PRODUCTION ESTIMATE
Client: Three
Product: Reasons To Choose Display & Social Campaign - RTC Q1 2020 Production Estimate
Account Manager: Sophie Leseberg-Smith
PRODUCTION COST Ballpark costs for new 3D object created (including. football doing caterpillar) £10,250.00
Sound & VO on YouTube Assets Estimated £2,000.00
Total Net: £12,250.00
POST PRODUCTION Producers fee (hours) 1 £8,400.00
£8,400.00
£20,650.00
INSURANCE Agency insurance @ .38% £78.47
£78.47
TOTAL TOTAL: £20,728.47