Professional Documents
Culture Documents
Flood Mitigation and Flood Routing
Flood Mitigation and Flood Routing
Flood Mitigation and Flood Routing
11.1 Introduction
Flooding is the inundation of normally dry land by a stream overtopping its banks. It is a natural
periodic event in the history of any river. Flooding of water channels and flood plains mainly
occurs as a result of heavy rains and sometimes melting snow in the watershed/catchment area of
the stream, river, or lake.
Floods have caused extensive damage and are likely to increase in the future due to increased
encroachment on flood plains in both urban and rural areas. To prevent such damage and losses, it
is important to find means of averting floods and initiating flood damage relief measures. Civil
engineers need to play a key role in flood mitigation and designing structures to withstand
flooding, placing a heavy burden on engineering to provide technical solutions to flooding (ICE,
2001).
The largest meteorological floods include the floods of 1953, 1963 and 1976 of the Amazon
River at Obidos and the 1870 flood of Yangtze River in China. The Amazon River drains the
world’s largest basin (7 million km2) and is in the tropics like the Yangtze, which also receives
substantial tropical moisture. Meteorological floods are by far the most common of the types of
floods for the human experience. They can bring good l alluvium soils like the floods of the Nile
Delta or they can lead to catastrophic life and destruction of property.
In general, larger basins produce larger floods; the variation to this is due to the larger unit
discharges, primarily between latitudes 10o S and 30o N. The largest floods in large basins within
the tropics are primarily derived from rainfall within areas affected by tropical cyclones or strong
monsoonal airflow like the Brahmaputra, Ganges, Yangtze, Mekong, Huangue River Basins.
Several large basins do not produce relatively large peak discharges. These include Congo, Niger,
Chari (in Chad) and San Francisco River Basins, which drain large areas of low relief or are
isolated from zones of major precipitation.
It should also be noted that the incidence of floods caused by different processes changes through
time. Most of the largest documented floods in the past 100 years resulted from the failures of
natural dams, but conditions that caused some of these failures are now absent. These periods can
be considered as flood epochs when climate and topography combine to produce higher than
typical frequencies of large floods. In many cases outsized floods from previous flood epochs
were dominant forces in establishing regional drainage networks and landscape patterns that
persisted into times of fewer extreme floods. Other geologically controlled floods, like those
resulting from large volcanic eruptions, or large valley blocking landslides, are likely to be more
distributed with time and the likelihood of occurrence is guided by the analysis of past events.
The largest floods are not evenly distributed around the world. Those caused by natural dam
failure and closed basin spillovers have been in the mid latitudes, whereas the largest
meteorological floods are in the tropical regions (USGS, 2004).
Flood damage can be direct or indirect. Indirect damages are further divided into tangible and
intangible losses. Direct damages constitute economic losses directly incurred as rural and urban
property, to facilities and utilities and agriculture crops and livestock.
Indirect damages refer mainly to the economic losses emerging from disruption of normal
economic activities, which depreciate the productivity of the affected area. Other indirect tangible
losses include expenditure amassed in alleviating hardships, safeguarding health during a flood
and providing relief. Loss of human life, rehabilitation costs and losses of livelihoods are indirect
intangible losses.
Table 11.1 gives a representation of flood damage in monetary terms that was incurred as a result
of floods that hit various parts of the world in the year 2000.
10/11/00 -
United Kingdom 3 0 1,000 5,900,000,000
10/14/00
07/31/00 -
Northern India 4 140 4,000 238,000,000
08/03/00
08/23/00 -
Southern India 9 162 3,000,000 177,000,000
08/31/00
Central and
09/01/00 -
southern China - 5 47 46,000 169,000,000
09/05/00
Typhoon Maria
Source: NASA-supported Dartmouth Observatory (summarized to give damage above US$ 100,000,000)
11.4.1 Mozambique
Mozambique faced fresh floods early 2001 less than six months since the devastating floods that
hit the country 2000. Devastating floods hit the southern Mozambique for nearly three months
late 2001, when some 700 people drowned and some half a million were displaced.
Mozambique has suffered massive floods for two years in a row from 2001-2002 though in
different parts of the country.
Mozambique appealed for US$30 million in aid to deal with the floods that affected almost
400,000 people in the Central Provinces of Zambezia, Sofala, Manica and Tete. The major
problem arose from the high discharges of the Zambezi River of about 11,000 m3/s, flowing into
the Cabora Bassa dam and yet the floodgates could only release a maximum of 7,500 m3/s.
11.4.2 Ukraine
In Europe, floods ravaged many areas in 2001-2002 In western Ukraine in March 2001 flooding
caused loss of life, disruption of life and extensive damage. More than 35,000 people had to be
evacuated from Ukraine's Zakarpattia region because of heavy rains and melting snow that
overflowed rivers and burst dikes around the Carpathian Mountains.
At least 20,000 houses were flooded and about 200 submerged villages in western Ukraine and
northeastern Hungary. More than 50 kilometres of roads and about 9 kilometres of railway were
destroyed in the Ukrainian part of the flooded area, where workers used almost half a million
sand bags sent from neighbouring regions to strengthen dikes.
In Hungary, efforts were made to build a second line of defense after a dike burst at
Vasarosnameny, 240 kilometres (150 miles) east of Budapest. The main road between the
villages of Takos and Csaroda, near the Ukrainian border, was also demolished in two places,
allowing floodwaters flow to low-lying areas. Experts pointed out that the water levels, which are
the highest in more than a century, are causing less damage than the record floods of 1998
because of dyke reinforcement work since then. The floods have caused damages of billions
of dollars to Hungary since 1998 (The Associated Press & Reuters, 2001).
River
Levee Revetment
Levees are most commonly used for flood mitigation because they can be built at relatively low
cost of materials available on site. Levees are usually built of materials excavated from burrow
pits parallel to the levee line. When designing levees, sufficient channel must be provided to
transmit the design flow with a reasonable freeboard against wave action. The channel width
between levees and the height of the levees are closely related. The cost of a levee system
consists of the cost of the land for the levees and channel plus the cost of the levee construction.
Levees should undergo regular channel inspection by competent engineers who will look for
evidence of dangerous developments like bank caving, weak spots, foundation settlement, bank
sloughing and erosion.
b)Floodwalls
Floodwalls are used in developed areas where it is difficult to obtain enough land for the
construction of levees. Levees require a very large base width, because of flat slopes. Where land
is costly or limited, like in urban areas, it is more economical to construct floodwalls. A floodwall
is a sort of gravity dam constructed along the river. Floodwalls are designed to withstand
hydrostatic pressure like gravity dams. Fig 11.3 shows typical floodwall cross sections.
Sheet Pile
c) Channel Improvement
Channel improvement involves improving the hydraulic properties of the channel. Removal of
brush and snags, dredging of bars, strengthening of bends and other devices can be effective;
though care must be taken not to make the channel susceptible to bank erosion. Channel
improvement aids flood mitigation by decreasing Manning's n for the reach, increasing hydraulic
radius by increasing depth and increasing the channel slope by shortening the channel length.
However channelization initiates so many environmental problems that it can only be justified on
the basis of providing an essential aid to navigation and/or a flood -protection measure in urban or
other highly developed areas.
Channel improvement therefore increases the discharge capacity of the river by increasing the
flow area; A and decreasing the surface roughness n. Roughness of the channel n is reduced by
the removal of bushes, dredging of sandbars and preventing cropping in the river bed.
Some of the various methods of channel improvement are;
(i) Increasing channel section
(ii) Realignment of the river
(iii) Increasing the river velocity
(iv) Increasing waterways at crossings
ii) The delaying of the flow and attenuation of the peak flow can be achieved by the construction
of reservoirs as expod-mitigation reservoirs store a portion of the flood flow in such a way as to
minimize the flood peak at the point to be protected. Ideally the reservoir would be situated
immediately upstream from the protected area and is operated to "cut off" the flood peak. This is
achieved by discharging all reservoir inflow until the outflow reaches the safe capacity of the
channel downstream. All flow above this rate is stored until the inflow drops below the safe
channel capacity and the stored water is released to recover the storage capacity for the next
flood.
Though the most effective flood mitigation is obtained from an adequate reservoir located
immediately upstream from the point (or reach to be protected, such a reservoir would often be
located in a broad flood plain where a very long dam would be necessary and a large area of
valuable land would be flooded. Sites further upstream require smaller dams and less valuable
land, but are less effective in attenuating flood peaks. This loss in effectiveness issues from the
influence of channel storage and from lack of control over the local inflow between the reservoir
and the protected area. Economic considerations and other factors often favour upstream sites
despite its lesser effectiveness (Linsleyand Franzini 1979).
Types of Reservoirs
There are two (2) types of flood-mitigation reservoirs,
a) Storage reservoirs and
b) Retarding basins
These differ only in the type of outlet works provided. Gates and valves regulate the discharge
from a storage reservoir. Storage reservoirs for flood mitigation differ from conservation
reservoirs only in the need for a large sluice way capacity to permit rapid draw down in advance
of or after a flood. A retarding basin is provided with fixed, ungated outlets, which automatically
regulate the outflow in accordance with the volume of water in storage. The outlet usually
consists of a large spillway or one or more ungated sluiceways. A simple spillway is normally
undesirable because storage below the crest of the spillway cannot be used. These dams should be
designed taking account of environmental considerations and an Environmental Impact
Assessment (EIA) should be conducted. In order to be cost effective, multiple uses of the water
should be considered. These could include in addition to flood control, irrigation, power
generation, domestic water supply, navigation, wildlife management and recreational activities.
iii) The diversion of flow can be achieved through the construction of floodways and diversion
channels.
Floodways
Floodways serve to alleviate flooding by diversion of floodwaters through floodways. These
structures provide two functions in flood mitigation.
(i) They create large shallow reservoirs, which store a portion of the floodwater and hence
decrease the flow in the main channel below the diversion.
(ii) Secondly, they provide an additional outlet for water from upstream, increasing
velocity and decreasing stage for some distance above the point of diversion.
Floodways store a quota of the floodwater during the peak flood period, and thus decrease the
discharge in the main channel of the river below the point of diversion. After the flood recedes in
the main channel of the river, the water stored in the floodway is allowed to flow back to the
main. Fig 11.4 illustrates the operation of floodway.
Diversion
River Flow
Flood Way
Flood control using floodways is only possible if the topography of the valley is suitable and low-
value land is available, which can be used for the floodways. The land used for floodways can be
used for agriculture for the rest of the period when floods are not occurring.
In this case, the area that is on average susceptible to flooding every year is less than that
susceptible to flooding every five (5) years. The areas which are extremely flood prone and those
which are comparatively less flood prone are demarcated as illustrated in Fig 11.6. The entire
flood plain area may be divided into zones, specifying restrictive uses for each, depending on its
vulnerability to flooding. The zones can be restricted to the following uses; the area that is prone
to flooding yearly may be put to agricultural use, however only crops that can be harvested well
before the onset of the rain season should be cultivated. There should be no buildings erected in
such areas.
Moderately flood prone areas can be used for structures that are less temporary. The flood plain
can therefore be divided into three (3) zones.
• Prohibitive zone
• Restrictive zone
• Warning zone
i) Prohibitive Zone
These are areas where no building activity is to be permitted; as they are highly liable to frequent
flooding. Squatters should under no circumstance encroach upon this area, at most only
temporary agricultural uses may be allowed.
Floodway
Flood Fringe Flood Fringe
“100-year” Floodplain
Channel
The design flood is defined as the discharges that may be expected from the most severe
combination of meteorological and hydrologic conditions that are considered reasonably
characteristic of the geographical region involved, excluding extremely rare combinations. Strict
implementation of such flood plain management tools as flood plain zoning can significantly
lessen the losses and damage incurred due to floods.
25 years (10.79 m)
5 years (6.73 m)
UGANDA SIDE
Fig 0.7 An arbitrary cross section of Lake Albert showing the different flood zones and
their magnitude
In a study on flooding of Lake Albert (Rugumayo and Kayondo, 2006), the cross section was
divided into different flood zones, based on the return periods as shown in Fig 11.8. Furthermore,
the recommended measures for flood mitigation include the establishment of an early warning
system, sensitization of local inhabitants, development of a land management policy, using the
flood zones and establishment of flood defences and installation of more automatic gauging
stations.
a) External walls
Cracks within the brickwork joints or render below the expected maximum flood level should be
repaired to reduce the amount of seepage through the wall. A variety of water-resistant paints and
coatings or tanking are available that can help prevent floodwater soaking into the external face
of the wall, thus allowing the wall to dry out more quickly.
b) Internal walls
The same principles as set out above for the internal face of external solid walls apply to internal
walls of masonry. Stud walls, comprising timber framing and plasterboard are vulnerable to
damage from flooding. Consideration should be given to replacing untreated softwood timber
with water-resistant timber.
c) Floors
After floodwaters have subsided, water is likely to be retained below a suspended floor within the
sub-floor void. The sub-floor void should be cleaned of debris to allow future floodwater to be
quickly pumped away and to avoid moisture retention. For modern buildings the sub-floor area is
likely to be covered with 100mm of concrete or heavy-duty polyethylene sheeting with concrete
or sand blinding. Any damage to these linings as a result of flooding should be repaired during
the drying-out period.
In suspended concrete floors, consideration should be given to providing a fall to sub-floor
surface at an identified drainage point. Concrete beams within suspended concrete floors contain
reinforcement that can corrode if there is a high chloride content within the floodwater.
d) Basements
Basement construction should be avoided for new properties within flood risk areas. For existing
properties with basements, specialist advice must always be obtained before undertaking any
measures to prevent water ingress.
The local authority acts initially as a support to emergency services and eventually serves as a
resource to facilitate a return to normal for the affected communities.
Rapid Assessment and Priority Setting
In the event that a flood occurs, these emergency plans need to be carried out as quickly and
effectively as possible to avert major damage to property, environment or life. This can be
referred to as rapid assessment and priority setting (Harvey and Reed, 2002). The very nature of
emergencies is such that there are rapidly changing situations creating a lot of uncertainity and
providing limited or no time for pre-planning. Initial assessments need to be fast and
comprehensive to ensure that needs are met properly.
The assessment process is made up of:
a. Data Collection
This involves the collection of necessary background information pertaining to physical
and environmental factors, political, security and demographic data. However the most
important information is that dealing with current water and sanitation services, facilities
and practices. Although common methods of data collection include mapping,
diagramming, focus group discussions, questionnaires and observations the most widely
used is a series of checklists. These checklists are divided into quality, quantity and usage
of the facilities and may be completed on location.
b. Sectoral Analysis
Once the data is collected, it is analysed by comparison with recommended minimum
objectives for quality, quantity and usage. These objectives are based on the Sphere
Project standards for water and sanitation. The objectives are divided into short term,
intermediate and long term. In complex situations, numerical comparison rather than
comparison by inspection is preferred.
c. Priority Setting.
Using the sectoral analysis, priority may be assigned to those areas requiring urgent
intervention. The use of numerical analysis allows for objective prioritization of needs.
It is essential that assessments and prioritization are made on qualitative, quantitative and
behavioral data with each group weighted equally. It is also important that these tools be viewed
as flexible methods, which can be adapted to local conditions.
Emergency Evacuation
Under certain circumstances, one of the most effective means of flood-damage relief is
emergency evacuation of the threatened area. With reliable flood forecasts this technique is used
in areas with sparse settlement where property values do not justify other control measures and
loss of life can be prevented by prompt evacuation. For example during the recent floods that
battered southern Africa in the months of February and March 2001, most especially
Mozambique, more than 58,000 people had to be evacuated from the towns of Marromeu and
Luabo. Evacuation in this case was the most effective means available as the onset of flooding
was without warning.
Evacuation is mainly realized by airlifting and using boats or canoes to move people to higher
and safer ground. Whenever there are evacuations of people other needs turn out to be evident
and these include food and shelter, which have to be taken into account. Evacuations of this
nature have become necessary because of the tendency to infringe on flood plains inside
riverbanks or lakeshores, which are highly desirable areas for settlement.
v) Flood Forecasting
In order to be able to mitigate flood effects, it is necessary to know the magnitude of floods of
given return periods. Flood forecasting techniques range from a relatively simple approach using
graphical methods to sophisticated procedures requiring the use of fast processing computers.
I. Risk-based Methods
Recent trends in design of minor and major structures are towards the use of economic risk
analyses rather than frequency-based designs. The risk method selects the structure size as that
which minimizes total expected costs. These are made up of the structure costs plus the potential
flood losses associated with the particular structure. The principles are illustrated in the Fig 11.8.
Minimum allowable
structure size, based on
Average annual cost US$
Structure cost
Risk cost
(flood damages)
Fig 0.9 Principles of economic risk analysis for structure size selection
Source: (USFHA, 1981)
The total expected cost curve is the sum of the other two curves. Risk cost (flood damages,
structure damages, road and bridge losses, traffic interruptions) and structure costs are estimated
for each of several sizes. The optimal size or design is that with the smallest sum. Structures
selected by risk analysis are normally constrained to sizes equal to or larger than those resulting
from traditional frequency-based methods.
1. Estimating the Probable Maximum Precipitation (PMP) and determining the associated flood
flow rates and volumes by transforming the precipitation to runoff.
2. Determining the Probable Maximum Flood (PMF) by determining the PMP and converting it
to a flood by application of a rainfall-runoff model, including snowmelt runoff if pertinent.
3. Examining the flood plain and stream to identify fast-flood evidences such as high-water
marks, boulder marks on trees or banks, debris lines, historical accounts by local residents, or
geologic or geomorphologic evidences.
4. In some cases, the critical event method involves estimating the magnitude of the 500-year
event by various frequency or approximate methods. Often, such as in mapping floodplains,
the 500-year flood is estimated as a multiple of the 100-year event, ranging from 1.5 to 2.5.
Due to lack of longer-term records, frequency-based estimates are seldom attempted for
recurrence intervals exceeding 500 years.
Traditional flood defense methods, which revolve around finite flood measures, have been found
to be inadequate. This inadequacy is mainly due to the fact that they are capable of only reducing
the frequency of flooding while the risk of flooding remains. It is also impossible to eliminate
flooding risks using finite methods only. It has been realized that using a combination of flood
defence measures (Khatibi and Haywood, 2002) is more effective than a single one.
The foremost defense mechanisms used are finite measures, maintenance programs, development
control and flood forecasting and warning services. Flood warning systems are needed to reduce
the risks of flooding incidents associated with partial finite measures. Integrating flood
forecasting and warning systems in the finite methods increases their sustainability. New flood
forecasting models are incorporating the proportion that other defence mechanisms contribute to
the final outcome. This has made it possible to incorporate flood forecasting and warning services
in the flood management measures.
Conventional economic analysis methods use an assessment of whether the loss prevented is
sufficiently large enough to justify protection costs. This requires the determination of risk-stage-
damage relationships with hydrological flood frequency analyses as the starting points and a
frequency distribution curve of damage as the end product. The costs of potential flood damage
should include the estimated cost of restoration to pre-flood conditions and capitalized loss of
income.
Secondary benefits from flood mitigation arise from activities that stem, use, or process products
and services directly affected by floods.
In general, the steps involved in the design of a flood mitigation project are,
a) Estimating the project design flood and flood characteristics of the area
b) Define the areas to be protected, and on the basis of a field survey, determine the flood
damages which can be expected at various stages.
c) Determine the possible methods of flood protection where reservoirs or floodways are
considered feasible selected sites and determine the physical characteristics of these sites.
d) Design the necessary facilities for each method of mitigation in sufficient detail to allow cost
estimates and an analysis of their effect on flood flows.
e) Select the facilities or combination of facilities that offer the desired protection at minimum
cost.
f) Compare the cost and benefit of the project to determine whether the project is economically
justifiable.
g) Prepare a detailed report outlining the possibilities explored, the protection recommended,
and the degree of protection that will be provided. (Linsely and Franzini,1979, Arora,2007)
Summary
The inundation of normally dry land by a stream overtopping its banks is known as flooding. It is
a natural periodic event in the history of any river. In this chapter, the different causes of
flooding, the World’s largest floods, flood destruction and flood related losses in different parts of
the World are discussed. Methods of mitigating floods include structural and non- structural
measures. Extensive structural methods act on the watershed and include increasing vegetation
cover, control of soil erosion, while intensive structural measures act on the river and include the
construction of levees, floodwalls and channel improvement, construction of reservoirs and the
diversion of flow. The non structural measures include flood plain management, flood proofing,
flood warning systems, insurance and forecasting. The combined use of the various methods is
quite economical and effective in mitigation measures.
References:
Further Reading
2. Dingman, S.L., Physical Hydrology, Prentice Hall, 1994, New Jersey, USA
3. Serrano, E.S., Hydrology for Engineers, Geologists and Environmental Professionals, Hydro
Science Inc, 1997, Lexington, Kentucky, USA.
4.
5. Watson, I.C., Burnett, A.D., Hydrology A Environmental Approach, Buchanan Books, 1993,
Florida, USA.
Questions
1. Discuss the major causes of flooding.
2. Gives examples of the damage that floods cause.
3. Compare structural and non structural flood mitigation measures.
4. There are two types of reservoirs. Mention and distinguish between them.
5. Discuss the following: i) flood proofing ii) flood failure in buildings.
6. Develop a flood emergency plan for a flood prone area of your choice.
12 FLOOD ROUTING
12.1 Introduction
Since ancient times, civilizations have always developed along rivers. This proximity to water
courses guaranteed man access to the sea coast, irrigation for crops, water supplies for urban
communities and more recently, power development and industrial water supply. Despite the
many advantages of being near rivers, there has always been the risk of flooding. In the past,
levees or flood banks were built along the main rivers to prevent inundation in the flood season.
In more recent times, storage reservoirs have been built as the engineering principles of dam
construction became better understood. Other flood mitigation measures like relief channels,
storage basins and channel improvements are continually being put in place, all over the world. It
is important for such works that estimates can be made of how the measures proposed, will affect
the behaviour of flood waves in rivers so that economic solutions can be found in particular cases.
Flood routing is the description that applies to this. It is a procedure through which the variation
of discharge with time at a point on a stream channel can be determined by consideration of
similar data for a point upstream. In other words it is a process that shows how a flood wave can
be reduced in magnitude and lengthened in time (attenuated) by the use of storage in the reach
between the two points.
In this chapter we shall concern ourselves with lumped flood routing, whereby the flow is a
function of time alone at a particular location. This is distinguished from distributed flood
routing, whereby the flood is calculated as a function of time and space throughout the system.
Routing by lumped system methods is called hydrologic routing and is based on the equation of
continuity, whereas routing by distributed system methods is called hydraulic routing and is based
on the St. Venant’s equation of motion of unsteady flow, or the dynamic wave equation. The
two main categories of lumped flood routing are reservoir routing and channel routing (Chow,
1988, Subramanya, 1994).
The storage function is a simple relation between storage and discharge or between storage and
inflow and discharge as shown in Eqs 12.2.
S = f (Q )
(12.2)
S = f (Q , I )
If the flow in a channel were always uniform (surface parallel to the bed) or, less restrictively, if
the slope of the surface in a given channel reach were a function only of the outflow or inflow or
some constant combination of these, then the storage in the reach would be uniquely determined
by the discharge, the inflow or the prescribed combination of discharge and inflow. However, this
is not the case during the passage of a flood wave; for a given discharge at the lower end of a
river reach, the slope of the surface within the reach will be greater during the passage of the
discharge which is diminishing upstream i.e. after the passage of the peak.
Before the peak of the flood, I will be greater than Q and thereafter I will be less than Q .
Consequently, for the same downstream discharge Q , the inflow will be greater and the profile
higher before the peak discharge than they will be after it. If the storage in the river reach is
plotted as a function of Q , a hysteresis loop will result. In an attempt to allow for this effect,
storage is sometimes expressed as a function of Q and I , but this alone may be insufficient,
particularly where the discharge is varying rapidly along a river. In these circumstances the
storage cannot adequately be represented by any constant combination of the flows at either of
the reach in question (Nash, 1983).
translation
attenuation
I, Q
I-Q outflow
t
Inflow
t
Fig 0.1b The difference between inflow and outflow.
S
Fig 0.1c The mass curve for storage in a river reach or reservoir
When the water level in the reach is almost horizontal, as in a reservoir, this effect is less
pronounced and hence we distinguish between reservoir and channel routing according to
whether the storage is expressed as a function of the discharge alone or of the discharge and
inflow combined. Figs 12.2a to 12.2c illustrate the general principles of flood routing as applied
to a river reach or a reservoir (Wilson, 1996, Chadwick and Morfett, 1986).
S = f (Q )
Assuming that we are given an inflow hydrograph I (t ) and required to produce the corresponding
discharge hydrograph Q (t ) we can precede as follows:
Let this inflow hydrograph be given at equal intervals ∂ t (one hour, one day, etc.) as I1 , I2 , I3
…………. and assuming knowledge of Q1 the initial condition, we may write approximately;
∂t
[ I1 − Q1 + I 2 − Q2 ] = S2 − S1 (12.3)
2
∂t
( I1 + I 2 − Q2 ) + S1 = S2 + ∂t.Q2 /2……… (12.4)
2
The right hand side contains two unknowns but these are related. If, therefore, we prepare a curve
∂t
of S + ( )Q as a function of Q , as shown in Fig 12.3 we may enter the abscissa with the left
2
hand side of Equation (12.4) and obtain Q2 on the ordinate.
Having found Q2 the calculation can be taken over the second time interval to obtain Q3 and so
on.
For a single reservoir, the discharge will continue to increase, while the inflow exceeds the
discharge and hence the peak of the discharge will occur simultaneously with the point at which
the falling inflow equals the discharge. ∂t should therefore be taken sufficiently small to define
the inflow and discharge with sufficient accuracy. No other restriction is implied (Nash, 1983).
S
δt
S+ Q
2
t Storage relationships
Fig 0.3 Discharge
Other methods commonly used are the Modified Puls Method and the Goodrich Method, which
are based on Equation 12.1 and can yield similar results to the above method.
Example 12.1
A reservoir has a constant plan area of 5.4 hectares and a spillway length of 13.2m. The
discharge, Q(m3 / s) over the spillway is given by the formula;
Q = 1.6BH 3 2 (12.5)
Where B is the length of the spillway and H is the head of water above the spillway crest, both
measured in metres, with values of H varying between 0 and 1m. After a period of dry weather
with no inflow to the reservoir, the water level is at crest level. Heavy rainfall then causes the
inflow to the reservoir to increase linearly from 0 to 12m3/s in 45 minutes to maintain this peak
flow value for 37.5 minutes and then to decrease linearly to 0 in a further period of 30 minutes.
a) Determine the values at 7.5 minute intervals of the outflow from the reservoir, and thus
determine the maximum water level in the reservoir.
b) Sketch the inflow and outflow hydrographs on one diagram and explain the significance of the
point where the two hydrographs intersect.
Solution a)
First determine the outflow storage relationships by assuming ~ 5 regular intervals of H, except
for the first one, where there is an extra value required (because of the closeness of the curves)
and obtain the values as shown in Table 12.1.
where;
− A = reservoir area, H = head of water above spillway crest
− Graphs of Q vs S and Q vs S + Qdt/2 are then plotted on the same axes as shown in
Fig 12.4.
The Reservoir Routing Table 12.2 is then generated. The time intervals and inflows are given and
the initial outflow O1, hence storage S1, is assumed zero. Values of Q2 and S2 are obtained from
Fig 12.4 after reading off values of S + Qdt/2, which as shown in Equation 12.4, is equivalent to
the last column in Table 12.2. The process is repeated for the next time interval to obtain Q3 and
S3. In general, for any value in the last column of Table 12.2, the corresponding values of storage
S and outflow Q can be read off from Fig 12.4.
Fig 0.4 Discharge storage relationships for Example 12.1
12
10
Flow (m3/s)
8 Inflow hydrograph
Outflow hydrograph
6
0
0 20 40 60 80 100 120
Time (min)
Fig 0.5 The inflow and outflow hydrographs for Example 12.1
Solution b)
The inflow and outflow hydrographs are shown in Fig 12.5. The point where the two hydrographs
intersect is that where the outflow hydrograph has reached a peak, the inflow and outflow are
equal and there is maximum storage in the reservoir.
6,000
5,000
Dis c harges (m3 /s )
4,000
3,000
2,000
1,000
0
Mar-74
A pr-74
May -74
Jul-74
Sep-74
Oc t-74
Nov -74
Dec -74
Jan-74
Feb-74
Jun-74
A ug-74
Inf low
Routed Outf low Months
A c tual Outf low
Fig 0.6 Reservoir routing for the year of Minimum Inflow (1974)
Flo w Hy d r o g r a p h s f o r t h e Y e a r o f A v e r a g e In f lo w ,1 9 6 9
3 ,5 0 0
3 ,0 0 0
2 ,5 0 0
Dis c harges (m3 /s )
2 ,0 0 0
1 ,5 0 0
1 ,0 0 0
500
0
Jan-69
Feb-69
Oc t-69
Mar-69
A pr-69
Jun-69
Jul-69
Sep-69
May -69
A ug-69
Nov -69
Dec -69
In f lo w
Ro u te d O u tf lo w Mo n th s
A c tu a l O u tf lo w
Fig 0.7 Reservoir routing for the year of Average Inflow (1969)
12.4Channel Routing
In this case the storage volume is not a simple function of stage, and therefore solution of the
continuity equation is complex. These equations may be solved using the full equations of
gradually varied unsteady flow. However, as mentioned earlier there are simpler techniques
(hydrologic routing) which can be applied if previous inflow and outflow hydrographs have been
recorded. They are based on the Muskingum method (after McCarthy in 1938).
WEDGE STORAGE
I
y1
PRISM STORAGE
yo
Q
Channel storage may be considered to consist of two parts, prism and wedge storage, as shown in
the Fig 12.8. If we assume there is no sudden change of cross section with the reach, then
approximate expressions for inflow, outflow and storage are
b c c
S = Q− Q+ I (12.10)
a a a
or
b c c
S = ( I + Q − Q)
a b b
Taking K = b / a and x = c / b
S = K ( xI + Q − xQ ) (12.11)
= K [Q + x ( I − Q )]
where K is called the storage constant and has dimensions of time and x is a dimensionless
weighting factor between 0 and 0.5 (but normally between 0.2 and 0.4).
Equation (12.11) is the Muskingum Equation. It is an approximation, but has been used widely
with reasonable results. (Chadwick and Morfett, 1986).
S = K [ xI + (1 − x )Q ] (12.12)
With known values of K and x the outflow Q from the reach can be obtained by combining and
simplifying equation,
I1 + I 2 Q1 + Q2
t− t = S2 − S1 (12.13)
2 2
and
I1 + I 2 S2 − S1 Q1 + Q2
= + (12.14)
2 t 2
I1 + I 2 K [ x( I 2 − I1 ) + (1 − x)(Q2 − Q1 ) Q1 + Q2
= +
2 t 2
Kx Kx (1 − x) (1 − x)
• I1 (0.5 + ) = I 2 (−0.5 + ) + Q1 (0.5 − K ) + Q2 (0.5 + K )
t t t t
Is obtained, where
Alternatively, the following theoretical/graphical method may be used. From Equation (12.12)
dS dI dQ
= Kx. + K (1 − x) (12.17)
dt dt dt
at the point, where the inflow and outflow hydrographs intersect, I is equal to Q and storage
within the valley attains its maximum value, thus dS dt = 0 . Consequently, the ratio of the
tangents to both hydrographs at the point of their intersection is:
dI dQ
= ( x − 1) / x (12.18)
dt dt
This graphical technique is quite demanding and Cunge (1969) presented a simpler approach,
known as the Muskingum-Cunge method. He demonstrated that K is approximately equal to the
time to travel of the flood wave i.e.
K ≈ ΔL c (12.19)
Where Δ L is the length of the river reach and c is the flood wave celerity.
Qp
x ≈ 0.5 − (12.20)
2So BcΔL
where Qp is the mean flood peak and B is the mean surface width of the channel.
Using these equations allows rapid calculation of K and x and the Muskingum-Cunge method
may also be applied to rivers without recorded outflow hydrographs.
In both the Muskingum and Muskingum Cunge procedures, the assumption is that there is no
lateral flow to the river reach between the upstream and downstream gauging stations. This
implies that the routing procedures can only be applied to short sections, which terminate at
tributaries, or tributary inflows should be added to main channel flow term. Subsequently, a
second modified Muskingham method was developed (O’Donnell, 1985) that takes into account
lateral inflow. It has the further advantage that i) it replaces the trial and error method for the
estimation of K and x parameters by a numerical best fit technique and ii) because it treats the
river as a whole, it avoids multiple routings over many sub reaches. This approach assumes that
the total rate of lateral inflow is proportional to the upstream inflow rate. The proportionality
constant, α, is assumed constant for any one event and takes different values for different events.
The three coefficients C0, C1 and C2 can be related to K, x and α and vice versa.
Example 12.2 (after Dake, 1983)
Agricultural land in a valley is to be protected against floods; the hydrograph for a possible dam
site located 36hrs crest travel time, upstream is given. If the required flood reduction at the
farmland is 40%, determine the minimum storage capacity due to the dam. Take x = 0.15. The
layout of the site is shown in Fig 12.9.
I Q
B
A
Farmland
Solution:
i. First calculate the subsequent outflow, Q at the farmland without the dam
ii. The resultant peak flood at the farm should be reduced by 40%
iii. The excess flow must then be stored by the dam.
Given the inflow hydrograph at A, K = 36hrs (Travel time). The inflow series has a time step of
dt = 12hr. The routing coefficients are calculated using Equation 12.16 as follows:
Check
C0 + C1 + C2 = 0.02 + 0.31 + 0.67 = 1
The coefficients are checked whether they add to unity and then they are applied in the
Muskingum equation. The outflows (without the dam) are calculated as shown in Table 12.3. It
is assumed that initially, the inflow, I is equal to the outflow, Q = 42m3/s. The routed outflow is
shown in the last column. Fig 12.10 shows the plots of the inflow and the routed outflow
hydrographs.
Q2 = Co I 2 + C1 I1 + C2Q1
We obtain a peak outflow after routing of 231.1 m3/s. It is required to reduce this flow by 40%
(to 138.7 m3/s). The excess flow (shaded area) should be stored by the dam. The reservoir
capacity of this dam is approximately 21 x 106 m3.
342 Inflow
350
Outflow without the dam
300
Discharge (m /s)
250 231.1
3
200
Stored volume
150
138.7
100
50
0
0 25 50 75 100 125 150 175 200 225 250
Time(hr)
Example 12.3
Table 12.4 gives the inflow and outflow hydrographs measured for a given river reach. Determine
the values the storage constant, K and the weighing factor x of the Muskinghum routing model
for this river
Time (h) Inflow Outflow (m3/s) Time (h) Inflow (m3/s) Outflow (m3/s)
(m3/s)
1 50 50 11 750 731
2 100 53 12 680 734
3 200 79 13 590 707
4 325 136 14 500 653
5 450 221 15 420 586
6 600 324 16 350 514
7 700 443 17 300 444
8 780 553 18 250 382
9 790 646 19 225 323
10 775 704 20 200 284
Solution:
To Obtain Estimates of x and K
The general Muskingum storage equation is given as S = K [ xI + (1 − x )Q] . To obtain
estimations of x and K, the values of ΔS are plotted against the corresponding K [ xI + (1 − x ) Q ]
values and the value of x is determined by trial and error until the plotted graph gives
approximately a straight. The computations of ΔS and K [ xI + (1 − x ) Q ] are performed as shown
in the Table 12.5.
Three trials were made with x = 0.3, 0.2 and 0.15 as shown in Fig.12.11. The third trial x = 0.15
was selected since it approximates a straight line.
Therefore X = 0.15. The value of K is the slope of the line which is approximately 8264 sec =
2.3hrs.
6000
5000
Storage, Sx 1000 (m )
3 4000
3000
2000
1000 x= 0.3
0
0 200 400 600 800
6000
5000
Storage, Sx 1000 (m )
3
4000
3000
2000
1000 x= 0.2
0
0 200 400 600 800
6000
5000
Storage, Sx 1000 (m)
3
4000
3000
2000
1000 x= 0.15
0
0 200 400 600 800
[x.I+(1-x)Q], (m3/s)
and
dH
= I (t ) − Q( H ) = F (t , H ) (12.22)
dt
Using initial conditions for time, inflow, outflow, elevation and storage and routing in time steps
of ∆t, the elevation H at the (i+1)th step is given by
1
H i +1 = H i + ( K1 + 2 K 2 + 2 K3 + K4 )Δt (12.23)
6
Where K1 = F (ti, Hi )
K2 = F(ti +Δt 2, Hi +1 2 K1Δt)
K3 = F(ti +Δt 2, Hi +1 2 K2Δt)
K4 = F(ti +Δt 2, Hi + K3Δt)
Beginning with initial conditions and knowing Q vs. H and A vs H , a hydrograph may be
routed by selecting Δt at any time t = (to + iΔt) the value of Hi and the coefficients
K1, K2 , K3, K4 are determined by repeated evaluation of the function F (t , H ) . With the values
of H i.e. H (t ) at various intervals, Q ( H ) and S ( H ) can be calculated.
Summary
Despite the many advantages of being near rivers, there has always been the risk of flooding. In
the past, levees or flood banks were built along the main rivers to prevent inundation in the flood
season. In more recent times, storage reservoirs have been built as the engineering principles of
dam construction became better understood. In order to design them appropriately, it is necessary
to be able to predict the impact of the storage on a flood wave. To do this it is necessary to
employ the techniques of reservoir flood routing and channel routing, which show how the peak
of a flood is attenuated and delayed for a reservoir and channel respectively. These techniques are
discussed together with examples and recent studies.
References
1. Carnahan, B.,Luther, H.A.,Wilkes,J.O., Applied Numerical Methods, Wiley, 1969, New
York, USA.
2. Chadwick, A., Morfett ,J., Hydraulics in Civil Engineering, Chapman and Hall, 1986,
London, UK
3. Chow, V.T., Maidment, D.R., Mays, L.W., Applied Hydrology, McGraw-Hill, 1988, New
York , USA.
4. Cunge, J.A., On the Subject of a Flood Propagation Method, Journal of Hydraulics
Research, IAHR, Vol 7, 1969, pp205-230. London, UK.
6. Nash, J.E. Deterministic Hydrology, University College Galway, 1983, Republic of Ireland.
8. Rugumayo, A.I., Kayondo,D.K., Flood Analysis and Mitigation on Lake Albert Uganda.
Advances In Geo-Sciences Vol 4 Hydrological Sciences, World Scientific Publishing 2006,
Singapore.
9. Subramanya, K., Engineering Hydrology, Second Edition, Tata McGraw Hill, 1994, New
Delhi, India.
10. Wilson, E.M., Engineering Hydrology, 4th Edition, Macmillan, 1996.London, UK.
Further Reading
1. Alexander, W.J.R., Flood Hydrology in Southern Africa, The South African Committee on
Large Dams, 1990, Pretoria, South Africa.
4. Dingman, S.L., Physical Hydrology, Prentice Hall, 1994, New Jersey, USA.
5. Featherstone, R.E., Nalluri, C., Civil Engineering Hydraulics, Essential Theory and
Examples, 1982, Granada Publishing, London, UK.
6. Serrano E.S., Hydrology for Engineers, Geologists and Environmental Professionals, Hydro
Science Inc, 1997, Lexington, Kentucky, USA.
Questions
1. A reservoir has a constant plan area of 5.56 x 106m2. Discharge from the reservoir takes
place over a spillway the characteristic of which is Q= 135H3/2. Storm run-off entering
the reservoir is estimated at the following figures.
Time (h) 0 6 8 10 12 14 16 18 20
3
Run-off (m /s) 0 113 170 283 226 170 113 57.5 0
It is noted that at 12 h the head H over the spillway is 0.813m and the reservoir surface level
is still rising. Estimate how much further the level will rise. Sketch the general shape of the
outflow hydrograph and explain what is meant by the lag effect of the reservoir.
The dam of the reservoir has a spillway 61m long (coefficient 2.21m1/2/s), and a culvert (ground
sluice) with its centre line 30.5m below crest level. At time zero the water level in the reservoir
was just at crest level.
Estimate
(a) the maximum discharge through the culvert, if the water is never to rise more
than 30.5cm above the crest;
(b) the size of the culvert, assuming it acts as a simple orifice, Cd = 0.64;
3. Describe the continuity function of hydrolic routing and define the terms in the
equation
4. Derive the Muskingum equation for flood routing in a river basin. Explain clearly the
significance of the factors x and K and indicate how they can be estimated.
The inflow hydrograph for a reach of a river is given below. Find the peak of the outflow
hydrograph and its time of occurrence if K = 1.5 days and x = 0.25 for the reach. Plot the
complete inflow and outflow hydrographs for the given flood. Assume that the outflow
from the reach is equal to the inflow at the start of the flood.
Date Hour Inflow(m3/s)
12 July 1200 52
13 July 0600 52
1200 55
1800 66
14 July 2400 100
0600 161
1200 256
1800 362
15 July 2400 343
0600 321
1200 299
1800 276
16 July 2400 249
0600 224
1200 209
1800 198
17 July 2400 176
1200 142
18 July 2400 121
1200 79
2400 73
5. The table below gives the inflow and outflow hydrographs for a reach of a river. Determine
the Muskingum factor K for the reach if x has been estimated fairly accurately to be 0.20. How
does your value compare with the time lag between inflow and outflow peaks?