Substation
Bay/Panel
Equipment Serial No
Ite
Description Done Remarks
m
1. Battery and Battery Charger are in service
2. AC/DC Distribution Board are in service
3. Main AC Supply is available (If Applicable)
4. UPS (DC/AC Converter) in is service (If Applicable)
Ite
Description Done Remarks
m
1. Raised Floor is mounted and secured
2. HVAC ducts in SAS room is in service
3. False Ceiling is mounted and secured
4. Light System is Installed & functioning
5. Room Openings are securely closed
6. Original Furniture are mounted
Ite
Description Done Remarks
m
Ite Done
Description Remarks
m
1 SAS panels are installed
GPS, LCDs , monitors and printers are Installed and
2
terminated as per approved drawings
FO&RJ cables are terminated and verified as per
3
approved drawings
Ite
Description Done Remarks
m
Cabling between LCC and GIS are completed and
1
verified as per approved drawings
Scheme check for LCC is completed as per final
2
approved drawings
BCUs are installed and terminated as per final
3
approved drawings.
4 BCUs configurations are completed by BCU Vendor
5 BCUs final approved SCD files are ready
Archiving System Website: http://AMAS
NATIONAL GRID
Ite
Description Done Remarks
m
Scheme check for relays and control panels are
1
completed as per final approved drawings.
IEDs are installed and terminated as per final approved
2
drawings.
3 IEDs configurations are completed by IED Vendor.
IEDs final acceptance test with witness are completed
4
and approved
5 IEDs final approved SCD files are ready
IEDs are connected to SAS panels as per approved
6
drawings.
7 IEDs are powered on
8.0 General
Ite Done
Description Remarks
m
Skilled protection engineer from main contractor side
1
shall be available with SAS team.
SCADA master station Communication parameters
2
should be available. Interoperability parameters.