Project Name: WATERFRONT PROJECT - ABU DHABI, UAE Project No.: P0389 Till the Month of : 2/28/20223
SUPPLY & INSTALLATION OF ALUMINIUM DOORS AND WINDOWS, CURTAIN WALLS, ALUMINIUM CLADDING
Package : Applied Date : 28-Feb-23
PANELS, SPIDER SYSTEM AND LOUVERS
Client LINK INVESTMENTS AND LINK INTERNATIONAL PROPERTIES Cert Due Date: 30-Mar-23
SUMMARY
VALUE OF WORKS DONE
Previous Cummulative Certified-PC NO.
Cumulative Claim This Period Claim
Item Description 26
% Value % Value % Value
WORK DONE ON THE BASIS OF ORIGINAL SCOPE
1 Value of Work Done ( 100 % ) 100.00% 70,826,308.04 95.65% 67,742,698.38 4.35% 3,083,609.66
2 Material On Site ( 70 % ) - -
3 TOTAL VALUE OF WORK DONE AED 70,826,308.04 AED 67,742,698.38 AED 3,083,609.66
ADDITIONAL VARIATIONS
Net Amount
12 NET Amount Due This Application AED 62,074,300.15 AED 54,194,158.70 AED 7,880,141.44
Net Amount for the application - AED: Seven Million, Eight Hundred Eighty Thousand,One Hundred Forty One and 44/100 Only
SUPPLY & INSTALLATION OF ALUMINIUM DOORS AND WINDOWS, CURTAIN WALLS, ALUMINIUM CLADDING PANELS, SPIDER SYSTEM AND LOUVERS
Installation Progress
Remarks
Rate Total
S/N Description of Item Unit Quantity % Factor (AED) (AED)
Previous Cummulative Certified Current Cummulative
HANDRAILS
Brackets / Channel m 6,575.00 35.00% 316.40 2,080,330.00 100% 6,575.00 2,080,330.00 0% - - 100% 6,575.00 2,080,330.00
Glass m 6,575.00 50.00% 452.00 2,971,900.00 100% 6,575.00 2,971,900.00 0% - - 100% 6,575.00 2,971,900.00
Cover cap m 6,575.00 10.00% 90.40 594,380.00 100% 6,575.00 594,380.00 0% - - 100% 6,575.00 594,380.00
Handing over m 6,575.00 5.00% 45.20 297,190.00 40% 2,630.00 118,876.00 60% 3,945.00 178,314.00 100.00% 6,575.00 297,190.00
Brackets / Channel m 440.00 35.00% 315.70 138,908.00 100% 440.00 138,908.00 0% - - 100% 440.00 138,908.00
Glass m 440.00 50.00% 451.00 198,440.00 100% 440.00 198,440.00 0% - - 100% 440.00 198,440.00
Cover cap m 440.00 10.00% 90.20 39,688.00 100% 440.00 39,688.00 0% - - 100% 440.00 39,688.00
Handing over m 440.00 5.00% 45.10 19,844.00 40% 176.00 7,937.60 60% 264.00 11,906.40 100% 440.00 19,844.00
-
ALUMINIUM LOUVER AT PODIUM CAR PARKING -
Brackets No 2.00 20.00% 1,346.40 2,692.80 100% 2.00 2,692.80 0% - - 100% 2.00 2,692.80
Louver Frame No 2.00 30.00% 2,019.60 4,039.20 100% 2.00 4,039.20 0% - - 100% 2.00 4,039.20
Louver Assembly No 2.00 35.00% 2,356.20 4,712.40 100% 2.00 4,712.40 0% - - 100% 2.00 4,712.40
Accessories No 2.00 10.00% 673.20 1,346.40 100% 2.00 1,346.40 0% - - 100% 2.00 1,346.40
Handing over No 2.00 5.00% 336.60 673.20 40% 0.80 269.28 60% 1.20 403.92 100% 2.00 673.20
Brackets No 1.00 20.00% 4,660.80 4,660.80 100% 1.00 4,660.80 0% - - 100% 1.00 4,660.80
Louver Frame No 1.00 30.00% 6,991.20 6,991.20 100% 1.00 6,991.20 0% - - 100% 1.00 6,991.20
Louver Assembly No 1.00 35.00% 8,156.40 8,156.40 100% 1.00 8,156.40 0% - - 100% 1.00 8,156.40
Accessories No 1.00 10.00% 2,330.40 2,330.40 100% 1.00 2,330.40 0% - - 100% 1.00 2,330.40
Handing over No 1.00 5.00% 1,165.20 1,165.20 40% 0.40 466.08 60% 0.60 699.12 100% 1.00 1,165.20
LV-03, 6000mm (W) x 1300mm (H) powder coated fixed aluminum
5 No 4.00 9,394.00 37,576.00 - -
louvers.
Brackets No 4.00 20.00% 1,878.80 7,515.20 100% 4.00 7,515.20 0% - - 100% 4.00 7,515.20
Louver Frame No 4.00 30.00% 2,818.20 11,272.80 100% 4.00 11,272.80 0% - - 100% 4.00 11,272.80
Louver Assembly No 4.00 35.00% 3,287.90 13,151.60 100% 4.00 13,151.60 0% - - 100% 4.00 13,151.60
Accessories No 4.00 10.00% 939.40 3,757.60 100% 4.00 3,757.60 0% - - 100% 4.00 3,757.60
Handing over No 4.00 5.00% 469.70 1,878.80 40% 1.60 751.52 60% 2.40 1,127.28 100% 4.00 1,878.80
LV-04, 6000mm (W) x 1300mm (H) powder coated fixed aluminum
6 No 2.00 9,394.00 18,788.00 - -
louvers.
Brackets No 2.00 20.00% 1,878.80 3,757.60 100% 2.00 3,757.60 0% - - 100% 2.00 3,757.60
Louver Frame No 2.00 30.00% 2,818.20 5,636.40 100% 2.00 5,636.40 0% - - 100% 2.00 5,636.40
Louver Assembly No 2.00 35.00% 3,287.90 6,575.80 100% 2.00 6,575.80 0% - - 100% 2.00 6,575.80
Accessories No 2.00 10.00% 939.40 1,878.80 100% 2.00 1,878.80 0% - - 100% 2.00 1,878.80
Handing over No 2.00 5.00% 469.70 939.40 40% 0.80 375.76 60% 1.20 563.64 100% 2.00 939.40
Brackets No 2.00 20.00% 2,029.00 4,058.00 50% 1.00 2,029.00 50% 1.00 2,029.00 100% 2.00 4,058.00
Louver Frame No 2.00 30.00% 3,043.50 6,087.00 50% 1.00 3,043.50 50% 1.00 3,043.50 100% 2.00 6,087.00
Louver Assembly No 2.00 35.00% 3,550.75 7,101.50 50% 1.00 3,550.75 50% 1.00 3,550.75 100% 2.00 7,101.50
Accessories No 2.00 10.00% 1,014.50 2,029.00 50% 1.00 1,014.50 50% 1.00 1,014.50 100% 2.00 2,029.00
Handing over No 2.00 5.00% 507.25 1,014.50 20% 0.40 202.90 80% 1.60 811.60 100% 2.00 1,014.50
RFQ- Value of Work Done Page 1 of 8
Installation
WATERFRONT PROJECT - ABU DHABI, UNITED ARAB EMIRATES
progress updated
in this column
SUPPLY & INSTALLATION OF ALUMINIUM DOORS AND WINDOWS, CURTAIN WALLS, ALUMINIUM CLADDING PANELS, SPIDER SYSTEM AND LOUVERS
Installation Progress
Remarks
Rate Total
S/N Description of Item Unit Quantity % Factor (AED) (AED)
Previous Cummulative Certified Current Cummulative
Brackets No 2.00 20.00% 1,659.60 3,319.20 50% 1.00 1,659.60 50% 1.00 1,659.60 100% 2.00 3,319.20
Louver Frame No 2.00 30.00% 2,489.40 4,978.80 50% 1.00 2,489.40 50% 1.00 2,489.40 100% 2.00 4,978.80
Louver Assembly No 2.00 35.00% 2,904.30 5,808.60 50% 1.00 2,904.30 50% 1.00 2,904.30 100% 2.00 5,808.60
Accessories No 2.00 10.00% 829.80 1,659.60 50% 1.00 829.80 50% 1.00 829.80 100% 2.00 1,659.60
Handing over No 2.00 5.00% 414.90 829.80 20% 0.40 165.96 80% 1.60 663.84 100% 2.00 829.80
LV-07, 3000mm (W) x 4500mm (H) powder coated fixed aluminum
9 No 2.00 16,258.00 32,516.00 - -
louvers.
Brackets No 2.00 20.00% 3,251.60 6,503.20 50% 1.00 3,251.60 50% 1.00 3,251.60 100% 2.00 6,503.20
Louver Frame No 2.00 30.00% 4,877.40 9,754.80 50% 1.00 4,877.40 50% 1.00 4,877.40 100% 2.00 9,754.80
Louver Assembly No 2.00 35.00% 5,690.30 11,380.60 50% 1.00 5,690.30 50% 1.00 5,690.30 100% 2.00 11,380.60
Accessories No 2.00 10.00% 1,625.80 3,251.60 50% 1.00 1,625.80 50% 1.00 1,625.80 100% 2.00 3,251.60
Handing over No 2.00 5.00% 812.90 1,625.80 20% 0.40 325.16 80% 1.60 1,300.64 100% 2.00 1,625.80
Aluminium louvers (not included in the louver schedule) to
Architects approval, including all necessary fixings,accessories etc., - -
as specified in drawings and specifications
Brackets Ls 1.00 20.00% 432,356.00 432,356.00 100% 1.00 432,356.00 0% - - 100% 1.00 432,356.00
Louver Frame Ls 1.00 30.00% 648,534.00 648,534.00 100% 1.00 648,534.00 0% - - 100% 1.00 648,534.00
Louver Assembly Ls 1.00 35.00% 756,623.00 756,623.00 100% 1.00 756,623.00 0% - - 100% 1.00 756,623.00
Accessories Ls 1.00 10.00% 216,178.00 216,178.00 100% 1.00 216,178.00 0% - - 100% 1.00 216,178.00
Handing over Ls 1.00 5.00% 108,089.00 108,089.00 40% 0.40 43,235.60 60% 0.60 64,853.40 100% 1.00 108,089.00
Brackets and Framing m2 118.00 30.00% 300.00 35,400.00 75% 88.50 26,550.00 25% 29.50 8,850.00 100% 118.00 35,400.00
Damp proof and insulation m2 118.00 10.00% 100.00 11,800.00 75% 88.50 8,850.00 25% 29.50 2,950.00 100% 118.00 11,800.00
Cladding panels m2 118.00 45.00% 450.00 53,100.00 75% 88.50 39,825.00 25% 29.50 13,275.00 100% 118.00 53,100.00
Accessories m2 118.00 10.00% 100.00 11,800.00 75% 88.50 8,850.00 25% 29.50 2,950.00 100% 118.00 11,800.00
Handing over m2 118.00 5.00% 50.00 5,900.00 15% 17.70 885.00 85% 100.30 5,015.00 100% 118.00 5,900.00
Metal shade with aluminium cladding finish as per drawings AR
- -
835 and as specified
Brackets Nos 4.00 20.00% 809.00 3,236.00 100% 4.00 3,236.00 0% - - 100% 4.00 3,236.00
Frame Nos 4.00 30.00% 1,213.50 4,854.00 100% 4.00 4,854.00 0% - - 100% 4.00 4,854.00
Door Nos 4.00 35.00% 1,415.75 5,663.00 100% 4.00 5,663.00 0% - - 100% 4.00 5,663.00
Accessories Nos 4.00 10.00% 404.50 1,618.00 100% 4.00 1,618.00 0% - - 100% 4.00 1,618.00
Handing over Nos 4.00 5.00% 202.25 809.00 40% 1.60 323.60 60% 2.40 485.40 100% 4.00 809.00
SUPPLY & INSTALLATION OF ALUMINIUM DOORS AND WINDOWS, CURTAIN WALLS, ALUMINIUM CLADDING PANELS, SPIDER SYSTEM AND LOUVERS
Installation Progress
Remarks
Rate Total
S/N Description of Item Unit Quantity % Factor (AED) (AED)
Previous Cummulative Certified Current Cummulative
Brackets Nos 3.00 20.00% 2,665.00 7,995.00 100% 3.00 7,995.00 0% - - 100% 3.00 7,995.00
Frame Nos 3.00 30.00% 3,997.50 11,992.50 100% 3.00 11,992.50 0% - - 100% 3.00 11,992.50
Door Nos 3.00 35.00% 4,663.75 13,991.25 100% 3.00 13,991.25 0% - - 100% 3.00 13,991.25
Accessories Nos 3.00 10.00% 1,332.50 3,997.50 100% 3.00 3,997.50 0% - - 100% 3.00 3,997.50
Handing over Nos 3.00 5.00% 666.25 1,998.75 40% 1.20 799.50 60% 1.80 1,199.25 100% 3.00 1,998.75
Brackets Nos 4.00 20.00% 1,217.00 4,868.00 100% 4.00 4,868.00 0% - - 100% 4.00 4,868.00
Frame Nos 4.00 30.00% 1,825.50 7,302.00 100% 4.00 7,302.00 0% - - 100% 4.00 7,302.00
Door Nos 4.00 35.00% 2,129.75 8,519.00 100% 4.00 8,519.00 0% - - 100% 4.00 8,519.00
Accessories Nos 4.00 10.00% 608.50 2,434.00 100% 4.00 2,434.00 0% - - 100% 4.00 2,434.00
Handing over Nos 4.00 5.00% 304.25 1,217.00 40% 1.60 486.80 60% 2.40 730.20 100% 4.00 1,217.00
AD-07, 1800mm (W) x 2200mm (H) 1 hr fire rated powder coated
16 Nos 8.00 26,650.00 213,200.00 - -
aluminum framed double shutter frosted glass door.
Brackets Nos 8.00 20.00% 5,330.00 42,640.00 100% 8.00 42,640.00 0% - - 100% 8.00 42,640.00
Frame Nos 8.00 30.00% 7,995.00 63,960.00 100% 8.00 63,960.00 0% - - 100% 8.00 63,960.00
Door Nos 8.00 35.00% 9,327.50 74,620.00 100% 8.00 74,620.00 0% - - 100% 8.00 74,620.00
Accessories Nos 8.00 10.00% 2,665.00 21,320.00 100% 8.00 21,320.00 0% - - 100% 8.00 21,320.00
Handing over Nos 8.00 5.00% 1,332.50 10,660.00 40% 3.20 4,264.00 60% 4.80 6,396.00 100% 8.00 10,660.00
Brackets Nos 150.00 20.00% 1,797.00 269,550.00 100% 150.00 269,550.00 0% - - 100% 150.00 269,550.00
Frame Nos 150.00 30.00% 2,695.50 404,325.00 100% 150.00 404,325.00 0% - - 100% 150.00 404,325.00
Door Nos 150.00 35.00% 3,144.75 471,712.50 100% 150.00 471,712.50 0% - - 100% 150.00 471,712.50
Accessories Nos 150.00 10.00% 898.50 134,775.00 100% 150.00 134,775.00 0% - - 100% 150.00 134,775.00
Handing over Nos 150.00 5.00% 449.25 67,387.50 40% 60.00 26,955.00 60% 90.00 40,432.50 100% 150.00 67,387.50
ALUMINIUM FRAMED STRUCTURAL GLAZING SYSTEM WITH
- -
DOOR
Brackets Nos 1.00 20.00% 26,021.80 26,021.80 100% 1.00 26,021.80 0% - - 100% 1.00 26,021.80
Framing Nos 1.00 30.00% 39,032.70 39,032.70 100% 1.00 39,032.70 0% - - 100% 1.00 39,032.70
Glazing Nos 1.00 35.00% 45,538.15 45,538.15 100% 1.00 45,538.15 0% - - 100% 1.00 45,538.15
Accessories Nos 1.00 10.00% 13,010.90 13,010.90 100% 1.00 13,010.90 0% - - 100% 1.00 13,010.90
Handing over Nos 1.00 5.00% 6,505.45 6,505.45 40% 0.40 2,602.18 60% 0.60 3,903.27 100% 1.00 6,505.45
Brackets Nos 1.00 20.00% 19,516.40 19,516.40 100% 1.00 19,516.40 0% - - 100% 1.00 19,516.40
Framing Nos 1.00 30.00% 29,274.60 29,274.60 100% 1.00 29,274.60 0% - - 100% 1.00 29,274.60
Glazing Nos 1.00 35.00% 34,153.70 34,153.70 100% 1.00 34,153.70 0% - - 100% 1.00 34,153.70
Accessories Nos 1.00 10.00% 9,758.20 9,758.20 100% 1.00 9,758.20 0% - - 100% 1.00 9,758.20
Handing over Nos 1.00 5.00% 4,879.10 4,879.10 40% 0.40 1,951.64 60% 0.60 2,927.46 100% 1.00 4,879.10
AD-12, 6720mm (W) x 4500mm (H) powder coated aluminum
20 Nos 1.00 99,356.00 99,356.00 - -
framed structural glazing system enclose casement door.
Brackets Nos 1.00 20.00% 19,871.20 19,871.20 100% 1.00 19,871.20 0% - - 100% 1.00 19,871.20
Framing Nos 1.00 30.00% 29,806.80 29,806.80 100% 1.00 29,806.80 0% - - 100% 1.00 29,806.80
Glazing Nos 1.00 35.00% 34,774.60 34,774.60 100% 1.00 34,774.60 0% - - 100% 1.00 34,774.60
Accessories Nos 1.00 10.00% 9,935.60 9,935.60 100% 1.00 9,935.60 0% - - 100% 1.00 9,935.60
Handing over Nos 1.00 5.00% 4,967.80 4,967.80 40% 0.40 1,987.12 60% 0.60 2,980.68 100% 1.00 4,967.80
Brackets Nos 1.00 20.00% 25,976.60 25,976.60 100% 1.00 25,976.60 0% - - 100% 1.00 25,976.60
Framing Nos 1.00 30.00% 38,964.90 38,964.90 100% 1.00 38,964.90 0% - - 100% 1.00 38,964.90
Glazing Nos 1.00 35.00% 45,459.05 45,459.05 100% 1.00 45,459.05 0% - - 100% 1.00 45,459.05
Accessories Nos 1.00 10.00% 12,988.30 12,988.30 100% 1.00 12,988.30 0% - - 100% 1.00 12,988.30
Handing over Nos 1.00 5.00% 6,494.15 6,494.15 40% 0.40 2,597.66 60% 0.60 3,896.49 100% 1.00 6,494.15
SUPPLY & INSTALLATION OF ALUMINIUM DOORS AND WINDOWS, CURTAIN WALLS, ALUMINIUM CLADDING PANELS, SPIDER SYSTEM AND LOUVERS
Installation Progress
Remarks
Rate Total
S/N Description of Item Unit Quantity % Factor (AED) (AED)
Previous Cummulative Certified Current Cummulative
Brackets Nos 1.00 20.00% 27,988.00 27,988.00 100% 1.00 27,988.00 0% - - 100% 1.00 27,988.00
Framing Nos 1.00 30.00% 41,982.00 41,982.00 100% 1.00 41,982.00 0% - - 100% 1.00 41,982.00
Glazing Nos 1.00 35.00% 48,979.00 48,979.00 100% 1.00 48,979.00 0% - - 100% 1.00 48,979.00
Accessories Nos 1.00 10.00% 13,994.00 13,994.00 100% 1.00 13,994.00 0% - - 100% 1.00 13,994.00
Handing over Nos 1.00 5.00% 6,997.00 6,997.00 40% 0.40 2,798.80 60% 0.60 4,198.20 100% 1.00 6,997.00
Brackets Nos 1.00 20.00% 25,976.60 25,976.60 100% 1.00 25,976.60 0% - - 100% 1.00 25,976.60
Framing Nos 1.00 30.00% 38,964.90 38,964.90 100% 1.00 38,964.90 0% - - 100% 1.00 38,964.90
Glazing Nos 1.00 35.00% 45,459.05 45,459.05 100% 1.00 45,459.05 0% - - 100% 1.00 45,459.05
Accessories Nos 1.00 10.00% 12,988.30 12,988.30 100% 1.00 12,988.30 0% - - 100% 1.00 12,988.30
Handing over Nos 1.00 5.00% 6,494.15 6,494.15 40% 0.40 2,597.66 60% 0.60 3,896.49 100% 1.00 6,494.15
Brackets Nos 1.00 20.00% 26,233.20 26,233.20 100% 1.00 26,233.20 0% - - 100% 1.00 26,233.20
Framing Nos 1.00 30.00% 39,349.80 39,349.80 100% 1.00 39,349.80 0% - - 100% 1.00 39,349.80
Glazing Nos 1.00 35.00% 45,908.10 45,908.10 100% 1.00 45,908.10 0% - - 100% 1.00 45,908.10
Accessories Nos 1.00 10.00% 13,116.60 13,116.60 100% 1.00 13,116.60 0% - - 100% 1.00 13,116.60
Handing over Nos 1.00 5.00% 6,558.30 6,558.30 40% 0.40 2,623.32 60% 0.60 3,934.98 100% 1.00 6,558.30
Brackets Nos 1.00 20.00% 28,620.20 28,620.20 100% 1.00 28,620.20 0% - - 100% 1.00 28,620.20
Framing Nos 1.00 30.00% 42,930.30 42,930.30 100% 1.00 42,930.30 0% - - 100% 1.00 42,930.30
Glazing Nos 1.00 35.00% 50,085.35 50,085.35 100% 1.00 50,085.35 0% - - 100% 1.00 50,085.35
Accessories Nos 1.00 10.00% 14,310.10 14,310.10 100% 1.00 14,310.10 0% - - 100% 1.00 14,310.10
Handing over Nos 1.00 5.00% 7,155.05 7,155.05 40% 0.40 2,862.02 60% 0.60 4,293.03 100% 1.00 7,155.05
Brackets Nos 1.00 20.00% 33,957.20 33,957.20 100% 1.00 33,957.20 0% - - 100% 1.00 33,957.20
Framing Nos 1.00 30.00% 50,935.80 50,935.80 100% 1.00 50,935.80 0% - - 100% 1.00 50,935.80
Glazing Nos 1.00 35.00% 59,425.10 59,425.10 100% 1.00 59,425.10 0% - - 100% 1.00 59,425.10
Accessories Nos 1.00 10.00% 16,978.60 16,978.60 100% 1.00 16,978.60 0% - - 100% 1.00 16,978.60
Handing over Nos 1.00 5.00% 8,489.30 8,489.30 40% 0.40 3,395.72 60% 0.60 5,093.58 100% 1.00 8,489.30
Brackets Nos 1.00 20.00% 35,765.60 35,765.60 100% 1.00 35,765.60 0% - - 100% 1.00 35,765.60
Framing Nos 1.00 30.00% 53,648.40 53,648.40 100% 1.00 53,648.40 0% - - 100% 1.00 53,648.40
Glazing Nos 1.00 35.00% 62,589.80 62,589.80 100% 1.00 62,589.80 0% - - 100% 1.00 62,589.80
Accessories Nos 1.00 10.00% 17,882.80 17,882.80 100% 1.00 17,882.80 0% - - 100% 1.00 17,882.80
Handing over Nos 1.00 5.00% 8,941.40 8,941.40 40% 0.40 3,576.56 60% 0.60 5,364.84 100% 1.00 8,941.40
AD-20, 7326mm (W) x 4500mm (H) powder coated aluminum
28 Nos 1.00 140,342.00 140,342.00 - -
framed structural glazing system enclose casement door.
Brackets Nos 1.00 20.00% 28,068.40 28,068.40 100% 1.00 28,068.40 0% - - 100% 1.00 28,068.40
Framing Nos 1.00 30.00% 42,102.60 42,102.60 100% 1.00 42,102.60 0% - - 100% 1.00 42,102.60
Glazing Nos 1.00 35.00% 49,119.70 49,119.70 100% 1.00 49,119.70 0% - - 100% 1.00 49,119.70
Accessories Nos 1.00 10.00% 14,034.20 14,034.20 100% 1.00 14,034.20 0% - - 100% 1.00 14,034.20
Handing over Nos 1.00 5.00% 7,017.10 7,017.10 40% 0.40 2,806.84 60% 0.60 4,210.26 100% 1.00 7,017.10
Brackets Nos 1.00 20.00% 25,137.40 25,137.40 100% 1.00 25,137.40 0% - - 100% 1.00 25,137.40
Framing Nos 1.00 30.00% 37,706.10 37,706.10 100% 1.00 37,706.10 0% - - 100% 1.00 37,706.10
Glazing Nos 1.00 35.00% 43,990.45 43,990.45 100% 1.00 43,990.45 0% - - 100% 1.00 43,990.45
Accessories Nos 1.00 10.00% 12,568.70 12,568.70 100% 1.00 12,568.70 0% - - 100% 1.00 12,568.70
Handing over Nos 1.00 5.00% 6,284.35 6,284.35 40% 0.40 2,513.74 60% 0.60 3,770.61 100% 1.00 6,284.35
Brackets Nos 1.00 20.00% 60,102.20 60,102.20 100% 1.00 60,102.20 0% - - 100% 1.00 60,102.20
Framing Nos 1.00 30.00% 90,153.30 90,153.30 100% 1.00 90,153.30 0% - - 100% 1.00 90,153.30
Glazing Nos 1.00 35.00% 105,178.85 105,178.85 100% 1.00 105,178.85 0% - - 100% 1.00 105,178.85
Accessories Nos 1.00 10.00% 30,051.10 30,051.10 100% 1.00 30,051.10 0% - - 100% 1.00 30,051.10
RFQ- Value of Work Done Page 4 of 8
Installation
WATERFRONT PROJECT - ABU DHABI, UNITED ARAB EMIRATES
progress updated
in this column
SUPPLY & INSTALLATION OF ALUMINIUM DOORS AND WINDOWS, CURTAIN WALLS, ALUMINIUM CLADDING PANELS, SPIDER SYSTEM AND LOUVERS
Installation Progress
Remarks
Rate Total
S/N Description of Item Unit Quantity % Factor (AED) (AED)
Previous Cummulative Certified Current Cummulative
Handing over Nos 1.00 5.00% 15,025.55 15,025.55 40% 0.40 6,010.22 60% 0.60 9,015.33 100% 1.00 15,025.55
AD-23, 1200mm (W) x 2200mm (H) powder coated aluminum
31 Nos 1,272.00 4,412.00 5,612,064.00 - -
framed single shutter door. Including curtain wall glazing works
Brackets Nos 1,272.00 20.00% 882.40 1,122,412.80 100% 1,272.00 1,122,412.80 0% - - 100% 1,272.00 1,122,412.80
Framing Nos 1,272.00 30.00% 1,323.60 1,683,619.20 100% 1,272.00 1,683,619.20 0% - - 100% 1,272.00 1,683,619.20
Glazing Nos 1,272.00 35.00% 1,544.20 1,964,222.40 100% 1,272.00 1,964,222.40 0% - - 100% 1,272.00 1,964,222.40
Accessories Nos 1,272.00 10.00% 441.20 561,206.40 100% 1,272.00 561,206.40 0% - - 100% 1,272.00 561,206.40
Handing over Nos 1,272.00 5.00% 220.60 280,603.20 5% 63.60 14,030.16 95% 1,208.40 266,573.04 100% 1,272.00 280,603.20
Brackets Nos 11.00 20.00% 4,707.40 51,781.40 100% 11.00 51,781.40 0% - - 100% 11.00 51,781.40
Framing Nos 11.00 30.00% 7,061.10 77,672.10 100% 11.00 77,672.10 0% - - 100% 11.00 77,672.10
Glazing Nos 11.00 35.00% 8,237.95 90,617.45 100% 11.00 90,617.45 0% - - 100% 11.00 90,617.45
Accessories Nos 11.00 10.00% 2,353.70 25,890.70 100% 11.00 25,890.70 0% - - 100% 11.00 25,890.70
Handing over Nos 11.00 5.00% 1,176.85 12,945.35 40% 4.40 5,178.14 60% 6.60 7,767.21 100% 11.00 12,945.35
Brackets Nos 17.00 20.00% 4,370.60 74,300.20 100% 17.00 74,300.20 0% - - 100% 17.00 74,300.20
Framing Nos 17.00 30.00% 6,555.90 111,450.30 100% 17.00 111,450.30 0% - - 100% 17.00 111,450.30
Glazing Nos 17.00 35.00% 7,648.55 130,025.35 100% 17.00 130,025.35 0% - - 100% 17.00 130,025.35
Accessories Nos 17.00 10.00% 2,185.30 37,150.10 100% 17.00 37,150.10 0% - - 100% 17.00 37,150.10
Handing over Nos 17.00 5.00% 1,092.65 18,575.05 40% 6.80 7,430.02 60% 10.20 11,145.03 100% 17.00 18,575.05
AD-26, 1600mm (W) x 2400mm (H) powder coated aluminum
34 Nos 1.00 11,655.00 11,655.00 - -
framed double shutter door.
Brackets Nos 1.00 20.00% 2,331.00 2,331.00 100% 1.00 2,331.00 0% - - 100% 1.00 2,331.00
Framing Nos 1.00 30.00% 3,496.50 3,496.50 100% 1.00 3,496.50 0% - - 100% 1.00 3,496.50
Glazing Nos 1.00 35.00% 4,079.25 4,079.25 100% 1.00 4,079.25 0% - - 100% 1.00 4,079.25
Accessories Nos 1.00 10.00% 1,165.50 1,165.50 100% 1.00 1,165.50 0% - - 100% 1.00 1,165.50
Handing over Nos 1.00 5.00% 582.75 582.75 40% 0.40 233.10 60% 0.60 349.65 100% 1.00 582.75
ALUMINIUM FRAMED WINDOWS - -
SUPPLY & INSTALLATION OF ALUMINIUM DOORS AND WINDOWS, CURTAIN WALLS, ALUMINIUM CLADDING PANELS, SPIDER SYSTEM AND LOUVERS
Installation Progress
Remarks
Rate Total
S/N Description of Item Unit Quantity % Factor (AED) (AED)
Previous Cummulative Certified Current Cummulative
Brackets Nos 2.00 20.00% 1,698.00 3,396.00 100% 2.00 3,396.00 0% - - 100% 2.00 3,396.00
Frame Nos 2.00 30.00% 2,547.00 5,094.00 100% 2.00 5,094.00 0% - - 100% 2.00 5,094.00
Glass Nos 2.00 35.00% 2,971.50 5,943.00 100% 2.00 5,943.00 0% - - 100% 2.00 5,943.00
Accessories Nos 2.00 10.00% 849.00 1,698.00 100% 2.00 1,698.00 0% - - 100% 2.00 1,698.00
Handing over Nos 2.00 5.00% 424.50 849.00 40% 0.80 339.60 60% 1.20 509.40 100% 2.00 849.00
WN-09, 4300mm (W) x 4500mm (H) aluminum framed fixed
43 Nos 1.00 15,212.0 15,212.00 - -
window.
Brackets Nos 1.00 20.00% 3,042.40 3,042.40 100% 1.00 3,042.40 0% - - 100% 1.00 3,042.40
Frame Nos 1.00 30.00% 4,563.60 4,563.60 100% 1.00 4,563.60 0% - - 100% 1.00 4,563.60
Glass Nos 1.00 35.00% 5,324.20 5,324.20 100% 1.00 5,324.20 0% - - 100% 1.00 5,324.20
Accessories Nos 1.00 10.00% 1,521.20 1,521.20 100% 1.00 1,521.20 0% - - 100% 1.00 1,521.20
Handing over Nos 1.00 5.00% 760.60 760.60 100% 0.40 304.24 60% 0.60 456.36 100% 1.00 760.60
WN-10, 2000mm (W) x 2400mm (H) aluminum framed fixed
44 Nos 50.00 3,774.0 188,700.00 - -
window.
Brackets Nos 50.00 20.00% 754.80 37,740.00 100% 50.00 37,740.00 0% - - 100% 50.00 37,740.00
Frame Nos 50.00 30.00% 1,132.20 56,610.00 100% 50.00 56,610.00 0% - - 100% 50.00 56,610.00
Glass Nos 50.00 35.00% 1,320.90 66,045.00 100% 50.00 66,045.00 0% - - 100% 50.00 66,045.00
Accessories Nos 50.00 10.00% 377.40 18,870.00 100% 50.00 18,870.00 0% - - 100% 50.00 18,870.00
Handing over Nos 50.00 5.00% 188.70 9,435.00 40% 20.00 3,774.00 60% 30.00 5,661.00 100% 50.00 9,435.00
WN-11, 12120mm (W) x 4500mm (H) aluminum framed fixed
45 Nos 1.00 42,875.0 42,875.00 - -
window.
Brackets Nos 1.00 20.00% 8,575.00 8,575.00 100% 1.00 8,575.00 0% - - 100% 1.00 8,575.00
Frame Nos 1.00 30.00% 12,862.50 12,862.50 100% 1.00 12,862.50 0% - - 100% 1.00 12,862.50
Glass Nos 1.00 35.00% 15,006.25 15,006.25 100% 1.00 15,006.25 0% - - 100% 1.00 15,006.25
Accessories Nos 1.00 10.00% 4,287.50 4,287.50 100% 1.00 4,287.50 0% - - 100% 1.00 4,287.50
Handing over Nos 1.00 5.00% 2,143.75 2,143.75 40% 0.40 857.50 60% 0.60 1,286.25 100% 1.00 2,143.75
46 STRUCTURAL GLAZING WORKS - -
Supply and fix 36mm thk double insulated glass glazing system,
color as per Architect's approval including all necessary fixings,
framings, other accessories, and ironmongeries complete as - -
specified in drawing AR-502 and all as per specification and Abu
Dhabi Civil Defense and all other authorities requirements.
Brackets m2 23,103.00 20.00% 181.60 4,195,504.80 100% 23,103.00 4,195,504.80 0% - - 100.00% 23,103.00 4,195,504.80
Framing m2 23,103.00 30.00% 272.40 6,293,257.20 100% 23,103.00 6,293,257.20 0% - - 100.00% 23,103.00 6,293,257.20
Glazing m2 23,103.00 35.00% 317.80 7,342,133.40 100% 23,103.00 7,342,133.40 0% - - 100.00% 23,103.00 7,342,133.40
Accessories m2 23,103.00 10.00% 90.80 2,097,752.40 100% 23,103.00 2,097,752.40 0% - - 100.00% 23,103.00 2,097,752.40
Handing over m2 23,103.00 5.00% 45.40 1,048,876.20 40% 9,241.20 419,550.48 60% 13,861.80 629,325.72 100.00% 23,103.00 1,048,876.20
RFQ- Value of Work Done Page 6 of 8
Installation
WATERFRONT PROJECT - ABU DHABI, UNITED ARAB EMIRATES
progress updated
in this column
SUPPLY & INSTALLATION OF ALUMINIUM DOORS AND WINDOWS, CURTAIN WALLS, ALUMINIUM CLADDING PANELS, SPIDER SYSTEM AND LOUVERS
Installation Progress
Remarks
Rate Total
S/N Description of Item Unit Quantity % Factor (AED) (AED)
Previous Cummulative Certified Current Cummulative
Brackets m2 2,925.00 20.00% 173.20 506,610.00 100% 2,925.00 506,610.00 0% - - 100% 2,925.00 506,610.00
Framing m2 2,925.00 30.00% 259.80 759,915.00 100% 2,925.00 759,915.00 0% - - 100% 2,925.00 759,915.00
Glazing m2 2,925.00 35.00% 303.10 886,567.50 100% 2,925.00 886,567.50 0% - - 100% 2,925.00 886,567.50
Accessories m2 2,925.00 10.00% 86.60 253,305.00 100% 2,925.00 253,305.00 0% - - 100% 2,925.00 253,305.00
Handing over m2 2,925.00 5.00% 43.30 126,652.50 40% 1,170.00 50,661.00 60% 1,755.00 75,991.50 100% 2,925.00 126,652.50
49 to balcony partitions, 470mm wide x 2000mm high Nos 444.00 1,289.0 572,316.00 - -
Steel Channel Nos 444.00 20.00% 257.80 114,463.20 100% 444.00 114,463.20 0% - - 100% 444.00 114,463.20
Glazing Nos 444.00 65.00% 837.85 372,005.40 100% 444.00 372,005.40 0% - - 100% 444.00 372,005.40
Accessories Nos 444.00 10.00% 128.90 57,231.60 100% 444.00 57,231.60 0% - - 100% 444.00 57,231.60
Handing over Nos 444.00 5.00% 64.45 28,615.80 40% 177.60 11,446.32 60% 266.40 17,169.48 100% 444.00 28,615.80
ADDITIONAL ITEMS - -
Brackets Nos 50.00 20.00% 661.80 33,090.00 100% 50.00 33,090.00 0% - - 100% 50.00 33,090.00
Framing Nos 50.00 30.00% 992.70 49,635.00 100% 50.00 49,635.00 0% - - 100% 50.00 49,635.00
Glazing Nos 50.00 35.00% 1,158.15 57,907.50 100% 50.00 57,907.50 0% - - 100% 50.00 57,907.50
Accessories Nos 50.00 10.00% 330.90 16,545.00 100% 50.00 16,545.00 0% - - 100% 50.00 16,545.00
Handing over Nos 50.00 5.00% 165.45 8,272.50 40% 20.00 3,309.00 60% 30.00 4,963.50 100% 50.00 8,272.50
Brackets m2 185.00 20.00% 157.40 29,119.00 100% 185.00 29,119.00 0% - - 100% 185.00 29,119.00
Frame m2 185.00 30.00% 236.10 43,678.50 100% 185.00 43,678.50 0% - - 100% 185.00 43,678.50
Window m2 185.00 35.00% 275.45 50,958.25 100% 185.00 50,958.25 0% - - 100% 185.00 50,958.25
Accessories m2 185.00 10.00% 78.70 14,559.50 100% 185.00 14,559.50 0% - - 100% 185.00 14,559.50
Handing over m2 185.00 5.00% 39.35 7,279.75 40% 74.00 2,911.90 60% 111.00 4,367.85 100% 185.00 7,279.75
Brackets Nos 39.00 20.00% 254.80 9,937.20 100% 39.00 9,937.20 0% - - 100% 39.00 9,937.20
Frame Nos 39.00 30.00% 382.20 14,905.80 100% 39.00 14,905.80 0% - - 100% 39.00 14,905.80
Window Nos 39.00 35.00% 445.90 17,390.10 100% 39.00 17,390.10 0% - - 100% 39.00 17,390.10
Accessories Nos 39.00 10.00% 127.40 4,968.60 100% 39.00 4,968.60 0% - - 100% 39.00 4,968.60
Handing over Nos 39.00 5.00% 63.70 2,484.30 40% 15.60 993.72 60% 23.40 1,490.58 100% 39.00 2,484.30
Brackets Nos 1.00 20.00% 764.20 764.20 100% 1.00 764.20 0% - - 100% 1.00 764.20
Frame Nos 1.00 30.00% 1,146.30 1,146.30 100% 1.00 1,146.30 0% - - 100% 1.00 1,146.30
Window Nos 1.00 35.00% 1,337.35 1,337.35 100% 1.00 1,337.35 0% - - 100% 1.00 1,337.35
Accessories Nos 1.00 10.00% 382.10 382.10 100% 1.00 382.10 0% - - 100% 1.00 382.10
Handing over Nos 1.00 5.00% 191.05 191.05 40% 0.40 76.42 60% 0.60 114.63 100% 1.00 191.05
Spider Glazing curtain wall for podium internal glazing ( Dwg Ref
54 m2 439.00 1,777.96 780,523.04 - -
AR.908 & 909)
Brackets m2 439.00 20.00% 355.59 156,104.61 100% 439.00 156,104.61 0% - - 100% 439.00 156,104.61
Framing m2 439.00 30.00% 533.39 234,156.91 100% 439.00 234,156.91 0% - - 100% 439.00 234,156.91
Glazing m2 439.00 35.00% 622.28 273,183.06 100% 439.00 273,183.06 0% - - 100% 439.00 273,183.06
Accessories m2 439.00 10.00% 177.80 78,052.30 100% 439.00 78,052.30 0% - - 100% 439.00 78,052.30
Handing over m2 439.00 5.00% 88.90 39,026.15 40% 175.60 15,610.46 60% 263.40 23,415.69 100% 439.00 39,026.15
EXTERNAL CLADDING - -
SUPPLY & INSTALLATION OF ALUMINIUM DOORS AND WINDOWS, CURTAIN WALLS, ALUMINIUM CLADDING PANELS, SPIDER SYSTEM AND LOUVERS
Installation Progress
Remarks
Rate Total
S/N Description of Item Unit Quantity % Factor (AED) (AED)
Previous Cummulative Certified Current Cummulative
Brackets m2 711.00 20.00% 176.00 125,136.00 100% 711.00 125,136.00 0% - - 100% 711.00 125,136.00
Framing m2 711.00 30.00% 264.00 187,704.00 100% 711.00 187,704.00 0% - - 100% 711.00 187,704.00
Cladding panels m2 711.00 45.00% 396.00 281,556.00 100% 711.00 281,556.00 0% - - 100% 711.00 281,556.00
Handing over m2 711.00 5.00% 44.00 31,284.00 20% 142.20 6,256.80 80% 568.80 25,027.20 100% 711.00 31,284.00
Brackets m2 21,589.00 20.00% 154.20 3,329,023.80 98% 21,157.22 3,262,443.32 2% 431.78 66,580.48 100.00% 21,589.00 3,329,023.80
Framing m2 21,589.00 30.00% 231.30 4,993,535.70 98% 21,157.22 4,893,664.99 2% 431.78 99,870.71 100.00% 21,589.00 4,993,535.70
Cladding panels m2 21,589.00 45.00% 346.95 7,490,303.55 98% 21,157.22 7,340,497.48 2% 431.78 149,806.07 100.00% 21,589.00 7,490,303.55
Handing over m2 21,589.00 5.00% 38.55 832,255.95 20% 4,317.80 166,451.19 80% 17,271.20 665,804.76 100.00% 21,589.00 832,255.95
4mm thick aluminium composite panel, to architects approval,
including accessories, connections, fixing clips, and fixing as shown
57 m2 818.00 457.0 373,826.00 - -
in drawings and all as per specification. To podium floating
restaurant roof cladding.
Brackets and Framing m2 818.00 30.00% 137.10 112,147.80 100% 818.00 112,147.80 0% - - 100% 818.00 112,147.80
Damp proof and insulation m2 818.00 20.00% 91.40 74,765.20 0% - - 100% 818.00 74,765.20 100% 818.00 74,765.20
Cladding panels m2 818.00 35.00% 159.95 130,839.10 100% 818.00 130,839.10 0% - - 100% 818.00 130,839.10
Accessories m2 818.00 10.00% 45.70 37,382.60 100% 818.00 37,382.60 0% - - 100% 818.00 37,382.60
Handing over m2 818.00 5.00% 22.85 18,691.30 40% 327.00 7,471.95 100% 818.00 18,691.30
Brackets and Framing m2 758.00 30.00% 141.90 107,560.20 100% 758.00 107,560.20 0% - - 100% 758.00 107,560.20
Damp proof and insulation m2 758.00 20.00% 94.60 71,706.80 100% 758.00 71,706.80 0% - - 100% 758.00 71,706.80
Cladding panels m2 758.00 35.00% 165.55 125,486.90 100% 758.00 125,486.90 0% - - 100% 758.00 125,486.90
Accessories m2 758.00 10.00% 47.30 35,853.40 100% 758.00 35,853.40 0% - - 100% 758.00 35,853.40
Handing over m2 758.00 5.00% 23.65 17,926.70 20% 151.60 3,585.34 80% 606.40 14,341.36 100% 758.00 17,926.70
Total Amount 64,410,193.04 61,416,564.53 2,982,351.27 64,410,193.04
Discount 335,240.00 319,658.86 15,522.44 335,240.00
Total Amount after discount 64,074,953.04 61,096,967.77 2,966,828.83 64,074,953.04
STEEL DIAGRID
Grand Total Amount ( Contract Value ) AED 70,826,308.04 67,742,698.38 3,514,639.95 70,826,308.04
Design, Supply and Installation of powder coated aluminium framed single leaf hinged
clear glass doors including all necessary fittings and accessories including
ironmongery, etc., as per Architect's approval.
2 VO-6
MD 05 - 1000mm (W) x 2200mm (H) powder coated aluminium framed single leaf
Nos 2 100% 2
hinged clear glass door 3,677.26 7,354.51 7,354.51
MD 06 - 1000mm (W) x 2200mm (H) powder coated aluminium framed single leaf
Nos 2 100% 2
hinged clear glass door
3,677.26 7,354.51 7,354.51
Additional cost impact for design and installation for BMU Restraint socket
Nos 568 100% 568
3 VO-09 on diagrid framing 216.16 122,778.88 122,778.88
Additional cost impact for providing Aluminium Perforated Sheeting in lieu of
CTI-WAD-P0389-L-392 100% 1
4 VO-10 ACP Cladding to the Floating Restaurant roof Lusum 1 30,493.70 30,493.70 30,493.70
5 VO-11_1 Additional Louvers requirement_R1 CTI-WAD-P0389-L-420 Lusum 1 61,419.30 61,419.30 100% 1 61,419.30
6 VO-11_2 Additional Z-tupe Louvers requirement CTI-WAD-P0389-L-463 Lusum 1 196,310.68 196,310.68 100% 1 196,310.68
6 VO-12 Additional silicon work between fascia and ceiling CTI-WAD-P0389-L-476 Lusum 1 149,379.00 149,379.00 100% 1 149,379.00
7 VO-13 Additional aluminum door at Podium Lower Level CTI-WAD-P0389-L-477 Lusum 1 35,063.42 35,063.42 100% 1 35,063.42
Additional cost impact due to Supply and Fixing of 30mmX30mm Powder
WF-P389-CTI-L-500 100% 1
8 VO-16 coated aluminum channel 2mm thick. Lusum 1 7,774.00 7,774.00 7,774.00
Additional cost impact for Supply and Fixing of 4 mm thick aluminium cladding
WF-P389-CTI-L-501 100% 1
9 VO-17 to façade. Lusum 1 38,550.00 38,550.00 38,550.00
Additional cost impact for providing Z-type Aluminium Louver in lieu of
Balcony Curtain wall Glass at Level-04 Tower-A elevation-03 and Tower-B WF-P389-CTI-L-502 100% 1
10 VO-18 Elevation-01 Lusum 1 6,206.00 6,206.00 6,206.00
0.00
Regarding Breakage of Installed SCW Glasses & ACP Pane at
CTI-WAD-P0389-L-513 27,000.0 100% 1
12 Towers Lusum 1 27,000.00 27,000.00
Charge of access ( Cradles) arrangment by M/S CTI on Behalf of
CTI-WAD-P0389-L-514 64,192.0 100% 1
13 Dhabi Lusum 1 64,192.00 64,192.00
Damage of Hinge Doors Threshold at Ground Floor (Tower A&
CTI-WAD-P0389-L-535 15,000.0 100% 1
14 B) Lusum 1 15,000.00 15,000.00
Cradles rental charges for 9 months along with hanging devices
CTI-WAD-P0389-L-588 299,177.0 100% 1
15 and cradle supports Lusum 1 299,177.00 299,177.00
16 Damages done by DC CTI-WAD-P0389-L-613 Lusum 1 431,835.6 431,835.58 100% 1 431,835.58