Hit Construction Zimbabwe

no 93 Harare Drive Malbrough East


0242787912/0719985697
info@hitconstruction.co.zw
CIVIL & STRUCTURES www.hitconstruction.co.zw

Prepaid :15/03/2023 Client: D TYPE MODEL


Project : MAIN HOUSE CONSTRUCTION
Location : ARLINGTON ESTATE

Material List
item Description Unit Quantity Unit Price Cost

A Foundations

1 bricks - load bearing no. 10000 $ 0.18 $ 1,800.00


2 concrete stones m3 40 $ 35.00 $ 1,400.00
3 cement - 32.5 bags 195 $ 11.00 $ 2,145.00
4 riversand m3 40 $ 19.00 $ 760.00
5 pitsand m3 10 $ 16.00 $ 160.00
6 brickforce 230mm - 20m no. 16 $ 2.00 $ 32.00
7 brickforce 115mm - 20m no. 3 $ 2.00 $ 6.00
8 gravel - hardcore filling 150mm m3 120 $ 15.00 $ 1,800.00
9 damp proof course 230 m3 4 $ 2.00 $ 8.00
10 damp proof course 115 m3 2 $ 2.00 $ 4.00
11 meshwire s193 - 6m x 2.4m no. 8 $ 40.00 $ 320.00
12 DPM- black micro polythene sheet no. 1 $ 100.00 $ 100.00
13 termite poison 5ltrs 10 $ 2.00 $ 20.00
14 setting out materials item 1 $ 250.00 $ 250.00

TOTAL FOR FOUNDATIONS $ 8,805.00


item Description Unit Quantity Unit Price Cost

B Superstructure and Beams

1 Common bricks - load bearing no. 21000 $ 0.18 $ 3,780.00


2 facebricks - load bearing no. 0 $ 0.45 $ -
3 air bricks - PAIRS no. 24 $ 0.50 $ 12.00
4 brickforce 230mm - 20m no. 26 $ 2.00 $ 52.00
5 brickforce 115mm - 20m no. 5 $ 2.00 $ 10.00
6 concrete stones m3 5 $ 35.00 $ 175.00
7 cement - 32.5 bags 145 $ 11.00 $ 1,595.00
8 riversand m3 5 $ 19.00 $ 95.00
9 pitsand m3 20 $ 16.00 $ 320.00
10 deformed bars kgs 600 $ 1.25 $ 750.00
11 tying wire kgs 4 $ 1.00 $ 4.00
12 38X38mm timber brandering m 72 $ 1.45 $ 104.40
14 soffits- timber 228 x 38mm x 6m no. 10 $ 20.00 $ 200.00
15 timber struts - 76mm x 38mm x 6 no. 15 $ 14.00 $ 210.00
16 2m round poles no. 15 $ 4.00 $ 60.00
17 nails kgs 10 $ 2.00 $ 20.00
18 230 standard size door frames double door no. 0 $ 65.00 $ -
19 115 standard size door frames no. 4 $ 45.00 $ 180.00
20 230 standard size door frames no. 2 $ 60.00 $ 120.00

TOTAL FOR SUPERSTRUCTURE $ 7,687.40


SUMMARY MATERIAL LIST

A FOUNDATIONS $ 8,805.00

B SUPERSTRUCTURE $ 7,687.40

SUB TOTAL $ 16,492.40

CONTIGENCY SUM 0.1 $ 1,649.24

GRAND TOTAL- MATERIAL COST $ 18,141.64