Professional Documents
Culture Documents
Manager Adjusted
Manager Adjusted
A. GENERAL REQUIREMENTS
a.1.1 Mobilization/demobilization lot 1.00 25,000.00 25,000.00
a.1.2 Hauling of spoils and materials (within site premises) lot 1.00 15,000.00 15,000.00
a.1.3 TEMFACIL lot 1.00 OWNER
a.1.4. Engineering Supervision lot 1.00 160,000.00 120,000.00
B. SITE WORKS
b.1.1 Site preparation/ Clearing and demolitions lot 1.00 9,600.00 4,800.00
b.1.2 Erection of Scaffoldings lot 1.00 16,800.00 8,400.00
b.1.3 Footing Excavation lot 1.00 24,000.00 12,000.00
SUB TOTAL: 13,200.00
C. STRUCTURAL WORKS
c.1.1 Footings
c.1.1.1 Rebarworks kgs. 11.62 31.70 368.21 15.00 174.23 542.44
c.1.1.2 Formworks sqm. 0.59 666.67 393.85 350.00 206.77 600.62
c.1.1.3 Concreting cu.m 2.00 510.00 1,020.00 2,000.00 4,000.00 5,020.00
c.1.2 Pedestal
c.2.1.1 Rebarworks kgs. 25.46 31.70 807.13 15.00 381.92 1,189.05
c.2.1.2 Formworks sqm. 0.10 666.67 69.65 350.00 36.57 106.22
c.2.1.3 Concreting cu.m 2.00 510.00 1,020.00 2,000.00 4,000.00 5,020.00
c.1.3. Stairs
c.3.1.1 2"x6" tubular pcs - - -
c.3.1.2 2"x4" c chanel for stair thread pcs - - -
c.3.1.3 B.I. checkered plate for landing pcs - - -
c.3.1.4 B.I. Welding works pcs - - -
c.1.4. Steel Beams (2ND FLOOR FRAMING & ROOF FRAMING)
c.4.1.1 Space Web Framing beam for Mezzanine & roofing extension kgs. - - -
c.4.1.2 existing rafter relocation of height kgs. - - -
c.1.5. Mezzanine Tubing framing with 1/2 Hardiflex flooring
c.5.1.1 2" x 2" B.I. Tubular Framing pcs - - -
c.5.1.2 2" x 4" B.I. Tubular Framing pcs - - -
c.5.1.3 4" x 4" B.I. Tubular Framing pcs 4.00 7,134.00 28,536.00 1,600.00 6,400.00 34,936.00
SUB TOTAL: 47,414.33
F. CEILING FINISHES
f.1.1 9mm thk Gypsum board on metal furring sqm. 80.00 650.00 52,000.0 400.00 32,000.00 84,000.00
f.1.2 9mm thk MR Gypsum board or Ficem board on metal furring sqm. - - -
SUB TOTAL: 84,000.00
G. DOORS
g.1.1 Wood panel door pcs. 1.00 3,200.00 3,200.00 2,000.00 2,000.00 5,200.00
g.1.2 Toilet & Bath Doors -
g.1.2.1 Ground floor pcs. - - -
g.1.2.1 Second floor pcs. - - -
SUB TOTAL: 5,200.00
H. PAINTING WORKS
h.1.1 interior wall Interior Face in Semi Gloss Paint Finish sqm. 126.90 400.00 50,760.0 350.00 44,415.0 95,175.00
h.1.2 exterior / interior wall Interior Face in Semi Gloss Paint Finish sqm. 44.80 400.00 17,920.0 350.00 15,680.0 33,600.00
h.1.3 9mm thk Gypsum board in flat latex finish sqm. 75.00 400.00 30,000.00 350.00 26,250.00 56,250.00
h.1.4 9mm thk MR Gypsum board in Flat Latex Paint Finish sqm. - - -
h.1.5 Quick dry enamel finish on Stairs & railings Lm - - -
SUB TOTAL: 185,025.00
I. WATERPROOFING WORKS
i.1.1 Waterproofing works on all T&B (Plexibond 3 coats) sqm. - - -
SUB TOTAL: -
K. FINISHING CARPENTRY
K.1.1 Install and fabricate of cabinet shelves sqm - - -
K.1.2 Install and fabricate of cashier table sets - - -
K.1.3 Cladding at Cashiers table wall sqm - - -
SUB TOTAL: -
L. ROOF FRAMING AND ROOFING SHEETS
L.1.1 Dismantling and re-installation of roof framing lot - - -
L.1.2 Additional roof framing and gutter lot - - -
L.1.3 chicken wire and insulation lot - - -
L.1.4 roofing sheets and gutter (new) lot - - -
SUB TOTAL: -
M. PLUMBING
M.1.1 Sanitary Line lot - - -
M.1.2 Waterline lot - - -
M.1.3 Downspout. Catch basin and drain line lot - - -
M.1.4 Toilet fixtures lot - - -
SUB TOTAL: -
N. ELECTRICAL
N.1.1 Conduits, Utility and junction boxes (PVC) lot 1.00 17,000.00 17,000.00 14,720.00 14,720.00 31,720.00
N.1.2 Wirings lot 1.00 72,000.00 72,000.00 29,440.00 29,440.00 101,440.00
N.1.3 switches, outlets and lighting fixtures lot 1.00 ######## 104,000.00 51,520.00 51,520.00 155,520.00
N.1.4 Panel board, wire gutter and service entrance lot 1.00 ######## 115,000.00 33,120.00 33,120.00 148,120.00
N.1.5 Consumable lot 1.00 7,500.00 7,500.00 3,200.00 3,200.00 10,700.00
SUB TOTAL: 223,750.00
NOT INCLUDED:
BATHROOM FIXTURE
DOUBLE DECK BED
LOUVRE WINDOW'S FOR MEZZANINE AR. JESSE G. CELESTIAL II
*audit on electricial for final expenses PRINCIPAL ARCHITECT