Professional Documents
Culture Documents
HAC-10143-MS-CIV-002-Method Statement For Mass Concrete
HAC-10143-MS-CIV-002-Method Statement For Mass Concrete
HAC-10143-MS-CIV-002-Method Statement For Mass Concrete
Document Title:
METHOD STATEMENT FOR
MASS CONCRETE
Document No.:
HAC-10143-MS-CIV-002
If, despite best endeavors, a conflict should arise between this method statement and the project specification
the requirements of the latter shall be observed and this document revised, accordingly.
Prepared Checked Approved
Rev. Issue Date
Constr. Manager HSE Quality Project Manager
00 March 2022
Al Arish Simple Cycle Power Plant
Project No. 10143
HAC-10143-MS-CIV-002
Table of Contents
1.0 Scope: ............................................................................................................................................... 3
2.0 Purpose:............................................................................................................................................ 3
3.0 References: ...................................................................................................................................... 3
4.0 Responsibilities: ............................................................................................................................... 3
4.1. Project Manager:.......................................................................................................................... 3
4.2. Construction manager: ................................................................................................................ 3
4.3. Technical office Manager: ........................................................................................................... 3
4.4. Site Engineer: ............................................................................................................................... 3
4.5. QC Engineer:................................................................................................................................. 3
4.6. Laboratory Technician: ................................................................................................................ 4
4.7. Safety Officer: ............................................................................................................................... 4
4.8. Lifting Team:................................................................................................................................. 4
4.9. Supervisors, Foremen and Subcontractor(s): ............................................................................ 4
4.10. Fitters and welders: ................................................................................................................. 4
5.0 Methodology: .................................................................................................................................... 5
5.1. Execution of “Mass Concrete”..................................................................................................... 5
5.1.1. Scope. ................................................................................................................................... 5
5.1.2. Definition. ............................................................................................................................. 5
5.1.3. References. .......................................................................................................................... 5
5.1.4. Fresh concrete placement and temperature control. ....................................................... 5
5.1.5. Procedure of thermal curing ............................................................................................... 6
6.0 Finally ................................................................................................................................................ 6
7.0 Materials matrix ............................................................................................................................... 8
8.0 Tools / Equipment ........................................................................................................................... 8
9.0 Health, Safety and Environmental Requirements ......................................................................... 9
Al Arish Simple Cycle Power Plant
Project No. 10143
HAC-10143-MS-CIV-002
1.0 Scope:
This method statement details the method and sequence for execution of mass concrete elements
as indicated in project specs No. 10143-9-3PS-C00Z-01 Rev. 1 – Civil work - Exhibit D - Technical
Specifications Clause No. 9.11 Reinforced Concrete Work.
2.0 Purpose:
Execution of mass concrete elements methodology.
3.0 References:
• Project Specification–10143-9-3PS-C00Z-01 Rev.1.
• Approved shop drawings.
• All related Standards.
4.0 Responsibilities:
4.1. Project Manager:
• Monitoring all project activities regarding to project schedule.
4.5. QC Engineer:
• Shall report to the QA/QC Manager.
• Ensuring that the project inspection test plan(s) (ITP) has been briefed to and is then
followed by the construction team.
• Hold point Inspection for cast-in-place concrete.
• Inspect all the material delivered to the site with approval inspection.
• Coordinate with the third-party laboratory for all test for fresh and hard concrete
samples.
Al Arish Simple Cycle Power Plant
Project No. 10143
HAC-10143-MS-CIV-002
5.0 Methodology:
5.1. Execution of “Mass Concrete”.
5.1.1. Scope.
This section covers requirements for mass concrete as designated in Contract Documents.
As indicated in project specs clause 9.11. – Reinforced Concrete work
“The provisions of "Mass Concrete" shall be applied to the following structures:
• CTG Foundation.
• Stack Foundation.”
This for summarize thermal curing process employed for mass concrete.
5.1.2. Definition.
Mass concrete defined as “any volume of concrete with dimensions large enough to require that
measures be taken to cope with generation of heat from hydration of the cement and attendant
volume change to minimize cracking” This is as per ACI 301M-4
5.1.3. References.
• Project specification No. 99999-9-3PS-DP02-01
• American Concrete Institute
o (ACI-207) “Guide to Mass Concrete”
o (ACI-301M) “Specification for structural concrete”
o (ACI-305R) “Hot Weather Concreting”
6.0 Finally
o Curing water should not be more than approximately 11° C cooler than the
concrete, because induced surface strains may cause cracking
o The curing should be continued until the temperature deferential between
the concrete the concrete core and the coldest daily ambient temperature is
less than 21° C. and the temperature differential between the concrete
surface and the ambient air is less than 14° C
o For vertical elements (walls, piers, and columns, …) shutter will not be
removed till complete the normal water and thermal curing.
o Temperature readings measuring devices to be inspected before concrete
placement and reading tables checked as well.
Al Arish Simple Cycle Power Plant
Project No. 10143
HAC-10143-MS-CIV-002
Al Arish Simple Cycle Power Plant
Project No. 10143
HAC-10143-MS-CIV-002
▪ Safety boots.
▪ Safety helmets.
▪ High visibility Vest.
• Utilities shall be clearly marked and identified. Signboards identifying the type
of utilities shall be displayed at the relevant locations indicating limits of their
limits.
• Only allowed persons are permitted into the work zone. The barricades shall
be kept interlocked and continues at all the times. Any accident shall be promptly
reported to the safety department for further investigations and action.
• Barrier shall be added for the excavated borders.
• Caution tape shall be provided to all excavated area.
• Housekeeping and removing any unrequired materials to be ensured all the
time.