This document provides a checklist for a third party audit of sewerage and septage management projects. It lists 34 technical documents that should be verified, including site drawings and designs, material testing reports, pump details, and work status of the sewage treatment plant. It also lists 5 points that the consultant would raise to the authority, such as trench depth and type of excavated road, and seeks a reply. The checklist aims to ensure thorough documentation and compliance for the audited infrastructure projects.
This document provides a checklist for a third party audit of sewerage and septage management projects. It lists 34 technical documents that should be verified, including site drawings and designs, material testing reports, pump details, and work status of the sewage treatment plant. It also lists 5 points that the consultant would raise to the authority, such as trench depth and type of excavated road, and seeks a reply. The checklist aims to ensure thorough documentation and compliance for the audited infrastructure projects.
This document provides a checklist for a third party audit of sewerage and septage management projects. It lists 34 technical documents that should be verified, including site drawings and designs, material testing reports, pump details, and work status of the sewage treatment plant. It also lists 5 points that the consultant would raise to the authority, such as trench depth and type of excavated road, and seeks a reply. The checklist aims to ensure thorough documentation and compliance for the audited infrastructure projects.
1. Name of the Project, city and implementing agency:
Name of the Project City Thane, Mumbai Name of Fortress Infracon Limited Third-Party Audit Consultant
Implementing agency
2. Technical Documents Verified by Third Party Audit:
Sr. No. Documents Requested by Whether TPA’s Remarks TPA Available for Inspection 1. Site Instruction (Site Order Book) 2. Record of Material/Equipment issued to Contractor 3. Lead Register of Material Brought on site 4. Physical and Financial bar Chart 5. Safety Plan 6. Excess-Saving Statement 7. Photograph Files 8. Time Extension (if Any) 9. Extra Items (If Any) 10. Soil Investigation Report 11. Drawings and designs of network 12. Set of Tender Documents 13. Set of General Layout and Working Drawings 14. Coarse Aggregate Test Report 15. Concrete Compressive Strength Test Report (Available/Not Available) 16. Bricks Compressive Strength Test Report (Available/Not Available) 17. Mix Design (Y/N) Report 18. If pumping is required, details of pumps and other appurtenances 19. Type of conduits, Details, dia etc. 20. General gradient of network 21. Outfall location, arrangements 22. % Coverage 23. Work Status of STP (Completed/Running) 24. Shape of Manhole (Circular/Rectangular 25. Inspection Chamber 26. Manhole Drops 27. Household connections 28. Total Length of collection network 29. Total number of Manholes 30 C/C distance between manholes 31. Trunk-main pipe length 32. Trunk-main pipe Dia. (mm) 33. Casing pipe/Steaning Depth 34. Types of Bricks used for Construction 35. Road excavation 36. Total Length of Road Restoration 37. Utility shifting
Sr.n Point Raised by Consultant Reply By Consultants Concluding Remark
o. TMC Concern Authority 1. Depth of trench found during inspection/ test check 2. Type of road excavated (moorum/Kaccha/BT/CC/Oth er) if any 3. Type in soil found (all kind of soil) Soft rock / Hard rock 4. Concrete cube test (Conducted or Not) 5. Grade of concrete is found as per design 3. Compliance Report: