Professional Documents
Culture Documents
Railway Sleepers and Fastenings On The South African Railways
Railway Sleepers and Fastenings On The South African Railways
(Member)
SYNOPSIS
LEEPERS and fastenings have a particular function to perform; and recent developments have
S necessitated the introduction of certain auxiliary features. Long welded rails, effective track
insulation for signalling purposes and the need for resilience have all been major developments.
The precise function of components to meet these requirements is dealt with, together with the
laboratory tests with which a fastening must comply before it is accepted for trials in the actual
track.
Wood and steel sleepers and fastenings are described together with the changes which have
taken place in the design of fastenings to comply with rnodern conditions.
Check rails are used on curves to minimise wear on the high leg. The requisite check rail
chairs have presented a problem for many years. Satisfactory designs for wood and steel sleepers
have recently been developed and are described.
Ash dropped in section is very detrimental to the track. The only way to obviate this is to
provide ash pits at watering stations. Conventional pits were not very successful and the solution
seems to be a shallow pit comprising cast iron pedestals carrying the rail and, in turn, supported
on concrete sleepers.
A major portion of the paper deals with concrete sleepers. Initially, in common with other
railways throughout the world, small scale experiments were first carried out and the use of
concrete sleepers has been gradually extended until substantial orders have been placed for their
supply. Initially, proprietary makes of sleepers and fastenings were used and these are described.
Recently, the South African Railways have developed their own design of fastening.
Reproduced by Sabinet Gateway under licence granted by the Publisher (dated 2011)
With long welded rails it is of paramount impor- Fig. 6-Clip and bolt fastening for steel sleepers
tance that the sleeper shall be heavy in order to re- Insulated fastenings
duce the tendency for blLlckling of the track. In this
regard the steel sleeper weighing only 150lb with vVith a steel sleeper which is a very good conductor
fasteni ngs compares unfavourably with wood or con- of electricity very efficient insulation must of necessity be
crete weighing respectively 210 and 4001b, on the provided between rail and sleeper if the one rail is to be
average, with fastenings. Fig. 5 shows a typicacl stretch of effect ively insulated from the other. In add ition, the
Reproduced by Sabinet Gateway under licence granted by the Publisher (dated 2011)
steel sleepered track. provisio n of insulat ion with in the narrow con fi nes of the
standard fasten ings is diffic u lt. One method which
has met with a certain measure of success 0 11 straights
and flat curves is the envelope insulation developed in
Switzerland and adapted for use in South Africa in
1956. This is illustrated in Fig. 7.
Nonnal fastenings
l?
noted on Fig. 7 that the protecting plates overlap one
another under the rail. This results in the one plate
being slightly different from the other. Tests have been
carried out with two identical half plates meeting on
,1
the centre line of the rail and these have been found to
be quite satisfactory. . \
pad, the rail is virtually enclosed in an insulated en- Fig. 8- Check chair for wooden sleepers
velope. This method has been developed by a private
organisation and is patented.
Check chairs
General
Check rails are used extensively for minimising the
wear on the rail on the high leg of sharp curv(:s. Of all
track fastenings the check rail chair has probably pre-
sented the greatest problem due to the multiplicity of
parts and the heavy lateral forces to which the fastening
is subjected.
In the main there are four components to be accom-
modated namely, two rails, a chair and' a bu ttress and the
complete assembly is required to provide a fixed flange-
way. It will be appreciated that manufacturing tole-
rances make it virtually irr.possible to obtain a good (it
Fig. 9 - Typical stretch of checkrailed track on wood sleepers
of all components and the heavy lateral forces to which - New design check chair low leg, old cast iron chair high leg
the chair is subjected in the track accentuates any inade- Photo: S(mth African Railways
quate fit which may be present.
Check chairs on steel sleepers
Check chair for wooden sleepers
I t will be noted that in the design for wood sleepers
Reproduced by Sabinet Gateway under licence granted by the Publisher (dated 2011)
The obvious solution was to provide an adjustal)le there is a button rib between running and checkrail.
buttress, but due to limitations in space and the necessity I n check c hairs for steel sleepers th is was su bs ti tu ted by
for producing an economic design this was not easy and a clip held down by a T-bolt in the normal way for
it was not un til 1954 that a satisfactory solution was steel sleepers. Despite all efforts in providing specially
found for wooden sleepers. This comprised a buttress designed bolts even in high tensile steel, continual
pivoting around a shoulder on the chair and forced breakage of these bolts was experienced. In 1952, a
up against the web of the rail by a bolt. By this means it design wa~ prepared in which the sleeper itself was
was possible to take up all slackness and still be able to converted to a special check rail sleeper by welding the
allow for a certain amount of wear, thus ensuring that requisite pieces into position and replacing the central
the lateral thrust was always taken by the buttress. bolt by a button rib. The design proved most satis-
At that time the cast iron chair with taper key was the factory and is the present standard. A further improve-
normal standard fastening for uncheckrailcd track and in ment is to adapt the fastening to take an adjustable
this check chair both the running and check rails were buttress similar to that for wood sleepers. A design for
held by a taper key. As has already been pointed out the this has been prepared and arrangements are in hand for
adoption of long welded rails rendered the taper key a number to be manufactured for test purposes.
ineffective and it became necessary to re-design the chair
to suit the new type of clip. The desired result was Ash pits
achieved in 1958 by introducing a bolt with a long
threaded portion. The clip securing the check rail is Ash dropped in section by steam locomotives has
then placed in position and secured by a nut. The always been a problem for maintenance engineers as
buttress is provided with wings which clamp over the much damage results. The simplest method of ob-
nut thus preventing the nut from slacking back. A viating this practice is to provide ash pits at watering
further nut placed above the buttress then draws the stations where disposal of ash can be suitably arranged.
buttress down to engage against the web of the rail. Initial trials with conventional pits were not very
The complete chair is illustrated in Fig. 8. Fig. 9 shows successful and the first significan t advance was made in
a stretch of check-railed track with the new chair on 1953 when a shallow ash pit was designed comprising a
the low leg and the old standard chair with taper key concrete sleeper with two concrete pedestals on which
on the high leg. the old design of cast iron chair was mounted. Due to
Table I
Reproduced by Sabinet Gateway under licence granted by the Publisher (dated 2011)
Sleeper Fastening
Dale
or Numher Approx.
Order Make Typc Reinforcem en l weight :vIakc [nsulated or
Ib 1I0n-insulattd
1958 30,000 Swedish 101 Block Post-stressed rod 430 Fist Insulated
~C_~------,l~1~[_I.-------jJ
, re' - \7/ 8"
To appreciate fully the information provided in
Table I , it must be realised that all orders placed , with
the exception of the two special experimental orders,
were the result of competitive tenders and is no indication
i• •I
of any marked technical preference for the types and
SONNEVILLE makes shown.
Sonneville and Vagneux sleepers both consist of
normal reinforced concrete blocks joined by a steel tie
c~ '1--\
\ ----f{ l.~
bar cast into the blocks. In the case of the Sonneville
sleeper, as dealt with later, the tie bar serves the further
function of an anchor for the head of the bolt which
L
.' -----------' co' - 2 I/I~"
~
I...i_ _ _ _ _ _ _ _ \
~
secures the rail fastening. The Stupp sleeper is a full
length flexible type pre-stressed with wires. The Sonne-
I• "j ville, Vagneux and Stupp sleepers all originate from
France. The Swedish 10 I sleeper originated in Sweden
VAGNEUX and consists of two lightly reinforced blocks of concrete
joined by a tie rod which in turn passes through a pipe
distance piece filled with concrete. This distance piece
serves the dual purpose of holding the gauge and
Reproduced by Sabinet Gateway under licence granted by the Publisher (dated 2011)
g
APPLIED LOAD
2". IVz" PLATE
TOP ROUNDED
2" RAO . ----~~
'---------"'8~.
SONNE.VILLE
--=----!SEAT
1<----
END SUPPORT
but also a tensile test and, for the sleeper itself, a bend
test is required where the minimum cracking resistan ce
is measured .
Proprietary fastenings
In the Sonnevil\e fastening used on the Sonnevil\e FIST
and Stupp sleepers the rai I rests on a grooved ru bber
pad and is held in position by a spring clip with two
leaves, the upper leaf holds the rail down and the lower
leaf positions the rail on the sleeper. With the Sonne-
ville sleeper the dip is held down by a T-headed bolt the
ALTEO NATIVE
head of which engages in a slot in the vertical leg of the BOL T/COACI-I5CQEW
tie bar. With the early Stupp sleepers a bolt/coach- COACI-15CCE.W.
screw was used instead of a bolt, the lower portion being
a coachscrew which engaged in a coil cast in the sleeper,
followed by a square collar used to screw the coach-
screw into position and which also engages in a square
hole in the lower leaf of the clip to prevent the coach-
screw slacking back. The upper portion is in the form
ofa bolt which enables a nut to be used to hold the upper
leaf on the rail. As a normal bolt is more satisfactory
the bolt/coachscrew was replaced in later orders by a
T-headed bolt, the head engaging in a plate cast into
the sleeper. These fastenings are non-insulated, but
tests are proceeding on a method of conversion to an BETON UNO MONIERBAU
insulated fastening. The latest order for Sonnevil\e
sleepers is for a special form of insulated fastening which
is still under test. Fig. 14-Proprietary fastenings in use on concrete sleepers
All concrete sleepers and fastenings purchased to inserted in the track is small being about one million and of
date are functioning satisfactorily and no serious defects these the majority have only recently come into use. The
have become apparent. Where new construction and average life of a good wooden sleeper is from 15 to 18
pre-fabricated track is involved mechanical methods of years as compared with anything up to 40 years for a
handling have been used with success, but handling these steel sleeper. Accurate figures for the life of concrete
sleepers on single lines for re-sleepering and maintenance sleepers are obviously not yet available but it is estimated
still remains a problem. Various methods of assisting in that should last at least as long as the steel sleeper.
this regard have been evolved and have met with some As regards capital costs there is little to choose be-
success, but in the main the work has to be done by tween the three types of sleepers; steel and concrete
hand. sleepers with insulated fastenings cost much the same as
wood sleepers with fastenings, namely, from R6.4 toR6.8.
Local production As already pointed out steel sleepers have recently
Prior to the second World War, the only track fallen into disfavour due to being light in weight and
fastening made in South Africa in quantity was the old thus unsuitable for long welded rails and to difficulty in
cast iron chair for use with the taper key. At that time providing satisfactory insulation. Concrete sleepers, due
taper keys, rail clips and soleplates were made overseas to their weight, are ideal for long welded rails but there
in rolled mild steel. are nevertheless problems to be solved with them as well.
During the war and post-war periods, material The wooden sleeper on the other hand still remains the
from overseas was almost unobtainable and the first general all purpose sleeper.
significant advance in South Africa was made when sole- Just exactly what type of sleeper will be ordered in
plates were made in cast steel and taper keys in mild future is difficult to forecast and will undoubtedly vary
steel by drop forging. At about the same time the use of from time to time according to prevailing conditions.
The Author wishes to thank the Railway Admini- I. GOLDSTEIN, A. and HAY, J. G. Modern European develop-
stration for permission to present this paper and to use ments in permanent way engineering. Trans. S. Afr. Instn.
the illustrations and diagrams included in it. Civ. Engrs. Vol. 3, No.7 (July, 1953).
The Author also wishes to thank the various firms 2. DOLL, A. The concrete sleepers of the German Federal
who have supplied sleepers and fastenings to the South Railways - Recent developments in design and manufac-
African Railways for giving him permission to include in ture. Published in the English edition of the Railway
the paper brief descriptions of these sleepers and fasten- Technical Revue, (May, 1959). Publishers Carl Rohrig
ings. (Darmstadt).
DISCUSSION
Written discussion on the above paper will be accepted until August 28,1962. This, together with the Author's Re-
ply, will be published in the December, 1962, issue of The Civil Engineer in South Africa, or later.
Such written discussion, which must be submitted in duplicate, should be in the third person present tense, and should
be typed in double spacing. It should be as short as possible and should not normally exceed 600 words in length. It
should also conform to the requirements laid down in the 'Notes for the Guidance of Authors and Contributors'
as published in the March, 1959, issue of The Civil Engineer in South Africa.
REFERENCE
Whenever reference is made to the above paper this publication should be referred to as the Transactions of the South
African Institution of Civil Engineers, and the volume and date given thus: Trans. S. Afr.lnstn.Civ. Engrs. 6 (June, 1962)
-------------------e-------------------
SO,rarn .agu
Reproduced by Sabinet Gateway under licence granted by the Publisher (dated 2011)
ASSENGERS. The cOInfortable fittings in the ERONAUTICS have received a little fillip in this
P S.A.R. passenger coaches' are only obtained at
considerable cost in weight to be hauled, sOInetiInes
A country during past years, by the exhibition of
two or three different types of Ina chines Inaking
running considerably over 2t tons of dead load per successful as well as' unsuccessful flights at different
passenger carried as COIn pared to ! in England and altitudes, but aeroplanes can hardly be reckoned as
It in AInerica. I think it will be conceded that our filling the bill for general utility although they have,
passenger trains COIn pare favourably for ease and we hear, been of SOIne value in the war between
COInfort of the journey with those other and older Italy and Turkey.
railways.