Professional Documents
Culture Documents
Lect 8
Lect 8
Irrigation Canal
Lecture 8
CEB-703 – Lecture 8
Contents:
• Canal network and irrigation plan
• Discharge
• Canal network and irrigation plan
• Maintenance and repair works
• Canal lining
• Minor scheme extension and
design
Annexes:
• How to enlarge the capacity of an
existing canal
• How to construct a canal
• How to determine the slope of a
canal alignment
2
CEB-703 – Lecture 8
3
CEB-703 – Lecture 8
4
CEB-703 – Lecture 8
5
CEB-703 – Lecture 8
Discharge
• The more fields that are served by a canal, the more water has
to be transported (rate at which water is transported by a canal
is called its discharge)
• Canal capacity - maximum discharge that any canal can
transport
6
CEB-703 – Lecture 8
Discharge
• Irrigation demand in a scheme is not constant during the
irrigation season since they are largely affected by the amount
of rainfall and by the water requirement of crops growing in the
scheme (higher demand during land prep, then decreases
during initial stage and increases again during crop
development stage)
• Ways of meeting the changing water demand (NA for
continuous supply):
o Manipulating the control structures or gate settings
o Changing the duration of water delivery to the farms
o Changing the interval between water deliveries
o Combination of these
7
CEB-703 – Lecture 8
Discharge
• In order to supply the required amounts of water to the crops
and to avoid waste by supplying too much, it is important to
know the discharges in the canals
8
CEB-703 – Lecture 8
Discharge
• In order to avoid spillage of water and overtopping
embankments, free board is provided between the top of the
canal banks and the maximum water level.
9
CEB-703 – Lecture 8
Discharge
10
CEB-703 – Lecture 8
Discharge
• Wetted cross-
section area
11
CEB-703 – Lecture 8
Discharge
• Wetted cross-section area
• Minimum required free board
levels for small and medium
canals:
o fb = 0.20 m (h1 < 0.40m)
h = h1 + 0.20 m
o fb = 0.5 x h1 (h1 > 0.40m)
h = 1.5 x h1
12
CEB-703 – Lecture 8
Discharge
• Cross-sections of unlined irrigation canals seldom have a
regular shape and the bed width and the water depth may vary,
even over short distances along the canal
• The same applies for lined canals, however the changes in bed
width and water depth in lined canals are less than in unlined
canals
13
CEB-703 – Lecture 8
Discharge
• Factors that determine the maximum discharge of a canal
are:
o area of the maximum wetted cross-section – larger area
permits larger flow to pass
o resistance to the flow or roughness of the bed and sides -
water flows more slowly in a rough, poorly maintained
canal than in a smooth, well-maintained canal (due to a
lower flow velocity, the water depth will increase and the
canal will risk overtopping)
o bed slope or longitudinal slope in the direction of water
flow - steeper the slope of a canal, the faster will flow the
water and thus the larger will be its capacity (0.05% and
0.15% to avoid canal scouring and overtopping)
14
CEB-703 – Lecture 8
The lower limits of bed width b and water depth h1 are valid for canals which have a steep
slope (close to 0.15%) and which are clean and well maintained. The higher limits are valid for
canals with flatter slopes and which are covered with plant growth. 15
CEB-703 – Lecture 8
18
CEB-703 – Lecture 8
20
CEB-703 – Lecture 8
21
CEB-703 – Lecture 8
22
CEB-703 – Lecture 8
23
CEB-703 – Lecture 8
24
CEB-703 – Lecture 8
25
CEB-703 – Lecture 8
26
CEB-703 – Lecture 8
27
CEB-703 – Lecture 8
28
CEB-703 – Lecture 8
29
CEB-703 – Lecture 8
Canal Lining
• Advantages
✓ Water conservation (limit losses)
✓ No seepage of water into adjacent land or roads
✓ Reduced canal dimensions
✓ Reduced maintenance
• Cost
✓ Costs of lining can be very high, depending on the
local cost of lining material and of labour, as well
as on the length of canal to be lined
✓ Benefit cost should be greater than the capital cost
and recurring costs
30
CEB-703 – Lecture 8
Canal Lining
• Types
Concrete, Sand cement,
Compacted clay,
Plastic
• Selection factors:
Local costs, Materials availability,
and Local skills availability
31
CEB-703 – Lecture 8
Canal Lining
• Types
Concrete, Sand cement,
Compacted clay,
Plastic
• Selection factors:
Local costs, Materials availability,
and Local skills availability
32
CEB-703 – Lecture 8
33
CEB-703 – Lecture 8
35
CEB-703 – Lecture 8
36
CEB-703 – Lecture 8
39
CEB-703 – Lecture 8
40
CEB-703 – Lecture 8
V = 0.22 m/s
V = 0.22 m/s
• Check: h1 > b/2 and hmax < 1.5 x b --- OK (otherwise these values)
• Side slope = 0.3/0.3 = 1.0
• p = 0.36/0.3 = 1.2
• f (from table) = 1.43
• Qmax = 1.43x39.6 = 56.628 L/s (max safe canal capacity) 42
CEB-703 – Lecture 8
43
CEB-703 – Lecture 8
44
CEB-703 – Lecture 8
45
CEB-703 – Lecture 8
46
CEB-703 – Lecture 8
48
CEB-703 – Lecture 8
49
CEB-703 – Lecture 8
50
CEB-703 – Lecture 8
• f = 60/45 = 1.33
• r (from table, with ss = 0.7 & f =1.34) =
1.7
• bnew = r x bold = 0.51 m
The canal bed should be enlarged by 0.21 m, from 0.30 m to a new bed
width of 0.51 m, or, in round figures, by 20 cm, from 30 cm to 50 cm. 51
CEB-703 – Lecture 8
Supplementary
• GEOMETRIC PROPERTIES OF OPEN CHANNELS
52
CEB-703 – Lecture 8
Supplementary
• GEOMETRIC PROPERTIES OF OPEN CHANNELS
53
CEB-703 – Lecture 8
Supplementary
• GEOMETRIC PROPERTIES OF OPEN CHANNELS
54
CEB-703 – Lecture 8
Supplementary
• GEOMETRIC PROPERTIES OF OPEN CHANNELS
Design a rectangular channel to carry a discharge of 10 m3/s. The channel
will be excavated through graded loam. The topography in the area is such
that a bottom slope of 1 in 4000 will be suitable. Assume bed width (B) is
twice the depth (y).
• n = 0.03 (graded loam)
• Manning’s equation:
• A = 2y2, P = 4y --- R = A/P = 0.5y
𝐴𝑅 2/3 𝑆 1/2
- 𝑄= • AR(2/3) = 18.97 = 1.26y2.67
𝑛 • Thus: y = 2.76 m and B = 5.52 m
• fb = 0.5y (since depth > 0.4m)
- AR(2/3) = 18.97 • Total depth = 1.5y = 4.14 m
• Flow A = 15.24 m2
• Flow V = 0.66 m/s 55