun 3/19/23Dur: 5 days
Comp: 0% Comp: 0%

PDA Test Trestle


Start: 3/6/23 ID: 163
Finish: 3/31/23 Dur: 26 days
Res: PDA Test T[5 nos]

Pekerjaan Preboring Support Crane Ø600mm Trestle


Start: 3/6/23 ID: 164
Finish: 3/31/23 Dur: 26 days
Res: Pekerjaan Preboring Support Crane Ø600mm T[294 titik]

Pilecap Segmen 7 Segmen 6


Start: Fri 3/10/23 ID: 173 Start: Fri 3/10/23 ID: 174 Start: Tue 3/14/23ID: 231
Finish: Fri 3/31/23 Dur: 22 days Finish: Wed 3/22/23
Dur: 13 days Finish: Tue 3/28/23Dur: 15 days
Comp: 0% Comp: 0% Comp: 0%

Page 2
Grid 1 Grid 4 Grid 5 Grid 6
Start: Wed 3/8/23 ID: 9 Start: Thu 3/9/23 ID: 21 Start: Thu 3/9/23 ID: 25 Start: Fri 3/10/23 ID: 29
Finish: Thu 3/9/23 Dur: 2 days Finish: Fri 3/10/23 Dur: 2 days Finish: Sat 3/11/23Dur: 3 days Finish: Sat 3/11/23Dur: 2 days
Comp: 0% Comp: 0% Comp: 0% Comp: 0%

Segment 4 Segment 3 Segment 2 Segment 1


Start: Sun 3/19/23ID: 83 Start: Tue 3/21/23ID: 100 Start: Sat 3/25/23 ID: 121 Start: Tue 3/28/23ID: 142
Finish: Wed 3/22/23
Dur: 4 days Finish: Sat 3/25/23Dur: 5 days Finish: Wed 3/29/23
Dur: 5 days Finish: Sat 4/1/23 Dur: 5 days
Comp: 0% Comp: 0% Comp: 0% Comp: 0%

Segmen 5
Start: Mon 3/20/23ID: 272
Finish: Fri 3/31/23 Dur: 12 days
Comp: 0%

Abutmen Platfrom Pembesian


Start: Fri 3/10/23 ID: 165 Start: 3/10/23 ID: 166 Start: 3/12/23 ID: 168
Finish: Sun 3/19/23Dur: 10 days Finish: 3/11/23 Dur: 2 days Finish: 3/12/23 Dur: 1 day
Comp: 0% Res: Res:

Page 3
Grid 7 Grid 8
Start: Sat 3/11/23 ID: 33 Start: Sat 3/11/23 ID: 37
Finish: Sun 3/12/23Dur: 2 days Finish: Mon 3/13/23
Dur: 3 days
Comp: 0% Comp: 0%

Mall Pengecoran Mall Pembesian


Start: 3/13/23 ID: 167 Start: 3/14/23 ID: 169 Start: 3/17/23 ID: 170 Start: 3/18/23 ID: 171
Finish: 3/13/23 Dur: 1 day Finish: 3/14/23 Dur: 1 day Finish: 3/17/23 Dur: 1 day Finish: 3/18/23 Dur: 1 day
Res: Res: Res: Res:

Page 4
Pengecoran
Start: 3/19/23 ID: 172
Finish: 3/19/23 Dur: 1 day
Res: Abutment T[17.45 m3]

Page 5
Critical Milestone Critical Inserted Marked Project Summary

Project: Project Dermaga


Noncritical Critical Summary Inserted Critical External Highlighted Critical
Date: Tue 3/7/23
Critical Milestone Summary Critical Marked External Highlighted Noncritical

Page 6