CHECKLIST FOR VDF FLOORING

Site CONSTRUCTION OF GENERAL CIVIL WORKS AT 4GW MANUFACTURING PLANT,GANGAIKONDAN

Client M/s TP SOLAR COMPANY LIMITED

PMC M/s TATA CONSULTING ENGINEERING LIMITED

Contractor M/s TATA PROJECTS LIMITED

Block/Element

Location/Grid

Date

Refer to the approved work method statement and relevant drawings

S.No. Description YES NO NA Date TPL TPS/TCE REMARKS

A Prior to the Vacuum Dewatered Flooring

1 Check for location of construction and Panel Sizes as per approved Pour plan

2 Check for cleanliness of area to be concreted.

3 Check for the stability and rigidity of Formwork and Supports?

4 Check for rigidity, alignment,level,sealing of formwork joints

5 Check for reinforcement if any

6 Check for MEP clearance

7 Check for provision of Slope for Drain

8 Mode of concrete proposed

9 Quantity of concrete poured

10 Starting time of concreting

11 Grade of Concrete

B During Vacuum Dewatered Flooring

1 Whether concreting is being done at alternate bays

2 Check for slump of the concrete being poured. Is it as specified? (write in mm)

3 Ensure proper vibration & compaction of concrete by using Surface Vibrator?

4 Ensure top level of concrete surface ? (write TOC)

5 Check for placing & spreading of filter layer. Is it OK ?

6 Check for vacuum dewatering.

7 Check for application of Surface Hardner as per approved make.

8 Check for Power float finish.

C After Vacuum Dewatered Flooring

1 Check for curing arrangements (7 days)

2 Check for groove cutting

3 Check for surface finish

4 Check for finished level of concrete

5 Check for sealing of joints with approved Sealant

Name& Sign: TPL EXECUTION ENGINEER SIGNATURE OF FQE TPS/TCE


Format No.08.03.05-FMT-C-SCW-CL-001-R00