Seven Hotel and Apartments Doc Ref: SEVEN-P391-CTI-L-164

The Palm, Dubai Date: 03rd November 2022

To: Airolink Building Contracting LLC

Attn: Mr. Prashanth Rao (Project Manager)

Project: Seven Hotel and Apartments

Subject: CTI-VO-24- Additional cost impact due to broken glass based on NCR-076

Dear Sir,

This serves to confirm the additional cost implications due to broken glass based on NCR-076
amounting AED 1,211.73 (UAE Dirham’s – One Thousand, Two Hundred Eleven and 73/100 only).
Pursuant to the Sub-contract terms and conditions, we record that the above work is a variation to
the Sub-contract and advice of our entitlement for reimbursement of the additional cost and time
implications.
In support, please refer to the attached documents, which identify the location and the required
quantities.

CTI trust this is acceptable and look forward to your confirmation of acceptance.

____________________
Syed Nasir
Commercial Manager

Cc: Mr. Charles Couteau (VP Operation –CTI)


Mr. Ahmad Hariri (Area Manger - CTI)
Mr. Mohammad Arshad (Project Manager- CTI)
For file
VARIATION SUBMISSION DETAILS Project No. : P0391

Project : SEVEN HOTEL & APARTMENTS, THE PALM, DUBAI

Cladtech Variation
Client : AL MEMZAR INVESTMENTS CTI-VO-24
No:

Consultant : CONIN INCORPORATED CONSULTANTS ABC REF No :

Main Contractor AIROLINK BUILDING CONTRACTING LLC Date of Submission 3-Nov-22

Engineer's
Date of Instruction /
Instruction 2-Nov-22
Document
Ref./ Source :

CTI-VO-24 Additional cost impact due to broken glass based on NCR-076

List of Yes No

Attachments: 1 Variation Summary P


2 Price Breakdown

3 NCR

Cost of the Variation: AED 1,211.73


Comments/ Remarks: PURSUANT TO CONTRACT CONDITIONS, WE RESERVE OUR RIGHT TO CLAIM FOR AN EXTENSION OF TIME FOR ADDITIONAL WORKS.

Prepared By & Date : Checked By & Date: Reviewed by & Date :

QS Commercial Manager Project Manager

Approved By & Date : Approved by & Date :


Airolink QS Airolink Project Manager
VARIATION SUMMARY
Project : Seven Hotel & Apartments
Client : Al Memzar investments
Contractor : Airolink Building Contracting LLC
Consultant : Conin Incorporated Consultants

VO No. Description

24 Additional cost impact due to broken glass based on NCR-076

S No. Description Unit Quantity Rate (AED) Total Amount (AED) Remarks
MATERIAL COST

1 Broken glass-CW-21-GL2-01CR m2 2.56 76.00 195


2 Installation m2 2.56 120.00 307

Transportation charge Trip 500

A Sub Total Amount ( AED ) 1,001.76 AED

B Add Prelims 8% 80.14 AED

C Add Overhead and profit 12% 129.83 AED

D GRAND TOTAL AMOUNT, D=(A+B+C) 1,211.73 AED


Sidharth Sathyan

From: Sajin John


Sent: Wednesday, October 26, 2022 3:01 PM
To: Site Engineer - Seven Residences; Document Controller - Seven Residences
Cc: Smiju Sashidharan; Mohammad Arshad; Shefeek Shereef
Subject: Broken glass - ground floor Tower B
Attachments: Material Damage Report - 021.pdf

Dear all, 
 
Please refer to the attached Material Damage report ‐21, for your information and record. 
 
Regards, 
 
 
Sajin John 
Sr.QA/QC Engineer 
 

Tel: +971 7 244 6114


Fax: +971 7 244 6112
Mobile: +971 521166409
Web: sajin.john@cladtech-int.com; www.cladtech-int.com
Address: 85A Al Yaqoot Street | Al Jazeera Al Hamra | PO Box 6674 | RAK | UAE

Privacy and Confidentiality Notice: The information contained in this transmission is intended for named recipients
only. It may contain privileged and confidential information and if you are not the intended recipient, you must not  
 
copy, distribute or take any action in reliance on it. If you have received it in error, please notify us immediately

You might also like