Download as pdf or txt
Download as pdf or txt
You are on page 1of 12

OTC 7634

Marlim-4: A Subsea Production Well Overtaking Deepwater Frontiers —


Part l—Planning and Installation Procedures
M.G.G. Morais, P.A. Bonesio, and Salim Armando, Petrobras S.A.

Copyright 1994, Offshore Technology Conference

This paper was presented at the 26th Annual OTC in Houston, Texas, U. S.A.,2-5 May 1994.

This paper was selected for presentation by the OTC Program Committee following review of information cvnlainod {n an abstract submitted by the author(s). Contents of the paper,
as presented, have not been reviewed by the Offshore Technology Conference and are subject to correction by the author(s), The material, as presented, dcas not necessarily reflect
any position of the Offshore Technology Conference or its officers. Permission 10 copy Is restricted to an abstract of not more than 300 words. Illustrations may not be copied, The abstract
should contain conspicuous acknowledgment of where and by whom the paper is presented.

ABSTRACT INTRODUCTION

Brazilian oil and gas reserves, concentrated offshore Since the discovery of the first o~shore production well
and particularly in deep waters, have led Petrobras to in Campos Basinj several emerging technologies have
establish a careful and strategic plan which has as the been used in order to anticipate oil production as well as
main target to get the technical capacity to produce to implement and test new ideas.
those areas.
Petrobras started its offshore production in 1977 with the
The exploration results have shown a necessity of Early Production System conception, which was
surpassing the technology bam”ers, established in 1000 dedicated for:
meters (3280 ff) water depth since 1988, and it has
involved both Petrobras and Material/Services Suppliers ● anticipating oil and gas production;
in research and development of new equipment and
installation methods. ● reservoir data collection;

The experience gained during the Marlim Field ● producing isolated and marginal areas;
development, putting 10 (ten) production wells on stream
to a Floating Production System named Marlim Pilot Atter the EPS phase and this conception being renamed
System (fig. 1), and 3 (three) production wells to to Floating Production Systems (FPS), the experience
Salema-B~upira Pilot System (fig. 2), has been the main acquired with 27 FPS installed anaYor re deployed ,
element to be used to ingress in a new stage where made it so useful and more cost effective to be adopted
1000 meters of water depth will represent the initial in Brazil’s oil and gas fields.
mark.
This conception has proved to be so applicable to our
The beginning of this new stage is characterized by reservoirs scenario that, during the feasibility studies
putting Marlim-4j a production well located in 1027 performed to define how a new area will be exploited,
meters (3369 ft) water depth, on stream by April 1994. this solution appears as the best one when compared to
other a/tematives.
The constant technological development aimed by
Petrobras in offshore production reflects all efforts The advantages of this conception has been:
applied in producing oil and gas fields located in deep
waters. ● Lower initial investment;

● Flexibility of changing the drainage grid;


References and Figures at end of paper

419

— —

— . . —
. .- .

— ——
-=
——. ——
~———. ——
——
— —

— ==—–=-.–= -–.
———. —. —
. -=.—= .— ——

.
2 MARLIM-4, A SUBSEA PRODUCTION WELL OVERTAKING DEEP WATERS FRONTIERS OTC 7634

● Possibility of being completely reused in another ● The laying methods such as layaway operation 1,
area; vertical connection 2, overboarding of intermediate
connections of flexible pipes and umbilical were
. Possibility of having the oil and gas cash flow analyzed, specified and tested;
anticipated;
● The guidelineless subsea tree ‘ was specified,
● Possibility of increasing or reducing the number of developed and supplied;
wells;
● Even a new laying vessel has been hired to lay well
● Anticipationof reservoir information. bundles up to 2000 meters (6562 ft) water depth and
it will be available by January 1995.
The main milestones established by Petrobras in
offshore productionhave been: Since Petrobras classifies as proved reserves only those
that are within the technology limits and there is a strong
● Enchova Field with a single well producing to EPS potential beyond 1000 meters water depth in Campos
by means of a BOP, test tree, completion riser and a Basin (fig. 3) as well as in Santos Basin, it was
dry x:mas tree (1977); mandatoty to start working on the depth considered as a
technological frontier for Petrobras present capacity.
● Enchova-Leste Field where the first subsea tree was
installed in 189 meters (620 ft) water depth as a The philosophy adopted is based on experiments which
satellite well of a EPS and flexible pipes were used have been designed, installed and monitored for specific
as dynamic structures (1979); areas and in conjunction with the field feedback they
were adjusted and became part of the technical memory
● Garoupa Field composed of a gathering system used for offshore production development.
with a manifold center and dry wellhead tree both
based on atmospheric chamber conception, installed This paper will present the planning activities for the
in an average water depth of 125 meters (410 tt) Marlim-4 Project highlighting the flexible pipes and
(1979); umbilical installation.

● Pirauna Field had the deepest well, RJS-294, put on CHARACTERISTICS OF THE FIELD
stream in 411 meters (1348 ft) water depth and
having the layaway operation performed with a The Marlim South is a field discovered in f 987 by the
subsea tree with guide lines (1987); exploration well 4-RJS-382 drilled in 7?50 meters (3773
R) water depth.
● Marlim Pilot System had the first semi-submersible
operating as stationary production unit anchored in The resetvoir is located on South of Marlim Field (fig. 4),
625 meters (2050 ft) water depth, the deepest between 1000 and 2000 meters water depth, and has
production well in 781 meters (2562 fi) and the approximately an estimated area of 250 km2 and oil in
deepest Single Buoy Mooring System installed in place volume of 943 million cubic meters (5.93 billion
400 meters (1312 fi)(1991A12). barrels).

The Marlim Pilot System was considered a major The reservoir mechanism is water drive and its depth is
breakthrough and it provided different ways for going about 2800 meters (9186 ft) horn the mud line with an
deeper in offshore production. At that time the Marlim estimated recovering factor of 25%.
Field exploitation was being defined and several points
were considered in advance, during the Pilot phase, to INSTALLATION PLANNING
develop the capacity of producing in a water depth of
7000 meters. Such points were: The Marlim South is considered as a promising area and
is supposed to be developed as soon as the technology
. The laying vessel capacity was adapted to handle applicable for that water depth is available in Petrobras.
the expected loads during the bundle installation;
A preliminary feasibility study has split the reservoir into
● The flexible pipes and control umbilical were two areas, the north and the south, where the premises
specified, designed and supplied for that water considered for this division were the reservoir
depth; configuration and the water depth (north area from 1000

— — — .
. . .x .

— — .


— —— -=

~———. .—

— ——————

OTC 7634 M.G.G. MORAIS, P.A. BONESlO, S. ARMANDO 3

to 1500 meters (4921 i?) WD and south area kom 1500 ● MRL-4 completion program and execution;
to 2000 meters WD).
● The bundle installation including layaway operation,
The north block, according to reservoir drainage studies, pipe and umbilical laying and pull-in operation at the
will have about 45 wells being 32 production wells and FPS;
12 water injection wells.
The budget for this program is estimated in US$ 24
FPS will be anchored in 1100 meters (3609 ft) WD millions with operations such as completion, bundle
having an oil processing plant which capacity is installation accounting for 35% of this total and the
estimated in 120.000 bpd. difference (65%) spent on flexible pipes and umbilical.

The overall investment will be about US$ 1.1 billions and The expected production is 1000 m3/d ( 6.300 bpd ) and
the system will be on stream by the year 2000. gas lilt will be used.

The Marlim Pilot System (FPS) had the oil production CRITICAL POINTS DETECTED
well MRL-20 shut-in. This action resulted in a complete
set of subsea production equipment available to be During the planning for this installation some activities
reused in another area (x-mas tree, flexible pipes and were considered critical and an special care was
umbilical, production adapter base, etc.) as well as dedicated to them.
production capacity and facilities on the FPS to receive a
new production well, which could provide Petrobras with Those main expected points for the installation and
some extra information about a new reservoir. production are:

Petrobras Production Department started looking for an ● The guidelineless layaway operation;
interesting and unknown area that could be elected for
using those facilities already available. Then, the Marlim- . The control of the bundle during the layaway and
4 (fig. 1) was chosen in order to provide Petrobras laying operations in such water depth;
technical group with answers for the questions raised
when this challenge was established. They can be listed ● The response time for the subsea tree operation
as follows.. with a direct hydraulic control 3;

● The long term test of a new reservoir in Marlim ● The loading capacity of the laying vessel for carrying
South Field; all the MRL-4 bundle.

● To incorporate the new reservoir accumulation in For those reasons the installation plan was prepared to
Brazil’s reserves; avoid them. The following points were considered:

● The consolidation of concepts gained throughout the ● Layaway operation will be followed up by ROV
extension of existing technology; allowing the perfect coordination of laying vessel and
completion rig;
● The control operation of a subsea tree about 19 km
(11. 8 miles) far from the FPS. The maximum ● The bundle will be laid full of water and its behavior
distance up to now is 13 km (8.08 miles) in Albacora monitored until reaching the sea bottom;
Field.
● Regarding to the laying vessel capacity, bundle
For this challenge come true it was necessary a program onloadings and offloadings will be done offshore in
planning (fig. 5) comprising of the following main steps: a shallow waters (180 meters) area close by Marlim
Field;
● Recovering, commissioning and hydraulic adaptation
of the subsea tree from MRL-20 well; ● To reduce the operation risk and cost for bundle
reloading in Vitona Base, a shuttle vessel will bring
● Recovering of the MRL-20 bundle, commissioning the pipes and umbilical tiom onshore base and
and pre-abandonment in an offshore location; another will perform the laying operation;

● Acquisition of the complement flexible pipes and FLEXIBLE PIPES AND CONTROL UMBILICAL
umbilical to be added to the original MRL-20 bundle; INSTALLATION

● The bundle installation procedure;

421

— -

— . . — .

. .- .


——
-=
4 MARLIM-4, A SUBSEA PRODUCTION WELL OVERTAKING DEEP WATERS FRONTIERS OTC 7634

The total length of this bundle will be 19300 meters ● Pull-in operation of the flexible risers at the FPS
where 18480 meters are of static structure and 820 (PETROBRAS 20);
meters of dynamic structure.
● Hydrostatic and functional tests;
The composition of the MRL-4 bundle will be as
following: ● Bundle as laid survey;

- PRODUCTION LINE ARRANGEMENT - (fig. 6) ● Well pre-operation.

● 4“ riser - deep water structure; CONCLUSION

● 6“ flowline - deep water structure insulated pipe; The Marlim-4 Project is considered the milestone for
Brazil Offshore Production in ultra deep water depth,
- ANNULUS ACCESS LINE ARRANGEMENT - (fig. 7) establishing a new era in Petrobras technical capacity
and development.
. 2 1/2” riser - deep wafer sfrucfure;
By achieving this goal, Petrobras will not only improve
● 2 1/2” flowline - deep water structure; the state of the art in producing in such water depth but
also will set a new world record as a result of need,
- CONTROL UMBILICAL ARRANGEMENT - (fig. 8) creativity, perseverance and commitment.

● Electric-hydraulic Umbilical riser and flowline. NOMENCLATURE

The installation will begin at the subsea tree side by ● EPS - Early Production System
transferring the flowline hub and well bundle to the ● FPS - Floating Production System
completion rig. It will end at the FPS with risers pull-in ● BOP - Blowout Preventer
operation. ● WD - Water Depth
● MRL-4 - Marlim-4 production well
The installation will be composed by the following main ● Riser - Dynamic Flexible Pipe Structure
steps: ● Flowline - Static Flexible Pipe Structure
● PETROBRAS 20- Floating Production System
● Track survey; ● PETROBRAS 13- Floating Production System
● FHL - Subsea Tree Flowline Hub
● Flowline hub and flexible bundle transference to the ● ROV - Remote Operated Vehicle
completion rig;
REFERENCES
● The flowline hub and subsea tree assembly and
tests at the completion rig moon pool; 1. Moreira, J.R.F. and Viegas, A. F.; “Guidelineless
Completions Offshore Brazil”; OTC 5975, 1989
● The layaway operation; OFFSHORE TECHNOLOGY CONFERENCE.

● Flowline bundle heading orientation check, subsea 2. Nagle, F.J. M., Mendonca da Silva, J. E., Costa
tree landing on the production base and tests; L.A. G., Capllonch R. W.; “Vertical Connection
System for Flexible Pipes: Offshore Tests and
● Flowline bundle laying operation, including Pioneer Installation’: OTC 7260, 1993 OFFSHORE
intermediate connection overboarding and tests; TECHNOLOGY CONFERENCE.

● Abandonment of the bundle extremities with 3. Dias, R.; “Marlim-4 - A Subsea Production Well
fishing/recovering devices; Overtaking Deep Water Frontiers Part II -
Installation Procedures’? OTC 7635, 1994
● Reloading of the laying vessel offshore; OFFSHORE TECHNOLOGY CONFERENCE.

● Recovering of the pre-abandoned bundle


extremities;

● Intermediate connections testing and bundle laying

422


. .- .

— ——
-=
——. ——
~———. ——
——
— —

— ==—–=-.–= -–.
———. —. —
. -=.—= .— ——

.
M.G.G. MORALS, P.A. BONESIO, S. ARMANDO 5

6. FLOW-IS] & C&]


/ 4. LRIWO 2 1/2, WWmJsl
w.

NV
G , ~ @-@

JAs
F 7-W-7

SSXJ
~

‘“ L
v .
1-
T
30C-SfELCMLf33
,,. /“ :?
/
/ h n\/


——
-=
——. ——
~———. ——
——
— —

— ==—–=-.–= -–.
———. —. —
. -=.—= .— ——

.
MARLIM-4, A SUBSEA PRODUCTION WELL OVERTAKING DEEP WATERS FRONTIERS OTC 7634


\ /
/
— \ ‘\
0009$
\\ \

\
/
\

000ss1

‘\
\

\
. \
J
<\\
I \. CC-W%{
I \\
\ i \
0. \ \ ‘\
% .
\
\ “.$’ \ -1

/ -----=%
I WQcsf
I
\
I
I \
I \
1 ‘,
I
.

7
CWzw

(’

$
‘\;
‘\ 1’
— l’. ,’;’
‘q://./
/-“ 000151
-4-— :
—.
-—.
. \.
\ . /
, . ‘. % ‘
/, ‘, %\
/-’/’ t-l
.0 \
.,
— \,
Y / —WY
6\
z-, \%

%- \
g\
1- ‘.
w
\
\
a.

\ \ J

C906?1
@’\ . \ ,.’
. &
‘.

\ .& .’ \
%’ .
. , /’


\

$--. =6

‘\
Ocdat(
\

‘\
//”
\ \
./
WLP$

I--=kw!w’”.
ImlJ. HARCELO
IF IG.21
1- CRL.AWI 1-”
h
M -V.
— JMW34 0


. .- .


——
-=
——. ——
~———. ——
——
— —

— ==—–=-.–= -–.
———. —. —
. -=.—= .— ——

.
/-” ,/. // /
/
.,~ /“’0 /“
.~’
,//” /
“’_x5!5i
.3- RL.J j
7- 80
~ RL-$+’ ,00011!-’
# ,- -
,.- MRL>J,
-- ● 7. /
7.M L-9
yy ~
~ ,f~
,/ 4 .377 S.MORL.2 ,~
MarIim,,’”
/ —
//-
f
.//

,---
,/

~e-.
,.
,/
//

//’
/
,Alarlirn Sout,/
//’ .4H

FIGURE 4

FIGURE 3

MARLIM-4 PROJECT

3[ October 1993 I November1993 I L7ecmber 1993 I JmuaIY 1994 I Febmary f994 I March 1994 I April 1924
TASKS 2Cl SllO1lT 12411117 [14121121 1611211912612191 t6123[SO16 113(201 27 16113120 IZ7I3I1OII7 124
1- PROJECT PLANNING I
2- FLEXIRLE PIPES ANO UMBILICAL A@JlS1770N

3- hW.L.20 ABANDONMENT
~fzzzzzz:
4- SUBSEA TREE REC0NDlTk3NlNG ANO 7ES7’ 1-

5- MRL.20 BUNDLE RECOVEi?JNGAND RECONDITIONING r


m
6. WELL COMPLETION

7. FLEXIBLE BUNDLE INSTALLATION

7.1- sUBSEA TREE lAYAViAY OPERATION

72- BUNDLE LAYING OPEfWnON

7.3- PULL-IN ATTNE FPS

1 -WELL PREaPERAnON

FIGUREs

425

— -



.- .


——
-=
——. ——
~———. ——
——
— —

— ==—–=-.–= -–.
———. —. —
. -=.—= .— ——

.
II
~1
I
I

I
1

o
m
-u
II
::
r-\
II
i
-o
z-
i,’
<
II
x=-
I 1’ -0
I ‘1, ‘1
,,,

1,
,,
II
I —
II

,,!”
II I 610 rri F) 1. 1381 m(F) 1. 1370 m{F)
I
1, l“ ‘1 11’

I
I
II
%%f!mti)-i
Ill,

11,
I -u 1370 m(F)
m 1.
1370 m(F)
1. 1480 miF)

c1
1,1, -i
~Vp!~~mjjY7d
0
z
1480 m(F) 1480 m(F) 1480 m(F)
1- 1. 1.
111

D
m ‘xTllT7ri!ii-d!l

1501 m(F) 1539 m[F) 1440 m(F)


b 1. 1.
+

z
-i

1,
II

!
: ’11
‘,
II
~1
I

1,

1,
II

1,
DESCRIPTION
4“ RISER END FITTING
II
]
2 1 4“ RISER BENDING STIFFENER
II
1( 11’ 3 876 4“ FLExIBLE RISER (Ex MRL-201

II I 4 1 4“ RISER END FITTING


11~

l-+-&-
6“ FLOWLINE END FITTING
’11, 1
’11 6“ FLOWLINE (Ex MRL-20)
‘II
i
6“ FLOWLINE (Ex MRL-20)
I!l 111 -0
‘,,
I
-n 6“ FLOWLINE IEX t4QL-20)
’11
,,, 1’ Ei
c
6“ FLOWLINE

6“ FLOWLINE
(NEW

ENO
AOUISITIONI

FITTING
I
1%
!
1,1,
,!

III II 11 3X1370 6- FLOWLINE (NEW AOUISITION)


I t

1, I
Cn 0 12 4x1480 6“ FLOWLINE (NEW AOUISITION)

E
‘II
111
z 13 1501 6- FLOWLINE (NEW AOUISITION)
Ii 1- 6“ FLowLINE (Ex MRL-20)
14 1539
111 I
15 1 6- FLOWLINE ENO FITTING FOR SUBSEA TREE SIDE

6“ FLOWLINE (EX MRL-20)


‘1,
9
xl
I 17 I 1 6“ FLOWLINE BENOING RESTRICTOR
;1
m CHINESE FINGER
Ii
RING GASKET API-6BX 8X-153
,,
II

El
I
‘1 z
--l
1,

I
1’11

I
1,
II
I
!
!1
II:
‘1,
1,
‘,
.

-8
-@

-@ 1

u
3
-@ ;

-@ AI
AI
x
@ ~ <
>
. Al
n
n
2

6 9
.
>
n x
d

1-
>
c 5. 3
z

& r .
-@ J
J
z d
t
cc n
L1
CJ J z
( u-l . 2
( w J
t c
.- n J
t
3
z
C )
J
d
Al
z
N
-@ 4 k3
J
-@ A.

..$
-u

.. Al
t
1

IF

c1 w
.
1- n
0 w

0
N -c — —

m
2m 0
u r

0
a
1- — —
&l
a

0 I I FEv/94 INORONHAI

REv. wscRIPllm DATE I BY I APPROI

o
nnc
PETROBRA’S
?ldl, M4S8L1#m ,.A. -21,/
ANNULUS ACCESS-LINE COMPOSITION

W*O m..! S4,cr,

FIGURE 7 0 1/1
—-

428

--

— -


. .- .


——
-=
——. ——
~———.——
——
— —

— ==—–--. –= -
———. —. —
. -= .—~ ——

.
II
~1
I

1,

1500 m(Rl 2570 mlF) 2570 mfF)

r 1 t- 1 r 1

1,
II

1,
2570 2600 ml F 1 2600 m(F )

— 1-
m4F )
~ r ~ r -1
II
II
1( 11’

II I
11~

’11, 1
’11 2450 mlF 1 2450 m(F)
‘II
i

I
1
I!l 111
‘,, WELL
I 3-h@ L-4
’11
,,, 1’ l#d ‘clqlclr
6
6
1,1,
,!

III II
II I ITEM OTD DESCRIPTION
‘II c
111 x 1 1 RISER Uh@l LICAL TERMINATION
Ii CD
2 1 UhiBIL I CAL RISER BENDING STIFFENER
I
3 1500 RISER Uh631LICAL (EX MRL-20)

‘1, 4 15 UMEIL ICAL BENOIG RESTRICTOR

1 UM81L1CAL TERMINATION
5
;1
6 7 SPL ICE BOX
Ii
FLOWLINE TERMINATION
, .7 ,,
,,
II 8 3x2570 FLOWLINE UMBILICAL (NEW AOUISITIONI

Q 9 2x2600 FLOWLINE UMBILICAL (NEW AOUISITION)


I
‘1 10 2x2450 FLOWLINE UMBILICAL (Ex MRL-20)

11 1 ‘ CHINESE FINGER
1,
12 1 FLOWL [NE UMBIL I CAL TERM1NATION I SUBSEA TREE SIOE 1

I
1’11

I
1,
II
I
!
!1
II:
‘1,
1,
‘,

.- .


——
-=
——. ——
~———. ——
——
— —

— ==—–=-.–= -–.
———. —. —
. -=.—= .— ——

You might also like