Thengwe Minutes of Progress Review Meeting 23
Thengwe Minutes of Progress Review Meeting 23
Thengwe Minutes of Progress Review Meeting 23
02 August 2021
National Department of Health
1629 - Limpopo Clinics - New Thengwe Clinic
Minutes of Project Progress Review Meeting No. 23 – 02 August 2021
Apologies:
Name Abb Organisation Role Email Mobile
Thabiso Maungwa TM NDOH Project Manager tkmaungwa@gmail.com 073 718 4491
10 Denver Seetal DS LDM Civil/Struc. Engineer denver.seetal@gmail.com 082 314 7700
Charles Mateketa CM TTA Foreman charlesmateketa@gmail.com 073 822 2938
Owen Chitonho OC TTA Project Manager owen@ttamail.co.za 072 376 3062
Eduan Naude EN TUSK/TTA Contracts Support eduann@tuskcss.co.za 083 263 9992
Kemis Magavhe KM TTA Foreman kemismagavhe@gmail.com 083 521 1797
Bethwel Matlopela BM TTA Member bethwel@ttamail.co.za 082 819 2749
Edison Rakhadani ER Community CLO edisonrakhadani@gmail.com 079 806 8959
Ndou Avhapfani NA Community Community 076 636 9605
Gilbert Nethengwe GN Community Traditional Council nethengwens@gmail.com 082 621 2128
T.P Nethengwe TPN Clinic Rep Community Thichalemi12@tmail.com 072 216 9381
11 Date of Next Meeting: 30 August 2021
12 Distribution: See item 8, 9 & 10 above.
14 Prepared by: Yolander Granger
15 Date: 06 August 2021
PAGE NO. 1
National Department of Health
1629 - Limpopo Clinics - New Thengwe Clinic
Minutes of Project Progress Review Meeting No. 23 – 02 August 2021
SECTION B : MINUTES
Item Description Who When
1 Welcome & Introduction
1.1 The meeting was chaired by ER who welcomed all to the Note
meeting. ER noted that due to the current COVID-19 and OHS
regulations the structure of meetings going forward will entail
Site inspections only followed by a Microsoft Teams meeting to
detail progress on site as well as follow up on action items. ER
further explained the use of the ‘raised hand’ icon to be
utilised if/when the need to interject or add to a matter been
discussed.
1.2 ER noted that the meeting would be recorded to ensure Note
accurate capturing of the meeting minutes – there were no
objections raised and was accepted by all.
Meeting recording link –
https://web.microsoftstream.com/video/a4d18efd-da63-4453-
9814-52d616896ca3
PAGE NO. 2
National Department of Health
1629 - Limpopo Clinics - New Thengwe Clinic
Minutes of Project Progress Review Meeting No. 23 – 02 August 2021
PAGE NO. 3
National Department of Health
1629 - Limpopo Clinics - New Thengwe Clinic
Minutes of Project Progress Review Meeting No. 23 – 02 August 2021
5 Site Matters
5.1 A Site Survey was completed and shared with all. SI was Note
issued for TTA to commence works, this also included remedial
works to be attended to as per CE/SE SI.
5.2 TTA removed the Surface Bed Steel Mesh and DPC as SI TTA Done
issued
5.3 GM noted that the stub columns at the ACUTE and CHRONIC Note Done
CARE are ready to be casted and requested approvals from SE,
of existing works/ installations, in order to proceed.
5.4 GM noted a problem with the Hold Down Bolts at the CENTRAL Note Done
AREA and requested assistance from the SE in order to resolve
the matter
5.5 GM noted that the materials for the Elevated Water Tank is on Note
site and that TTA requires the drawings for the layer works
under the proposed surface bed/slab in order to continue the
works.
SE to issue drawing design for the Water Tank, once ME SE Done
specification is completed
5.6 Arch/SE noted that the paving and apron details and Note Done
measurements are to be executed as indicated on latest
revised drawings.
5.7 GM submitted a rate for the cavity wall door frames to LDM TTA Done
5.8 GM submitted a rate for the cavity wall Fire door frames to TTA Done
LDM
5.9 The project RFI schedule was issued. TTA Done
5.10 Refer to Item 8.3 below Note Done
5.11 GM noted that there was a further EOT to come with regards Note Done
to the standing time since February 2019.
5.12 SE has issued an SI of the following: SE Done
- Surface Bed must be ripped and re-compacted,
- Soil Poisoning to be redone,
- Steel fixing to proceed.
5.13 It was indicated that the brickwork at the courtyard is to be Done
executed as per drawing
5.14 TTA to provide shopdrawings for water storage tank to ME for TTA Done
approval
5.15 QS advised that the drainage pipe material must be uPVC as Note
installed
PAGE NO. 4
National Department of Health
1629 - Limpopo Clinics - New Thengwe Clinic
Minutes of Project Progress Review Meeting No. 23 – 02 August 2021
PAGE NO. 5
National Department of Health
1629 - Limpopo Clinics - New Thengwe Clinic
Minutes of Project Progress Review Meeting No. 23 – 02 August 2021
5.24 Arch to issue fullbore outlet detail on deck/slab at MOU Arch Done
5.25 TTA queried how the brickwork at the dispensary will join the Arch Done
steel column. Arch responded as follows: Brickwork to be
taken to the steel column. Allow for softboard joint between
brickwork and steel
5.26 TTA requested pumphouse construction drawings from Arch Arch Done
5.27 TTA advised that there are issues with the manufacturing of TTA Note
lintels, however, they are expecting delivery of some of them
in the coming week
5.28 ER highlighted that the lintels should not be left lying around TTA Done
on site and should be protected and stored to avoid possible
rusting (this applies to all materials in general)
5.29 TTA to prepare plaster sample on bleeding bricks – a specific TTA Done
wall has been marked out. ER requested TTA to constantly
water the plaster panel and to send photos to ER/Arch daily –
Arch has accepted the plaster sample
5.30 SE to issue SI – circular slab to sit flush with columns and not SE Done
centre as indicated on the drawings
5.31 TTA noted that there is a discrepancy in the window schedule Arch Done
vs elevation drawings at the MOU – Arch to revert back
5.32 TTA to provide methodology as to how the rusted frames will TTA Done
be made good. Arch noted that the painted door frames that
have not been prepared properly have been rejected
5.33 TTA requested the base detail for the pumphouse SE Done
5.34 ME raised concern that quotations for the pumps and TTA Done
purification plant have not been submitted. As there are
usually long lead times for these items. TTA to submit
quotations for ME to review urgently
5.35 TTA requested Arch and all Engineering to reissue drawing Arch/ME/CE/SE/EE Done
registers. TTA further requested soft copies of drawings issued
must have a hard copy delivered to site at the next site
inspection
Arch requested all latest revisions of drawings (and room data TTA Done
sheets) on site to be emailed for all disciplines – Arch to email
list of outstanding drawings, TTA to coordinate with Arch when
Arch visits site
5.36 Arch to review and provide feedback on samples, etc. for the Arch Done
aluminium shopfronts – approved, alternate hinges were
provided and approved. Arch noted that the manufacturing of
all shopfronts must be in accordance with on site
measurements
5.37 TTA queried the VO that was submitted for the aluminium Note
shopfronts. YG noted that at the last site inspection it was
agreed that rates will be used in the BOQ for windows and
shopfronts of similar sizes – an average rate per m2 will not be
applied and that TTA have been given the instruction to
proceed with the procurement thereof
5.38 TTA requested Arch to respond to RFI – storeroom at MOU Arch Done
(omission of door)
5.39 MS noted that an RFI was submitted – Arch Done
1. 150 x 150mm wall tile was not available; however,
they have now been able to source said tile
2. Confirmation of specification of vinyl floor and floor
tiles -Arch to respond accordingly
5.40 MS requested Arch to issue changes to central area i.e. Arch Done
drawings indicating the louvres/windows, etc. – Arch to
forward drawings accordingly
PAGE NO. 6
National Department of Health
1629 - Limpopo Clinics - New Thengwe Clinic
Minutes of Project Progress Review Meeting No. 23 – 02 August 2021
PAGE NO. 7
National Department of Health
1629 - Limpopo Clinics - New Thengwe Clinic
Minutes of Project Progress Review Meeting No. 23 – 02 August 2021
PAGE NO. 8
National Department of Health
1629 - Limpopo Clinics - New Thengwe Clinic
Minutes of Project Progress Review Meeting No. 23 – 02 August 2021
7 Sub-Contractors
7.1 Trade Name Status
Plumbing and Tshilangano Appointed
Drainage Construction
Building Works Frocon Projects Appointed
Building Works RMI Building Appointed
Construction
Building Works Netshitungulu Appointed
Building Works Ezomdeni Projects Appointed
PAGE NO. 9
National Department of Health
1629 - Limpopo Clinics - New Thengwe Clinic
Minutes of Project Progress Review Meeting No. 23 – 02 August 2021
8 Contractual Matters
8.1 GM submitted all contractual documentation to LDM TTA Done
8.2 TTA forwarded the confirmation of the Insurance Policy to TTA Done
LDM.
8.3 NDOH reviewed and conclude all outstanding/existing EOT NDOH Done
claims.
8.4 GM noted that the VO on the plumbing material changes is still Note Done
pending and require approval to proceed.
8.5 ER reiterated and noted that he (Edward Rothwell) is the Note
appointed Principal Agent on the project. This was accepted by
TTA
8.6 TTA noted that the notice of dispute that was issued is TTA Note
withdrawn
PAGE NO. 10
National Department of Health
1629 - Limpopo Clinics - New Thengwe Clinic
Minutes of Project Progress Review Meeting No. 23 – 02 August 2021
8.7 OC noted that ER’s rejection of the notification of delay is not Note
necessary as a Contractor can submit a notification of delay
and only once a claim has been submitted can a PA then
reject. ER responded that he was rejecting the basis of the
notification as it was incorrect and not relevant
8.8 TTA to submit NOD’s and EOT claims as the approved PC date NDOH Done
is 26 February 2021 which will not be achieved – ER noted
that a recommendation has been submitted for EOT 17 has
been approved 14 days have been granted without cost; EOT
18 is with NDOH awaiting their feedback
TM expressed his concern that TTA are not submitting Note
notification of delays timeously which have been affecting the
critical path, which will result in penalties being imposed an
further cashflow challenges
PAGE NO. 11
National Department of Health
1629 - Limpopo Clinics - New Thengwe Clinic
Minutes of Project Progress Review Meeting No. 23 – 02 August 2021
December’s certificate
9.11 ER encouraged TTA to submit quotations timeously so that TTA Done
VO’s can be approved in order to avoid any further delays in
the programme due to late procurement of materials
9.12 TM noted that a response to EOT on 20 March 2020 – TM Done
approved
9.13 TTA to submit Variation Order for COVID-19 compliance costs TTA Done
to the QS
9.14 QS noted that the borehole quotation has been approved Note
9.15 November’s claim to be submitted by 20 November 2020 TTA Done
9.16 ME/TTA to enquire on the borehole capacity and revert back ME Done
9.17 TTA to submit a rate build up/comparison from the tendered TTA Done
aluminium shopfronts and windows and the current schedule.
9.1.18 TTA to submit claim for plastic sheeting on roof TTA Done
9.1.19 TTA queried approvals on the following: Note
1. J Bolts – approved
2. Steel lintels – as per BOQ rate
3. Steel cleaning – rejected
4. Retaining wall – approved as per BOQ rates, market
related new rates provided
9.1.20 TTA to provide detailed breakdown/measures of queried TTA Done
variances between claim and payment certificate
9.1.21 It was noted that July’s claim has been submitted – valuation TTA 02/08/2021
thereof in progress
A request was made to ensure the timeous submission of the Ongoing
payment certificates and invoices to the Client – TTA to ensure
that their entire claim for the month is issued prior to the site
inspection meeting
9.1.22 TTA have submitted a VO for smooth formwork to be reviewed QS Done
by the QS
9.1.23 It was noted that MOS will be adjusted in line with the last site Note
inspection as there is a duplication in the valuation detail
9.1.24 TM noted that as a result of the new procurement regulations TM 06/08/2021
that have taken affect, SCM will be carrying the procurement
of the HCT. TM indicated that within a month the appointment
of the HCT should be finalised
TM added that procurement of services will be carried out by TM 06/08/2021
SCM; procurement of goods (selected sub contractors) will be
done through the Main Contractor. TM will forward the list of
returnables that will need to be included when going out to
tender i.e. BBBEE, CSD registration, etc.
10 Technical
10.1 Architect
10.1.1 Arch to set up meeting with all PSP’s in order to finalize co- All Ongoing
ordination.
10.1.2 Arch to prepare and update the project Sample Register Arch Ongoing
10.1.3 GM noted shopfronts was ordered. Arch requested sample for TTA 31/07/2019
PAGE NO. 12
National Department of Health
1629 - Limpopo Clinics - New Thengwe Clinic
Minutes of Project Progress Review Meeting No. 23 – 02 August 2021
approval
GM noted Shopfront sample is on site. Arch to inspect for Arch Done
approval.
Arch requested TTA to provide shopdrawings. TTA is awaiting TTA Done
the suppliers submission
10.1.4 TTA requested the detail for the Emergency Exit at MOU Arch Done
threshold by the double door
10.1.5 Arch highlighted that all services through face brickwork must TTA Refer to QCR
be cored to the correct diameter
10.1.6 Arch noted that TTA is to ensure that the underside of lintel(s) TTA Refer to QCR
and top of door frame(s) must be level – in progress
10.1.7 TTA are to highlight and get confirmation from Arch if there TTA Refer to QCR
any discrepancies between room data sheets and electrical
layouts – however in principal the room data sheet takes
precedence
10.1.9 Arch noted that the rejected Aluminium shop drawings were Arch Done
resent – TTA to correct and resubmit shopdrawings to Arch to
approve, submitted to Arch – Arch to revert back with
feedback/approval
10.1.10 Arch to forward missing page of sanitary schedule Page 5 to Arch Done
TTA
10.1.11 Arch requested TTA to submit method statement as to how TTA Done
cavities will be cleaned without damaging the dpc – in
progress
10.1.12 Arch noted that ‘damaged’ bricks cannot be used for Note
construction
10.1.13 Arch to forward insulation specification below the roof; and Arch Done
isoboard specification to central area.
10.1.14 EE noted that the DB duct size depths are smaller than TTA Done
specified. TTA to submit methodology as to how sizes will be
rectified – and TTA to rectify accordingly – done - Arch to
revert back with comments
10.1.15 Arch noted as a reminder that the planter boxes are to be Note
omitted
10.1.16 Arch noted that he will issue a sketch indicating the bib tap Arch Done
positions around the clinic
10.1.17 Arch noted that the main steel structure is rusting – TTA to TTA Done
submit methodology (namely at the plates and joints) and
ensure the cleaning, etc. is carried out in accordance prior to
painting
Arch to provide comments Arch Done
10.1.18 Arch noted that SE will issue specification for rectification of SE Done
cracked bases
10.1.19 Arch noted that he will issue the Contractor’s HT list in order Arch Done
for procurement to commence
10.1.20 Arch noted that he will issue all signage drawings, Arch Done
specifications, details, etc. TM requested Arch to contact the
clinic nurse/representative to confirm emergency numbers,
etc.
Quotations to be acquired. ER to follow up with TM regarding ER 16/08/2021
the procurement process
PAGE NO. 13
National Department of Health
1629 - Limpopo Clinics - New Thengwe Clinic
Minutes of Project Progress Review Meeting No. 23 – 02 August 2021
10.1.21 Arch noted that he will issue updated ceiling drawings – Arch Done
indicating trap doors, etc.
10.1.22 Arch noted that he will forward emails of information that were Arch Done
issued to Godwin to MS, to confirm that all information has
been received on site
10.1.23 Arch to respond to RFI regarding paint to walls specifications Arch Done
Arch noted that TTA is to be aware of executing work out of TTA Note
sequence as this may result in double work being carried out
10.1.24 Arch requested MS to provide dimensions i.e. height, levels, MS Done
length, etc. of the pedestrian entrance ramp from the road to
guard house as landings will be required for paraplegic access
compliance
10.1.25 TTA to submit shop drawings for Joinery i.e. cupboards, etc. – ER/ TTA 16/08/2021
Sub Contractor to be procured – ER to follow up with TM
regarding the procurement process
10.1.26 Arch noted that TTA have made provision for hydroboil points TTA Done
– an instruction was given that hydroboils are to be excluded.
TTA to close all hydroboil points
10.1.27 Arch noted that he has issued a revised HCT list which depicts Note
work to be carried out by HCT and TTA
PAGE NO. 14
National Department of Health
1629 - Limpopo Clinics - New Thengwe Clinic
Minutes of Project Progress Review Meeting No. 23 – 02 August 2021
10.2.5 ME issued 3 x hard copies of HVAC drawings and water tank Note
specification
10.2.6 ME noted that that TTA is to ensure that all drainage pipes are TTA Done
capped off so that rubble does not fall in
ME added that the drainage pipes in the ground have been
torched and as a result weakened the pipe and compromised
the integrity of the pvc – ME added that the pipes were to be
capped with either caps or plastic – in conclusion an
instruction has been given for all pvc pipes to be redone
10.2.8 TTA to submit ventilation quotation(s) for items on drawing TTA Done
not included in BOQ – approved
10.2.9 TTA noted that they will be submitting HVAC queries TTA Done
10.2.10 ME noted that any chased in coper pipes are to be wrapped. Note Done
10.2.11 ME highlighted that the piping at the MOU maternity sluice is TTA Done
incorrect (wrong sizes) and need to be installed as per the
latest plumbing drawings
10.2.12 ME noted that he is awaiting sample of external louvre to TTA Done
Maclaren ac units – square louvre was presented, however,
the round louvre will be installed
10.2.13 ME noted 50mm pipes chased in single skin brickwork to have TTA Note
mesh installed over opening before plastering
10.2.14 ME noted 110mm pipes cannot be chased in single skin walls, TTA Note
pipes must be installed below surface bed
10.2.15 ME noted some sleeves for ac units are very skew – TTA to TTA Ongoing
rectify – In progress
10.2.16 ME noted his concern on progress for both plumbing and TTA Ongoing
HVAC as no services have been installed in the roof space as
yet – NT responded that work will commence next week, in
progress, focus to be made on internal installation and
increase in resources
10.2.17 ME noted that the HVAC Sub Contractor informed him that MS Done
TTA are not allowing openings through brickwork. MS to
address accordingly and will provide feedback
10.2.18 ME confirmed with TM that all appointments – rfq’s etc. have Note
been concluded
10.2.19 ME noted that tests in the ceiling should be carried out in Note
sections as the plumbing is progressing very so link and as a
result the installation is being installed in links
PAGE NO. 15
National Department of Health
1629 - Limpopo Clinics - New Thengwe Clinic
Minutes of Project Progress Review Meeting No. 23 – 02 August 2021
PAGE NO. 16
National Department of Health
1629 - Limpopo Clinics - New Thengwe Clinic
Minutes of Project Progress Review Meeting No. 23 – 02 August 2021
10.3.5 EE noted that the lightning protection conduits are to be fixed TTA Note
in brickwork and installed prior to casting the surface bed slab,
this applies to the telecom sleeves to the server room
10.3.6 EE noted that all sleeves including the MOU and DB-D are to TTA Done
be installed as per drawings
10.3.7 EE highlighted that the floor boxes at the main reception TTA Refer to QCR
entrance has not been installed. TTA to action accordingly
10.3.8 EE noted that access control and electronics conduits are to be TTA Done
installed at doors, etc. as indicated on drawings
10.3.9 EE highlighted that the power outlets indicated on the data TTA Ongoing
sheets takes precedence over Electrical power layout drawing
10.3.10 EE noted that he will issue TTA with a tender list of Electronics TTA Done
Sub Contractor suppliers (done) for TTA to review and add to
the list. If there is no response from TTA by the end of the
week, it will be deemed accepted by TTA with no additions. EE
to proceed with going out to tender (an extension has been
given for TTA to provide supplier details to be included in the
tender process)
EE to commence tender process – currently out to tender – EE Done
instruction to appoint has been issued
10.3.11 EE highlighted that the two junction boxes that must be TTA Done
installed in the server room are only indicated on the
Electronics drawing
10.3.12 TTA to straighten all skew outlet boxes TTA Refer to QCR
10.3.13 TTA to ensure TV point is installed under slab TTA Done
10.3.14 EE issued the bed head ducting specifications. TTA to provide TTA Done
shop drawings – received, EE has provided comments,
awaiting amended shop drawings
10.3.15 Lightning protection supplier to submit soil resistivity test TTA Done
results – EE requested the credentials to be submitted
Awaiting soil resistivity test results and methodology as to how TTA 09/07/2021
they will execute the works, as the lightning protection
installation has commenced. Note any remedial work that may
be required will be at the cost to the Contractor
EE added that he has received the test results despite the
work not being completed, furthermore, a methodology was
not received and questions if the work is compliant – TTA to
respond accordingly in line with what has been formally
captured in the QCR (TTA noted that work will be re-done and
a new certificate will be issued; Sub Contractor to be present
at the next site inspection)
10.3.16 EE raised concerns that although there is roof plastic covering TTA Note
- the rain is still seeping through the plastic and falling on the
cable trays, baskets and power trunking that is being installed,
which will cause corrosion and result in the work being
defective and will have to be redone
10.3.17 EE noted that HVAC power points have not been installed and TTA Ongoing
first coat paint has been applied – TTA to action urgently
EE noted that he has received the credentials of the smoke Note
detection sub contractor and that they are to standard
10.3.18 EE requested TTA to give at least 5 working days’ notice prior TTA/EE Done
PAGE NO. 17
National Department of Health
1629 - Limpopo Clinics - New Thengwe Clinic
Minutes of Project Progress Review Meeting No. 23 – 02 August 2021
PAGE NO. 18
National Department of Health
1629 - Limpopo Clinics - New Thengwe Clinic
Minutes of Project Progress Review Meeting No. 23 – 02 August 2021
PAGE NO. 19
National Department of Health
1629 - Limpopo Clinics - New Thengwe Clinic
Minutes of Project Progress Review Meeting No. 23 – 02 August 2021
PAGE NO. 20
National Department of Health
1629 - Limpopo Clinics - New Thengwe Clinic
Minutes of Project Progress Review Meeting No. 23 – 02 August 2021
QS
10.6.4 Quantity and Quality of the “Clearvu” Fencing Materials was Note Done
verified
10.6.5 ER noted that the underground “JOJO” tank is currently being Note Ongoing
used by the contractor on site. Noted that the tank may need
to be replaced.
10.6.6 The quality of the MOS was discussed. It was noted that some Note
of the materials may no longer been suitable for use during
construction.
MOS to be inspected and unsuitable materials to be Quantified LDM Done
and Costed for submission to NDOH for possible VO
SE to provide feedback to QS for finalization SE/QS Done
10.6.8 TTA to submit reconciliation of condemned material TTA Close
10.6.9 TTA queried the certificate numbers as the last issued Note
certificate from the previous PSP was certificate 16 and the
latest certificate issued by LDM is 20. ER advised that the
negative certificates of same value have been issued monthly
over the past three months
10.6.10 TTA submitted RFI – BOQ for retaining wall QS Done
TTA to provide quotations – QS to issue approval – Approved TTA Done
as per market related rates provided and BOQ rates
10.6.11 TTA to provide detailed breakdown for proposed new rate for TTA Done
lintels
10.6.12 ER to adjudicate and provide a fair cost for the cleaning of the ER N/A
steel
10.6.13 OC requested feedback from ER with regards to the TTA 19/07/2021
information submitted justifying the extent of the bulk
earthworks – ER noted that he will respond formally via email
but still requires more information i.e. contract instructions
issued, or correspondence between previous PSP and TTA
11 Client Matters
11.1 EL presented the Project Issues to the Community Note
11.2 TM advised that payments for payment certificates will be TM Note
processed from 1 April 2020
12 CLO/Community
12.1 CLO Budget to be revised due to the prolonged period of the Note
contract.
12.2 The Community concerned about the slow progress was Note Done
addressed
12.3 The Ward Speaker’s concern regarding the Contractor’s Note
competency and project completion now only being in 2020
was noted.
12.4 The Community noted that they are happy that an instruction Note
has been given for works to commence. The message will be
relayed back to the rest of the community. It was highlighted
that the community urgently require the completion of the
clinic
12.5 The CLO highlighted that he has only been paid up to August TTA Done
PAGE NO. 21
National Department of Health
1629 - Limpopo Clinics - New Thengwe Clinic
Minutes of Project Progress Review Meeting No. 23 – 02 August 2021
13 General
13.1 Noted that no further MOS may be ordered until within Note
requirement of lead time period for installation/construction on
site
13.2 LDM noted that the Consultants will be issuing Quality Control TTA Ongoing
Reports after the Site Inspection and Progress Meetings. TTA
are attending to the issues and items in the reports are being
closed
ER stressed the importance of TTA attending to all Quality TTA Note
Control Reports that are issued by the Professional Team
monthly. ER emphasised the fact that the QC reports should
be used as a guideline in terms of what quality of work will be
accepted. TTA are to ensure that quality issues are completed
and marked off the Quality report; issued to the Professional
team so that during the next Site Inspection meeting the
Architect and Engineers can close these items. Particular
attention was drawn to the Electrical Quality Report (chasing
of all conduits) – TTA to respond with photos to support
completed items
13.3 Arch requested a register of all drawings indicating the latest TTA Done
revision numbers. Arch issued the register to TTA, TTA to
mark against register where revisions differ
13.4 SE to supply setting out point of water purification base SE Done
13.5 RK noted that he is happy with the progress on site and stated RK Note
that pushing the work should not compromise the quality
13.6 OC indicated that the issues raised by the Professional team, OC Note
namely, the Quality, OHS, Site Management will be addressed
and improved
13.7 Arch requested TTA to acquire the paving block sample for TTA
PAGE NO. 22
National Department of Health
1629 - Limpopo Clinics - New Thengwe Clinic
Minutes of Project Progress Review Meeting No. 23 – 02 August 2021
PAGE NO. 23