Professional Documents
Culture Documents
Operations Research (Organizer)
Operations Research (Organizer)
Queuing Model
Non Linear
Game Theory
K
Programming Problem
112
122
133
136
ARE
Duality Theory
L 140
We
Ne
POPULAR PUBLICATIONS
, with the same objective, ruling the optimal decision in battle. In fact that many experts
Consider the start of Operational Research in the III century B.C., during the II Punic
With analysis and solution that Archimedes named for the defense of the city of
Syracuse, besieged for Romans. Enter his inventions would find the catapult, and a
system of mirrors that was setting to fire the enemy boats by focusing them with the
Sun's rays.
Leonardo DaVinci took part, in 1503, like engineer in the war against Prisa due to he
knew techniques to accomplish bombardments, to construct ships, armored vehicles,
cannons, catapults, and another warlike machine.
Another antecedent of use of Operational Research obeys to F. W. Lanchester, who made
a mathematical study about the ballistic potency of opponents
and he developed, from a
system of equations differential, Lanchester's Square Law,
with that can be available to
determine the outcome of a military battle.
Thomas Edison made use of Operational Research, contributing
in the antisubmarine
war, with his greats ideas, like shields against torpedo for
the ships.
From the mathematical point of view mathematical, in
centuries XVII and XVIIL,
Newton, Leibnitz, Bernoulli and Lagrange, worked
in obtaining maximums and
minimums conditioned of certain functions. Mathematical
French Jean Baptiste Joseph
Fourier sketched methods of present-day Linear Programming.
century XVIII, Gaspar Monge laid down the precedents And at late years of the
to his development of Descriptive Geometry.
of the Graphical Method thanks
Janos Von Neumann published his work called
"Theory of Games", that provided the
basics Mathematicians to Linear Programming.
At a later time, in 1947, he viewed the
similitude among them Programming
linear problems and the
developed himself. matrix theory that
In 1939, mathematical Russian L. Kantorovich,
in association with
Dutchman T. Koopmans, developed the mathematical
the mathematical theory called "Linear
programming", thanks to that went rewarded
with the Nobel.
OPRS-2
OPERATIONS RESEARCH
the late
years 30, George
Joseph Stigler presented
al diet optimal or more particular problem known as
a particular
worry of the commonly known prooiime bout
as problem of the diet, which came about
USA army to guarantee
byt equests for his troops to the
st Drice. It was solved with a heuristicsome
lowest
nutritional requests
imes against the solution contributed yearsmethod which solution onlyly differs in some
later
the years 1941 and 1942, Kantorovich by the Simplex Method. independent
ring the
During
Duhe Transport Problem for first time, and Koopmans studied in
knowing this type of problems like proo f
VaopImans-Kantorovich. For his solution, hat are related
they used geometric methods that are related to
Minkowski's theorem of convexity.
believed that Charles Babbage is
t is beli
It the father of the Operational Research due tto his
abou
research out the transportation's costs and sorting of mail realized for the Uniform
research
Penny Post in in England in 1840
tit does not considered than has been born a new science called Operations Researoch
until the II World War, during battle of England, where Deutsche Air Force, that is the
Luftwaffe, was submitting the Britishers to a hard Air raid, since these had an little aerial
Capability, although experimented in the Combat. The British government, looking for
some method to defend his country,
convoked several scientists of various disciplines for
try
to resolve the problem to get the peak of benefit of radars that they had. Thanks to his
work determining the optimal localization of antennas and they got the best distribution
of signals to double the effectiveness of the system of aerial defense.
To notice the range of this new discipline, England created another
groups of the same
United States
nature in order to obtain optimal results in the dispute. Just like
when joined the War in 1942, creating the project
SCOOP (Scientific Computation Of
Optimum Programs), where was working George
Bernard Dantzig, who developed in
1947 the Simplex algorithm.
(URRS), excluded of the Plan Marshall,
During the Cold War, the old Soviet Union Berlin. In
communications, including routes fluvial, from
wanted to control the terrestrial deutsche
and his submission to be a part of the
order to avoid the rendition of the city, by means
States decided supplying the city, or else
communist zone, England and United by means
would be able to give rise to.new confrontations) or
of escorted convoys (that in any event the blockage from Berlin. Second option was
of airlift, breaking or avoiding .June 25, 1948. This went another from the
(airlift) at
chosen, starting the Luftbrücke year, could carry
SCOOP group, in December of that same
problems in which worked the Operations optimized the supplying to get
Research
4500 daily tons, and after studies of This cipher was the same that would have
March of 1949.
to the 8000-9000 daily tons in aeCided to suspend the
blockage
means, for that the Soviet
een transported for terrestrial
(energy,
atMay 12, 1949. United States' resources (USA)
After Second World War,
the order of by. models of
took opportune to accomplish it
supplies)
dmaments, and all kind of
resolved intervening linear progradnmngResearch is being developed, the
nization, doctrinie of
Operations time of
same time, that the developing, thanks them the
the of computation and
computers are also
Tesues decreased.
ution of the problems
OPRS-3
POPULAR PUBLICATIONS
there are various properties that constrain the blends produced. These include the octane
number, lead and sulfur content, volatilities and Reid vapor pressure, to name a few. In
addition, regulatory constraints impose certin restrictions as well.
As an initial response to this complex problem, in the early to mid 1980's Texaco
developed a system called OMEGA. At the heart of this was a nonlinear optimization
model which supported an interactive decision support system for optimally blending
gasoline; this system alone was estimated to have saved Texaco about $30 million
annually. StarBlend is an extension of OMEGA to a multi-period planning environment
where optimal decisions could be made over a longer
planning horizon as oppósed to a
Single period. In addition to blend quality
constraints, the optimization model also
each period in the planning
ncorporates, inventory and material balance constraints for
modeling language called GAMS and a
norizon. The optimizer uses an algebraic managing
with a relational database system for
nonlinear solver called MINOS, along
within a user-friendly interface and in additionto
ata. The whole system resides scenarios for
also be used to analyze various what-if"
blend planning it can
ediate
e Tuture and for long-term planning a
third application we look at the use of
For our
FMS
Scheduling at Caterpillar: was applied to derive schedules for a Flexible
model interested reader may refer to
Aation model. This Caterpillar, Inc. [3]. The typically, they are
utacturing System (FMS) atmanufacturing for details about FMSs;automated
on computer integrated together by anan automated material
machines linked question at
at
systems
of gene
general purpose CNC computers. The FMS in question
Che FMS
hand controlled by
lling system and completely
OPRS-5
POPULAR PUBLICATIONS
Caterpillar had seven CNC milling machines, a fixturing station and a tool ol station,
material and tool handling being performed by four automated guided
vehicles With ire
aveling alon a one-way guided wire path. FMSs can provide tremendous increas)
inherent in therm
capacity and ctivity because of the high levels of automation
their notet
their potential O to manufacture a wide variety of parts. On the other hand,
this c nd
a price; these systems are also very complex and the process he planning and scheul
very difficult uing
difficlt one "
production on an FMS and then controlling its operation can be a
erfect on the magnit
ency of the scheduling procedure used can have a profound nitude
of the benefits realized.
was being underutilized and
Caterpillar, a preliminary analysis showed that the FMS m
the
the objective of the project was to define a good production schedule that uld
woulc improve
improv
orientation phase
ualization and free up more time to produce additional parts. In the
was determined that the environment was much too complex to represent it accuratel
urougn a mathematical model, and therefore'simulation was selected as an alternative
span (which is the
modeling approach. It was also determined that minimizing the make
time required to produce all daily requirements) would be the best objective since this
wOuld also maximize as well as balance machine utilization. A detailed simulation model
was then constructed using a specialized language called SLAM. In addition to the
process plans required to specify the actual machining of the various part types, this
model also accounted for a number of factors such as material handling, tool handling
and fixturing. Several alternatives were then simulated to observe how the system would
perform and it was determined that a fairly simple set of heuristic scheduling rules could
yield near optimal schedules for which the machine utilizations were almost 85%
However, what was more interesting was that this study also showed that the stability of
the schedule was strongly dependent on the efficiency with which the cutting tools used
by the machines could be managed. In fact, as tool quality starts to deteriorate the system
starts to get more and more unstable and the schedule starts to fall behind due dates. h
order to avoid this problem, the company had to suspend production over the weekents
and replace worn-out tools or occasionally use overtime to get back on schedule. The key
point to note from this application isthat a simulation model could be used to analyze a
highly complex system for a number of what-if scenarios and to gain a betr
understanding of the dynamics of the system.
Fleet Assignment at Delta Airlines: One of the most challenging as well as rewardng
application areas of O.R. has been the airline industry. We briefly describe here one su
application at Delta Airlines [4. The problem solved is often referred to as the tiee
assignment problem. Delta flies over 2500 domestic flight legs each day and uses ab0u
450 aircraft from 10 different fleets, and the objective was assign aircraft to fiign
to ifa
in such a way that revenues from seats are maximized.
The tradeoff is quite simpi
plane is too small then the airline loses potential revenue from passengers who ca cannottbe
accommodated on board, and if it is too large
who
then the unoccupied seats represent
reprcrate
s
last
revenue (in addition to the fact that larger aircraft
are also more expensive to operalwhen
Thus the objective is to ensure that an aircraft
of the "correct" size be availaoi Is
required and where required. Unfortunately, happen
ensuring that this can nay
OPRS-6
tremendously
a1sly complicated OPERATIONS RESEARCH
since there
bility of aircraft: at different are a number
hlem is modeled times and locations.of logistical issues that
by a
hefion could result in about very large mixed-integer cosra" the
*
ormfor each problem is one 60,000 variables and linear prograr ram a typical
day 40,000 constraints.
hoated
sis repeated each day (CXCeptions
each since the assumption The
Tn planning
repeahiective such as weekend is made that the ssame schedule
of the problem
things as crew is to minimize schedules are handled separatey arately). The
SUch cost, fuel cost the sum of operating
evenues. The bulk of the constraints
and landing ot o
fees) and costs from
costs (including
passeng
ervation of flow o aircrart trom are structural in nature and result fromlost modeling tne
tem at different scheduled arrival the different fleets to different locations
ystem
arounu
verning the assignment of specificand departure times. In addition there are constraints
governing
fleets to specific constrain
also constraints relaung to the availability
are legs in the flight schedule.
schedule. There
1nere
governing
sOverning crew assignments, of aircraft in the different fleets,
estrictions. AS the
Scheduled maintenance reguiauos
reader can imagine, the requirements, and airport
teformation required to task of gathering and maintaining
mathematically specify all the
While building
such a model is difficult but of these is in itself a tremendous task.
antimality was impossible not impossible, the ability to
until the very recent past. However, solve it to
developed to the point computational O.R. has
that it is now feasible to solve
Delta is called Cold start and uses
such complex models; the system at
highly sophisticated implementations
integer programming solvers. The financial benefits
of linear and
from this project were tremendous,
for example, according to Delta
the savings during the period from June 1 to August 31,
1993 were estimated at about
$220,000 per day over the old schedule.
KeyCorp Service Excellence Management System: For
our final application we turn to
the service sector and an industry that employs
many industrial engineers banking. This
-
tightly controlled and good records, and "C items" with the simplest controls possible
and
minimal records.
The ABC analysis provides a mechanism for identifying items that will have a significant
impact on overall inventory cost, while also providing a mechanism for identifying
different categories of stock that will require different management and controls.
The ABC analysis suggests that inventories of an organization are not of equal value.
Thus, the inventory is grouped into three categories (A, B, and C) in order of ther
estimated importance.
'A' items are very important for an organization. Because of the high value of these 'A'
items, frequent value analysis is required. In addition to that, an organization needs to
choose an appropriate order pattern (e.g. Just- in- time') to avoid excess capacity. B
items are important, but of course less important than 'A' items and more important than
'C' items. Therefore 'B items are intergroup iterms. C' items are
marginally important.
b) Write note on Bin Card. WBUT 2014
Answer:
A bin card is a common element in a perpetual inventory
system. "Perpetual" simp
means the inventory is always in flux. A bin card is particularly common etail
in a r
stockroom. The card includes a number of data points
about a particular product, Du
most important function is to show how many units
of a particular product are in stock.
OPRS-8
What are thefunctions of purchase OPERATIONS RESEARCH
Answer: department?
aior companies and even some WBUT 20141
MOment department
procu government
as
pre organizations
that is the backbone part of everyday operations. have a ipurchasing or
sorganizations. Many of many manufacturing, These departme
artments provide
individuals, even retail, military and
at the purchasing department some who work for these industrial
other inuu
tand better what does, why companies,
npanies, are aware
understand it exists or what purpose
the role of the purchasing
performs. oses it serves. To
it
department mctions
is, consider some functions
wnlain the difference
d) Exp between marketing
Answer: and selling.
WBUT 2014]
and sales are both
Marketing and
aimed at increasing
intertwined that
intertv revenue. They
peopie orten don't realize ney are so closely
emall organizations, the difference between
the same people typically the two. Indeea,
Nevertheless, perform both sales and marketing in
Na marketing is different from tasks.
sales and as the organization
and responsibilities become more
specialized grows, the roles
Comparison chart
Marketing
Approach Broader range of activities Sales
to sell makes customer demand match
product/service, client relationship etc.;products the|
determine future needs and has a strategy the company currently offers.
OPRS-9
POPULAR PUBLICATIONS
MMING
FORMULATION OF LINEAR PROGRAMMIN
PROBLEM
guestions
LMultiple Choice Type
1. WBUT
For an LPP 2013
aonly the objective function needs to be linear to be linear
Only the constraints' equation/inequalitytoneed
Conly the non-negativity conditions need be linear
d) all these three must be linear
Answer: (d)
OPRS-10
What is the method used to OPERATIONS RESEARCH
7.
solve an LPP
involving artificlal
artificial varian
a) Simplex method variables?
ESTIONN
c) VAM b) Charnes-M-methodMODEL QUESTION
Answer: (b) d) None of
these.
8. basic feasible solutions
of the system
t*X =8 of equations
quations [MODEL QUESTION]
3x +2x, = 18 are
a) no basic solution
b)(2,6,0)(6,0,2)
(,7,0) (7,1,0)
d(2,2,0) (6,6,2)
Answer: (b)
oPRS-11
POPULAR PUBLICATIONS
Answer:
Let x and x, production runs must be undertaken for the processes
1
d 2 respectively
and
so that we are to
Maximize z = 4x, + 6x,
Subject to the constraints:
6x +5x, 250
4x+6x, 200
6x +5x, 2150
9x +5x, 2130
and * 20.
. Four different metals namely Fe, Cu, Zn, Mn are required to produce three
Zn, ka
commodities A, B and C. To produce one unit of A 40 kg Fe, 30 kg Cu, kg Mn4 are
7
Mn are needed. Similarly to produce one unit of B 70 kg Fe, 14 kg Cu, 9 kg
required and for producing one unit of C 50 kg Fe, 18 kg Cu, 8 Kg Zn are required
The total no. quantities of metals are 1 ton Fe, 5 Quintals Cu, 2 Quintals Zn and Mn
each. The profits are Rs 300, Rs 200, and Rs 100 in selling per unit of A,
B and c
500T
IHNLIANLAII
NIIIIIAITIUUTMUMDK
300
100
100 300
2 +3x 21200
tS 400
2x+1.5x,2900
This LPP has no feasible region.
OPRS-13
POPULAR PUBLICATIONS
Answer:
X2
70 z
at D(0, 3) 21
XI
3x +8x, s24
+ S4
10x+7x, s35
Therefore, n and=
7. A small ink manufacturer
Rs. 3 per bottle and sells at aproduces a certain type of ink at a total
average cost of
price of Rs. 5 per bottle. The
week-end and is sold during the following ink
is produced over the
weekly demand has never been week. According to past
less than 78 or greater than experience the
Formulate the loss table. 80 bottles in his place.
Answer: WBUT 20161
Demand
78 79 80
Production 78 0 0 0
79 3
0
80
63 0
Loss Table
8. Explainthe purpose of
problem. What is degeneracySlack variables and Artificial
in Linear Programming variables used in LP
Problem? WBUT 20171
OPRS-14
OPERATIONS RESEARCH
Answer
implex algorithm, in a
maximization problem
type
constraints are
converted to equality to convert standard form, less than
ert thestandara
variables. Slack variables
help to form the
iing slack'
type constraints after introduCIng* lack
we could not find initial basis initial basis of simplex algor
lgorithm.
in a
d surplus variables,
and.
and surplus initial
then to form initial
standard
ard form LPP after incorporating S1aack
torm of LPP
in feasible solution,
basicfe basis we var
In a basic if any one of the basichave to introduce artificiallevel he
then the
solution is called degenerate. variables occu
ccurs in zero
The 1 constrain needs a slack variable xs (say) and the constrain needs a surplus
2
variable xy (say). Now, writing the problem in its standard form, we get
Maximize Z=x-3x, + Sx,-Sx, +0x, +0.x,
subject to
+2 +X4-* +s=7
-2+X, -X5 -X, =2
-3x +X +2x, -2x, =5,
20.
z4ks,¥
[MODEL QUESTION]
10.Define convex set.
Answer: x, x, EX, the line
convex set it, for any two points
Convex Set: A set X is said to be a
Segment joining those two points
be also lie in the set.
Questions
Long Answer Type
QUESTION
programming. [MODEL QUESTION]
in Linear
a Explain the major assumptions
assumptions
Answer: optimisation if the following major
T inear programming can be used for
are satisfied
OPRS-15
POPULARPUBLICATIONS
lamne aecorator manufactures two types of lamps, Alpha and Delta. Both thi
lamps require the services a cutter and a finisher. Alpha requires 3 hours of
cutter's time and 2 hours ofof finisher's time. Delta requires 2 hours of cutter
er's time
a nour of finisher's time. The cutter has 180 hours finisher has 110 hours tima
each
E month.
onth. An gives a profit of Rs.10 and a Delta a profit of Rs. 7.
Alpha type gives
probiem
Formulate the problem of how many lamps of
Omulate p of each
each type should be
type should be produced
produced each
month as a LPP. Solve this LPP and each
obtain the optimal solution.
[MODEL QUESTION
Let ,
Answer:
n, be the no. of alpha and delta type lamp respectively
Formulation: Max. Z =10x
+7x
Subject to 3x+2x, s180, 2x +x, S110;
Optimal solution by graphical
method:
,x 20
OPRS-16
OPERATIONS RESEARCE
C,B |
C
5
1
2
00
,
0
Mini. ratio
S/3
2 0
0
5/3 1
2/3 1/3 0 2
|7, 2
-1/3| 1/3 0
1/3 0 1/32/3
1
2 1 0
+0+-=
Or, +0 +0--= s0
(Gomory's constraint)
- +XS-1 .()
OPRS-17
POPULAR PUBLICATIONS
(lable-2 for dual simplex algorithm for the solution ofthe problem).
Table-2
Min 2
CB
1 1/3 0
1/3 -2/3 0 1/3
0 0
0
1/3 1/3 0
0 -1/3 1/3
0
-1
-
Since all of xj, 2 and
0 0
0 0
x 20
2/3 1/3
30
20 C4,18)
D6, 18)
10 ItZI 40
X 20 30
-10t
3 +2 =30 1 +3 =60
X2
A(15,0)
=6, x =12 and zmin240.
ce the required solution
is x
OPRS-19
POPULAR PUBLICATIONS
S0
10
X
O
2
S0
50 t 70 90
X
+5x =150
8x,+4x, =80
=
200
5x+5x, =100 P+4x
OPRS-20
OPERATIONS RESEARCH
are OACO is the feasible region.
Z= 30, Z|=80,
AtA
At C Z=0
opticalsolution is
So the x =0, x, Ato
=20
3. Solve graphically:
Minimizez=x\+X2
Subject to 5x+9x2 [MODEL QUESTIONI
S 45
X+ X222
2 S4
and X, X220.
Answer:
S +9x2 = 45
E
23 4 6 9
1t22
The shaded region ABCDEA is the convex
set of feasible solution. Now,
A=(2,0). B =(0,2). C=(0,4).
D=4 and E=(9,0)are the vertices of this
convex set. Minimum Z attains both
at A=(2,0), B=(0,2).
Min. Z 2. Note that every point on the line AB is an optimal
solution.
20 WBUT 2016]
OPRS-21
POPULARPUBLICATIONS
Answer
we begin by solving value constraint,
graphically the related LPP, ignoring the integer
which yields 268
max 13
"18
(29
13' 13
4+16x, s32
X
14x+4x,28
SInce neither x nor x is integer we can choose either variable to begin implementation
of the next step.
20
13
2-14 22
246 324
13 13
Z 22
=1 =2 No feasible solution
13
No feasible solution
4=25
Hence, the solution is z,a14, l, X =l
25
20
IS 20 25 2x+6y = 60
Sx+2y 50 r+3y=36
OPRS-23
POPULARPUBLICATIONS
OABCDO is the
feasible region.
Z=200 Z=300
At A
2=240, z330, At
At B At C
So the optical
solution is x=3,
y=9
TV requires 4 hon
urer produces TVs and VCRs in a factory. Each
o assemble 2. Each VCR requires
hours to workstation 1 and 2 hours in workstationworkstation 2. Workstation4
ana 2 function for 40 hours and 60 fit on each
TVis Rs. 3000 and on hours respectively in a w TVs, VCRs are
each VCR is Rs.4000. Assuming that all the
What should so as to earn maximum
profit using LPP? be the strategy of the manufacturer [MODEL QUESTION
Answer
et and x, be the numbers of TV and VCR to be produced to maximize profit.
W.S,-I W.S.-II
TV 4h | 2h
VCR 2h |
5h
The L.P.P. is 40 h 60 h
Max Z =3000x, +4000x,
subject to
4x +2x, S 40 (for W.S. 1) -
20.
20 30
A=(0,12), C=(10,0)
Optimal solution: x =5, x, =10 and Max Z=Rs.55,000/
OPRS-24
OPERATIONS RESEARCH
SIMPLEX METHOD
Multiple Choice Type
Questions
Some Linear Programming
a) a unique Problems
optimal solution may have WBUT 2013]
c) no solution b)an infinite number of optimal solutions
Answer: (d) d) all of these
OPRS-25
POPULARPUBLICATIONS
an 4-C 20 with some
So
8. multiple solutions,
In Simplex method, there will be MODEL QUESTION
Z-C=0 corresponding to vectors
a) all vectors b) only basis
d) none of these
c)basis vectors and non-basis vectors
Answer:
Answer: (c)
guestions
ShortAnswer Type
WBUT 2015
T. Find the basic feasible solutions of the set of equations
2x-y+3z +t = 6; 4r-2y-z+ 2 =16
Answer: We have
2x-y+3z +t = 6
4x-2y-z+2t = 16
This system of equations can be expressed in matrix form:
,,,,}=
4-1)4-13-
Let
Now, |=0,
B-.,
-
A-{.). B={4,). B,={i,), B,={2,,), B,={4.}
|B, |=-14,|B,=0,|B,=7, |B, |=0, |B.=7
Therefore,
27
B 3 2]16 14-s4
14-4 8
So, B.F.S. i
-54
7613]6 7
B.F.S. is 0,-
OPRS-26
RESEARCH
OPERATIONS
and
B.F.S. is 0,
CB B
a
oPRS-27
POPULARPUBLICATIONS
Answer:
rom the column ,. it is clear that the first constraint
is of 's' form and also
from
COnumns and a, it is clear that the 2d constraint is of 2' form.
The original L.P.P. is
given by Max Z=3x, t* 22
Subjectto
2x+x, $2
3x+4x,212
and x, 20
5x +2x2 -x =12 tX
The auxiliary objective function to be maximized is given by,
z=0.x+ O.x, +0.x3 t+0.x4 -Xs-
Phase-1 0
CB B b
8
a2 23 Min. Rati0
12 5 2 4
d6
112/5
-7t 5
0 0 -1
B
0 a2 16/11
20/11 -5/11 as
2/11 5/11 2/11
211 3/11 -2/11 3/11
Here all Z
Cj20, So the optimality
condition of simplex
ve see that Maxz
We =
0and artificial variables method is satisfiea. ru ther
ctart the phase-Il table are not in the basis
where the objective in the final table. so w
function to be maximized
will be
Phase-II Z-3-4x2
C -3 -4
B b
a2 16/11 0 a3 d4
-S/11 2/11
3 20/11
2/11 -3/11
14/11 1/11
All
2C20, so the optimal solution is x = 20/11, x2 = 16/11 and
ZM 3x 20/11+4x16/11 =124/11.
b) Solve the following Linear Programming Problem using Charne's Big M Method:
Minimize Z =4X, +X2
Subjected to: 3X +X, =3
4X +3X, 26
X +2X, Ss4
WBUT 2013]
X1,X2 20
Answer: following
surplus variables, the given LPP can be written in the
Introducing slack and
Torm:
+0.x3 +0.x4 +0.xs +0.x
Max z= -4x -x2
3
subject to 3x + +X
3
3x +2
-x =6
4x+3 4
+2x +4
20
23,X OPRS-29
POPULAR PUBLICATIONS
0 0 -M -M
SaB b 0
d6 asMin. Ratio
-M a7 3 0 0 1
-M a 4 0 0 -1 0 3/2
a 4
-7MT-4M M M
+4 +1
-M
Ba3 bA
0 0
5 d6 agMin. Ratio
4 1 1/3 0 0 -1/3 0 3
|-M 2 5/3 0 4/3 -I 1
0 6/5
43 0 -1/3 0 1/3
5M/3T 0 -4M/3 M 0
-1/3 +4/3
0
CR B Min. Ratio
0 a3 0 0
-4 3/5 -3/5 1/5 3
-1 6/5 0
17/5 4/5 -3/5
3/5 -1/5
0 8/5 -1/5, T
0 0
0 0
-
-1 3 -3
0 -1
0
OPRS-30
OPERATIONS RESEARCH
tHere a
2-C2, So tne optimalty condition
of simplex method is satisfied.
solution
lution is Xi=0, ¥2 = and
*
optimal zMin
4x0+1x3=3.
M method to solve the following
UseBig LP problem: WBUT 2014]
2
Minimize z= 5x, +2x, +10x,
Subjectto %S100
+X210
where, x, 2
, 20and x, 20
Answer:
slacKand surplus variables the standard form of the LPP is
aroducing slack
introducing
Max z=-5% -2X -10x, +0°x,+0°x,
S.t. + =10
+ =10
Now applying
Simplex algorithm we obtain,
Table-1
-1000 0
5-2
Min Ratio
BX L61 10
0 1
10 0
-10
0 0 5 10
3
Table-2
0
52 -10 0
aMin
Ratio
CB B
0 10
10
-10 4 10 0
0 10
Table-3 0
5 2 -10.0
X b
C 20
1
-2 10 0
0
3 4 0 0 M
a a, Min
Ratio
0 | 480 5/2 0
21/4 1
1/4 0
640
3 z, | 120 1/2 1
3/4 0 -1/4 0
7
160
-M x, | 180| 1/2 0 3/4 0 3/4 1
240
M 2
0 3M
4
0 3M 0
OPRS-32
Ca B
X6 23 4 0 0
OPERATIONS RESEARCH
-M
4 640 10 a Min
7 Ratio
21 0 1920
3 4 480
2 1 21
0
0
M a, 780
0
-
0
1
156
M 0
M 5M
7
21
,23 4 0 0
CBX6
4
4| 16 46 16 0
105 105 105
3 a 792 1
1
7
as | 156 0
-37 105
0 0
105
OPRS-33
POPULARPUBLICATIONS
Answer:
Introducing slack variables
the given LPP is given by
,
x(20) to the
ndard form
respective constraints the standard fom
f
C B a2 a Min Ratio
0 15
0 300 30 20
o. 100 5
10
-8 0
6 3 0
Cs B a a Min Ratio
100 8
100
10
20 -2 5
20
10
-2 0 8
10
6 8
C B
6 1
0
20 10
15
8 0 3
40 20
0 0
10
6
10
Here all z,-c; 20, so optimality condition of simplex method is satisfied.
15
Hence the optima solution is. =5, 1 =and zma =90.
OPRS-34
hodtto solve
Use enalty method OPERATIONS RESEARCH
5.
Minimize Z =6x+4y the following
L.P. Problem:
subject to, 2x+4y S12 WBUT 2016]
3x+2y=10
5x+3y215
X, y20.
Answer:
Ancing slack.
ntroducing slack and surplus
variables into
the LPP can be written as follows: the given constraints,
the stand
tandard form of
Max W=-6x-4y +0-2+0:s
subject to 2x+4y +2 12
3x+2y =10
5x+3y -S = 15
and X, y,
Z, s20
Now to form the initial basis, we introduce two
d constraint and finally the set artificial variables u and v with 2 and
of constraints becomes:
2x +4y+2 =12
3x+2y +u =10
5x+3y -s +V=15
and X, y, Z, S, U, v20.
Now according simplex algorithm we get,
CB
0 a
B XB b
12 2
4
4
0
1
0-M-M
0
as
0
, 0
Min. Ratio
6
0 1 0 10/3
-M
-M
10
15
3
3
2
0
0
-
M
0
13 3 0
-8M-5M
+6 +4
0 -M
5 4 Min. Ratio
as
a 2/5 0 15
14/5
0 5/3
0
-M
Z
6
1 0
1/5 03/5 -1/5
1
3/5 0
-
1
-3M/5 0
6 3
-MI5 0
0 +6/5T
+2/5
OPRS-35
POPULAR PUBLICATIONS
0 0 -M
-4
as Min Ratio
b
Ca BX 14/5
1 2/5 0 15
0 z 6
-M as 0 1/5 0 /5
-1/5
1
0
5/3
3/5 0
-6 3
-MI5 -3MI5
+2/5 +6/5T
0 0
4
B Xn
C a 16/3 0 8/3
1 0
0 5/3 0 1/3 0
-6 a x 10/3 2/3
0 0
subject to
=
3x +X-x, +*, 27
} +X, -X, +x, = 21
+ = 30
x+2x, -x,
andx,X2 X, X4» Ks» Xg X7, K 20; and M is a very large (+)ve integer.
Step : (Simplex for Big-M method)
OPRS-36
c 0
OPERATIONS RESEARCH
0 0 M-M-M
M 3 a4 , 7,Ratio
M
a7 |*, |21 0 0min {9, 21, 30}
30 0
= 9
M 0
*OM*4T4M+2 0
+MM
+M M
1/3 -1/3 0
M
,/12 0 2/3 1/3
0
0 min{27,
63/5
18,
21 0
-M S31 1/3 0
63/5
-7M/3 -2M/3 +M +M
24/5
4/3 +4/3
-2/5 1/5 min{24,9}
-M 7, x 18/5 0 +1/5 = 9
63/5 0 1/5 0 -3/5
0
a2 a-M/5 a,7,
+M -2M/S
Ratio
+6/5 |+2/5
-/2
9 0 -5/2
2 |18 1/2 -3/2 0
0 +1 |+3
Step I1: All z, -c, 20 the artificial r variables are removed from the basic variables.
Optimal solution is x, = 3; x, = 18 and Min Z = 4x3+2x18 = 48.
Answer: *220
The form by introducing surplus variables.
ThVen problem can be reduced to the standard
s can also be recast into a maximization problem.
Maximize
(2)=(-Z)=-2, -3x, +0-x +0x
OPRS-37
POPULAR PUBLICATIONS
S.t.
3x +512-X 30
+3x2 -x, = 60
20, i=1,2,3,4.
Here x, x, are surplus variables.
NOW to obtain initial basis we introduce artificial variables X, ¥s ana we get,
- Mx
Maximize
Z=-2x-3x +x +0 x -Mi,
S.t. 3x +5, -X +X 30
Sx +3x2 X4 +s 60
x,20, (i=,2,,)
CB B
-M
, 2
30
-3 0
aMin.
-1
0
0 1
-M -M
0
Min.
Ratio
10
-M i 60 5 3 0-1 0
0
1 12
-8M+2 -8M+3 M M 0
3 0 0
M
Min.
Ratio
1 5/3 -1/3 00
M 6 10 0
0
-16/3 5/3 -11 6
16M
3
15M1 M0
-3
-2 3/5 -l/5
0 -16/5 1
3/5
0 9/5 2/5
Here all
z,-,20, so optimality condition is satisfied.
=
=12, x, =0 and Zmnin 24.
OPRS-38
OPERATIONS RESEARCH
the following LPP by simplex method:
Minimize Z=-2x2-X3 (MODEL QUESTION
subjectto +2-2x S7
-3x +2 +2x S3; X, *2,*3 20.
Answer:
verting the ggiven minimization problem
Converting
to a maxímization problem we obtain,
MaxZ'=2x +X3, Z'=(-2)
s.t. +*2-2x, $7
-3x +2 +2x, S3
, X2 20
troducing slack variables xa, * ,(20), the initial table of the simplex is given by
Introd
C, o 2 1 0 0
CB B b Min. Ratio
-2 1
7
Z-C 0
t
Here a, is departing vector and ä, is entering vector.
C
, 15
2
a
0
Min. Ratio
0 a 0 4 1 -1
2 3 1 1
3/2
0 -1 0 2
2,-C
0
2
CB B, 2 1
10 -2
1/2
3/2 -3/2 1/2
3/2
1
0 0 1/2
-3/2
OPRS-39
POPULAR PUBLICATIONS
MODEL QUESTION
od:
b Solve the following LPP by Charnes' Big-M metnou
Maximize Z 3x +2X
subject to
2x +h S4
Sx, +8x, Sl5;X, X2, 4, 20.
Answer: the standard tom of the
.. r. and surplus
variable x,
ntroducing slack variables
given LPP is
Max Z =3x +2x, +0.x, +0.x, +0.xs
s.t. =l
2.x +X2 +4 =4
Sx +8x2 + =15
Min. Ratio
|-M ä, | 1 -1 0 0 1
0 2
2
as 155
Z,-C -M-3 -M-2
0
M
0
0
03
3 2 0
4 a Min. Rati
1
3 -I 0
2 -1 0
10 3 5
0 12
,-C 0 -3 0
OPRS-40
OPERATIONS RESEARCH
2
0
2 Min. Ratio
0 1/2 0
-1/2 1
1/2 0
-5/2 1
5/8
2,-C -1/2 03/2 0
2 0
B
27/16 1
21/32 -1/16
21/16 1 11/32 1/16
2 2,-C
5/8
0 -5/16 1/8
0 43/32 1/16
Here all Z-C, 20. So optimality condition is satisfied. Hence the optimal solution is
101
16
= 1000
+2x, +X5
Simplex Tables:
7 as Min Ratio
a
1000
0
a 1000 2
0
1 0 600
600
1000
500
0 0
-4 -7
, 0
|
500
a,
7
a2 a
1 0
0
a Min Ratio
1000
3
a 100 0 1
200 200
500 0 1000
4 7 0
CB b a a
200 0 1
200 1
-1
400 0 0
0 3
2
Here allz,-c, 20. So, the optimality condition of simplex method is satisfied.
The optimal solution is
200,x, =400 and zMax =4x200+7x 400=3600
OPRS-42
Using Simplex method OPERATIONS RESEARCH
solve
Minimize Z=4x,+3x2, the following LPP:
MODEL QUESTION]
subjectto +2x, 28
3x+2x,212
and x,X20 by Charmes
swer:
BigMmethod.
A troducing surplus and artificial
ni Z =Maximize (-2)=-4xvariables, the problem isre-stated as
-3x, +0.x,
S.t. +0x - Mr, -
M,
x+2x,-X
3x+2x
- +X5
+x, =12
=8
C,4 -3 0 0 -M -M
a2 as
Min
Ratio
M 8
2 4
-Ma 12 3
2 0
16
,- 4M 4M M
0
M 0 0
+4 +
C,4 -3 0
-M
Min
Ratio
4 /4 -/4 0 16
-M 5/2 /2 8/5
4 0 -1
Z-C SM 0 -M/2 M 0
+3/4
OPRS-43
POPULAR PUBLICATKONS
& ASSIGNMENT
PROBLEM
Multlple
ChoiceType
1. in most ot the transportation
9uestions
a) North-West probleme,
Corner Rule (NwCR) the nearest optimal solution
b) Vogel's APproximation isgivn
c) Stepping Stone Method Method (VAM) VBUT 2013]
d) None of these
Answer: (b)
2,Hungarian method
is applied for solution
a) Assignment problems 80lution of
WBUT 2013, 2016
c) Queuing problems D) Decision
theory related problems
Answer: (a) d) All of these
WBUT 2015
Hugarian method is a special type of b) Simplex method
a) LPP
c) Transportation problem d) Inventory
Answer: (6)
must be WBUT 2015
balanced assignment problem the cost matrix
ina) square b) singular
c) non singular d) none of these
Answer:
(a)
OPRS-45
POPULAR PUBLICATIONS
WBUT
should be
transportation problem demand and supply 2015
b) not same
a) same
d) none of
these
c) both (a) and (b)
Answer: (c)
the optimistic and pessimistictima
0. In PERT the span of time between WBUT 2017
estimates of an activity is d) none of thesa
a) 3a b) 6o
c) 12
Answer:(6)
16. The total number of possible solutions for n*n assignment problem is always
a) n b) n-1 c)1 d) n! DMODEL QUESTION
Answer: (d)
17. Which of the following is not method to obtain the initial basic feasible solution
in transportation problem? MODEL QUESTION
a) VAM b) Least cost method
c) North-West corner method d) MODI Method
Answer: (d)
OPRS-46
RESEARCH
OPERATIONS
unbounded. ls the
21. The solution of the transportation problem is never
statement (MODEL QUESTION)
a) True b) False
Answer: (a)
Questions
Short Answer Type
five workers. The
machines (of the same type) and
1. factory there
In a are six
(i=1,2,3,..)t handle-the j th machine ( =1,
handling costs for the ith worker optimal assignment
in the form of a matrix. Find the
43,6)minimumare given below machine and find which
machine will remain
cost of handling the WBUT 2013]
ind the
unused:
OPRS47
POPULARPUBLICATIONS
M6
M M M3 M M
18
10 14
W 12 8
12
W2 14 14 8 15 17 12
13 15 6
W 9 11
11 8 14
W 9 9
12 13 10 12
Ws10 15
Answer:
we add a fiction worker
ne given problem is an unbalanced problem. To make it balance
zero cost and then apply Hungarian methods to solve it.
WIn
Subtracting the minimum element of each row from every element of that row and we
Subtracting the least element of each column of from every element of that column
zeros
get. Now we draw minimum number of horizontal and vertical line to cover all the
ne number of lines is 5 but the order of the matrix is 0. Now we suouract minimum We
element from every uncovered element and adding at the of intersection of the lines
get.
Again we draw minimum number lines to cover the zeros.
Here number of lines is equal to the order of the matrix.
Therefore, the optimal assignment is
WM,, HW,
M,,W,>M,,W,>M,,W, >M,
Minimum cost: 8+8+12+8+10=46 units
M M M, M, M M
12 8 10 1411 18
W 14 14 8 15 17 12
W 9 11 13 15 6 12
W 11 9 11 8 14
Ws |10 12 15 13 10 12
W 000 00
OPRS-48
OPERATIONS RESEARCH
4
8
2
7 1
0
0
M, M, M, M. M, M,
4
W 6 6
9
W 3
7
W. 3 1 1
0 3
W 2 5 X x
W.2 2 2 2
7
2. Five menare available to do five different jobs. From past records the
hrs) that each man time (in
takes to do each job is known and is given in the following
table. Assign each man
to ajob to get minimum time. WBUT 2014]
Man Job
Answer:
T8 9
assignment problem.
apply Hungarian method to solve the given
Her
OPRS-49
POPULAR PUBLICATIONS
3 4 5
2 3
4 5 I2
18 4 2 6 1 17 3 1
5 0
20 2/0 9 5 5 4
9 5 5 4
313 8 9 2 6 Rowoperation 31 6 7 0 4
414 3 44 3 1
0 3
1
0 3
0
519 5 8 9 5 s4 0 3 4
12 3 4 5
1 2 3 4 5
D D2
D D
J 10 10993 So the required
assignmentis
J 9 20
22 D, J, ->D,, J, ->D2, J,D,
Js13 3
J9 12| 14
4. Explain how an assignment
problem can
be solved as a transportation
Answer: problem.
The assignment WBUT 2016]
problem becomes
variabfes is relaxed.a linear programming problem when
restriction on the
problem is unimodular In fact, the coefficient the 0-I
and therefore, we matrix of the assignment
linear programming can relax the 0-1 restriction
problem to get the optimal and solve it as a
rarely solved using solution.
the simplex algorithm But assignment
problem faster and
more efficiently. but have special algorithms problems are
that solve the
You may also have
transportation problem
observed by now that the
assignment problem is
since the objective functions similar to the
matrix. The first
difference however, is that are similar and so is
the assignment problem the coefficient
equal number of rows (resources) has a square matrix
can have unequal and columns (tasks)] while
number of supply and demand points. the transportation problem
what we do if the Later in this chapter, we
assignment problem is not square will see
The assignment
problem is a special case of the transportation
a, =l
and all b, = 1. We do not solve problem with m= n, all
the assignment problem using the transportation
algorithm because it is
a degenerate transportation problem. We have
degenerate LP problems and transportation already seen that
and take problems may require additional iterations
long time to reach optimality.
A feasible
solution to the nxn assignment problem has exactly n assignments
LP formulation while the
has n decision variables and 2n constraints. Out of the 2n
ere are 2n-1 basic variables because the coefficient matrix constraints
represents a
pendent system of equations. Since the assignment solution has n allocationslinearly
der
out of
2n-1 basic variables, it means thatn-1 basic variables take value "0' indicating
a racy.
s a linear Hence assignment problem is neither solved as a transportation problem not
programming problem.
OPRS-51
POPULARPUBLICATIONS
solution of the
t
5. By North-Westco method, find a basic feasible WBUT gven
transportation problem: 2017
Destination
BB,B,| B
42 11 10 3
Source 4| 1
47 4
2
8
5
A 3 9
34 5
Answer:
According to North-West corner method:
B B2 Bs B4
Az
A 4
bi 4
Bs B4
10
B3 B4
As
OPRS-52
OPERATIONS RESEARCH
Ba
Let 24-26,-T(say)
i=
Consider the solution
then,
=
Similarly,= ",
Therefore, solution
solution.
x, = , satisfies all the constraints. Hence it is
a feasible
OPRS-53
POPULAR PUBLICATIONS
Men A B
C D
Machine
M 18 26 17 11
26
M2
13 28 14 15
Ma 38 1918
Answer: M 19 26 | 24 10
A B C D
Mi 18 26 17 11
M2 |13 28 14 26
115
M3 38 19 18
M4 19 26 24 100
Here, order of the matrix n = 4
Step 1: After Row Operation
B D
MM2 15
|13
15
M3
23 4
M4 9 16 14 0
Step 2: After Column Operation
B C D
A
M7 11 5 0
M 011|UTT
M 23-0-2-1
M 9 12 13 O
The minimum number of lines that covers all the zeros is N=3>N =3 <n =4
Hence optimal condition is not satisfied.
Step 3:
Minimum of the uncovered elements is 5. Subtract from each of the uncovered element
and add 5 to each of elements which is covered by both horizontal
and vertical lines and
other elements left unchanged.
B D
M
M2
Ms -23
185
M4
Step 4:
Now, N=n= 4, hence optimality condition is satisfied
and optimal assignment is MiCi
MA;M3->B and M4>D.
Minimum cast = 17+13+19+10 59.
OPRS-54
8. Prove that the number
(m+n-1). of basic OPERATIONS RESEARCH
varlablee
ADs
H
denote the
warehouses
na
In a tranaportation
transpor
problem s
., .Let
n. Let xy be the
t amount as W, and [MODEL QUESTION]
of a certainmarketbyM.
fow at W; and the total intlow product for i = 1,
supplied
.....,
2, m andj=1,2,
from
rom W, to M;,
atM are respectively W, o Then the total
for a balanced T.P. x, andx and, u
a,, i =1,2,...,
j=|
m,.)
and
X=b
i=l
j=12,.
Also sincee
the supplies
Xi, in order
x20 for alli and J and the to be feasible,
total cost Transportation should be non-negative
of i.e.,
1e
(which has
Minimize Z = to minimize) 1s
J=l
Moreover, we have
(4)
Rewriting, we
get
Minimize Z =
subject to constraints
2x a,; i =12,.
)
2,-b j=1,2
S-
i=l ja
and
in the
x20
above formulation the T.P., we have m x
of n cost coefticients
Ci m * n variables
and (m +n) linear equations (as
in (). Due to une presence ot (6), all
r equations in (5) are not linearly independent. Oniy
linearly independent. So, this situation dictates us (m*n-1)
the (m +n)
re that out
liear equations in
ofm *n variables x
n n-1) variables xij, at most should be basic variables and remaining mn-(m+
n-1) variables should non-basic variable for a T.P.
be
OPRS-55
POPULAR PUBLICATIONS
warehouses is at least equal to the total demand at the markets, ie. 2 bWhen
markets i.e.,
all markets
the total supply from the warehouses met exactly total demand of
ie
as balance transportation
Eo-,,
i=l
J=
then the transportation problem is known
problem.
Now if, ie, a,, theT.P. becomes unbalanced.
In physical sense, if 4>6,, there would be surplus left at the warehouses after all
the markets' demand met, and if a <,, there would be deficit at the warehouses to
meet all the markets' demand. Problems involving surpluses and deficit are very common
and significant in practical life. These type of problems-to be posed properly to have
feasible solutions after introducing artificial market / warehouse as required to make it
balanced T.P.
OPRS-56
QPERATIONS RESEARCH
20
la
4
30 30
20
3
O 2
2
0 10
S0
AC31-(4, +)=4-(4+1)=-1<0
Ay =Cn -(u +V2)=2-(4+2)=4<0
Hence the I.B.F.S (obtained by N-W corner method is not an optimal solution.
LB.F.S. by VAM-method: Using the idea of penalty, we get the I.B.F.S. as in the table
below:
Di D D3 DA
20 10 30
O 20 10
20 50
O2 2 10
2 20
Os
100
20 40 30
OPRS-57
POPULARPUBLICATIONS
OPRS-58
OPERATIONS RESEARCH
Answer:
Q
A R Supply
B
s9 1 3 8
C
7 7
3 4
6
Demand o
hasic feasible solution by North-West corner 30
X9, 2 =3, *2 method (rule):
=7, Xz
=7 and x, =
4.
14. There are three A, Y and Z
D and D4. The production which supply goods
to
oer month capacities of these factoriesfour
respectively. The requirements
different dealers Di, D2
are 1000, 700 and 900 units
400 units per
month from the dealers are 900, 800, 500 ano
transport to the dealersrespectively. The profit matrix at the factories for
problem:
are given below (in
Rs.). Find optimal solution unt
[MODEL QUESTION
tne ot
4
5
Answer:
6 8
First, we convert maximization problem
to a minimization problem by subtracting all
unit profits from the largest unit profit the
Rs. 8 and solve this minimization problem
VAM using
D D D D4 Capacity au
X 200 800
.2 1000
Y 700
700 u2
2
z 500 400 900
Demandd
3 2 -1
900 800 500 400 2600
sbi
This is a balanced
V=2 V22 va-2 V4=1| D
a, = 2600
T.P. 2)
Using VAM, we
find I.B.F.S. as
200,x12 =800, x2 =700,x3 =500& *u =400
nch is degenerate solution (m+n-1=3+4-I5 6).
OPRS-59
POPULAR PUBLICATIONS
9| 7 10 9
Answer:
J8
Step : (Row operation)
We subtract least element of each row from each element of that row (for each row).
Step II: (Column operation)
Performing similar operations for each column, we get the modified matrix as
(Table 1)
M1 M2 M3 M4
JI
03 2
J2
33 0 20-0-
4 3
3 2-9-
I Table -1
Step Il1: (Optimality test)
Now, we draw minimum numbers of lines to cover all
the zeros (see Table 1). Order of
-
OPRS-60
OPERATIONS RESEARCH
MI M2 M3
J1 M4
2
32
1
J3 J2
J4
N 4;therefore
HereNa
therefor n=N=4 and Table-2
(Assignment) the optimality
condition
Sep IV: is satistied.
on is satisfied.
J M1,
J M,J
M, and
imum cost
Minimum cost (forthis assignment) =
1
+10+5+5=21
J M
W W
F Fa
10
70 30
50 10
Capacity
40 60 9
Fs 40 70 20
Requirement: 5 18
14
Answer:
Initial basic feasible solution by North-West Comer method:
5, =2, A =6, =3, 4, =4, z =14
OPRS-61
POPULAR PUBLICATIONS
Answer:
Using VAM we obtain,
D4
D D D3
F
100 / 100 100 X
(2)
4 (2)
BoV45 125 45 45
X
77/
20 30 20
2 (2)
75
(2)
75
(2)
75
(2)
55 55
F 32 (1) (1) (1) (1) (1)
120 80 75 25
2()(0_()_
120 75 25
X
(2) () ()
20 75 25
(3) () 0)
X
75 25
()_ 0)
30 25
(3) (0)
Here the number of allocations is 6(=m+n-1)
x2 80, x 45, x = 20, X=30, 4=20.
So the initial solution is X =100, =
12
Requirement 14
4
Answer:
Given problem is an unbalanced problem,
at first to balance it we
fictitious column M, Wth zero cost have to add one
Then to solve we apply VAM:
OPRS-62
QPERATIONS RESEARCEH
M M2 M M Ms M,
Ms a,
82)80)8O)| 4(1)4(1)
AAAY 12(1 12(1 4(2) 4(3)
4 6
4 % 14(3 10(1|10(110(2) 10(2)
by 4 4
3
(1) (2) (1) (0) (2) (0)
4 4 6 8 8
(1) (2 () (0) 2)
4 4 6 8 X
(2) () (0)
4 X 6 8
() (0)
4 6
(2) () (5)
So theinitial feasible solution is
2 4, K«4, *4, *zs 8, X5=4, =6, z=4.
We see that no. of allocations is 7 while
m+n-1=3+6-1 =8.
Thus the problem is degenerated
To complete the basis, we allocate a very small positive quantity e in (1,1) such that
this does not form a loop among some or
all of the occupied cells and make them
independent. To test the current basic solution for optimality, we calculate «, and v, and
then the cell evaluation for non-basic cells as
in the following table:
M M M M Ms M 4,
0
2 6
F 0
4 5 2
2
F
2 2 2
Allthe cell\ev hence the optimal solution is
evaluations are pesitive and
andthe2,
nd 444, zu=4, s =8, z1=4, 4 6
theansportation =80 (Rs.)
transp cost =4x2+4x2+4x2+8xl+4x6+6x4+4x0
OPRS-63
POPULARPUBLICATIONS
3. The warehouse acities a, market demands b and the unit cost ofWBUT
shippln
201
are given in the following table
M M
W 2
W2 10
Ws 15
W2 B/4
/10/s75/4 7(1 7(1) 3(3)x
) (23 (1)_ *
1
-5
2
2
10 -1
3 6 8 4 =0
7 Here alf 20,
6 6
so optimality condition is satisfied.
Hence the optimal solution is
3, *=3, =4, 11, 2 =3, x =1
OPRS-64
OPERATIONS RESEARCH
optimal shipping charge is
and the
and 68 units.
y is producing a
A.A in different cities. single product and is selling
All of a sudden, rough five agencies
it through
nother five cities not having any agency there is a demand for fiveduct
he pro in
pro
oroblem of dealing on how to of the company. The compa tn is faced
th the
with
roduct to edy
need cities in assign
such a way that the exiating agencies to o atch the
prbetween the surplus and deficit
kms) the travelling dista ed (in
cities. details
distance matrix. The are given in the to wing
Deficit Cities WBUT 2015]
Surplus Cities- I IV
160 130
135 120 175 190 200
140 110 130 175
160
155 170 185
50 50 80 80 110
55 35 105 | 70 80
Answer:
To solve the given assignment problem,
we apply Hungarian method as follows:
I II III IV V
A 160 130 175 190 200 30 60 70
0 45
B 135 120 130 160 175 15 10 40 55
Row
Operationn
C 140 110 155 170 185 30 45 60 75
D 50 50 80 80 110 30 30 60
45
E
55 35 70 80 105 20 0 35 70
30
35 30 15 Here no. of straight lines = 3<5
10 (order of the matrix)
So optimality condition is not satisfied.
Column
operation
30 35 30 20
20 0 05
20 | 25
15 15
Now subtract minimum most élement among all coyered elements from each element and
add at the point of intersections.
05
OPRS-65
POPULAR PUBLICATIONS
E 05 10
10
10 8 3
Answer:
It is an assignment problem. We have to assign
4 jobs among 4 machines optimally.
Mi M2
M M4
Mi M M M4
11
6 1
Row
operation 3
7 10 7
J 0 3
10 4 8 3
J
Column J2
operation
M
. Ma
2
Ma
6
M4
OPRS-66
OPERATIONS RESEARCH
M M Ms
M
J
Here also
J no. of straight lines
require to cover
all the zeros is
Js 2 3< order of
1 the matrix. So
optimality condition
satisfied. We is not
follow the same
procedure again.
Mi M M M
Here no. of straight
lines = 4
order of the
matrix. So
optimality condition is
satisfied. Now we can
assign
the jobs among the machines in
the last matrix as follows:
Mi M2 M3 M4
J XRequired assignment is
5
or,
M M, },>M, J>M,
2 1 M3. JM,, J,>M,, J,>M,
or, M,,M,. Jy->M1, J,M,
& x or,
M, JMg. J> M, J>M,
Or, M,. M, J,>M, J>M,
Or, M2, JaM,, J,>M,, J,> M,
6 Apply Vogel's approximation method to find the optimal transportation cost for
the following WBUT 2016]
problem:
Destination
Supply
|
D D,| D,D,
19 30 50 10
Factory
70 30 40 60
9
40 8 40 20 18
d5 87 34
14
Demand
OPRS-67
POPULAR PUBLICATIONS
Answer:
Here we use VAM:
D D D Da di
2 (40) 2 (40)
7 (9) 7 (9)
O 19 30 i0 10
b 5 14
(21) (22) (10) (10)
14
(21) (10) (10)
14
(10) (10)
7 4
(10) (50)
2
(40) (60)
7 10
19 30 S0 10
70 30 40 60 60
40 8 70
8 20
20
b 5 8 7 14
y +9 -12 -20 0
OPRS-68
OPERATIONS RESEARCH
Adjustingt allocation from X2 iS X22
We get,
30 50
0
70 9
30 40 60
32
40 8 70
18 10
20
b 5 8 7 14
Vj 19 2 10
1 Find the initial solution for the following transportation problem using VAM and
check for optimality: [MODEL QUESTION]
Destination
Supply
5
Source
IV 14
Demand
|
7 18 34
Answer:
Initial basic feasible solution by VAM
=10).
5, x23 =8, x =7, x4 =2, * =2,*
OPRS-69
POPULAR PUBLICATIONS
Optimality test:
A B C
2
II u, =-2
3
8
3
III 4-3
IV 4,-1
6 2
2
=2 =7 3
A =Ca-(4 +,)=7-(0+7)=0
AC-(4 +,)=4-(0+3)=1>0
ACa-(4, +%)=3-(-2+2)=3>0
Aa C-(u, +v,)=3-(-2+7)=-2<0
AC-(4, +v)=5-(-3+2)=6>0
A7-(-3+3)=7>0
Hence the solution
5, X» =8, Xz2 =7, X =2, =2, Xa =10, is not an optimal solution.
Value of z =5x2+8x1+7x4+2x1+2x6+10x2
= 10+8+ 28+2+12+
20 80 units.
OPRS-700
profit matrix
n ,] for this problem OPERATIONS RESEARCH
The
and
numbe of column
n=5. This type
is not a square
matrix.Here
Assignmeni problem of assignment number rows m 4
uen I: (Dummy rows) problem
sep is kn
known as Unbalanced
a we
First of Aummy
make it balanced by adding
roWs are du rows 1.e., A and Y two dummy
are two dummy rows (see Table - 1; 5h
machines) 1, and 6
A
A B C D IE
B 62
71 9
78 50 101
C 7184 82
D
87
92 61|7359
| 111 71
X 48 64 | 87 77
81
80
0 0 0
Table-1 00
en J1: (From maximization problem
T change this profit to minimization
matrix to a problem)
maximum element loss matrix, we subtract
11l and rewriting (see each element from the
Table 2)
J1
A J2 33 J4 J5
B
49|33 61 10 29
40 27 | 38 52
50
C 24 190 40 30
D 63
47 24
X O 0O 343100
Step 111: (Row operation)
Table-2
After subtracting least element,
for each row from each element of that row.
A B D E
39 2351 0 19
II 13 0 23 11 25
III 24 19 040 30
IV 39 230 10
0000
Table-3
Step IV:
(Column operation)
r operations are performed for the entire column, we get Table -3.
I 39 23|1|25
II 13
III 24 030
IV 39 7
V
Table-4
OPRS-71
POPULARPUBLICATIONS
A B E12
II 6 18
B
III
IV 1723
32
1L40 23
0 0
V
Since, all the rows and columns have at least one zero, we draw minimum
number of
lines (both horizontal and vertical) covering all the zeros
and test the optimality
Conaition. Since m= 5 and n = 5, i.e., N=n=6,
the optimality condiion is satisfied.
A BC D E
I
32 23S1 012
II
02319040 23 11 | 18
II 17 23
IV 230
32 10 0
Step Vl: (Assignment)
000 0 0
ID, II>B, II->C, IV>E; Max. profit= 376 units.
9. Solve the transportation problem and checking the
solution optimality, find the optimal
[MODEL QUESTIONJ
O1 D3
O2 10
0 13
Os
Answer:
12
Optimal solution:
x, =5, *4=5, 2=4, x2 =8, x24 =1 and x =12
Minimum cost of transportation
=23.
Herea =l10+ 13+ 12=35butb, =8+5+4=17 a,>
indicates that to make it a balanced
T.P,, we have to create
b,.
The problem
with demandb, =
a,
with heading D4. We use
-26,
an artificial destinationD
=35-17=18. So, we also have created
the 4 column
unit transportation
suggested by Goyel) for the cells cost as the maximum unit cost 8
of 4" column.
OPRS-72
OPERATIONS RESEARCH
D D2
D
D
O 5
3 2 u
O2 8 4
10 =0
S 0 13
Os 12
3
3 12
8 6 ug0
b 18
V1 V2=3 |
Va=0V=8
35
Table
1
Assume, c14C24 C348
ngVAM,
Using VAM we get I.B.F.S. as,
X2 S, X14 =5, X21 =8, X23
4,* X24 x34 1=12
mality test: (for all non-basic cells): =land
=l and X34
After finding allu's and v's, we calculate (see
Table 1)
A C(4+)=4-(0+1)=3
Ay
C4
Az2 C-(42
+",)=2-(0+0)=2
+v)=5-(0+3)=2
A C4 +)=3-0+1)=2
Ag2Cg2-(4, + v,)=8-(0+3)=5
As C-(4, +",)=6-(0+0)=6
Since all Aj>0 for all non-basic cells, optimality conditions are satisfied and optimal
solution is
(1,2) (1,4)
(2,4)
(2,2)
1-1
OPRS-73
POPULAR PUBLICATIONS
2x a,;i = 1,2...m
a,
2, sb,;j=1,2. . ..
m
amd x, 20
i=l J=l
The actual supply from the warehouses (W, I= 1, 2, .
m) fails to meetthe maket
demands. This type of problems are solved by introducing a artificial row (i.e., with a
artificial/dummy warehouse) with a storage a b, -2a >0, to make the problem
j=
a balanced T.P.
Now, the number of warehouse becomes (m + 1) but the number of markets remains n
Unit costs of the (m + 1th row may be considered the largest unit cost of the actual
problem or zero.
Optimal solution: x\, =5, =5, I=4, X = Xzu =1 and x = 12
8,
Minimum cost of transportation = 23.
5 11 16
13 16 1 10
Man 16 11 3 3 8
E 9
10
113 12
11
10 16
3 16
Answer:
After row operation the matrix takes the form
Order ofthe matrix = n
=5> N=4 (minimum number oflines).
Minimum uncovered element is 3. Subtract 3
from each of the uncovered elemenS a d
add 3 to each of the crossed elements
and put other elements unchanged
OPRS-74
2 3
4 5
OPERATIONS RESEARCH
8
---0--
12 15 9
C
D
-3-0
3
E
5 3
8
12 3 4
5
A-F
B 9
-9-t
c- D dx 2
C
6
E
i 4
2
Ootimal assignments :
A+2,B>1,C>5,D3,E4
or
A-2,B4,C-> 5,D >1,E >3
Minimum cost= 34 units.
11. Solve the following balanced Transformation problem: MODEL QUESTION
D D D1 DA Capacity
F1 2
F2
F3 10
Requirement
Answer:
This is a balanced transportation problem. Initial B.F.S. by Vogel's approximation
method.
D, D DA
s
2 3 11
9
15
OPRS-75
POPULAR PUBLICATIONS
For the optimality test, et u = 0 and write all the cell evaluations A, = Cy( v,in
the circles (for non-basic cells).
D D2 D3 D4 u
Fi
11
u-5
F u 3
15
VV-2 V3V 12 V6
we choose A21=C3 -(u,+v,) =6-(6+12) =6-7--1<0, as the intering cell is the
basis. The cell to be removed from the basis is shown below. We form a loop which
includes the cell (2, 3).
0+1 1-1
(2,3) (2,4)
3-3) (3.4) +1
From the above, it is clear that the cell (2, 3) enter into the new basis and the cell (2, 4)
leaves the basis.
D D D D
F 11|
u-0
(+3
F2
u
F
5 15
2 9
u3
0+1
(1.1) (1,3)
(3, 1)
(3,32-1
6+1
OPRS-76
OPERATIONS RESEARCH
0
= ACp -(4, +V,) =11-(12+0) =
-1<0
Let
D Da D
F
11 0
F 6
F
8
2 15 u4
V-VV-1V3 V1Vs
Let u = 0
Since allthe A, 20, the optimality conditions are satisfied.
Optimal solution: X12 =3,¥13 =1,X23 =1,x31=7,x33 =1 and
x4 =2
min Z= 5x3+1xl1+1x6+7x5+1x15+2x9=|100
12. Find the optimal assignments to find the minimum cost for the assignment
following cost matrix: MODEL QUESTION]
J1 J2 J3
12 24 15
P2 23 18 24
P3 30 14 28
Answer:
After row and column operations
P 15 0x
P2
Uptimal Assignment P->J,, B+J, and R
in. assignment cost =12+ 24+14 50]
VAM and find out the optimal
13.
So ve the following transportation problem by- [MODEL QUESTION
solution:
OPRS-77
POPULAR PUBLICATIONS
n=N=4,0Optinalitity condition
satisfied
1C,2A,3-> B
and 4 D. Min cost = 59
15. Find by North-West Corner method the initial basic feasible solution of the
Tollowing transportation problem. Also find the optimal solution of the resultina
MODELQUESTION
degenerate transportation problem.
D Da Da
O 7 3 4
2 1 3
Os
Answer:
Step I: (L.B.F.S.)
Initial basic feasible solution by North-West corner method:
O 3
42-5
Os 4-2
3 5
b,
K1o
V =6 V, =8
Set u= 0;
Cell evaluation for non-basic cells
A Ca-4, +v,)=3-(0+6)=-3
Similarly, A,=-4; A-2 and A =0;
Though A = 4 is the most negative we use cell (3, 1) to get better result.
OPRS-80
OPERATIONS RESEARCH
Loop formation
p I1: 2-2
(2,1) 2+
(2,3)
3.1)
0+2 3,3
(new solution its optimality 5-2
StepIV: testing)
D D D
O1
2 a u,
, =0
2tE
Os 2T 3
3 3
4 4
6 5
b,
=7
4
, =8
=10
Set u = 0, 2-2 0+2
For non-basic cells: (1,1) (1,3
Ap- As-6; A2 =2; Ag =0
So, the cell now enter in the basic cell.
Step V: (loop formation) (3.1) (3,3
Step V1: (New solution and optimality testing) 2+2 3-1
D
,
Da D3
a
O 2
2
=0
O 2+E -1
3 3
Os 4 3
32
6
Cell evaluation
b,
, 4
' 2 4
for non-basic cells =
=6>0; A 1>0; A2 =2>0 and Ay, 0
Hence,
optimal solutionis
2, X22
=lx =2;x,1 =4 and x (making€0)
=1
OPRS-81
POPULARPUBLICATIONS
B
C
Answer:
It is a unbalanced Transportation Problem (T.P.). Za,=2200<b=2500. Using an
dummy plant P, we make this problem a balanced T.P. with all zero transportation costs
for thus dummy plant P.
I.B.F.S. by Vam: Ware houses
D E F G H
0 300 u4-6
0
8 V46 Vs5
(Table 1)
Here, m
+n-1=4+5-1=8> no. of basic cells (7).
So, we introduce at the cell (2,5) a small non-zero amount e >0 to remove degeneracy
of L.B.F.S. (see table 1).
This solution is not an optimal solution. We make the loop and get
the table 2.
500-E
(1,3) (1, 5
300+E
2,4)
100+E
.)-E
4,3 4,4)
0+E 300-E
OPRS-82
QPERATIONS RESEARCH
D E
G H
A 500-E
300+E O
400 3
B 7 100+E
8
400
C 6 500
= 1
P o300-E O -6
Vi4 V25 - 8
V4 =6 Vs 5
. colution is also not an optimal solution proceeding
in this way, we get op
.
solution as
6, s
800+6, *a400, =100+, x
K 400, X33 = 200-6, X34= 300-, x 300
Naw, making&>0, we gét optimal solution
=
K 0, is =800, Xz1 400, * =100, x =400
200,
33
X34300 and X 300 and minimum transportation cost Rs.9200/-
Sources 60
9 70
3b 11
50
3 80
80 80
Also verify, whether the solution is optimal or not.
Answer:
Using VAM, we get a degenerate basic feasible solution (as a initial basic feasible
Solution): xi3 = 60, x = 50, x23 20 and x32 80.
Here, m = 3, n = 3m+n-1=3+3-1 5, which indicates the solution is degenerate
solution.
D2 D3
D
60 u 0
Oi
50 20
O2 3
u26
Os
80 U3-4
111 3
Vj VI-3|=7.Vs3
Table
OPRS-833
POPULAR PUBLICATIONS
Set u= 0
Optimality test: Aj=0, for the basic cells.
his gives us, u +V^ = 3;u,
+V, = 9;u, + v, = 3&u, V3 3.
t+
Setting u0, we cannot find the values of all other 5 unknown u's and v's."This is
is due
due
appearance of degeneracy in the 1.B.F.S. What cell will represent the S" componento
of
the basic cel1?
o overcome this problem, we tactically allocate a small amount & to a cell such
that this cell and other basic cells does not form, in any way, a loop. With this view in
mind, we allocate e amount in the cell (1, 2) (see Table) and this gives V2 */ and ug 4 .
So, all the values ofu's and v's are now known.
Now, we calculate A for all non-basic cells.
AC-4 +y)=11>0
A C-(, +»)=-5 <0
AC-u, +)=18>0 and
Ags C3-(4, +V3)=6>0
Hence, the I.B.F.S.
W 2
33 0 13
X 0
7 27 43
Y 0 12 33 24
Z 0 5 3 7
OPRS-844
OPERATIONS RESEARCH
Z --
Step Il: Minimum element of the uncovered elements is 2.
A B C D
W 2 26 |0 4
o
X 27 34
15
Y 33
Z 2
OPRS-85
POPULAR PUBLICATIONS
Capacity
A B C
400 80
400
50 40
400
2 400
80 70 40
3 500
60 70 60
200 200
400
60 60 60
800
800
30
50 40
Req 800 600 1100 2500
50
400
40 n4
80 =0
Let , =0
Cell evaluation
2 400
80 70 40 =0 A,=C-(4+",)F
500 or Basic cells
60 70 14,20
60
A0
200 200
4,20
60 60 60
800 & 0
30 40
30 40,=40
A50-(0+30)=20>0
A 80-(0+40)=40>0
A 80-(0+30)=50>0
Az 70-(0+40)=30>0
A60-(20+30) 10>0
A =70-(20+40)=10>0
A =60-(20+30)=10>0
As50-(0+40) =10>0
OPRS-86
Hence the olution obtain by VAM OPERATIONS RESEARCH
. Minimum cost of is optimal
transportation a optimal
Min4400x40+500x60+200x60+200x60+800x30= solution
solu (making
0)
Obtain
ain an Initi
Initial Basic 110,000
20.
20.following Feasible Solution (1.B.F.S)
tothe following Transportation Problem and total transportation
using North West transportation cost
Corner Rule.
Destinations [MODEL QUESTION
S
D
10 | Supply_
SourcesS2 1 15
S3 0
| 25
Demand| 15 18
10
le that Initial Basic Feasible 15 15
Solution (l.B.F.S) a Non-Degenerate
Solution? Justify your answer. is Basic Feasible
Answer:
nitial Basic feasible solution
by North-West Corner
Rule:
D D D D Supply
S1 5
10 20
S2
12 20 5 25 26 5
S3 10
14 16 18 10
Demand
0 15
Here
50
m=3,
n=4;
m+n -1=3+4-1= 6
I.B.F.S. by North-West Corner Rule:
=15,
z5,
215,
245,
34 10
and z = 600. is less than 6, this indicates that the
Sinc
Ce non-zero components of this solution 5 which
soluti
is a degenerated Basic
feasible solution.
OPRS-87
POPULAR PUBLICATIONS
o 8
4 13 (0) 13 (0) 5 (0) 1
(5)
12 12(3)
D8(2) 5(2) 4(2) 18 (0)
5(2) 6 (0)
5(3) 5
(0)
So, B.F.S.is
25, 44=5, A21 =8, 12=4,x4 =1, x4 =12.
and minimum cost is
5x3+8xl=23.
Now test the optimality of the solution by computing cell evaluation unoccupied cells.
at
OPRS-88
OPERATIONS RESEARCH
D D2 D
o 4
D
0
O 8) 2
O 12
1
3
3
8 s 0
0
21 16 15 3
6 10 12 4(18)
10 12 (4)
6
10 6 (0)
10 (17) 9 (18)
OPRS-89
POPULARPUBLICATIONS
So the B.F.S. is
4 11,
6,
23,
244,
210.
=9
The minimum cost is 11x3+6x17+3x14 +4x23 +10x17+9x18=601 .
Now we test the optimality of this solution by computing cell evaluation at unoccupied
cells. P R
-20
21 16 15 3
B 6
17 18 14 23
10 9 4
32 17 18 41
17 13 14 23
It is seen that all the cell evaluations are positive so the solution is optimal.
23. Find out the initial basic feasible solution and the corresponding transportation
cost of the following transportation problem by using VAM: [MODEL QUESTION
O1
D D2 Da DA
Supply
O2
21 16 25 110
Os
17 18 14 130
Demand
32 | 17 | 18 41 190
60 100 120 150
Answer:
Here we put all the computation (of VAM) in
a single table instead of different shrunken
matrices, as follows:
OPRS-90
OPERATIONS RESEARCH
D D2 D3
D
Os
7L10
21 16 2s\/13110 (3) x
60 70|
1718142330 130(3)|130 (3|130 (3 70 (4)
Os 1005040
32 17 190 (1)|190 (1Dl150
18 41 (1)|150 (1)|150 (1)
b, 60 100 120 150
(4) () 4) (10)
60 100 120 40
(15) (1) (4)_(18)
60 100 120
X
(15)()_ (4)
x 100 120
(1) 4)
100 50
(17) (18)
Here the number of allocated cells is 6(=3+4-1).
So, the initial basic feasible solution is
2
-6
Answer:
Step I: (Row operation)
elect minimum element in each row and then Subtract it from each of the row: We get
the following table.
B5
B1 B2 B3 B4
6
Al 4 014
A2 9 0
OPRS-91
POPULAR PUBLICATIONS
A3 6
AS
Step I1: (Column operation)
After column operation B5
B4
B2 T0B3
Al
A2
6 4:
0 9
6
4
A3 6 TO 20
A4 0 3 1
A5 04 1 3
Step III: (Optimality test)
Here N <n, optimality condition is not satisfied.
The minimum of the uncovered elements is 2. Subtract 2 from each
uncovered element
vertical lines
and add 2 to those elements only which are crossed by both horizontal and
and construct the table below for optimality testing.
B1 B2 B3 B4BS
Al
4-4Hof-to
A2
7 4 2 2
A3
410-5.--0
A4
3-54
AS
Here N n=4.
-6-3
Step IV: (Optimal Assignment)
So, get the optimal solution.
A1> B3,A2-> B2,A3>B5, A4- B1,A5 > B4.
Minimum cost=-8-9-6-4-9=-36.
OPRS-92
-
OPERATIONS RESEARCH
DECISION THEORY
Multiple Choice
Type Questions
criteria
Laplace criteria is applicable for decision
1. a) certainty b) uncertainty making under WBUT 2014, 2016]
c) risk d) none of these
Answer: (b)
6.
Branch and bound method divides the feasible solution space
parts by into smaller
a) MODEL QUESTION]
branching b) bounding c) enumerating
Answer: (a)
d) all of these
OPRS-93
POPULAR PUBLICATIONS
.
bolt can be chosen under Laplace and Herwicz a(=0.6) criterion.
Estimated levels ofsale in units
Types of bolts 20,000 10,000 2,000
25 15 10
40 20
60 25 WBUT 2013]
Answer:
Laplace Criterion:
We associate equal probability for each event say 1/3. Expected payoff is:
50
I25x+15x+10x==16.67
3
- 21.67
OPRS-94
OPERATIONS RESEARCH
60+253x-29.33
as maximum
Since II has expected payoff,
Laplace
criterion. IIl is the bolt that we have
ve to choose under
Harwicz alpha Criterion:
D 5x0.6+10x0.4 =19
D. 40x0.6+5x 0.4 26
D. 60x0.6 +3x0.4 =37.2
Gince D is maximum, we have to choose
the bolt III.
A mechanjcal engineer is seriously
nast, only 70% of well considering drilling a tube well. n thne
drilled were successful at of
Moreover on finding no water at 200 200 ft of depth in that area.
ft, some persons drilled it fúrther up to 250 ft
only 20% struck water at 250 ft. The
prevailing cost of drilling is
foot. The engineer has estimated that in case
will have to pay Rs.15,000 over the next
s.
hé does not get his own tube well he
10 years, in order to buy water from the
neighbourhood. The following decision can be optimal:
) Do not drill any well
ii) Drill up to 200ft
iii) If no water is found at 200 ft drill up to 250 ft.
Draw an appropriate decision tree and determine engineer's strategy under EMv
approach. WBUT 2013]
Answer:
At D, point:
Decision: (a) Drill up to 250 ft. (6) Do not drill
Event: (a) No wate (b) Water
Probability: (a) 0.2 (b) 0.8
EMV for drill up to 250 ft. = (12500 x0.2)+ (27500 x0.8) =24500.
EMV for do not drill =25000.
EMV is smaller for the act drill up to 250ft. So it is optimal act
At D, point:
(b) Do not drill
Decision: (a) Drill up to 200 f. (b) Water
Event: (a) No water (6) 0.3
Probability: (a) 0.7
0.7)+(24500x 0.3) =14300.
MV for drill up to 200 f. = (10000 x
EMV for do not drill =15000.
is optimal act.
the act drill up to200ft. So it
is smaller for
and D, the optimal strategy 1s to drill the
well up to 200 ft.
refore, combining D drill it up to 250 t
It no water is struck, then further
OPRS-95
POPULAR PUBLICATIONS
At the point Di
Decision: (a) Do not droll (b) Drill up to 200 feet
Event (a) Water (6) Water
Probability: (a) 0.7 (b) 0.4
EMV for drill 200 feet =10,000x 0.4 +18,000 x 0.7 = 16,600
EMV for do not drill =18,000
At the point D2
Decision: (a) Do not drill (b) Drill up to 250 feet
(a) Water (6) Water
(a) 0.8 (b) 0.2
EMV for drill 250 feet=12,000x 0.2+30,000 x 0.8 =26,900
EMV for do not drill = 28,000
Hence Mr. Sinha will take the decision that if there is not no water at 200 ft. then drill
further 250 ft. for water.
OPRS-96
many copies OPERATIONS RESEARCH
maximum? should he order
so that his expected
Compute EPPI profit wilDe
) vendor is thinking of
i)
onal information regarding
spending on a
small market survey to OD
e
be willingto spend on the
such a survey? demand levels. How mnuc
uch should he
Answer: WBUT 2016]
Conditional profit table:
Demand Probability
Possible stock action no.
(D) (in ofcopies)
15 0.04 15
225
16 17 18 19 20
16 200 175 150 125
0.19 210 240
100
17 215 190 165 140
0.33 195 225
18 255 230 205 180
0.26 180 210
19 240 270 245 220
0.11 65 195 225 255 285 260
20 0.07 150 180 Z10 240 270 300
Expected profit table:
Deman
Demand Profit Possible stock(s) action
robability
probability 15 16
17 18 19 20
15 0.04 9 5 5
4
16 0.19 39.9 45.6 40.85 36.1 31.35 26.6
17 0.33 64.35 74.25 84.15 75.9 67.65 59.4
18 0.26 46.8 54.6 62.4 70.2 63.7 57.2
19 0.11 18.26 21.45 24.75 28.05 31.35 28.6
20 0.07 10.5 12.6 14.7 16.8 18.9 21
EMV 188.81 216.5 233.85 233.05 217.95 196.8
. Max (EMV) = 233.85
Nowwe calculate EPPI from the following table:.
Demand Profit under certainty_ Probability Expected profit under certainty
15 0.04 9
225
16
240 0.19 45.6
17 0.33 48.15
255
18 0.26 70.2
270 31.35
19 0.11
285
20
300 0.07 21
Total: 225.3
Then
EVPI =233.85-225.3 = 8.55
expected profit.
should be ordered to maximize the
C(0i) copies
Total EPPI=225.3
OPRS-97
POPULARPUBLICATIONS
coet
5. How can you determine the standard cost of product? How is standard
helpful in budgeting concept? Name the various types oruages. Analyze the th
Importance of budgetary control in improving company's performance.
WBTU 2017
Answer:
Both Standard Costing and Budgetary Control are based on the principle that costs canbe
controlled along certain lines of supervision and responsibility, that focuses
parameter
controlling cost by comparing actual performance with the predefined
HOwever, the two systems are neither similar nor interdependent. Standard Costin
delineates the variances between actual cost and the standard cost, along with the reasons,
In the contrary, Budgetary Control, as the name suggest, refers to the creation of
budgets, then comparing the actual output with the budgeted one and taking corrective
action immediately.
The two systems aim at measuring performance by fixing targets. Nevertheless, The
former, forecasts, cost accounts but the later projects detail about financial accounts.
Similarly, there are many differences between Standard Costing and Budgetary Control
which has been discussed below.
Standard Costing Vs Budgetary Control
1. Comparison Chart
2. Definition
3. Key Differences
4. Conclusion
Here, budget refers to a written financial statement expressed in monetary terms prepared
in advance for future periods, containing the details about the economic activities of tne
business organization.
The Budgetary Control system facilitates the management to fix the responsibilities and
coordinate the activities to achieve the desired results. helps the management
measure the pertormance of
It
the organization as a whole. Moreover, it heips m
formulation of future policies by reviewing current trends.
OPRS-98
OPERATIONS RESEARCH
dairy firm wants to determine the quantity
6. Ademand. st records of butter
butteriit should produce to meet
the Quantity required (kg)have shown the following demand
of days demand occurred
15 20 25 30pattern 40 50
35
NO
The
ck levels are
restricted to the 14
facilities. Butter costs Rs. 40 per kg
14 20 20
range 15 to 50 kg 80
due to
40 30 storing
quate
inadequ
100
OPRS-99
POPULAR PUBLICATIONS
TABLE 2
Expected profit table
Possible Possible stock action (alternative) (kg)
demand Probability| 15 20 25 30 35 40 50
50
(event) ) )*(i) | (i)*(ii) | (i)*(iv)| (O*) |OV) |(vi)|ixti vii)
(kg)
15 0.03 4.50 1.50 7.50 13.50 19.50 25.50 37.30
20 0.07 10.50 14.00 0.00-14.00-28.0042.00-70.0
-70.00
25 0.10 15.00 20.00 25.00 5.00-15.00-35.00-75.00
-75.00
30 0.40 60.00 80.00 100.00 120.00 40.0040.00-200
35 0.20 30.00 40.00 50.00 60.00 70.00 30.00-50.00
40 0.15 22.50 30.00 37.50 52.50
45.0060.00 0.00
0.05 7.50 10.00 12.50 15.00 17.5020.00 25.00
50
EMV ( 150.00 192.50 217.50 217.50 117.50-32.50407.50
in) The calculations for expected payoftis and EMV for each action are shown in Table 2.
Since the maximum EMV is 7 217.50 for stock of 25 as well as 30 kg of butter, the dairy
firm may produce 25 kg or 30 kg of butter and can expect an average daily profit of
217.50.
iii) The EVPI is calculated from Table 3.
TABLE 3
Expected profit table with perfect information
Market size Conditional profit Probability of Expected profit with
(event) under certainty () market size perfect information ()
15 150 0.03 4.50
20 200 0.07 14.00
25 250 0.10 25.00
30 300 0.40 120.00
35 350 0.20 70.00
40 400 0.15 60.00
50 500 0.05 25.00
EPPI 318.50
The expected value of perfect information is given by
EVPI EPPI - max. EMV=7(318.50-217.50)=7101
OPRS-100
OPERATIONS RESEARCH
7.
Write short notes on the following:
i) Training scheme
WBUT 2014]
ii) Budget and budgetary control
i) Industrial disputes
iv) Industrial safety
Answer:
) Training
scheme:
The legal defin ofa training schemeiis:
study or training that
(a) leads to an award; but
(b) does not, of itself, lead to an
award of a qualification listed on the Qualifications
Framework. "
H8.s00
This Table 2 shows that the alternative 'subcontract' results
in maximum average payoff
Rs. 8,500 (which is the optimistic return).
OPRS-102
OPERATIiONS RESEARCH
Table 3
Alternative States of nature
High Moderate (demand) | Maximum of|
(Rs.) Low Nil therows
Expand facility
(Rs.) |(Rs.)
20,000 S,000 (Rs.)
Constant new facility 0 |24,000 |35,000 35,000
|39,000 70,000
Sub contract 40,000 J15,000 70,000
Amount of regrets for Table 1, are shown in 40,000
ill minimize its
company wil| the Table This Table 3, tells us the
3. Thi
regrets to Rs. 35,000
by selecting the alternative 'Expand
facility
Alternatives |
TableTable 2
States of nature (Demands) Max. of
High (Rs) Moderate Low No demand|each row
(Rs) (Rs) (Rs)_
a) Expand 450 200 50 50 450
b) Add new facilities 0 0 250 300 300
Sub-contract 400 225 0 400
From Table 2, it is clear that the company will
minimize its regret to Rs. 300.00
selecting the altermative "Add new facilities. Here,
300= min. {450,300.4007
OPRS-104
OPERATIONS RESEARCH
(iv) Hurwicz Crietrion (Criterion
ofRealism):
nder this criterion rational decision-maker
nletely pessimistic.
They always choose should not be comp
completely optimistic nor
help decision between
help of linear combination. Thus, if these two with the
limits w
two limits
(1-a) will represents the coefficient
a
(0<a <l) is the coefficient of optimism
sm, ue
ther
weighted average criterion. of pessimism. This method is also know"
known as
The working principle is as follows:
Choosethe weight factor
a)Choose a,(0<a<1) and this gives (1 a) -
b) Determine the maximum as well as
minimum pay off for each alternative and
P axmaximum pay off + (1-a)x calculate
minimum pay off, for each of the alternatives
(i.e., for ith row).
c)Select an alternative with value of
Pas maximum i.e. find MaxPfor all the rows
(i 1,2,3) and we considerthe above example =
with a 0.6 (0 <a <1); and construcCt
Table 3
Alternatives States of Nature (Demands) Maxi-mum| Minimum P=ax Max
High Moderate Low No Demand (Rs) (Rs)
(Rs.(Rs.) (Rs) (Rs) +(1-a)Min
(Rs.)
a) Expand 250 (200 -100 -150 250 -150 90
b) Add new facilities-700 400 -300 -400 700 -400 260
c) sub-contract 300 175 50 -100 300 -100 140
We get Max{P} Rs.260. It is to be noted that when a =
0the criterion is too
pessimistic and a =1 the criterion is too optimistic doe a = %, the value has no
influence of any one of the above, and a = V seems to be reasonable.
from Table 1 as
24 48 36=(0.1,0.2,0.4,0.3)
120 120 120 120)
Table 2
Cases Probabilit Conditional Profits (Rs)
sold Stock
y(P) |15 16 |
18
15 0.1 450. 420 390 360
16 0.2 450 480 450 420
7 0.4 450 480 510 480
18 0.3 450 480
|510 |540
From column three to column seven, each column represents the pay off of the stock
alternatives (see, Table 2).
Now we construct the expected conditional profit pay off table (Table 3) by multiplying
probabilities with these columns.
OPRS-106
OPERATIONS RESEARCH
Probability Table3
Cases sold Possible stock action
15
| 16
15 0.1 45.0 42.0 18
16 0.2 90.0 39.0 36.0
0.4 96.0 90.0 84.0
17 180.0
192.0
18 0.3 135.0
204.0 192.0
144.0 162.0
EMV 450 153.0
EMV for the :strategy (when stock is 474
15 cases) is 475.
486 474
So,
enilarly, for the otner strategies i.e. when
stock is 16, 17 or 18 cases and EMV's are
4 486 and 474 respectively. So,
74, profit becomes maximum when stock is 17 cases of t
heries. So, to get maximum (optimum) profit, the retailer should purchase 17 cases per
day (See, able
I 3).
15000+12500-27,50
No water
Do not dri
Drill up to 250 ft
Water
250x50-12,50
No water
Drill up to 200 Do not drill
Water I5000+10000-25,00
200x50=10,00
Decision Tree
A, B and C in
Rs. 1 lakh among three companies
10. A person is planning to
invest returns on capital are
in terms of growth in capital and
equity shares. The pay-offs under each of the three economic conditions
investments Assuming that the
known for each of the recession, growth and stability.
which may prevail, that
is, period of one year in
among the three portfolios for a 1 lakh portfolio are
person must take his choice earnings (in Rs. 000's)
on his
of net
advance, his expectations
given beloW: Table 1
Stability Growthn
Recession 10
Company A 15
15 6
Company B 6 Laplace's rule and minimax
|6.5
Company G_ strategy for investment under (MODEL QUESTION]
etermine the optimal
regret criterion.
OPRS-107
POPULAR PUBLICATIONS
Answer:
Table 2 Expected pay off (RRs)
(i) By Laplace rule
Alternative Recession Stability Growth 15+6+10 =0.33
10
6
Company-A - 15 3
4+15+8-6.5
Company-B 7.5
6.5+6+1-4.8
6 15
Company-C 6.5 3
that the alternative 'company B' results in maximum average
By Laplace method we get
pay off of Rs.6500.00. So, invest in Company B. 1
Table first we construct Table 3, which is
(i) By Minimax regret criterion. From from the maximum pay off of that
obtained by subtracting each pay off of a column
column.
Table 3
Growth Max. of the rows (Rs.)
Recession Stability
Company- A 21.5 1.5 5
21.5
7 7
Company-B 2.5 0
Company-C_ 0 1.5 13
Amount of regrets for Table are shown in Table 3. This table shows that the company
1
will minimize its regret to Rs. 1500.00 by selecting the alternative "Company-C' for
investment
Note: In this problem by choosing two different criterion for decision- making, we have
selected two different alternatives (companies).i.e. by Laplace rule Company-B is
selected where as by Minimax regret criterion it is Company-C.
11. A news agency receives its weekly order for a magazine every Monday and
cannot recorder during the week. Each copy costs Rs.1.80 and is sold for Rs. 3.00.
Unsold copies may be returned the following week for a Rs.1.20 rebate. When the
agency runs out of copies and cannot supply a customer, it estimates its
"goodwill" loss at Rs. 2.40 in future profits, as the customer will take his business
else where for a couple of weeks at least. Demand has been remarkably constant
between 28 and 40 copies a week, as shown below:
Demand (Copies) 28 32 36 40
Fraction of time 0.30 0.40 0.20 0.10
) Construct a pay-off table and determine the optimal number of copies to
ii) How much would it be worth to know
stock.
the exact demand each week? What
would be the expected profit if this were possible? [MODEL QUESTION
Answer:
Conditional profit table: Table 1
Demand | Probability Possible stock action ( no.
in of copies)
D) 28 32
28 0.30 33.6 31.2
36 40
32
28.8 26.4
0.40 31.2 38.4
36 36.0 33.6
0.20 31.2 36.0 43.2 40.8
40 0.10 31.2 | 36.0 40.0 48.0
OPRS-1088
OPERATIONS RESEARCH
Here, C.
c.P=1.2xS-2.4, when D> S
= (3D-1.8S) + 1.2(S-D)
when D S
2c.P =1.2S-Z.4, D>S
= 1.8D-0.6S, D<S
Ddemandand
S-stock required
table:
Expected Profit Table 2
Demand Probability Possible stock (S) action
D
0.30
28 | 32 |36 40
28 10.08 9.2 12.0
.40 8.64
32 12.48 15.6 14.40 13.44
36 0.20 6.24 7.2 8.64 8.16
40 0.10 3.12 3.6 408 4.8
EMV 31.92 |35.60 35.76
From I|38.4
Table 2, we get max {EMV} = Rs. 38.4. Now, we will calculate EPPI from the
tablebelow:
Demands Profit under Probability expected profit under
(1) certainty certainty
(2) (3) (4)
28 33.6 0.30 10.08
32 38.4 0.40 15.36
36 43.2 0.20 8.64
40 48.0 0.10 4.80
EPPI 38.88
Then EVPI= Rs.(38.88- 38.40) =Rs.0.48. Here, the column (2) is constructed from the
diagonal elements of Table 1
OPRS-109
POPULAR PUBLICATIONS
E (Deluxe Shampoo)=(55+20+3)= 26
shampoo.
Max 16.69, 20, 26 =26 which indicates to launch deluxe
sale (pay oft) 400 eacn altemauve shampoo (Epp
Regret Criterion: The minimumrespectively. Now Max{30,40,55) 55
= which
Clinic, Deluxe) are 30, 40, 55 ich
corresponds to deluxe shampoo.
of optimism(a)= 0.6.
ii) Hurwiez's Criterion: Here given company's degree
P= aMax +1(1-a)Min
For egg-shampoo: P = 0.6x 30+(1-0.6)x10
= 18+4 22
For clinic shampoo: P = 0.6x40+(1-0.6)x5
24 +2=28
For Deluxe shampoo: P = 0.6x55+(1-0.6)x3
=33+1.2=34.2
Max{P,P,B} which corresponds deluxe shampoo.
After 1 hour
3 machines are
If the company hired the
breakdowm
slow-cheap repairman
OPRS-110
OPERATIONS RESEARCH
the cxpected cost at the node A
Now is
7(3x 20)+R 40 =*100
Expected cost at the node B is
(3x 20)+R 72=T132
lence slow-cheap repairmen should be hired.
14. A newspaper Doy
sels newspapers on off peak hours. He can
urchase at a concession rate of 50 paise andbuses during 60 paise. Any unsold copy
is a dead loss. He has estimated sell it for
the following probabilities for the number O
copies demanded:
Number of copies 20
Probability 21 22 23 | 24 | 25
0.1 | 0.15 0.25 0.3 0.12 0.08
Prepare a pay-ott table to find out how many copies
should be ordered so that
expected profit is maximized. [MODELQUESTION]
Answer:
Let S be the number of newspapers ordered per day and be the demand for it (number
papers sold each day). Given
of that C, =70.5, C, =z(0.6-0.5)=70.1. Now let us work
out the cumulative demand for the newspapers (because the demand for units is discrete).
Demandd
20 21 22 23 24 25
|
()
P() 0.1 0.15 .25 0.3 0.12 0.08
OPRS-111
POPULAR PUBLICATIONS
NETWORK ANALYSIS
Multiple Choice Type Questionns
1. The common error(s) that occur(s) in a network construction is/are
WBUT 2013,20161
a) Looping (cycling) b) Dangling c) Redundancy d) All of these
Answer: (a)
2. In constructing a network, Forward Pass computations are done for
determining. [WBUT 2013]
a) Earliest Event Time b) Latest allowable Time
c) Floats and Slack Times d) none of these
Answer: (a)
3. The shortest path between any two nodes in a Network is determined by the
followingg WBUT 2014]
a) Dijikastra's Algorithm b) Floyd's Algorithm
c Critical path method d) Decision tree
Answer: (a)
4. In PERT the span of times between the optimistic and pessimistic timee
estimates of an activity is WBUT 2014, 2017]
a) 3a b) 6o c) 12o d) a
Answer: (d)
5. Critical path method (CPM)is WBUT 201M5
a) probabilistic b) deterministic c) both (a) & (b) d) none of these
Answer: (6)
OPRS-112
OPERATIONS RESEARCHH
Anactivity is said tobe critical if
9 a) its free float is zero
WBUT 2017]
citsindependent float is zero b) its total float is zero
Answer: (b) d) its time duration is zero
13.The process of reducing the activity duration by putting an extra effort is called
crashing the activity MODEL QUESTION
a) True b) False
Answer: (a)
[MODEL QUESTION
14. An activity is said to be critical activity is
a) its free float is zero b) its total float is zero
d) its time duration is zero
c) its independent float is zero
Answer: (b)
vertex A is [MODEL QUESTION]
15. In a flow pattern a=J when the
b) any vertex other than source
a) arbitrary vertex d) none of these
c) source
sink vertex)
Answer: (a) (other than source and
pessimistic
variance of a job having optimistic time 5,
16. In PERT analysis, the [MODEL QUESTION]
likely time 8, is
time 17, and most c) 7 d) none of these
a) 3 b)4
Answer: (b)
MODEL QUESTION)
c) event oriented d) all of these
17. CPM is
a)probabilistic b) deterministic
Answer: (b) OPRS-113
POPULAR PUBLICATIONS
20 -.18
23
Answer:
The following diagram will give the solution:
20 19 39
20
8. 18 19
23 24
OPRS-114
Answer OPERATIONS RESEARCH
Duration
Most indays
OptimisticC
likely(tm)_ Pessimistic Expected
(t) Time
B
3.33
D 6.67
E 3.0
9.33
7.67
Network with expected 6.0
times (t) 4.0
T-10-T, TE-19.33-T
T=0=T.
333
T-3.33-T 3.0 c 0
25.33
L
TM-10 T TE-19.33-T
To find the critical path, use
calculateboth forward pass
Forward pass: Let T then
and backward pass
=0; T=3.33
TE10.0;TE"=max {3.33+3.0, 10.0+0}= 10.0
TE max {19.33 +
;
TE=10.0+9.33= 19.33 TE=max { 10.0+7.67, 19.33
+0}= 19.33
4.0, 19.33+
4.0,19.33+6.0) 25.33
Backward
pass: Start with T=25.33; T=25.33-6.0 19.33
T= min {19.33 -0, 25.33-4} = 19.33
T= 19.33-9.33 10.0;T= min {10.0-0, 19.33 7.67) 10.0
TLmin {10-6.67, 10-3 =3.33
T3.33-3.33=0.
A B dummy D dummy
Critical path is
()2(2)3)45) 6.67 )
The minimum expected project compilation time = 25.33 days.
3. A small project consists of seven actívities for which the relevant data are given
below: [MODEL QUESTION]
Activity Preceding9 Activity Duration
Activities (days)
A, B
A, B
C, D,E
C, D,E
OPRS-115
POPULAR PUBLICATIONS
F(6)
t 46 10
-3 -2 2 o8
t,=8
Answer:
A4= 20
As-34-
5
10 AF42-
A24 4
A-0-0
10
8
As5, Ch-21 A-30, -32
Aearliest expected completion time and
0latest allowable completion time for such event
OPRS-116
OPERATIONS RESEARCH
Events EECT= A LACT O; Slack time
0
4
2 16
24
24
34
30 32
42 42
Critical path: O
Total min. time = 42 units.
0 0 0 0
Long Answer Type Questions
1. small maintenance project consists of the
A
following jobs, whose predecessor
relationshipsare given below:
Jobs 1-3
Durationn
-2 2-3 2-5 3-4 3-6 4-5 4-6 5-6|6-7
L (Days)
15 15 3 12 14 3 14
14
15
2
Network Diagram
Forward pass calculation: In this esumate ine earuest start and the earliest finish time
(1i)
ES, are given by,
ES, = 0
ES, = ES +
=0+15 = 15
ES = Max(ES, +/23,ES, +1)= Max(15 +3,0+15)= 18
ES = ES, +fz4 = 18+8 26
ES Max(ES, + t25,ES, +s)= Max(15+5,26 +1) =27
ESMax(ES, + l26, ES, +46, ES, +ts6)= Max(18 +12,26 +14,27 +3)= 40
OPRS-117
POPULAR PUBLICATIONS
ES ES LF LF
1-2 15 15
0
1-3 15 15 18
2-3 15 18 15 18
2-5 15 20 32 37 17
3-4 18 26 18 26 0
3-6 12 18 28 40 10
4-5 26 27 36 7 10
4-6 14 26 40 26 40 0
5-6 27 30 37 40 10
6-7 14 40 54 40 54 0
From the above table we observe that the activities 1-2, 2-3, 3-4, 5-6, 6-7 are the critical
activities and the éritical path is given by, 1-2-3-4-6-7.
The total project completion is given by 54 days.
OPRS-118
OPERATIONS RESEARCH
d) at
What is the probadity that the
the pro
expected time? project will be
than completed at least 4 weekS
OR. WBUT 2014]
mall maintenand
ASmalna ance project
A
relationship is given belov consist of the following
jobs whose
whose precedn
precedence
Estimated WBUT 2015)
Activityy Optimistic duration (weeks)
| Most likely
1-2
1-3
Pessimistic
2-5
3-5
4-6 14
8
5-6 15
(a) Draw the project network.
(b) Find the expected duration and variance of
ic) Calculate the early and late occurrence for each activity.
each event and the expected project
length.
(d) Calculate the variance and standard deviations of project length.
(e What is the probability that the project will be completed
() 4 weeks earlier than expected??
(i) Not more than 4 weeks later than expected?
If the project due date is 19 weeks, what is the probability of meeting the due date?
Answer:
Complete the table using,
e
to+4mtp.
ActivityOptimistic Most likely Pessimistic 2
to) (ten) G)
(1,2)
(1,3)
O
1,4)
(2,5)
3, 5) 2 14
8
(4, 6) 2
(5,6) 15
3
Te and TL values along
and number the nodes and calculate the
Let us draw the network
with S values.
OPRS-119
POPULAR PUBLICATIONS
T=4 TE 0=T
O
Backward Pass:
TE4 T
T =17
T=[17-7]=10 TE 17T
TE=3
T' =17-5=12 TL-12
T=[10-6]=4
T =[10-1]=9
T = Min (9-2).(4-4).(12-3)]=Min[7,0,9]=0
a) Critical path is 1 -3-5-6
b) Expected project length 4+6+7= 17 weeks.
c =yoi +ojs +o, =V+4+4 =3
Standard Normal Deviation (SND) =isie-
Oc
8-17-33
Z 0 3
0.3 0.1293
Probability of completion the project in 18 weeks
.5+0.1293 =0.6293 62.93%
Probability of not completing project in week
.1-.6293=.3707=37.07%
d) ) P(Zsz,) where, Z, = 3
-1.33
P(Zs-1.33)=1-P(Z21.33)
=1-(0.5+0.4082)
= 1-0.9082 =0.0918
i) P(ZsZ,) where
z---1.33
P(Zs1.33)=0.5+0.4082 =0.9082
PZ =P(Zs0.666) =0.5+0.2514
(40,0)
Answer:
(10,0) (20,0)
\(10, 5)
(30,0)
(30, 0)
(20, 0)
(20,0)
(40,0)
Forward Pass:
Let TE (1)=0; then TE (2) =20
TE (3)= Max {30, 20+40, 10+5= 60;
TE (4) = Max{10, 60+10 =70;
TE (5) = Max{70+20, 20+30, 60 +20 90.
Hence, the maximum flow in the network is 90.
below: WBUT 201M77
4. Determine the maximal flow in the network shown
(25,0)
(15,0)
O (30,0)
(20, 0)
(30,0)
(15,5)
(25,0)
(35,0)
OPRS-121
POPULAR PUBLICATIONS
QUEUING MODEL
Multiple Choice Type Questions
.
When customers move from one queue to another hoping to receive quicker
service, it is termed as WBUT 2013, 2016]
a) Reneging b) Balking c) Jockeying d) none of these
Answer: (6)
2. "Balking" is a term associate with WBUT 2013]
a) Transportation problem b) LPP
c) Queuing problem d) Decision theory
Answer: (a)
Answer: (b)
-A
b)
- -1) d) none of these
7. When customers move from one queue to another hoping to receive quicker
service, it is termed as WBUT 2016)
a) Reneging b) Balking c) Jockeying d) None of these
Answer: (¢)
OPRS-122
OPERATIONS RESEARCH
8. In a M/M1 queue, the
Poisson service rate
a) D linear is
(a)9 WBUT 2016
Answer: c) exponential
d) none of these
Queuing theory deals with
a) materialhandling the problem of
c) reduce the WBUT 2017
waiting time or idle b) effective use of
machines
Answer: (c, d) time d) better utilization
of man services
10. If everything else remains
rate, except that the constant, including
service time becomes the mean arrival rate and service
a) The average queue constant instead of exponential,
length will be halved
b) The average waiting MODEL QUESTION]
time will be doubled
c) The average queue length
will increase
d) None of these
Answer: (d)
P D1-p) o- P
Answer: (6)
OPRS-123
POPULAR PUBLICATIONS
16. For Queuing model MIM/1:0o/FIFO, which of the following is not true?
a) Input follows Poisson distribution [MODEL QUESTION
process follows exponential distribution
b) output
c)capacity is finite
d) it has only one service provider.
Answer: (c)
[MODEL QUESTION
17.A queue-system will remain unchangedif
d) none of these
a) p<l b) p=1 c) p>l
Answer: (6)
8x8x5hours.
Hence, the required idle time is (8-5) hours = 3 hours.
2. In a Supermarket, the average arrival rate of customers is 10 every 30 minutes
following poisson distribution. The average time taken by a cashier to list and
calculate the customers purchase is 2.5 minutes, following exponential
distribution. What is the probability that the queue length exceeds 7? What is the
expected time spent by a customer in the system? WBUT 2015]
Answer
Mean arrival rate of custpmer A =10/30=1/3 per minute.
=
u5 per minute.
OPRS-124
OPERATIONS RESEARCH
Prob.queuelength
27]=
(ii)Expected
Expectedwaiting
timeof a customer in
E0.279
=0.279
the system
()-3-2352minutes
3. A self service store
an average every
employs one
ASSuming 5minutes while cashier at its counter. Nine.customers
Poisson distribution the cashier can serve 1 customers arive on
service time. Find for arrival rate in5minutes.
and exponential distribution
i) average number for
i) average of customers in
number of customers the system
i) average time a customer in the queue or average
queue length
iv) average time a customer spends in the system..
Answer: waits before being
ng served. WBUT 2016, 2017]
Here, =per minute
9
5
0
per per minute
() Average no. of customer in the system
915
L
1-p 1-p 109
5
2 minutes 5 sec.
W A(4-A)
20
36(36-20) 144 hour 2minutes
12
=
Answer:
Arrival rate, i =9/5=1.8 customers/minutes
Service rate, u=10/5=2 customers/minutes
1.8 -=9
9Average no. ofcustomers in the system
()=72-18
ii) Average no. of customers in the queue (,=F
of customer spends in the system
it) Average time (,)= 2-183mimutes
= =4.5minutes.
iv) Average time a customer spends in the queue
6. If the arrival rate is 1 and service rate is 4, then prove that the expected queue
[MODEL QUESTION]
length is
A4-2)
Answer:
Since there are (n-1) units in the queue excluding one being serviced,
L-r-1)-»"-
---
n=l
n=l _n=0
-1-)-4-1-1--4-
n=
n=
1-p A4-2)
7. What is meant by traffic intensity? [MODEL QUESTIONI1
OPRS-126
OPERATIONS RESEARCH
AnSwer:
rival rate and
athe mean arriva g is the mean departure
is
dtensity(or
utiliza
utilization tactor)
i5 defined by
and p= /4
rate of a queue then fraye
traffic
8 customers/hr. and =10 customers /hour of a p <l.
Customers/nr.
Let,
1hen
,
p 10
which means that utilization
queue-system.
ofthe service facility is 80%.
8.With reference
reference to Queuing Theory,
what do you mean by (M/M/):(«/FIFO)?
at do you mean by "transient state" and "steady
What
state" of queuing model? Write
the formula for L, and L.
[MODEL QUESTIONJ
Answer:
r'Part:
(MIM/1/0-FiFo) is tne Simplest queue system where the arivals follow a Poisson
nrOcess, service times are exponentially
distributed and there is only one server. In other
words, it is a system with Poisson input, exponential
waiting time and Poisson output
with single channel.
Queue capacity ot the system is infinite with first in first out mode. The first M in the
notation stands tor Poisson input, second M for Poisson output, for the number of
1
2d Part:
A system is said to be in transient state when its operating characteristics are dependent
on time.
A steady state condition is said to prevail when the behaviour of the system becomes
independent of time.
3 Part:
Formulas
Average number of units in the system (L,)=-
OPRS-127
POPULAR PUBLICATIONS
Answer:
Here, p = traffic intensity =4= 9
H per sec.
100
P4_20 x100 =
3600
Average waiting time of a customer is
1 1 100x9
= 225 sec.
A-P) 100
4
11. Briefty discuss the Kendall notation of queuing model. MODEL QUESTIONI
Answer:
Kendall's Notation for Representing Queuing Models
Generally, queuing model may be completely specified in the following symbolic form
(a/blc): (d/e), where
a Probability. law for the arrival (or inter-arrival) time
b Probability law according to which the customers are being served
Number of channels (or service stations)
Capacity of the system, i.e., the maximum number allowed in the system (1in
service and waiting)
Queue discipline
OPRS-128
sider a self-servi store OPERATIONS RESEARCH
with
nential service time Suppose one cashier.
5 minutes and the ca r. Assume
Assum Poisson arrivals
cashier can that nine customer and
averagenumber
The arobability of custe serve 10 ers arrives
in 5 minutes. Find on an average
having moreors queuina fnnutes.
The probability of having
arobability
that a customerthat 10 customers in system
has to queue the and
for more than 2 minutes.
Answer:
[MODELOUESTION)
QUESTION
9
verage arrival rate (2) =per min.
0.000145.
OPRS-129
POPULAR PUBLICATIONS
6 x0.000145, 0Sns3
P,=
3
x0.000145,
3 3 Sn s7
=APL -5(n-3P,+3-P
N
Now, L, =L, +S-P
n=0 n! n!
n=3 n=0
OPRS-130
OPERATIONS RESEARCH
Prob. (waiting time in the system2
)P 10)
30
dx=0.03.
10
3.
Customers arrive at a one-window
ibution with mean 10 per
distrib drive-in bank according to a
an 5 minutes. The
mean o space hour.
space in fron
Service
vice time
time per customa
customer to Poissona
mean
ar can
nutes. The front of the window, including is exponential WIt
accommodate a maximum of 3 cars. that for the servi
rviced
ca
space. Other cars can wait outside this
i)What is the probability that an arriving customer can drive
space in front of the window? directly to the
ii) What is the probability that an arriving customer will
the indicated space? have to wait outside
ii) How long is an arriving customer expected to wait before starting service?
iv) How many spaces should be provided in front of the window so that all
the
arriving customers can wait in front of the window at least 20% of the time?
WBUT 2015]
Answer:
Here,
i) Po+P+p, =1-
-
A=10 cars / hour and u=12 cars /hour
= 0.42
in the queue
(ii) Expected waiting time
W
H(-2)
Since W =3, 4=i, A=1 for second booth.
3 l=0.16
minute.
Hence, increase in the arrival rate= 0.16-0.11=0.05 per
(iv) Probability (waiting time is the system2 10)
20
= ]S(4-2)edw=e1u-)=e=
10
OPRS-132
OPERATIONS RESEARCH
S =S2 +Y2
and f6,)= minly? + S,6)
3
minlyi + s)
Ss)=
iG)= =6, -n}
w.r.t. y, is zero.
minimum, ifits derivative
+(s-y2is
ie. 2 +2(6, -v2)=0
or,
OPRS-133
POPULAR PUBLICATIONS
Hence, f6,)=2
Now,
4t,)-mini-*]
O S05)- mipl +505-»*] ky+»*»21s|
s1s)-+05-5 =75.
Thus =
s15®yj 5,
25-=15-5=10n=2=5,
- =10-5 =5 =5.
Hence, the optimal solution is (5,5,5 and fs63)=75.
2. Use the method of Lagrangian multipliers to solve the following non-linear
programming problem:
Minimize Z = 2x + +3x +10x, +8x +6x, -100
=
subject to
t +, 20
g>0. WBUT 2016]
2
Answer:
Lagrangian function can be formulated as:
L)=2++3 +10x, +8x, +61,-10-(4 ++%-20)
The iecessary conditions for maximum or minimum are
aL L
4x+10-2
Ox
=0;=2x, +8- =0
OL
+6-A =0; (%+%+%-20)=0
Putting the value of x,x, and x, in the last equation 0 and solving for
30. Substituting the value of A in the other three equations, we get an extreme point:
423,)=5,11,4
To prove the sufficient condition whether the extreme point solution gives maximum or
minimum value of the objective function we evaluate (n-1) principal minors as follows:
OPRS-134
OPERATIONS RESEARCH
o1
0 11 1
40 4
10 2
is
Since sign of A, and A, are alternative, therefore extreme point: (%zs)=(5,11,4)
= 281.
a local maximum. At this point the value of objective function is, Z
OPRS-135
POPULARPUBLICATIONS
GAME THEORY
Multiple Choice Type Questions
matrix is formed in favVour of player A
game theory problem if the payoff
(all the elements of the matrix will be profit of
A), then he should follow
WBUT 2014
a) max-max principle b) min-max principle
c) max-min principle d) min-min principle
Answer: (c)
A1 4 64
18|
A2 2 13 7
6
A3 115 173
A4 12 2
76
Answer:
We have,
B1 B2 B3 B
A 18 4 6 4
Az 6 2 13 7
As
115173 12 2
A7 6
is dominated by Therefore we can discard
B3. B3 and the
By dominance property, B2
reduced matrix is
B
B2
B4
A 18 44
Az6 2 7
As1 5 3
47 6|2
Again the linear combination of B2 and Ba dominated by B1, so we can discard B and we
get,
B B4
A4 4
A22 7
A 5 3
A62
OPRS-136
OPERATIONS RESEARCH
Answer:
Given, the payoff matrix is
U U0.27 U0.35-0.02
U Row minima
-0.02
C 0.25
0.03, 0.00=0.06
Max (Row minima) = Max {-0.02, 0.06,
0.35, 0.08) =0.08
in (Column maxima) = Min {0.30, 0.27,
Therefore, this game has no pure strategy.
propetties and the resulting matrix is:
strategies, now we apply dominance
rixed
(1) U, is dominated by U,; therefore,
U U U
C 0.25 0.27-0.02
0.20 0.06 0.08
C H
C 0.14 0.12 0.03
0.30 0.14 0.00
C
(2) U, dominates U; therefore,
U U
G 0.27-0.02
C 0.06 0.08
C 0.12 0.03
0.14
C 0.00
Now we apply graphical method, in order to obtain the mixed strategies:
Axis- (U) Axis-lI (Ui)
Min (Max)
2.5
Ca 1.5
.5. C 0.5
0 0
-0.5 - -0.5
-1.5 -1.5
OPRS-138
OPERATIONS RESEARCH
P Pa 0 0PtPa =1|
(U, U, U, U\
and
Su0 0
0.08-0.06 0.02
"(0.27+0.08)-(0.06-0.02) 2
0.31 31
29
Pa1 31 31
0.08+0.02
0.31 31
30
and a 31
The value of the game is5X027+0.06x0.02 = 0.07355
0.31
OPRS-139
POPULARPUBLICATIONS
DUALITY THEORY
2 20
OPRS-140
OPERATIONS RESEARCH
Answer:
problem is given by
Dual of the given primal
Min W=50y +80y, +20y,
subjectto ++2y,22
+2 +y2-1|
+4,21
and Pa 20
Long Answer Type Questions
Write down the dual of the following L.P. Problem:
1. WBUT 2016
Minimize Z 2x, +5x, +X
subject to, 2x +2-z $2
-3x +2x,-5x,2-6
4x+3x,+x 210
2 220
Answer:
The standard form of the given LPP is
Max W-(2x, +5x, +)
subject to 2x, +- $2
3x-2x, +5x, S6
4-3x2-,S-10
and 2 20.
So the dual of the given primal is
Min W'=2u+6v-10w
subject to 2u+3v-4w2-2
u-2v-3w2-5
-u+5v-w2-1
and u, V, w20.
OPRS-141
POPULAR PUBLICATIONS
Answer:
Since the primal
problem has 3rd constraint is equality in sign, so the 3 variable
dual problem will unrestricted of
Similarly, as the be3rd variable
in sign.
the primal LPP is unrestricted in sign, therefore,
constraint of the dual LPP will of 3
The standard form of be equality in sign.
the given LPP is
Max Z =2x +3x,-4x,
subjectto 3x +x +x, S2
4x-3x, S4
and , X20-5x
Therefore, the required
and
+x
z
=5
is unrestricted in sign.
dual problem is
Min W = 2 -4y, +3Ys
subjectto 3y, +4y+y, 22
-5y 23
y5 + y, =-4
and y y2 20 and y, is unrestricted in sign.
OPRS-142
OPERATIONS RESEARCH
INVENTORYCONTROL
Multiple Choice Type Questlons
Answer: (a)
1. The rate of use of particular raw material from stores is 20 units per year. The
cost of placing and receiving an order is Rs. 40. The cost of each unit is Rs. 100.
The cost of carrying inventory in percent per year is 0,16 and it depends upon the
average stock. Determine the economic order quantity. WBUT 2017]
Answer:
Given R=20 units per year
C =CxI=100x0.16=R16per unit per year
C=R40per order
Optimal lot size
16
No. of orders peryear=2
C
units.
OPRS-143