Professional Documents
Culture Documents
Administration - Sheet (1) 2
Administration - Sheet (1) 2
Administration - Sheet (1) 2
1
Assignment No.1 ERU Egyptian Russian University
Dr: Said Ahmed Mahrous Faculty of Engineering
Construction Administration Construction Department
------------------------------------------------------------------------------------------------------------
5-
2
Assignment No.1 ERU Egyptian Russian University
Dr: Said Ahmed Mahrous Faculty of Engineering
Construction Administration Construction Department
------------------------------------------------------------------------------------------------------------
6-
7-
8-
3
Assignment No.1 ERU Egyptian Russian University
Dr: Said Ahmed Mahrous Faculty of Engineering
Construction Administration Construction Department
------------------------------------------------------------------------------------------------------------
9-
10-
4
Assignment No.1 ERU Egyptian Russian University
Dr: Said Ahmed Mahrous Faculty of Engineering
Construction Administration Construction Department
------------------------------------------------------------------------------------------------------------
11-A project consists of 8 activities. The activity completion times and the
precedence relationships are as follows:
5
Assignment No.1 ERU Egyptian Russian University
Dr: Said Ahmed Mahrous Faculty of Engineering
Construction Administration Construction Department
------------------------------------------------------------------------------------------------------------
G 11 D,F
H 6 G,E
-Find the least time required to complete the whole project and identify the
critical activities .How is the project completion time affected if:
14- The table below defines the activities within a small project:
6
Assignment No.1 ERU Egyptian Russian University
Dr: Said Ahmed Mahrous Faculty of Engineering
Construction Administration Construction Department
------------------------------------------------------------------------------------------------------------
E Sales brochure A 2
F Cost analysis C 3
G Product testing D 4
H Sales training B, E 2
I Pricing H 1
J Project report F, G, I 1
15- Draw a network form for the following activity and find the critical path
and duration of project.
Activity Duration (days)
1-2 30
1-3 07
2-4 10
3-4 00
3-10 30
4-5 14
4-8 21
5-6 10
6-7 07
7-8 00
7-9 07
8-9 12
9-11 15
7
Assignment No.1 ERU Egyptian Russian University
Dr: Said Ahmed Mahrous Faculty of Engineering
Construction Administration Construction Department
------------------------------------------------------------------------------------------------------------
10-11 15
16- For the data given below of a construction project scheduled .Draw the
diagram and determine the critical path and all floats.
Activity Predecessor Duration
(weeks)
A - 6
B A 7
C A 1
D - 14
E B 5
F C,D 8
G C,D 8
H D 3
I H 5
J F 3
K E,J 4
L F 12
M G,I 6
N G,I 2
O L,N 7
--------------------------------------------------------------------------------------------