Requirement Origin Method

Must be possible to lock on To effectuate the treatment Procurement requirement

constant pressure and pressure process

levels

Should be customized such that To prevent patients from Procurement requirement

the pressure settings are adjusting pressure

lockable

Ought to be designed for tele To allow people to send the Interview with patients

medicine sleep data from home

Must not resemble a classic Suitable for the home Designers

MedTech product environment, reminds of

ailments

Fast Humble, Dependable, Value words based on patients Designers

Unpretentious

Detailed Requirements

Architectural requirements

Clench a rubber on the For the purpose of friction Observation patient

underside upon pressing buttons

Possible of adjusting To customize Benchmarking, and nurse

language usability test

Fitted with a control dial For navigation efficiency Benchmarking and nurse

usability test

Separate power on button For patients and users Patients Interview


interested in launching the

flow of air

Lower than 13 cm This is the height of the Mock-up test patients

lowest mock up design

Tube twisted towards the bed Mock-up test patients

Control dial towards the right Apparent connection to the Mock-up test patients

side of the display display

Humidifier installed towards To prevent muddling of the Mock-up test patients

the right side of the display tube and the display

Possibility of observing the To view the amount of water Nurse and patient Interview

level of water that is left

Shift to the clinic mode by To see to it that entering to Procurement requirements

pressing both buttons of 3 mode is deliberate and not an

seconds accident

The mask fitting test ought to Common function for nurses Observation nurse

be first to access
Schedule

CPAP Machine Project Schedule

Project Start Date 1/29/2019 Display 1

(Tuesday) Week

Project Lead  

WB TASK START END DAYS % WOR

S DON K

E DAYS

1 Theoretical Framework   -     -

1.1 Planning and   Tue Thu 5 100% 223

defining 1/29/19 12/05/19

1.2 Usage and design   Fri Wed 5 60% 9

expression 1/03/20 1/15/20

1.3 Transformation   Sat Sat 4 0% 5

2/08/20 2/15/20

1.4 Physical Product   Sun Sun 4 75% 10

3/01/20 3/15/20

1.4.1 Interface   Thu Wed 2 50% 10

4/02/20 4/15/20
1.4.2 Product   Tue Fri 5 0% 9

Architecture 5/05/20 5/15/20

1.5 Detailed Design   Sat Mon 7 0% 6

5/16/20 5/25/20

1.6 Process   Mon Mon 7 0% 6

management 6/01/20 6/08/20

1.7 Test Procedure   Tue Fri 4 0% 4

6/09/20 6/12/20

1.8 Deployment   Sun Mon 3 0% 1

6/14/20 6/15/20

Costing
CPAP Machine Design

Project Budget Fees Costs Implement Projec Maximu Actual

(1) (2) -ation t Price m Percen

Costs (3) Percent t of

of Total Total

Project Project

Price (5) Price

Pre-Construction Fees and

Costs

Design and Other $ $ $ $ 20.0% 14.9%

Engineering 2,00 3,000 5,000 10,000

Pre-Construction Services $ $ $ $ 15.0% 9.0%

1,00 2,000 3,000 6,000

Other Pre-Construction $ $ $ $ 17.0% 14.9%

Costs 2,00 3,000 5,000 10,000

Construction Fees and Costs

Design-Build Subcontractors N/A $ $ $ N/A N/A

1,000 1,000 2,000

Direct Purchase Equipment N/A $ $ $ N/A N/A

3,000 3,000 6,000


Construction Management $ $ $ $ 12.0% 9.0%

1,00 2,000 3,000 6,000

Project Engineering $ $ $ $ 12.0% 9.0%

1,00 2,000 3,000 6,000

General Conditions $ $ $ $ 12.0% 9.0%

1,00 2,000 3,000 6,000

Construction Completion $ $ $ $ 20.0% 14.9%

1,00 4,000 5,000 10,000

Subtotals $ $ $ $

9,00 22,00 31,000 62,000

0 0

Other Fees

Miscellenious $ $ N/A N/A

2,00 2,000

Contingency $ $ 9.0% 4.5%

3,00 3,000

TOTAL PROJECT PRICE $


67,000