PROJECT TITLE : Construction of G+3+2R Comm & Residential Bldg.

Company Name : Al Aflaj Building Contracting LLC


Wed, 15/02/2023
Remaining Work Start Date
1

13 Feb 2023 20 Feb 2023 27 Feb 2023 6 Mar 2023 13 Mar 2023 20 Mar 2023 27 Mar 2023 3 Apr 2023 10 Apr 2023 17 Apr 2023 24 Apr 2023 1 May 2023 8 May 2023 15 May 2023 22 May 2023 29 May 2023
TASK PROGRESS START END DAYS 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S

Internal Plastering

Ground Floor 0% 5/3/23 17/3/23 12

Lower Roof 15% 15/2/23 27/2/23 12

External Plastering

Elevation Right 10% 15/2/23 27/2/23 12

Elevation Left 0% 27/2/23 11/3/23 12

Internal Painting

Ground Floor 0% 22/3/23 6/4/23 15

Typical Floor 20% 15/2/23 1/4/23 45

Lower Roof and Machine Room 0% 9/3/23 31/3/23 22

Internal Finishes

Ground Floor 0% 22/3/23 6/4/23 15

Typical Floor 20% 15/2/23 6/4/23 50

Lower Roof and Machine Room 0% 27/3/23 11/4/23 15

External Finishes 50% 5/2/23 11/3/23 34

External Painting

Elevation Right & Rear 0% 23/3/23 12/4/23 20

Elevation Left & Front 0% 3/3/23 23/3/23 20

Combo Roof Water Proofing

Third Floor Slab 0% 28/3/23 9/4/23 12

Lower Roof Slab and Stair Tower 0% 11/4/23 23/4/23 12

Wet Area WaterProofing

Ground Floor 0% 12/3/23 18/3/23 6

Typical Floor 0% 2/3/23 20/3/23 18

Lower Roof 0% 17/3/23 23/3/23 6

Aluminium Works 0% 25/3/23 24/4/23 30

Stair and Blacony Railing 0% 23/3/23 17/4/23 25

Wooden Works 0% 23/3/23 22/4/23 30

Kitchen Cabinet and Wardrobes 0% 20/3/23 14/4/23 25

Electrical Works 25% 23/1/23 23/4/23 90

Telephone Works 10% 24/2/23 25/4/23 60

Video, TV and CCTV works 10% 20/2/23 21/4/23 60

Drainage Work 50% 20/2/23 6/5/23 75

Plumbing Work 50% 10/2/23 26/4/23 75

AC & Mechanical Ventilation Work 10% 20/2/23 21/4/23 60

Fire alarm & Fire Fighting Works 25% 5/2/23 6/4/23 60

Lift works 10% 15/2/23 7/3/23 20

Window Cleaning System 0% 27/3/23 11/4/23 15

Central LPG Works 10% 7/3/23 21/4/23 45

False Ceiling Work 0% 7/3/23 6/4/23 30

External Works 0% 25/4/23 25/5/23 30

Site Cleaning , Testing and Final


0% 10/5/23 30/5/23 20
Inspection