Download as pdf or txt
Download as pdf or txt
You are on page 1of 12

1) Material Master data

2) Creation Profile
3) Vendor Master Data
4) Create Scheduling Agreement
a. For Forecast Schedules
b. For JIT ( Just in time ) Schedules

Scheduling Agreement :

• Create a Material with JIT Schedule Indicator


• Create a Release Creation Profile
• Assign a Release Creation Profile to Vendor Master
• Create a Scheduling Agreement with Release Documentation
• Maintain SA delivery schedule
• Generate Forecast delivery schedule & Generate JIT delivery schedule

Material Master record


• JIT indicator in Material master record controls the JIT delivery schedules.
Creation Profile :
• Spro -> Materials Management -> Purchasing -> Scheduling Agreement -> Maint. Rel.
Creation Profile for Sched. Agmt. w. Rel. Docu.

Vendor Master Record


• Release Creation Profile is adopted as a default value from Vendor Master Record
• We unable to see the field Release creation Profile
• Go to Extras -> Add Purchasing Data

• Again go to Extras -> add Different data


• Then we can find Creation Profile field

• Assign creation Profile


Create Scheduling Agreement
T code : ME31L

Document Type / Agreement Type – LPA

• Select the line item & go to Item -> More functions -> Additional Data
• Verify whether the JIT schedule indicator & creation profile are adopted or not
• Save the Scheduling Agreement

• Maintain Scheduling Dates / Delivery dates


• T code – ME38

• Select the line item


• Go to Item -> Delivery Schedule
a. For Forecast Schedules
• Go to Edit -> Generate Forecast Schedule (or) just go back & select line item & go to Edit –>
Generate Forecast Schedule . in both ways we can generate

• Go to Item -> SA Release Document


• So, Forecast Schedule generated with Release Number 1

• If we go to creation/Transmission tab, can see the creation profile we had maintained. Based on
that the aggregation takes place

• Click on Symbol “I” ( Profile details ) to see the details of creation profile

• Select Forecast schedule line & click on Schedule lines/release


• We had maintained weekly aggregation up to 100 days from the date of creation in creation
profile. So that it is aggregated in weekly wise

• Go back & SAVE


b. For JIT Schedule
• T code – ME38
• Select line item & Go to Edit -> Generate JIT Schedule

• Select the line item Go to Item -> SA Release Document

• So, JIT Schedule generated with Release Number 1


• We had maintained in creation profile like
• No aggregation in workdays - up to 6 days
• Daily aggregation in workdays – 7 - 10 days
• Select the JIT delivery schedule line with the Release number 1 & then Go to Schedule lines / Release
• We can see that the none of the scheduling agreement schedule lines after the 10th working day have
been taken into account in JIT schedule
• save

You might also like