7: PLTU Tanjung Jati B Unit 3 & 4
Desa Tubanan Kecamatan Kembang.
EE Kabupaten Jepara Jawa Tengah
llr Indonesia59453,
Tel,0291 4270493 Fax.0291 4270601
To: All Division Manager PageNo : 1/1
Ref: ITRN-25403-06-2023- 01}
Date: February 14", 2023
ce : Station Manager
From : Mr. Robert Manyuzar
HSE Manager
Subject: Full Cycle Contractor Safety Management System (CSMS) Implementation
Dear Sirs,
Refer to:
Standar PT. PLN (Persero) SPLN U1.006:2021 Keputusan Dircksi PT. PLN (Persero)
No.0325.K/DIR/2021 Tentang; Sistem Manajemen Keselamatan Kontraktor (Contrator
‘Safety Management System /CSMS);
TIB 3&4 Procedure Number : KPJB — 0958 12 Contractor Safety Management System
PT. KPIB Decision Making Number: PT. KPJB - 51202 - 06 — 2022 Subject ;
“Implementation of Contractor Safety Management System (CSMS) Policy PT. KPJB;
Herewith HSE Division would like inform to all Division:
1.
2.
Full Cycle CSMS Implementation process at PLN Holding by website; htips://esms,pln.co.id/
User of Material (Goods) / Service are required to submit / include the Safety Risk Level (
(Low, Medium, High, Very High, Extreme) on Term of Reference (TOR) in accordance tihe
Attachment 1. Risk Assessment or by attaching the Hazard Identification Risk Assessment
and Determining Control (HIRADC) where the Risk Level has not been identified at SPLN.
All Procurment Plan documents it is mandatory to include the level of work risk (Low,
Medium, High, Very High, Extreme) in the planning document / work plan document and the
requirements (Rencana Kerja dan Syarat - Syarat)
Started from 1 February 2023 until to 30 June 2023 all Procurement Process is Mandatory
Required to have a CSMS Certificate issued by PLN which can accommodate all Levels of
Work Risk.
. The implementation of procurement of High, Very High and Extreme Risk Level must
requirement a CSMS certificate accordance with Level of Work Risk Starting 1 July 2023ZZ PLTU Tanjung Jati B Unit 3 & 4
Desa Tubanan Kecamatan Kembang
Li Kabupaten Jepara Jawa Tengah
ae IndonesiaS9453
z= Tel,0291 4270493 Fax.0291 4270601
6. In the procurement process, Procurement Team is required to input contract data into the
CSMS aplication after contract / aggrement is signed.
7. For contractors who have fatality accidents and serious injuries, the CSMS certificate is not
valid until the final phase of the evaluation / work is completed and continued with the
revocation of the CSMS certificate in accordance with the provisions of SPLN U1.006: 2021
8. Exceptions to CSMS requirements are intended for government agencies/services, police,
military, health/hospitals, community social institutions, individuals and universities.
9, Full cycle CSMS Implementation will be included in the measurement of maturity level of
safety and become safety compliance performance in all operational units and directorates
‘Your timely response and affirmative cooperation regarding this matter will be highly appreciated.
Attachment;
1. Risk Assesement List
2. RASCI TabelZB
ZZ PLTU Tanjung Jati B Unit 3 & 4
Desa Tubanan Kecamatan Kembang
Le Kabupaten Jepara Jawa Tengah
Ze IndonesiaS9453
Tel.0291 4270493 Fax.0291 4270601
RASCI Tabel
Cet
o-
Gambar 1. Alur proses penerapan CSMS.
RASCI Aspect
No ‘Alur Tahapan Risk Assessment in | Se | ee
1. |Menentukan Ruang Lingkup, Jenis dan Kategori Pekerjaan s 1
Melakukan penilaian risiko pekerjaan sesuai dengan Daftar
2 |Risiko Pekerjaan atau Penilaianrisiko pekerjaan dangan re i
IBPPR standard HIRARDC jka pekerjaan belum terakomodir
|___|dalam Daftar Risiko Pekeriaan
3 |Menentukan level risiko pekerjaan berdasar Tabel Risk
[Assessment CSMS atau Form HIRARDC
KETERANGAN RASC!
R- Responsible Pihak yang melakukan suatu pekerjaan
‘A-Accountable Pihak evaluator/pengambilan keputusan
$S- Support. _Pihak yang memberikan dukungan sumber daya
C-Consulted —_Pihak yang dimintai pendapat'expert
I-Informed —_Pihak yang diberikan irformasi'stakeholderBB
Li,
PLTU Tanjung Jati B Unit 3 & 4
Desa Tubanan Kecamatan Kembang
‘Kabupaten Jepara Jawa Tengah
IndonesiaS9453
‘Tel.0291 4270493 Fax.0291 4270601
No
RASC Rapect
‘Aur Tahapan Pre Qualification miro
User_[_ HSE,
MOeM
hontaktor
1 [Kextraltor mengaiukan permchonan proses prakualfias|
[Tim Prakuaiikasi mengiimkan formu prakualiisi
konvaktorkepede kontraktor
Ikontraktor mens formu prakualfias|Korvaltor secar
[Set Assessment dengan metampirkan evidence tert
[Tim Prokuatfkasi melkukan verfixsi dokumen dan/atau
\erifkasi apancan kepada kontrakor
cn
lacara
[Tim Prakvalfkas! melaporkanhesi prakuslical dalam Bora
cn
losms
Metkukan veiiasl dan meverbikan seritkal Kuala)
cn
No
‘Alur Tahapan Pre Qualification
|Mempersiapakan dokumen permohonan proses pengadaan
|(PR, RAB, TOR, den Lain -Lain) dengan menambahkan Level]
IRisiko pekerjaan pada dokumen TOR (Term of Reference)
latau KAK (Kerangka Acuan Kerja)
|Membuat RKS (Rencana Kerja & Syare-syart) dengan
2 |menambahkan Level Risiko pkerjaan den mensyaratkan i
Ietengkapan dokumen rencana K3L (HSE Plan) dan Sertikat
Ikualkasi CSMS eiau Berita Acara Hasi Prekvalfkas|
13 |Peiabat pelaksana pengadaan mengumumkan atau i
|mengundang koniraktor sesuai dengan RKS
Kontraktor menyampaikan dokmen rencana K3L (HSE Pian)
4 |dan Seriiket CSMS yang beriaku atau Berita Acara Hasil
Prokualifkas’ kepada pejabat pelaksane pengedaan
5 [tdakrya doku
Prokvelitkas!|
/Pejabat pelaksana pengadan melakukan evaluasi ada atau
level risiko pada Serfikat CSMS/Berita Acara Hasil
smn rencana K3L (HSE Plan) dan kesesuaian ,
dengan level risko pada RKS.
|Jika dokumen
[Pengadaan dapat dianjutkan
Ginyatakn sesuai dan lengkap maka proses i
KETERANGAN RASCI
R- Responsible Pihak yang melakukan suatu pekerjaan
A-Accountable Pihak evaluator/pengambilan keputusan
$ - Support
C - Consulted
1- Informed
Pihak yang membenkan dukungan sumber daya
Pihak yang diminta pendapat'expert
Pihak yang diberikan informasi’ stakeholderZEA
PLTU Tanjung Jati B Unit 3 & 4
Desa Tubanan Kecamatan Kembang
Ee Kabupaten Jepara Jawa Tengah
a IndonesiaS9453
=A ‘Tel.0291 4270493 Fax.0291 4270601
WSC Repeat
No ‘Aur Tahapan Pre Job Aetvty Contraciot —[— Project Gwner
‘ito Rep [HSE Rep| User | Leader | NSE _|MOISM
Perenconnan dual Kickoff meeingperieman ove
1 |rnobises pekezan \ at] |
2 [Pdaksaraankckoff meeting 8 w fs [ot
5 |Perraranencana mobisas elas petapan don PSE ee De
Pian
[Evaluast HSE Pandan penentuan target KPIK3L 1
Penyusunan nolan Kick off meting dan Bridging Document
ka diperukan,
6 |Patoksenaan s
Safety induction
7 |Pengurusan working permit
2. |pelaksanaan mobilsasi
7 aise
ata
we dr Tahpan Workin Promos Canracar [hoe Garr
‘Site Rep | HSE Re} User | Leader Hse MovoM
7 [sear ara are
= fesieannnPaiaon a a Ca
np on Sep Wa Ay SA s | s | [ws 1
7 Pain ina Serre sts 1s [1s 1
KETERANGAN RASCI
R- Responsibl
le Pihak yang melakukan suatu pekerjaan
‘A- Accountable Pihak evaluator’pengambilan keputusan
'S - Support Pihak yang memberikan dukungan sumber daya
-Consulted —_Pihak yang diminta pendapatiexpert
I-Informed —_Pihak yang diberikan informasi stakeholderPLTU Tanjung Jati B Unit 3 & 4
Desa Tubanan Kecamatan Kembang
Kabupaten Jepara Jawa Tengah
Indonesias9453,
Tel.0291 4270493 Fax.0291 4270601
RASC Aspect
‘Aur Tahapan Final Evaluation
‘Contractor
Project Owne? | por.
‘Site Rop [HSE Rep
Usor_| Leader
ors
Ikontaktor memberitanukan kepada User Project bahwa
lpakeraan oan selesa dlakukan
luser Project meminta HSE Division untuk melakukan eves
lle kina K3 Konivaktor dengan mengisiformulrPeniaian
IKPIKaL Kontraktor
JASE Division malakukan evelaussitahap elir alas program -
lerooram K3 Kontrakor dan pelaksanaan dari indakan -
hincakan perbakan yang telah drekomendasikan saat
linspeksiassesmentlapangan diakukan bersama dengan
[cist pekeriaan
HSE Division memiberikan hasilevaluasl akhir 3 kontraktor
kepada User Division. Hasil evaluat akin juga memberkan|
Ikeputusan apakah level kinera K3 dalam sertfkat penlaian
letap atau mengalamperubahan
IRSE Division K3 memberkan hasl evaluss a berupa
rekomendasi pencabutan serfkat CSMS Diamana saat
pekeraan berlangsung konraktor mengalam kecelakaan kerja
yang berakbat kematan (atalty) atau itangrya jam kerja
[(UTMost Time injury)
cn
|HSE Division menyerahkan hail evaluasi akirKepace User
[Division dan Kontvaktor dan melakukan verficasi alr
{terhacap status Seritkat Kuafiasi CSS
KETERANGAN RASCI
R - Responsible : Pihak yang melakukan suatu pekerjaan
‘A- Accountable : Pihak evaluator/pengambilan keputusan
'S - Support Pihak yang memberikan dukungan sumber daya
-Consulted _: Pihak yang dimintai pendapat/expert
1 Informed Pinak yang diberikan informasi/stakeholder‘SPLN U1.006: 2021
NO AKTIVITAS KEGIATAN BIDANG TRANSMIS!
[Pemasangan dan pelepasan clam PT
3
6_|Pengukuran tahanan pentanahan
7_|Penguiian leakage current monitor LA
@_[Pemasangan dan pelepasan clam LA
@ [Pengukuran tahanan pentanahan
10 | Thermovisi Lightning Arrester (Online)
LEVEL RISIKO
oa]
on]
ro
REM
Pekerjaan pengoperasian WTP
Pekerjaan pengoperasian WWTP
Pekerjaan pengoperasian Coal Handling Facility
1
| 2 jPekerjaan pengoperasian WTP
3 [Pekerjaan pengoperasian Boiler, Turbin, Generator
4
5. |Pekerjaan pengoperasian H2 Plant
PEMELIHARAAN
[Rehabiltasi Refractory Cyclone
Perbaikan pompa Hpp SWRO
Perbaikan Plat Vortex Cyclone
(Cleaning area Furnace dan ESP
(Cleaning area Coal Feeder dan Bunker
Ej
Perbaikan kerusakan part instrument ESP.
[Cleaning area Furnance dan perbaikan Drain Coal Feeder
E
Perbaikan Kebocoran Wall Tube Boiler
c
|Condensor
Perbaikan Kebocoran Water Box Plat pemisah Inlet dan Outlet See Water
Perbaikan On Leak Sealing (OLS) Safety Valve Steam Drum
BEDRIESEoSESe
(Cleaning Pasir Area Furnace Unit
Perbaikan Lapping Valve Mov Discharge dan Valve Manual BFP
Cleaning Blocking Batubara Area Coal Feeder
Perbaikan Ring Hammer Coal Crusher
Perbaikan Expansion Joint Fan B
a
Penggantian Seal Drive Pully Belt
Conveyor
=
Penggantian Roller Idler Coal Handling
e
Perbaikan Modul lgnitor Burner Furnace
19 |Perbaikan Motor Valve Main Steam
20 |Perbaikan Strainer Debris Kondensor
24
Pemasangan Peralatan Instrument Part Boiler
43
11_|Pengujian Counter Arrester STREM
12 [Pengulian tahanan isolasi LA EKSTREM
Acuan level risiko pekerjaan bidang Pembangkitan:
INo AKTIVITAS KEGIATAN BIDANG PEMBANGKITAN aa
PLTU
OPERAS!
ea)
a
roa)
roaSPLN U1.006: 2021
INO AKTIVITAS KEGIATAN BIDANG PEMBANGKITAN aS
23 [Pemasangan Scafolding Eoin
24 |Perbaikan Shield Tube Furnace dan Economizer una
25 | Support dan Pengadaan Kabel Tray, Junction Box Transformator oe]
26 |Perbaikan Nozzle Fan Boiler Sue
27 [Perbaikan dan Reverse Engineering Card Modul n
28 |Perbaikan Gearbox Butterfly dan Travelling Screen n
29 [Perbaikan Coal Feeder oi
30 [Perbaikan Pompa CWP Poe
31 |[Perbaikan Hammer Crusher eg
32 [Perbaikan Embeded Tube
33 |Pekerjaan Overhaul PLTU cra)
34 [Perbaikan Online Leak Sealing Superheater iu
[PLTGIU
OPERAS!
[Pengoperasian Mesin / Engine
2 |Pengoperasian Turbin roy)
3. [Pengoperasian Generator Eo
4 [Pengoperasian Fasiitas Pendingin (Kondensor)
5. [Pengoperasian Pesawat Angkat - Angkut
6 [Pengoperasian Emergency Diesel Genset (EDG) / Black Start
7
é
9
[Pengangkutan dan penagunaan bahan bakar
[Pengangkutan dan penggunaan bahan kimia
[Pengoperasian H2 Plant
10 [Pengoperasian CNG Plant
PEMELIHARAAN
Pemelinaraan Turbin Gas
[Pemelinaraan Kompressor
[Pemeliharaan Generator
Pemelinaraan Pesawat Angkat Angkut
Pemeliharaan perlengkapam penyaluran Bahan Bakar
[Pemelinaraan Boller, Exhaust stack dan perlengkapan
Pemeliharaan insatalasi Air Pendingin
[Pemeliharaan Boiler, Exhaust stack dan perlengkapan
Pemeliharaan peralatan dan perlengkapan Fire Fighting System
Pemeliharaan Transformator
INSPEKSI
1 [Pengecekan Switchyard
2 [Performance Test
3 |[Pengujian NDT pada HRSG (Boller)
PLTD/ PLTMG
[OPERASI
1_ [Pengoperasian Satuan Pembangkit Diesel (SPD)
[ 2 |Pengoperasian alat bantu Kompresor
[65 [Pengoperasian alat bantu Radiator
lel@slelelelels/-
3
44SPLN U1,006: 2021
AKTIVITAS KEGIATAN BIDANG PEMBANGKITAN
[Pengoperasian HRTO.
[Pengoperasian Separator
[Loading dan Unloading BBM
[Pengoperasian CW dan JW System
Pengoperasian Fuel System
Pengoperasian Oil Lubrication System
Pengoperasian Air Starting System
Pengoperasian Generator
Pengoperasian Grane
Penerimaan minyak pelumas
Penerimaan Material/Spare Part
[Pemelinaraan PO-PS Satuan Pembangkit Diesel (SPD)
[Pemelinaraan Top Overhaul Satuan Pembangkit Diesel (SPD)
[Pemelinaraan Semi Overhaul Satuan Pembangkit Diesel (SPD)
[Pemeliharaan Major Overhaul Satuan Pembangkit Diesel (SPD)
[Pemeliharaan Generator
Pemeliharaan Kubikel
[Pemeliharaan Trafo
[Pemelinaraan Battery
Pemeliharaan Kompresor
Pemeliharaan Supply DC
Pemeliharaan Separator
Pemeliharaan Heat Exchanger dan Intercooler
Pemeliharaan Exhaust Gas System
[Pengoperasian Air Removal System
Pengoperasian Auxiliary Cooling Water System
[Pengoperasian Fuel System
Pengoperasian Generator (Circuit Breaker, Exciter, Transformer)
Pengoperasian Crane
Pengoperasian Main Cooling Water System
[Loading Bahan Kira
Pengoperasian Fire Protection System
|PEMELIHARAAN
1
[Pemeliharaan Air Removal System
Pemeliharaan Auxillary Cooling Water System
Pemeliharaan Fuel System
[Pemeliharaan Generator (Circuit Breaker, Exciter, Transformer)
[Pemeliharaan Crane
Pemeliharaan Main Cooling Water System
Pemeliharaan Fire Protection System
45SPLN U1.006: 2021
LEVEL
NO AKTIVITAS KEGIATAN BIDANG PEMBANGKITAN RISIKO
1 [Pengoperasian Water Gate System
2 |Pengoperasian Bendungan
33 [Pengoperasian Trash Rack System (Penyaringan Sampah)
4 |Pengoperasian Turbin
5
6
Pengoperasian Generator
Pengoperasian Transformator
7 |Pengoperasian Crane /Lifting System
PEMELIHARAAN
Pemeliharaan Water Gate System
[Pemeliharaan Dam System
Pemeliharaan Trash Rack System
Pemeliharaan Turbin
Pemelinaraan Generator
Pemeliharaan Transformator
[Pemeliharaan Crane /Lifting System
yfe]o]+]o]s]=
Acuan level risiko pekerjaan bidang Konstruks!
No. AKTIVITAS KEGIATAN BIDANG KONSTRUKSI LEVEL RISIKO
KONSTRUKSI JAR TRANSMIS!
PEKERJAAN PERSIAPAN KONTRUKS!
[Re-Check dan Re-Survey
[Tempat kerja Clearing
Inventarisasi Lahan dan ROW
[Tempat Kerja / Soil Investigation (Sondir dan Boring)
[Mobilisasi Manpower
[Pekerjaan pembuatan tempat kerja office dan gudang
PEKERJAAN SIPIL
(Pekerjaan Moblisasi dan handling material untuk peralatan pondasi
Pekerjaan galian dan timbunan
Pekerjaan setting stub
Pekerjaan pembesian pondasi
Pemasangan grounding rod
Pekerjaan pengecoran pondasi
[Back Fill dan Finishing
[Pekerjaan dinding penahan tanah (Retaining Wall)
PEKERJAAN ERECTION
[Mobilisasi material tower dan perelatan erection
[Sortir material
Pekerjaan pemasangan guy rope (skur) dan Bamboo derrick
Pekerjaan erection
48SPLN U1.006: 2021
AKTIVITAS KEGIATAN BIDANG KONSTRUKSI LEVEL RISIKO
Pengencangan baut
Final check
Pekerjaan tack weld atau lock nut
PEK
ERJAAN STRINGING
[Penebangan pohon (ROW)
a)
/Mobilisasi material dan peralatan stringing
Pemasangan isolator EKSTREM
Pemasangan montage roll
Pemasangan skur
Eeret-eret (puller) | penarikan tambang pancingan Panay]
Penarikan sling dan konduktor Boney
alee wo] 0)» els a
Pekerjaan Mid Span Joint (Penyambungan Konduktor)
[Sagging dan clamping
[Pemasangan spacer
Pemasangan Grounding
Final check
PEKi
ERJAAN TESTING dan COMMISIONING
1
Final check Ean
2
Tes Tahanan Isolasi
3
Energize (Pembebanan)
IKONSTRUKSI JAR GI
PEKERJAAN PERSIAPAN KONSTRUKSI
1
[Re-Check dan Re-Survey
[Tempat Kerja Clearing
[Tempat Kerja / Soil Investigation (Sondir dan Boring)
Mobilisasi Manpower, peralatan dan material
[Cut and Fill Eon
ola|ale|ro
[Pembuatan Pagar / Barricade
[Pembuatan Direksi kit, gudang dan plank name project
ITRAI
PEKERJAAN SIPIL JAR-GI PONDASI PERALATAN HV APPARATUS, GANTRY, PONDAS!
FO, FIREWALL, CABLE DUCT, AREA SWITCHYARD
1 [Galian pondasi
2 |Fabrkasi Besi Bone
3_[Lantai Kerja dan pembesian
4_ |Pemasangan Bekisting Fone
5 [Pengecoran
6 _|Pekerjaan Earthing grid = Poe
| 7_|Backtil ee
[8 [Pekerjaan dinding penahan tanah (Retaining Wall) Boned
[9 [Pekerjaan jalan (aspal)
10 [Pekerjaan jalan (beton)
PEKERJAAN SIPIL JAR-Gl CONTROL BUILDING
1
[Galian pondasi
47SPLN
U1,006: 2021
AKTIVITAS KEGIATAN BIDANG KONSTRUKSI LEVEL RISIKO
[Fabrikasi besi pondasi, sloof, balok, Kolom, cable duct dan plat
Pembesian pondasi, sloof, balok, kolom, cable duct dan plat
Pemasangan Bekisting pondasi, sloof, balok, kolom, cable duct dan plat.
[Pengecoran pondasi, sloof, balok, kolom, cable duct dan plat
[Pemasangan dinding batu bata dan plesteran
/Pemasangan rangka dan atap (GI Baru)
[Pemasangan plafon
Pemasangan Kusen, pintu, dan jendela
Pemasangan sanitary gedung
Pemasangan instalasi listrik
ERJAAN SIPILJAR-GIPRASARANA
ana
1 [Guard House (Pos Jaga) oe
2_|Pump House Ene
3. |Pekerjaan pagar
4
Drainage
PEKERJAAN E/M AREA SWITCHYARD
Mobilisasi peralatan dan material
[Erection steel support dan peralatan dan gantry (termasuk Final Check) Esco
[Erection HV Apparatus dan Trafo oa
Pulling and wiring cable
os |oo]ro] =
[Pemasangan conductor dan aksesoris (busbar dan crossbar)
é
Individual Test dan Pre-Commisioning Esau
PEMELIHARAAN
1
Mobilisasi peralatan dan material
Fixing panel (RCP dan Cubicle 20 kv)
3
Pulling and wiring cable
PEKERJAAN TESTING dan COMMISSIONING
Individual test dan pre-comissioning
Energize dan pembebanan
Pemelinaraan kubikel
Pemeliharaan trafo
Pemelinaraan battery
Pemelinaraan kompresor
Pemeliharaan supply de
Pemelinaraan separator
12
Pemelinaraan heat exchanger dan intercooler
13
[Pemeliharaan exhaust gas system
IKONSTRUKSI JAR GI
PEKERJAAN PERSIAPAN KONSTRUKSI
1_|Survey dan tempat kerja investigation (awal) |
2__[Mobitisasi, loading dan unloading material Ean
3__[Tempat Kerja Clearing
“4_|Tempat Kerja Development TREM
48SPLN U1.006: 2021
No
AKTIVITAS KEGIATAN BIDANG KONSTRUKSI
Pembuatan tempat kerja office dan gudang
LEVEL RISIKO
Pengoperasian main cooling water system
[Loading bahan kimia
Pengoperasian fire protection system
PEKERJAAN SIPIL SUBSTRUCTURE
Pekerjaan survey dan setting out (re-check for construction)
Pekerjaan galian dan timbunan
Pekerjaan pondasi dalam (tiang pancang)
Pekerjaan pembesian
Pekerjaan pengecoran (termasuk lantai kerja / lean concrete)
Demolition formwork (pembong karan bekisting/ scaffolding).
IPEKERJAAN SIPIL UPPER STRUCTURE
Pekerjaan erection steel structure boiler, main power house, bop
2_|Pekerjaan kolom dan dinding gedung
3 |Pekerjaan chimney
4_ [Pekerjaan atap dan plafon
5_[Pengecatan
PEKERJAAN SIPIL AUXILARY
1_[Pekerjaan acces road
2 |Pekerjaan jetty dan bangunan air (inlet, outlet, breakwater, water
tunnel)
PEKERJAAN MEKANIK
[Pekerjaan Handling Material
2_|Pekerjaan unloading dengan crane
3_|Pekerjaan instalation Equipment
4_|Pekerjaan Pengelasan dan NDE
5_|Pekerjaan individual test dan komisioning
PEKERJAAN ELEKTRIKAL
7
Pekerjaan pemasangan kubikel
eat]
oat]
ia]
Sa
Eon
2. [Pekerjaan penggelaran kabel power
3_[Pekerjaan pemasangan grounding
4_ |Pekerjaan pemasangan conduit pipe
5_|Pekerjaan lifting equioment
6 _|Instalasi pengkabelan / pengujian generator
7_[instalasi pengkabelan / penguiian transformator
8_[Pekerjaan pemasangan cable tray
9 |Pekerjaan terminasi kabel power
10 |Pekerjaan pengujian kontinuiti kabel power dan uj isolasi
11 |Pekerjaan pemasangan lampu
12 |Pekerjaan pemasangan cathodic protection
13 [Energize
14 [Commissioning
Ee
PEKERJAAN INSTRUMENT dan CONTROL
49SPLN U1.006: 2021
No AKTIVITAS KEGIATAN BIDANG KONSTRUKSI LEVEL RISIKO
1_[Pekerjaan kalibrasi equipment
2__|Mobilisasi material ke lokasi pemasangan a)
3__[Pekerjaan pemasangan pipa instrument rou]
4. |Pekerjaan pemasangan equipment instrument oy)
5 _[Pekerjaan penggelaran dan penarikan kabel kontrol Sone
6 _[Pekerjaan pemasangan panel
7_[Pekerjaan terminasi kabel kontrol
8 _|Pekerjaan pengujian kontinulti kabel kontrol
9 |Pekerjaan loop check Ene
10_|Pekerjaan interlock test
11. [Kommissioning ho]
12 |Pekerjaan installasi battery
13 [Pekerjaan pemasangan control vaive
14 [Pekerjaan pemasangan / kalibrasi analytical
IKONSTRUKSI KIT PLTMG
PEKERJAAN PERSIAPAN
1_|Survey dan tempat kerja investigation (awal)..
2 |Mobilisasi, loading dan unloading material. EKSTREM
3 [Tempat kerja clearing.
4 [Tempat kerja development. Eon
5_|Pembuatan tempat kerja office dan gudang
PEKERJAAN SIPIL SUBSTRUCTURE
1_[Pekerjaan survey dan setting out (re-check for construction)
2__[Pekerjaan galian dan timbunan’ Ex
'3_[Pekerjaan pondasi dalam (tiang pancang) one
‘4_|Pekerjaan pembesian
'5_[Pekerjaan pengecoran (termasuk lantai kerja / lean concrete) Eros]
6 [Demolition formwork (pembong karan bekisting/ scaffolding). Boe
PEKERJAAN SIPIL UPPER STRUCTURE
1 [Pekerjaan erection steel structure boiler, main power house, bop
2 |Pekerjaan kolom dan dinding gedung
3 |Pekerjaan chimney exhaust
4 _[Pekerjaan atap dan plafon EK
5_|Pengecatan Ee
PEKERJAAN SIPIL AUXILARY
1. [Pekerjaan acces road
2 _[Pekerjaan jetty dan bangunan air (inlet, outlet, breakwater, water tunnel)
PEKERJAAN MEKANIK
1. [Pekerjaan handling material
Pekerjaan unloading dengan crane ToT]
[Pekerjaan instalation equipment io]
[Pekerjaan pengelasan dan nde
[Pekerjaan individual test dan komisioning
50SPLN U1.006: 2021
AKTIVITAS KEGIATAN BIDANG KONSTRUKSI LEVEL RISIKO
Instalasi pengkabelan / pengujian transformator Boe
Pekerjaan pemasangan cable tray
1__Pekerjaan pemasangan kubikel
2 |Pekerjaan penggetaran kabel power ESney
3 |Pekerjaan pemasangan grounding
4 [Pekerjaan pemasangan conduit pipe EKSTR
5_|Pekerjaan iting equipment Oey
6 _[instalasi pengkabelan / pengujian generator oie]
7
é
3
Pekerjaan terminasi kabel power Eon
Pekerjaan penguijian Kontinulti kabel power dan ujiisolasi i
Pekerjaan pemasangan lampu EKSTF
Pekerjaan pemasangan cathodic protection
[Commissioning ona
[Pekerjaan pernasangan control vaive.
[Pekerjaan pernasangani kalibrasi analytical
IKONSTRUKSI KIT PLTA
PREPARATION WORK
[Survey dan tempat kerja investigation (awal)
2 |Mobilisasi, loading dan unfoading material Bone
3 |Tempat kerja clearing
4 [Pembuatan tempat kerja office dan gudang
[STRUCTURE WORK
1_[Mobilisasi material
2_ |Pekerjaan pembersihan dan pengerukan sungai ia
3 [Pekerjaan cofferdam (anak bendungan) ey)
4_|Pekerjaan pengeringan Oi
5 |Lantai kerja Bouse
6 _|Pemasangan bronjong (slope protection)
7__|Pemasangan batu pondasi
&_ [Destruction work (galian batu) oa)
| [Pekeriaan galian dan timbunan tanah (lermasuk pembuatan tanggul ay
| ° |bencungan
| 10 |Pekerjaan pondasi dalam (tiang pancang) ona
11 [Pekerjaan pembesian Sia
12 |Pekerjaan pengecoran (termasuk lantai Kerjalean concrete) oun
13_ [Demolition formwork (pembongkaran bekisting/scaffolding) Su
14 [Blasting work ois
15 |Pekerjaan terowongan
16 [Pekerjaan acces road
PEKERJAAN MEKANIK
1
[Pekerjaan Handling Material
51SPLN U1,006: 2021
AKTIVITAS KEGIATAN BIDANG KONSTRUKSI LEVEL RISIKO
Pekerjaan Erection Steel Structure Turbin House, Control Room
Pekerjaan Assembly Equipment
Pokerjaan Pengelasan
Pekerjaan individual test dan komisioning
PEKERJAAN ELEKTRIKAL
Pekerjaan pemasangan kubikel
Pekerjaan penggelaran kabel power
Pekerjaan pemasangan grounding
Pekeriaan pemasangan conduit pipe
Pekerjaan iting equipment
6 _[Pekerjaan pemasangan cable tray
7_|Pekerjaan terminasi kabel power EKSTREM
| 8 |Pekerjaan pengujian kontinuiti kabel power cua
| 9. [Pekerjaan pemasangan lampu EKSTREM
10 [Pekerjaan pemasangan cathodic protection
11 [Commissioning Pen
PEKERJAAN INSTURMENT dan CONTROL.
Pekerjaan kalibrasi equioment
Mobilisasi material ke lokasi pemasangan
Pekerjaan pemasangan pipa instrumen
Pekerjaan pemasangan equipment instrumen
[Pekerjaan penggelaran dan penarikan kabel kontrol
Pekerjaan pemasangan panel
Pekerjaan terminasi kabel kontrol
Pekerjaan pengujian kontinuiti kabel kontrol
Pekerjaan loop check
10
[Pekerjaan interiock test.
1
(Commissioning
IKONSTRUKSI KIT PLTB
[PREPARATION WORK
[Survey dan tempat kerja investigation (awal)
[Tempat kerja clearing
Pekerjaan jalan akses
Pekerjaan cable trench
Mobilisasi, loading dan unloading material
leleelep
Pembuatan tempat kerja office dan gudang
TRUCTURE WORK
Pekerjaan pondasi wind turbine generator
Pekerjaan pondasi switchyard
3
PEKERJAAN JETTY SEMENTARA (OPTIONAL)
PEKERJAAN MEKANIK
1
[Pekerjaan handling material
2
Pekerjaan erection steel structure
52SPLN U1,006: 2021
No AKTIVITAS KEGIATAN BIDANG KONSTRUKSI LEVEL RISIKO
3 [Pekerjaan asembly equipment
4 [Pekerjaan pengelasan
'5_|Pekerjaan individual test dan komisionin,
PEKERJAAN ELEKTRIKAL
Pekerjaan pemasangan kubikel
Pekerjaan penggelaran kabel power
Pekerjaan pemasangan grounding
Pekerjaan pemasangan conduit pipe
Pekerjaan lifting equioment
Pemasangan generator
Pemasangan trafo,
Pekerjaan pemasangan cable tray
Pekerjaan terminasi kabel power
Pekerjaan pengujian kontinuiti kabel power
Pekerjaan pemasangan lampu
12_|Pekerjaan pemasangan proteksi petir
13. [Pekerjaan pemasangan cathodic protection
14 [Pemasangan kabel 20 kv dari pole pli ke switchyard
15 [Commissioning
PEKERJAAN INSTRUMEN DAN CONTROL
Pekerjaan kalibrasi equipment
IMobilisasi material ke lokasi pemasangan
Pekerjaan pemasangan equipment instrumen
Pekerjaan penggelaran dan penarikan kabel kontrol
Pekerjaan pemasangan panel
Pekerjaan terminasi kabel kontrol
Pekerjaan pengujian kontinuiti kabel Kontrol
Pekerjaan loop check
Pekerjaan interlock test
Commissioning
KONSTRUKSI KIT PLTS.
PREPARATION WORK
1 [Survey dan tempat kerja investigation (awal)
2_[Tempat kerja clearing
3_|Pekerjaan jalan akses
4 |Pekerjaan cable trench
5_|Mobilisasi, loading dan unloading material
6 _|Pembuatan tempat kerja office dan gudang
alee
[STRUCTURE WORK
1 [Pekerjaan pondasi panel ory)
2__[Pekerjaan pondasi switchyard Peay)
3 |Pekerjaan jetty sementara( optional, Oey
PEKERJAAN MEKANIK
53SPLN U1.006: 2021
z
6
AKTIVITAS KEGIATAN BIDANG KONSTRUKSI LEVEL RISIKO
Pekerjaan handling material
Pekerjaan asembly equipment
Pekerjaan pengelasan
Pekerjaan individual test dan komisioning
KERJAAN ELEKTRIKAL
Pekerjaan pemasangan kubikel
[Pekerjaan penggelaran kabel power
Pekerjaan pemasangan grounding
[Pekerjaan permasangan conduit pipe
Pekerjaan Iifting equioment
Pemasangan trafo
Pekerjaan pemasangan cable tray
Pekerjaan terminasi kabel power ao)
Pekerjaan penguiian kontinult kabel power ema
Pekerjaan pemasangan lampu
Pekerjaan pemasangan proteksi petir
Pekerjaan pemasangan cathodic protection
Commissioning ane
|PEKERJAAN INSTRUMENT DAN CONTROL.
Pekerjaan Kalibrasi Equioment
IMobilisasi Material ke lokasi pemasangan
Pekerjaan Pemasangan Equipment Instrumen
Pekerjaan Penggelaran dan penarikan Kabel Kontrol
Pekerjaan Pemasangan Panel
Pekerjaan Terminasi Kabel Kontrol
Pekerjaan Pengujian Kontinuiti Kabel Kontrol
Pekerjaan Loop Check EKSTREM
Pekerjaan Interlock Test
[Commissioning Eo
cy
Bl a|ofr| |
2l2|=[2/2]* J+)» |]
elo|+2|2]+/*[s]=
‘Acuan level risiko pekerjaan yang membutuhkan izin Kerja Khusus:
"AKTIVITAS KEGIATAN
YANG MEMBUTUHKAN IZIN KERJA KHUSUS.
Pekerjaan Confined Space REM
Pekerjaan Hotwork EKSTREM
Pekerjaan Working at height ee]
Pekerjaan Vicinity oi
LEVEL RISIKO
Pekerjaan Near and underwater ita
Pekerjaan Lifting
Pekerjaan Isolation
Pekerjaan Excavation
Pekerjaan Chemical Handling
Pekerjaan Rediation Work
54Formulir Identifikasi Bahaya Penilaian dan Pengendalian Ri:
Lampiran 3
Tabel 3.1 Tingkat Kemungkinan
SPLN U1.006: 2021
Tingkatan Penjelasan
Kriteria i
Kemungkinan 3 Lingkungan Hidup
E Sangat Besar | Hampir dapat dipastikan akan terjadi | Sering terjadi
> 90% | insiden Untuk paparan ! exposure dan
Terjadi lebin dari‘ kali dalam rentang | atau menghasilkan waste / polusi
waktu 6 bulan terakhir ke lingkungan terjaci pada Untuk
konsumsi energi/ sumber daya
alam, terjadi pada aktivitas rutin,
Terjadi lebih dari 1 kali dalam
rentang waktu 6 bulan terakhir.
D Besar | Kemungkinan besar akan terjadi | Mungkin terjadi, umumnya terjadi
70% -90% | insiden pada aktiftas rutin,
. Untuk paparan / exposure dan
ried 1 all dalam rentang wektu 6 | stay menghasikan waste / polusi
aed ke lingkungan terjadi pada Untuk
konsumsi energi / sumber daya
‘alam, terjadi pada aktivitas rutin
Terjadi 1 kali dalam rentang waktu
6 bulan terakhi.
c ‘Sedang | Kemungkinan sama antara akan | Jarang terjadi. Umumnya terjadi
> 30%-<70 | tetjadi dan tidak terjadi insiden pada kasus abnormal atau Non
% Terjadi 1 kali dalam rentang waktu 1 | Rutin
tahun terakhir. Untuk paparan / exposure dan
atau menghasikan waste / polusi
ke lingkungan terjadi pada
| aktivitas non rutin / abnormal.
| Untuk konsumsi energi/ sumber
| daya alam, terjadi pada aktivitas
| non rutin / abnormal.
| | Terjadi 1 kali dalam rentang waktu
| | 4 Tahun terakhir.
B | Keel | Kemungkinan Kecil akan _terjadi | Hampir tidak pernah terjadi
| 10%-30% | insiden. Tidak pernah terjadi dalam rentang
| Tidak pernah terjadi dalam rentang waktu 1 tahun terakhir
| waktu 1 tahun terakhir.
A Sangat Kecil | Hampir dapat dipastikan tidak akan | Hampir dapat dipastikan tidak
10% | terjadi insiden akan pernah terjadi pelanggaran
Tidak pernah terjadi dalam rentang | @5Pek lingkungan.
waktu lebih dari 3 tahun. Tidak pernah terjadi dalam rentang
waktu lebih dari 3 tahun.
55SPLN U1.006: 2021
Tabel 3.2 Tingkat Dampak
Tingkatan Penjelasan
Dampak Kriteria K3 Lingkungan Hidup
5 Sangat 1. Kecelakaan mengakibatkan 1. Penutupan lokas! atau
Signifikan kematian atau gangguan fungsi_ | pemidanaan oleh KLHK
tubuh permanen, 2, Dampak langsung pada
3. Copal tatap/ kehiangen kerusaantnglungan sd var
| ‘sebagian fungsi tubuh namun aul
tidak memungkinkan untuk a Wise Restian Wonca
dipekerjakan kembali pada cose ter at kneel
bidang yang lin 4. Konsum enerai yang tidak
3. Kerusakan onitical asset dapat diperbaharui dalam
‘membutuhkan perbaikan > 6 jumlah besar dan kontinu
Bulan, atau penggantian 6, Disyaratkan dalam
4, Aset rusak berat (tidak dapat perundangan / persyaratan
digunakan lagi). lingkungan dengan Baku Mutu
5. Kondisi emergency (kebakaran / | 6: Terjadi pencemaran lingkungan
ledakan /keracunan masalcil)- | dilvar ambang batas KLHK dan
Disyaratkan dalam perundangan | _dampak terhadap lingkungan
/persyaratan lain yang terkait. pee Permanen, tidak dapat
4 Signifikan | 1. Kecelakaan dengan cedera yang | 1. Denda dari KLHK
mengganggu fungsi tubuh. 2. Dampak pada seluruh area
2. Cacat tetap / kehilangan perusahaan,
‘sebagian fungsi tubuh namun | 3. Pemulihan akibat dampak periu
masih memungkinkan untuk kualifkasi khusus,
dapat dipekerjakan kembali pada 4
bidoatans be 4 Menaheetan, limbah es .
3, Penurunan kesehatan permanen msiene| eneyl yang tiie
dapat diperbaharui dalam
/Himbuinya penyakitakibat kere. tia rotan ida
4. Kerusakan critical asset kontinu atau dalam jumiah kecil
membutuhkan perbaikan 1 - 6 tetapi kontinu
a 6. Terjadi pencemaran lingkungan
5. Aset rusak berat (periu diluar ambang batas KLHK dan
perbaikan), dampak terhadap lingkungan
bersifat permanen, tidak dapat
diatasi segera.
3 Medium 1. Cedera sedang. 1. Ada peringatan dari KLHK.
2. Perlu penangenan 2. Dampak pada beberapa
khususitindakan departemen dan perlu
‘medis/pemulihan. penanganan khusus tertentu.
3, Tidak menyebabkan Lost Time 3, Menghasilkan limbah Non B3
Injury (LT). 4, Konsumsi energi yg tidak dapat
4. Masa Recovery < 1 Minggu diperbaharui dalam jumtah
5. Kerusakan cntical asset besar tetapi tidak kontinu atau
membutuhkan perbaikan hingga _-Konsumsi dalam jumlah kecit
4 bulan. tetapi kontinu
G:Kenisaksh asst sedang. 5. Terjadi pencemaran lingkungan
diluar ambang batas KLHK dan
dampak terhadap lingkungan
dapat diatasi > 1 bulan
56SPLN U1.006: 2021
Tingkatan Penjelasan
Dampak Kriteria 3 Lingkungan Hidup
2 Minor 1. Cedera ringan dan dapat 1. Ada teguran dari KLHK.
ditangani dengan tindaken P3K | 2. Dampak pada area lokal unit
2. Cedera tidak menganggu fungsi_ | kerja.
tubuh 3, Limbeh dapat diperbaharukan /
‘3. Dapat kembali bekerja ci hari terdegradasi oleh lingkungan.
yang sama saat terjadinya 4, Konsumsi energi yg dalam
insiden. jumiah kecil dan tidak kontinu.
4. Kerusakan critical asset 5. Terjadi pencemaran lingkungan
membutuhkan perbaikan hingga namun masih dalam ambang
‘heart batas KLH dan dampak
5. Kerusakan aset ringan. terhadap lingkungan dapat
diatasi < 1 bulan.
1 Tidak Signifikan | 1. Tidak ada cedera yang terjadi. | 1. Tidak ada teguran dari KLHK
| 2. Kerusakan critical asset hanya 2. Tetjadi pencemaran lingkungan
membutuhkan perbaikan minor. namun masih dalam ambang
Kerusakan aset ringan. batas KLH dan dampak
|
|s.
|
I
terhadap lingkungan dapat
segera diatasi
87SPLN U1.006: 2021
Tabel 3.3 Tingkat/Level Risiko
Bias Selera Riso
‘Sangat Besar) E
; ews | 0
§ sean |
:
3 Kecil B
&
Sangat Kecil | A
1 3
Tidak Signifikan Medium Signifikan | Sangat Signifikan
Tingkat Dampak
Tingkat Risiko ditetapkan dalam 5 peringkat, mulai dari yang terendah sampai dengan
yang tertinggi sesuai dengan pedoman yang berlaku sebagai berikut.
* Ekstrem Risk/Risiko Ekstrem (E), kegiatan dihentikan can akan dilaksanakan jika
sudah dilakukan tindakan pengendalian risiko. Tindakan ini dilakukan segera setelah
penilaian risiko dilakukan.
* Very High Risk/Risiko Sangat Tinggi (VH), kegiatan dihentikan dan akan
dilaksanakan jika sudah dilakukan tindakan pengendalian isiko. Tindakan ini
dilakukan segera setelah penilaian risiko dilakukan.
" High RiskiRisiko Tinggi (H), tindakan pengendalian risiko dilakukan sesegera
mungkin namun pekerjaan masih dapat dilakukan dengan kondisi tertentu.
* Moderate Risk/Risiko Sedang (M), tindakan pengendalian risiko dilakukan dalam
waktu tertentu yang ditetapkan.
= Low Risk/Risiko Rendah (L), kendalikan dengan prosedur rutin dan tindakan
pengendalian tambahan dapat diambil bila diperlukan.
58leetcanatare) ll Wessels Gas
egies 5 | og eu
s 3
equals)“ seseg) “a. | Suepas oysiy / 4s!¥ 10.9p0
winpayy *E ‘Buepas) Bu oysiy / ysy Yi = HI AoueGiew3: = wa
Gi] teuougy: av
Joan) 2 pay] a | tim yebves ope in an = a ious NW
veyyuls you] “t | yay yeBues| y unysyg sy / sy awarng= 3} @i| unmyuon: uN
i :
dINWO LYHONLL _NYNDKONAINY OWIST AVON. = upny uy
s ueBues8}2y
MddAl aununod y'¢ joqe,
1202 ‘900° IN N1dS-